November 29, 2005 Mr. James A. Spina Vice President Nine Mile Point Nuclear Station, LLC P.O. Box 63 Lycoming, NY 13093

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF NINE MILE POINT NUCLEAR STATION, UNITS 1 AND 2, AMENDED LICENSE RENEWAL APPLICATION (TAC NOS. MC3272 AND MC3273)

Dear Mr. Spina:

By letter dated July 14, 2005, Constellation Energy Group, Inc. (CEG or the applicant),

resubmitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54 (10 CFR Part 54), to renew the operating licenses for the Nine Mile Point Nuclear Station (NMP),

Units 1 and 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). The NRC staff is reviewing the information contained in the amended license renewal application (ALRA) and has identified, in the enclosure, areas where additional information is needed to complete the review.

Based on discussions with Mr. David Dellario of your staff, a mutually agreeable date for your response is within 30 days from the date of this letter. If you have any questions regarding this letter or if circumstances result in your need to revise the response date, please contact me by telephone at 301-415-1458 or via e-mail at nbl@nrc.gov.

Sincerely,

/RA/

N. B. (Tommy) Le, Senior Project Manager License Renewal Branch B Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos.: 50-220 and 50-410

Enclosure:

As stated cc w/encl: See next page

ML053340117 DISTRIBUTION: See next page Document Name: E:\\Filenet\\ML053340117.wpd OFFICE RLRB:PM DLR:LA RLRB:BC (A)

NAME NLe LLund DATE 11/ 29 /05 11/ 29 /05 11/ 29 /05

DISTRIBUTION: Ltr. To J. Spina, Re: Nine Mile Nuclear Station, Units 1 and 2, Dated: November 29, 2005, Accession No.: ML053340117 HARD COPY DLR RF N. Le (PM)

E-MAIL:

RidsNrrDlr RidsNrrDe RidsOgcMailCenter RidsNrrDci RidsNrrDss G. Bagchi K. Manoly R. Jenkins D. Thatcher R. Pettis G. Galletti R. Weisman M. Mayfield A. Murphy S. Smith (srs3)

S. Duraiswamy Y. L. (Renee) Li DLR Staff C. Holden R. Laufer T. Colburn B. Fuller, RI E. Knutson, RI J. Trapp, RI T. Koshy P.Y. Chen H. Ashar D. Jeng J. Burns M. Lemoncelli S. Mazumda OPA

Enclosure NINE MILE POINT NUCLEAR STATION, UNITS 1 AND 2 (NMP1 and NMP2)

AMENDED LICENSE RENEWAL APPLICATION (ALRA)

REQUEST FOR ADDITIONAL INFORMATION (RAI)

RELATED TO AGING MANAGEMENT OF ELECTRICAL AND INSTRUMENTATION AND CONTROLS SYSTEMS a-RAI 3.6.2-1 The ALRA states None in the Aging Effect Requiring Management column, the Aging Management column and the Notes column in the following tables:

a.

Table 3.6.2.C-2, Electrical and I&C Systems, Non-Segregated/Switchyard Bus - Summary of Aging Management Evaluation, Component: Switchyard Bus Conductors.

b.

Table 3.6.2.C-4, Electrical and I&C Systems, Switchyard Components - Summary of Aging Management Evaluation, Components: (a)

High Voltage Insulators - Cement, Porcelain, and Metal, and (b) Transmission Conductors.

Provide justifications why no Aging Effect Requiring Management and Aging Management Program are required for these components, including plant and industry experience where available and if any special treatment or provision is made to prevent oxidation or corrosion.

a-RAI 3.6.2-2 Table 3.6.2.C-4, Electrical and IRC systems, switchyard components - Transmission conductor corrections states in Aging Management Program column that Preventative Maintenance Program is used. Describe how loosening of bolted corrections will be prevented by this program.

Nine Mile Point Nuclear Station, Units 1 and 2 cc:

Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 126 Lycoming, NY 13093 Supervisor Town of Scriba Route 8, Box 382 Oswego, NY 13126 Mr. James R. Evans LIPA P.O. Box 129 Lycoming, NY 10393 Charles Donaldson, Esquire Assistant Attorney General New York Department of Law 120 Broadway New York, NY 10271 Mr. Paul D. Eddy Electric Division NYS Department of Public Service Agency Building 3 Empire State Plaza Albany, NY 12223 C. Adrienne Rhodes Chairman and Executive Director State Consumer Protection Board 5 Empire State Plaza, Suite 2101 Albany, NY 12223-1556 Kathryn M. Sutton, Esquire Morgan, Lewis & Bockius LLP 1111 Pennsylvania Avenue, NW Washington, DC 20004 Mark J. Wetterhahn, Esquire Winston & Strawn 1700 K Street, NW Washington, DC 20006 Mr. Michael J. Wallace President Nine Mile Point Nuclear Station, LLC c/o Constellation Energy Group, Inc.

750 East Pratt Street Baltimore, MD 21202 Carey W. Fleming, Esquire Sr. Counsel - Nuclear Generation Constellation Generation Group, LLC 750 E. Pratt Street, 17th Floor Baltimore, MD 21202 Mr. Peter R. Smith, President New York State Energy, Research, and Development Authority 17 Columbia Circle Albany, NY 12203-6399 Mr. James Ross Nuclear Energy Institute 1776 I St., NW, Suite 400 Washington, DC 20006-3708 Mr. Mark Flaherty Manager - Fleet Licensing R.E. Ginna Nuclear Power Plant 1503 Lake Road Ontario, NY 14519 Mr. M. Steven Leonard General Supervisor - Nuclear Regulatory Matters Nine Mile Point Nuclear Station, LLC P.O. Box 63 Lycoming, NY 13093

Nine Mile Point Nuclear Station, Units 1 and 2 cc:

Mr. Peter Mazzaferro Site Project Manager - License Renewal Nine Mile Point Nuclear Station, LLC P.O. Box 63 Lycoming, NY 13093 Mr. Mike Heffley Senior Vice President and Chief Nuclear Officer Constellation Generation Group 1997 Annapolis Exchange Parkway Suite 500 Annapolis, MD 21401