| | Start date | Site | Title | System |
|---|
| ML25268A072 | 24 September 2025 | Salem | License Amendment Request to Modify Salem Generating Station Renewed Facility Operating Licenses in Support of Cobalt-60 Production | Control Rod |
| ML25260A487 | 17 September 2025 | Technical Specifications Task Force 99902042 | Correction to TSTF-585, Revision 5, Revise LCO 3.0.3 to Require Managing Risk | Steam Generator Reactor Coolant System Feedwater Service water Reactor Protection System Main Steam Isolation Valve Auxiliary Feedwater High Pressure Core Spray Residual Heat Removal Circulating Water System Emergency Core Cooling System Decay Heat Removal Main Steam Line |
| ML25169A010 | 17 September 2025 | MIT Nuclear Research Reactor | Examination Report Letter No. 50-020/OL-25-01, Massachusetts Institute of Technology | Control Rod |
| TSTF-25-06, TSTF Response to NRC Request for Additional Information on TSTF-585, Revision 4, Revise LCO 3.0.3 to Require Managing Risk and Transmittal of Revision 5 | 10 September 2025 | Technical Specifications Task Force 99902042 | TSTF Response to NRC Request for Additional Information on TSTF-585, Revision 4, Revise LCO 3.0.3 to Require Managing Risk and Transmittal of Revision 5 | Steam Generator Reactor Coolant System Feedwater Service water Reactor Protection System Main Steam Isolation Valve Auxiliary Feedwater High Pressure Core Spray Residual Heat Removal Circulating Water System Emergency Core Cooling System Decay Heat Removal Main Steam Line |
| RA-25-0014, License Amendment Request to Adopt the Full Spectrum Loss of Coolant Accident Methodology and Axiom Fuel Cladding Topical Reports and Associated 10 CFR 50.46 Exemption Request for Use of Axiom Fuel Cladding | 18 August 2025 | Mcguire Catawba McGuire | License Amendment Request to Adopt the Full Spectrum Loss of Coolant Accident Methodology and Axiom Fuel Cladding Topical Reports and Associated 10 CFR 50.46 Exemption Request for Use of Axiom Fuel Cladding | Steam Generator Reactor Coolant System Feedwater Reactor Protection System Emergency Diesel Generator Auxiliary Feedwater Residual Heat Removal Main Steam Safety Valve Emergency Core Cooling System Main Steam Line Control Rod Containment Spray |
| ML25118A117 | 3 July 2025 | 05000083 | Examination Report Letter No. 50-083/OL-25-01, University of Florida | Reactor Coolant System Reactor Protection System Control Rod |
| ML25085A422 | 22 May 2025 | 05200050 | SDAA - FSER Chapter 16 - Technical Specifications | Steam Generator Reactor Coolant System Feedwater Secondary containment Reactor Protection System Emergency Diesel Generator Main Steam Isolation Valve Primary containment Shutdown Cooling HVAC Reactor Pressure Vessel Residual Heat Removal Automatic Depressurization System Remote shutdown Emergency Core Cooling System Decay Heat Removal Main Steam Line Control Room Envelope Control Rod Main Steam Containment Spray |
| ML25094A166 | 22 May 2025 | 05200050 | SDAA - FSER Chapter 15 - Transient and Accident Analyses | Steam Generator Reactor Coolant System Feedwater Reactor Protection System Main Steam Isolation Valve Residual Heat Removal Emergency Core Cooling System Decay Heat Removal Control Rod |
| ML25086A180 | 2 May 2025 | Fermi | – Amendment 231 to Adopt TSTF-505, TSTF-439, TSTF-591 | Reactor Coolant System Feedwater Service water High Pressure Coolant Injection Reactor Protection System Reactor Core Isolation Cooling Primary containment Main Turbine Shutdown Cooling Reactor Pressure Vessel Core Spray Residual Heat Removal Automatic Depressurization System Standby Liquid Control Emergency Equipment Cooling Water Residual Heat Removal Service Water Steam Jet Air Ejector Emergency Core Cooling System Main Steam Line Safety Relief Valve Moisture Separator Reheater Control Rod Main Turbine Bypass System |
| IR 05000193/2025201 | 30 April 2025 | Rhode Island Atomic Energy Commission | Rhode Island Atomic Energy Commission - Us Nuclear Regulatory Commission Safety Inspection Report No 05000193/2025201 Cover Letter and Enclosure | |
| ML25107A192 | 30 April 2025 | | Accident Sequence Precursor Program 2024 Annual Report | Steam Generator Reactor Coolant System Feedwater Service water Emergency Diesel Generator Auxiliary Feedwater Reactor Core Isolation Cooling Main Transformer Core Spray Residual Heat Removal Residual Heat Removal Service Water Emergency Core Cooling System |
| ML25099A279 | 9 April 2025 | 05200050 | LLC - Part 4, US460 Generic Technical Specifications, Revision 2, Volume 1 - Specifications | Steam Generator Reactor Coolant System Feedwater Main Steam Isolation Valve Reactor Pressure Vessel Emergency Core Cooling System Decay Heat Removal Main Steam Line Control Rod Main Steam |
| IR 05000416/2024302 | 7 April 2025 | Grand Gulf | NRC Examination Report 05000416/2024302 | Secondary containment Service water Reactor Protection System Residual Heat Removal Fuel Pool Cooling and Cleanup Emergency Core Cooling System Containment Spray |
| LR-N25-0015, License Amendment Request (LAR) - Hope Creek Technical Specification Conversion to NUREG-1433, Revision 5, Supplement 2 | 4 April 2025 | Hope Creek | License Amendment Request (LAR) - Hope Creek Technical Specification Conversion to NUREG-1433, Revision 5, Supplement 2 | Reactor Coolant System Feedwater Secondary containment Service water High Pressure Coolant Injection Reactor Protection System Emergency Diesel Generator Reactor Core Isolation Cooling Primary containment Shutdown Cooling Reactor Pressure Vessel Core Spray Residual Heat Removal Reactor Water Cleanup Control Room Emergency Filtration System Automatic Depressurization System Standby Liquid Control Intermediate Range Monitor Emergency Core Cooling System Decay Heat Removal Main Steam Line Control Room Envelope Main Condenser Control Rod Low Pressure Coolant Injection |
| ML25072A013 | 2 April 2025 | Hope Creek | Authorization and Safety Evaluation for Alternative Request No. VR-04 Fourth Inservice Testing Interval Program | Secondary containment Service water |
| ML25029A125 | 26 March 2025 | 05200050 | US460 SDAA Chapter 15 SER | Steam Generator Reactor Coolant System Feedwater Reactor Protection System Main Steam Isolation Valve HVAC Reactor Pressure Vessel Residual Heat Removal Emergency Core Cooling System Decay Heat Removal Control Room Envelope Control Rod Main Steam |
| ML25066A098 | 7 March 2025 | Technical Specifications Task Force 99902042 | Transmittal of TSTF-585, Revision 4, Revise LCO 3.0.3 to Require Managing Risk | Steam Generator Reactor Coolant System Feedwater Service water Reactor Protection System Main Steam Isolation Valve Auxiliary Feedwater High Pressure Core Spray Residual Heat Removal Circulating Water System Emergency Core Cooling System Decay Heat Removal Main Steam Line |
| LR-N25-0029, Response to Request for Additional Information Associated with Emergency License Amendment Request to Extend Completion Time for Inoperable D Emergency Diesel Generator | 2 March 2025 | Hope Creek | Response to Request for Additional Information Associated with Emergency License Amendment Request to Extend Completion Time for Inoperable D Emergency Diesel Generator | Emergency Diesel Generator |
| LR-N25-0027, Emergency License Amendment Request to Extend Completion Time for Inoperable D Emergency Diesel Generator | 27 February 2025 | Hope Creek | Emergency License Amendment Request to Extend Completion Time for Inoperable D Emergency Diesel Generator | Reactor Coolant System High Pressure Coolant Injection Emergency Diesel Generator Reactor Core Isolation Cooling Core Spray Residual Heat Removal Automatic Depressurization System |
| IR 05000416/2024004 | 13 February 2025 | Grand Gulf | Integrated Inspection Report 05000416/2024004 and Notice of Violation | Service water Reactor Protection System Main Steam Isolation Valve Reactor Core Isolation Cooling High Pressure Core Spray Core Spray Residual Heat Removal Standby Liquid Control Control Rod |
| ML25041A106 | 13 February 2025 | Grand Gulf | Integrated Inspection Report 05000416/2024004 and Notice of Violation | Service water Reactor Protection System Main Steam Isolation Valve Reactor Core Isolation Cooling High Pressure Core Spray Core Spray Residual Heat Removal Standby Liquid Control Control Rod |
| ML25042A102 | 12 February 2025 | Vogtle | Integrated Inspection Report 05200025/2024004 and 05200026/2024004 | Steam Generator Reactor Coolant System Feedwater Reactor Protection System Residual Heat Removal Control Room Emergency Ventilation Automatic Depressurization System Main Steam Safety Valve Decay Heat Removal |
| 05000237/LER-2024-001, Containment Cooling Service Water Valve Failure Resulted in a Condition Prohibited by Technical Specifications and Loss of Safety Function | 27 January 2025 | Dresden | Containment Cooling Service Water Valve Failure Resulted in a Condition Prohibited by Technical Specifications and Loss of Safety Function | Service water Low Pressure Coolant Injection |
| NL-24-0325, License Amendment Request: Move Surveillance Requirements from Technical Specifications (TS) 3.3.15 and 3.3.16 Engineered Safety Feature Actuation System (ESFAS) Actuation Logic | 24 January 2025 | Vogtle | License Amendment Request: Move Surveillance Requirements from Technical Specifications (TS) 3.3.15 and 3.3.16 Engineered Safety Feature Actuation System (ESFAS) Actuation Logic | Steam Generator Reactor Coolant System Feedwater Residual Heat Removal Automatic Depressurization System Main Steam Safety Valve Decay Heat Removal Main Steam Line Control Rod |
| SECY-25-0005, Weekly Information Report Week Ending January 10, 2025 | 16 January 2025 | | SECY-25-0005: Weekly Information Report Week Ending January 10, 2025 | Service water Residual Heat Removal Service Water |
| ML24305A241 | 7 January 2025 | | SDAA Chapter 16 Technical Specifications SE with No Open Items | Steam Generator Reactor Coolant System Feedwater Secondary containment Reactor Protection System Emergency Diesel Generator Main Steam Isolation Valve Primary containment Shutdown Cooling HVAC Reactor Pressure Vessel Residual Heat Removal Automatic Depressurization System Remote shutdown Emergency Core Cooling System Decay Heat Removal Main Steam Line Control Room Envelope Control Rod Main Steam Containment Spray |
| ML25002A202 | 6 January 2025 | | Monthly (28-day) Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: January 21, 2025 | Reactor Coolant System Service water Primary containment Shutdown Cooling Residual Heat Removal Standby Liquid Control Residual Heat Removal Service Water |
| RBG-48323, License Amendment Request to Revise the Licensing Basis and Minimum Basin Water Level for the Ultimate Heat Sink | 30 December 2024 | River Bend | License Amendment Request to Revise the Licensing Basis and Minimum Basin Water Level for the Ultimate Heat Sink | Reactor Coolant System Service water Emergency Diesel Generator High Pressure Core Spray Residual Heat Removal Circulating Water System Emergency Core Cooling System Main Steam Line Main Steam |
| ML24312A367 | 20 December 2024 | Hatch | Issuance of Amendments Nos. 324 and 269 Regarding Revision to TS to Adopt Risk-Informed Completion Times for Residual Heat Removal Service Water and Plant Service Water Systems | Service water Primary containment Shutdown Cooling Residual Heat Removal Circulating Water System Residual Heat Removal Service Water |
| IR 05000348/2024012 | 11 December 2024 | Farley | Biennial Problem Identification and Resolution Inspection Report 05000348/2024012 and 05000364/2024012 | Steam Generator Feedwater Service water Auxiliary Feedwater Main Steam Safety Valve Main Steam Containment Spray |
| 05200025/LER-2024-004, Condition Prohibited by Technical Specification Due to Main Steam Safety Valve Lift Pressure Setpoint Drift | 9 December 2024 | Vogtle | Condition Prohibited by Technical Specification Due to Main Steam Safety Valve Lift Pressure Setpoint Drift | Steam Generator Main Steam Safety Valve Main Steam |
| ML24347A006 | 6 December 2024 | Hatch | NRR E-mail Capture - (External_Sender) State of Georgia - Hatch Units 1 and 2 - Revise TS 3.7.1 & 3.7.2 to Adopt Risk-Informed Completion Times for (RHRSW) System, (Psw) System and (UHS) License Amendment Request | Service water Residual Heat Removal Service Water |
| ML24326A135 | 21 November 2024 | 05200050 | Response to NuScale Technical Report Audit Question Number: A-16.3.6.3-2 | Steam Generator Reactor Coolant System Feedwater Main Steam Isolation Valve Reactor Pressure Vessel Emergency Core Cooling System Decay Heat Removal Main Steam |
| ML24317A249 | 18 November 2024 | Hatch Vogtle Farley | Southern Nuclear - Presentation Material Supplement - TS Bases | Steam Generator Reactor Coolant System Feedwater Residual Heat Removal Automatic Depressurization System Main Steam Safety Valve Decay Heat Removal Main Steam Line |
| IR 05000397/2024003 | 12 November 2024 | Columbia | Integrated Inspection Report 05000397/2024003 | Reactor Coolant System Service water Reactor Protection System Reactor Core Isolation Cooling Reactor Recirculation Pump HVAC Core Spray Residual Heat Removal Reactor Water Cleanup |
| ML24249A050 | 3 September 2024 | Hatch | Revision to Technical Requirements Manual, Part 2 of 2 | Feedwater Secondary containment Service water Reactor Protection System Main Steam Isolation Valve Primary containment Core Spray Main Steam Line Rod Worth Minimizer Main Condenser Control Rod Main Steam |
| IR 05000348/2024002 | 12 August 2024 | Farley | – Integrated Inspection Report 05000348-2024002 and 05000364-2024002 and Exercise of Enforcement Discretion | Steam Generator Reactor Coolant System Service water Emergency Diesel Generator Main Steam Isolation Valve Reactor Pressure Vessel Residual Heat Removal Main Steam Safety Valve Main Steam Line Main Steam |
| IR 05000461/2024002 | 9 August 2024 | Clinton | Integrated Inspection Report 05000461/2024002 | Service water Reactor Protection System Emergency Diesel Generator Main Steam Isolation Valve HVAC Residual Heat Removal Standby Gas Treatment System Standby Liquid Control Remote shutdown Control Rod |
| ML24183A108 | 8 August 2024 | Quad Cities | – Issuance of Amendment Nos. 302 and 298 Adoption of Tstf-505, Provide Risk Informed Extended Completion Times – RITSTF Initiative 4b | Reactor Coolant System Feedwater Secondary containment Service water High Pressure Coolant Injection Reactor Protection System Main Steam Isolation Valve Reactor Core Isolation Cooling Primary containment Main Turbine Shutdown Cooling Reactor Pressure Vessel Core Spray Residual Heat Removal Reactor Water Cleanup Control Room Emergency Ventilation Automatic Depressurization System Standby Liquid Control Intermediate Range Monitor Residual Heat Removal Service Water Emergency Core Cooling System Decay Heat Removal Main Steam Line Control Rod Main Steam Low Pressure Coolant Injection |
| LR-N24-0044, Relief Request VR-04 | 6 August 2024 | Hope Creek | Relief Request VR-04 | Secondary containment Service water Main Steam Isolation Valve |
| ML24215A178 | 2 August 2024 | 05200050 | LLC, Response to SDAA Audit Question Number A-16-10 | Steam Generator Reactor Coolant System Feedwater Main Steam Isolation Valve Emergency Core Cooling System Decay Heat Removal Control Rod Main Steam |
| IR 05000261/2024002 | 1 August 2024 | Robinson | Integrated Inspection Report 05000261/2024002 | Steam Generator Reactor Coolant System Feedwater Service water Emergency Diesel Generator Auxiliary Feedwater Residual Heat Removal Main Steam Safety Valve Control Room Envelope |
| ML24176A120 | 29 July 2024 | Grand Gulf | Issuance of Amendment 234 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b | Service water Reactor Protection System Reactor Core Isolation Cooling Primary containment Shutdown Cooling High Pressure Core Spray Residual Heat Removal Automatic Depressurization System Standby Liquid Control Emergency Core Cooling System Decay Heat Removal Main Steam Line Safety Relief Valve Control Room Envelope Containment Spray Low Pressure Coolant Injection |
| IR 05000298/2024002 | 25 July 2024 | Cooper | Integrated Inspection Report 05000298/2024002 | Reactor Coolant System Secondary containment Service water High Pressure Coolant Injection Reactor Protection System Emergency Diesel Generator Reactor Core Isolation Cooling Main Turbine Core Spray Residual Heat Removal Automatic Depressurization System Residual Heat Removal Service Water Control Rod Main Steam |
| ML24141A007 | 3 July 2024 | Oregon State University | Examination Report Letter No. 50-243/OL-24-01, Oregon State University | Control Rod |
| NL-24-0238, RIPE License Amendment Request to Change Containment Air Temperature Actions, Supplemental Information | 14 June 2024 | Farley | RIPE License Amendment Request to Change Containment Air Temperature Actions, Supplemental Information | Reactor Coolant System Core Spray Residual Heat Removal Control Room Emergency Filtration System |
| ML24052A209 | 6 June 2024 | 05000200 | Examination Report Letter No. 50-020/OL-24-01, Massachusetts Institute of Technology | Control Rod |
| ML24113A005 | 20 May 2024 | University of California - Irvine | Examination Report Letter No. 50-326/OL-24-02, University of California-Irvine | Control Rod |
| ML24081A007 | 16 May 2024 | River Bend | Issuance of Amendment No. 213 Revision to Technical Specifications to Adopt TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b | Service water Reactor Protection System Reactor Core Isolation Cooling Primary containment Shutdown Cooling High Pressure Core Spray Residual Heat Removal Automatic Depressurization System Standby Liquid Control Emergency Core Cooling System Main Steam Line Safety Relief Valve Control Room Envelope Control Rod |
| NL-24-0195, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water. | 7 May 2024 | Hatch | Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water. | Service water High Pressure Coolant Injection Reactor Core Isolation Cooling Residual Heat Removal Residual Heat Removal Service Water |
| ML24191A332 | 6 May 2024 | Callaway | Final Safety Analysis Report Rev. OL-27 and Technical Specification Bases Rev. 25, Implemented Change Notice Log | Steam Generator Main Steam Line Containment Spray |
| ML24191A310 | 6 May 2024 | Callaway | Final Safety Analysis Report Rev. OL-27 and Technical Specification Bases Rev. 25, Chapter 3.7, Plant Systems | Steam Generator Feedwater Service water Emergency Diesel Generator Main Steam Isolation Valve Auxiliary Feedwater Residual Heat Removal Control Room Emergency Ventilation Main Steam Safety Valve Main Steam Line Control Room Envelope Main Steam |
| ML24191A288 | 6 May 2024 | Callaway | Final Safety Analysis Report Rev. OL-27 and Technical Specification Bases Rev. 25, Operating License Amendment Index | Steam Generator Reactor Coolant System Feedwater Service water Emergency Diesel Generator Main Steam Isolation Valve Auxiliary Feedwater Residual Heat Removal Control Room Emergency Ventilation Fuel Pool Cooling and Cleanup Main Steam Safety Valve Emergency Core Cooling System Decay Heat Removal Main Steam Line Control Room Envelope Control Rod Main Steam Containment Spray |
| ML24191A327 | 6 May 2024 | Callaway | Final Safety Analysis Report Rev. OL-27 and Technical Specification Bases Rev. 25, Chapter B 3.7, Plant Systems | Steam Generator Reactor Coolant System Feedwater Service water Emergency Diesel Generator Main Steam Isolation Valve Auxiliary Feedwater HVAC Residual Heat Removal Control Room Emergency Ventilation Fuel Pool Cooling and Cleanup Circulating Water System Main Steam Safety Valve Remote shutdown Emergency Core Cooling System Decay Heat Removal Main Steam Line Control Room Envelope Main Condenser Main Steam Containment Spray |
| IR 05000298/2024001 | 3 May 2024 | Cooper | Integrated Inspection Report 05000298/2024001 | Feedwater Secondary containment Service water Reactor Protection System Emergency Diesel Generator Main Steam Isolation Valve Primary containment Main Turbine HVAC Residual Heat Removal Standby Liquid Control Residual Heat Removal Service Water Rod Worth Minimizer Control Rod |
| ML24052A345 | 25 April 2024 | University of Lowell | Examination Report Letter No. 50-223/OL-24-01, University of Massachusetts - Lowell | Control Rod |
| L-2024-063, Periodic Update of the Updated Final Safety Analysis Report, Chapter 10, Steam and Power Conversion (Redacted) | 23 April 2024 | Point Beach | Periodic Update of the Updated Final Safety Analysis Report, Chapter 10, Steam and Power Conversion (Redacted) | Steam Generator Reactor Coolant System Feedwater Service water Main Steam Isolation Valve Auxiliary Feedwater HVAC Residual Heat Removal Circulating Water System Main Steam Safety Valve Steam Jet Air Ejector Decay Heat Removal Main Steam Line Moisture Separator Reheater Main Condenser Auxiliary Feed Water Main Steam Extraction steam |
| ML24100A440 | 9 April 2024 | Hatch | NRR E-mail Capture - (External_Sender) RAI - Hatch, Units 1 and 2, Revise Technical Specifications to Adopt Extended RICTs for RHRSW and Psw Systems LAR | Service water Residual Heat Removal Residual Heat Removal Service Water |
| ML24102A269 | 5 April 2024 | National Bureau of Standards Reactor | National Institute of Standards and Technology Reactor (Nbsr) - Operations Report No. 74 for the the Period January 1, 2023 to December 31, 2023 | |
| IR 05000193/2024201 | 3 April 2024 | Rhode Island Atomic Energy Commission | Rhode Island Atomic Energy Commission - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000193/2024201 | |