| title = Letter to B. Nick Request for Additional Information Regarding Dairyland Power Cooperative'S Decommissioning Funding Plan Update for La Crosse Boiling Water Reactor Independent Spent Fuel Storage Installation
| title = Letter to B. Nick Request for Additional Information Regarding Dairyland Power Cooperatives Decommissioning Funding Plan Update for La Crosse Boiling Water Reactor Independent Spent Fuel Storage Installation
| author name = Longmire P
| author name = Longmire P
| author affiliation = NRC/NMSS/DSFM/SFLB
| author affiliation = NRC/NMSS/DSFM/SFLB
Line 14: Line 14:
| document type = Letter
| document type = Letter
| page count = 3
| page count = 3
| project = EPID:L-2017-FPR-0037
| project = CAC:001028, EPID:L-2017-FPR-0037
| stage = RAI
| stage = RAI
}}
}}


=Text=
=Text=
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 8, 2018  
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 8, 2018 Ms. Barbara Nick President and Chief Executive Officer Dairyland Power Cooperative 3200 East Ave. S., P.O. Box 817 La Crosse, WI 54602-0817  
 
Ms. Barbara Nick President and Chief Executive Officer Dairyland Power Cooperative 3200 East Ave. S., P.O. Box 817 La Crosse, WI 54602-0817  


==SUBJECT:==
==SUBJECT:==
REQUEST FOR ADDITIONAL INFORMATION REGARDING DAIRYLAND POWER COOPERATIVE'S DECOMMISSIONING FUNDING PLAN UPDATE FOR LA CROSSE BOILING WATER REACTOR INDEPENDENT SPENT FUEL STORAGE INSTALLATION  
REQUEST FOR ADDITIONAL INFORMATION REGARDING DAIRYLAND POWER COOPERATIVES DECOMMISSIONING FUNDING PLAN UPDATE FOR LA CROSSE BOILING WATER REACTOR INDEPENDENT SPENT FUEL STORAGE INSTALLATION  


==Dear Ms. Nick:==
==Dear Ms. Nick:==
 
By {{letter dated|date=March 14, 2016|text=letter dated March 14, 2016}}, Dairyland Power Cooperative (DPC) submitted for U.S. Nuclear Regulatory Commission (NRC) staff review and approval, a decommissioning funding plan update (DFP Update) for the independent spent fuel storage installation (ISFSI) at La Crosse Boiling Water Reactor (Agencywide Documents Access and Management System Accession No. ML16102A101). The NRC staff reviewed DPCs DFP update for the ISFSI and believes DPCs submittal was not sufficient to meet the intent of the requirement in Title 10 of the Code of Federal Regulations (10 CFR) 72.30(c). The DFP update does not provide sufficient information to allow the NRC to determine that the events listed in 10 CFR 72.30(c)(1)-(4) have been specifically considered.
By letter dated March 14, 2016, Dairyland Power Cooperative (DPC) submitted for U.S. Nuclear Regulatory Commission (NRC) staff rev iew and approval, a decommissioning funding plan update (DFP Update) for the independent spent fuel storage installation (ISFSI) at La Crosse Boiling Water Reactor (Agencywide Documents Access and Management System Accession No. ML16102A101). The NRC staff reviewed DPC's DFP update for the ISFSI and believes DPC's submittal was not sufficient to meet the intent of the requirement in Title 10 of the Code of Federal Regulations (10 CFR) 72.30(c). The DFP update does not provide sufficient information to allow the NRC to determine that the events listed in 10 CFR 72.30(c)(1)-(4) have been specifically considered.
The NRC staff need the information identified in the enclosure to this letter. We request that you provide this information within forty-five (45) working day of the date of this letter. Inform us at your earliest convenience, but no later than 2 weeks prior to the due date, if you are not able to provide the information by that date. To assist us in re-scheduling your review, you should include a new proposed submittal date and the reasons for the delay. Discussion of the request for additional information (RAI) and RAI response date occurred February 27, 2018.  
The NRC staff need the information identified in the enclosure to this letter. We request that you provide this information within forty-five (45) working day of the date of this letter. Inform us at your earliest convenience, but no later than 2 weeks prior to the due date, if you are not able to provide the information by that date. To assist us in re-scheduling your review, you should include a new proposed submittal date and the reasons for the delay. Discussion of the request for additional information (RAI) and RAI response date occurred February 27, 2018.  


The staff is available to clarify these questions, and if necessary to meet and discuss your proposed responses. If you have any questions regarding this matter, please contact me by e-mail at pamela.longmire@nrc.gov.       Sincerely,  
The staff is available to clarify these questions, and if necessary to meet and discuss your proposed responses. If you have any questions regarding this matter, please contact me by e-mail at pamela.longmire@nrc.gov.
 
Sincerely,  
        /RA/
/RA/
Pamela Longmire, Ph.D.       Spent Fuel Licensing Branch Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards Docket No.: 72-46 CAC No.: 001028 EPID No.: L-2017-FPR-0037  
Pamela Longmire, Ph.D.
Spent Fuel Licensing Branch Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards Docket No.: 72-46 CAC No.: 001028 EPID No.: L-2017-FPR-0037  


==Enclosure:==
==Enclosure:==
Request for Additional Information  
Request for Additional Information  


B. Nick 3 REQUEST FOR ADDITIONAL INFORMATION REGARDING DAIRYLAND POWER COOPERATIVE'S DECOMMISSIONING FUNDING PLAN UPDATE FOR LA CROSSE BOILING WATER REACTOR INDEPENDENT SPENT FUEL STORAGE INSTALLATION, DOCUMENT DATE: MARCH 8, 2018  
B. Nick 3
 
REQUEST FOR ADDITIONAL INFORMATION REGARDING DAIRYLAND POWER COOPERATIVES DECOMMISSIONING FUNDING PLAN UPDATE FOR LA CROSSE BOILING WATER REACTOR INDEPENDENT SPENT FUEL STORAGE INSTALLATION, DOCUMENT DATE: MARCH 8, 2018 DISTRIBUTION:
DISTRIBUTION: SFM R/F JMcKirgan ABowers SHarwell KLois MHenderson BWatson MVaaler  
SFM R/F JMcKirgan ABowers SHarwell KLois MHenderson BWatson MVaaler ADAMS Package No.: ML18067A084 Letter: ML18067A085 Encl.: ML18067A086 C = COVER E = COVER & ENCLOSURE N = NO COPY OFC NMSS/DSFM NMSS/DSFM NMSS/DSFM NAME PLongmire WWheatley via e-mail JMcKirgan DATE 2/27/18 3/6/18 3/8/18 OFFICIAL RECORD COPY}}
 
ADAMS Package No.: ML18067A084   Letter: ML18067A085   Encl.: ML18067A086 C = COVER   E = COVER & ENCLOSURE   N = NO COPY OFC NMSS/DSFM NMSS/DSFM NMSS/DSFM NAME PLongmire WWheatley via e-mail JMcKirgan DATE 2/27/18 3/6/18 3/8/18 OFFICIAL RECORD COPY}}

Latest revision as of 06:45, 6 January 2025

Letter to B. Nick Request for Additional Information Regarding Dairyland Power Cooperatives Decommissioning Funding Plan Update for La Crosse Boiling Water Reactor Independent Spent Fuel Storage Installation
ML18067A085
Person / Time
Site: 07100046
Issue date: 03/08/2018
From: Pamela Longmire
Spent Fuel Licensing Branch
To: Nick B
Dairyland Power Cooperative
Longmire P
Shared Package
ML18067A084 List:
References
CAC 001028, EPID L-2017-FPR-0037
Download: ML18067A085 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 8, 2018 Ms. Barbara Nick President and Chief Executive Officer Dairyland Power Cooperative 3200 East Ave. S., P.O. Box 817 La Crosse, WI 54602-0817

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION REGARDING DAIRYLAND POWER COOPERATIVES DECOMMISSIONING FUNDING PLAN UPDATE FOR LA CROSSE BOILING WATER REACTOR INDEPENDENT SPENT FUEL STORAGE INSTALLATION

Dear Ms. Nick:

By letter dated March 14, 2016, Dairyland Power Cooperative (DPC) submitted for U.S. Nuclear Regulatory Commission (NRC) staff review and approval, a decommissioning funding plan update (DFP Update) for the independent spent fuel storage installation (ISFSI) at La Crosse Boiling Water Reactor (Agencywide Documents Access and Management System Accession No. ML16102A101). The NRC staff reviewed DPCs DFP update for the ISFSI and believes DPCs submittal was not sufficient to meet the intent of the requirement in Title 10 of the Code of Federal Regulations (10 CFR) 72.30(c). The DFP update does not provide sufficient information to allow the NRC to determine that the events listed in 10 CFR 72.30(c)(1)-(4) have been specifically considered.

The NRC staff need the information identified in the enclosure to this letter. We request that you provide this information within forty-five (45) working day of the date of this letter. Inform us at your earliest convenience, but no later than 2 weeks prior to the due date, if you are not able to provide the information by that date. To assist us in re-scheduling your review, you should include a new proposed submittal date and the reasons for the delay. Discussion of the request for additional information (RAI) and RAI response date occurred February 27, 2018.

The staff is available to clarify these questions, and if necessary to meet and discuss your proposed responses. If you have any questions regarding this matter, please contact me by e-mail at pamela.longmire@nrc.gov.

Sincerely,

/RA/

Pamela Longmire, Ph.D.

Spent Fuel Licensing Branch Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards Docket No.: 72-46 CAC No.: 001028 EPID No.: L-2017-FPR-0037

Enclosure:

Request for Additional Information

B. Nick 3

REQUEST FOR ADDITIONAL INFORMATION REGARDING DAIRYLAND POWER COOPERATIVES DECOMMISSIONING FUNDING PLAN UPDATE FOR LA CROSSE BOILING WATER REACTOR INDEPENDENT SPENT FUEL STORAGE INSTALLATION, DOCUMENT DATE: MARCH 8, 2018 DISTRIBUTION:

SFM R/F JMcKirgan ABowers SHarwell KLois MHenderson BWatson MVaaler ADAMS Package No.: ML18067A084 Letter: ML18067A085 Encl.: ML18067A086 C = COVER E = COVER & ENCLOSURE N = NO COPY OFC NMSS/DSFM NMSS/DSFM NMSS/DSFM NAME PLongmire WWheatley via e-mail JMcKirgan DATE 2/27/18 3/6/18 3/8/18 OFFICIAL RECORD COPY