2 v.4smsatoN. o c. rosss x,.- q; ScFETY FVALUAT 0N REPORT EY THE OFFICE OF SPECIAL PROJECTS
.EPPLOYEE C0hCERN ELEMENT REPORT CO 11202-SON, "CPAFT-DESIGNEL HANGERS AS FELATED TO CONSTRUCTION" TENhESSEE VALLEY AUTHORITY SE0VOYAH huCLEAR POWER PLANT UNITS 1 & 2 00CtET NOS. 50-327 AND 50-328 I.
St,b;cet i
Category: e.c r.s tru ction (10000)
Subca te gory :
Wor 6 Centrol (11200)
Elerent:
Craft Designec Hangers as Related to Construction (11102)
The bases for Elerent Feport C0112C2-50N, Rev. 2, dated October 10, 1956 are Latts Bar Ersloyee Conccrr IN 86-261-0C2 and Sequoyah-specific Employee Concern n-EE-120-LCC, which state (respectively)
"Ot.e to werk recuied by FCRs/ECN's not being perfortred promptly, the craf t rany times are working to an obsolete drawing. After requestin; j
ins M ction for corpleted work, GC may inform craft that completed work it rot accepttb'e as e previous FCR/ECh requirerrent was incorporated tri the crawing, but the work has r.ot been performed. Example, panels in the Unit i Relof Room. Construction Departrent concerr.
Cl has no additional information. No follow up required."
l "Secucyah-Har.ser cre.s rere instructed (Supervisor known) to go ahead and build tangers withcut drawings, and engineering would craw the harger up t
later. Far.y of these hangers were subsequently rejected and reworked.
Censtruction Cepartrent ccncern. Cl has no further informatice."
Erployee Concern Ih-EC-261002 was evaluated by TVA as potentially rucle w safety-related and potentially applicable to Sequoyah (generic); xx-65-120 006 I
was evaluatec ty TVA as potentially ruclear saf ety related.
l 11.
Surrary of Issue i
TVA cefined the issue an hangers were either installed by the craf ts without a Cssign drawirg cr with a s'.perseded design drawirig, and engireering woulc later r ase as-constructed crawirgs.
The NFC staff fourc that the iss 4 also itcha: :** ress':' lit.* of failure to identify ceviaticns fror firai,
.e: n
.,co"
.*1:-
res ts n un(na.r r3rgins cf saf ety,
i esi122o 79 es t id 4 ADOCK0500g, ptip P
L 2
III. Evaluation The TVA evaluators reviewed decurentation erd interviewed TVA personnel ir. solved in the installation of hangers.
They determined thet although sore hangers were installeo prior to the issuance of desi 1 drawings, the tangers 3
were later as-tuilt, analyzed and approved by engineering personnel.
The hangers were inspected and accepted by QC based only on approved design drawingc. Current work practices at Sequoyah require a work plan, which must incluce approved design drawi qs, prior to performing work.
t After this eierent report was issued, there were staff inspections and accitional licensee esaluations. Partially es a result of this employee concern, the 11cer.see initiated the Design Baseline and Verification Prograr ar.d etter corrective action projects described in the Sequoyah Nuclear l
Ftrforrance Plan. The staff roniterte the progress of these prcgrams through several irspecticos ar.c four.d the corrective actions to te acequate.
1 IV.
Cor.c lu s ier s The staf f foute that the employee concern was substantiated and the corrective l
actiers were acceptable.
.*