Forwards Equipment Qualification Manual Discussion Highlighting Methodology & SER Discrepancies, & Environ Qualification of Safety Related Electrical Equipment, Vols 1-6
ML20031G927
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 10/12/1981
From: Crouse R
TOLEDO EDISON CO.
To: Stolz J
Office of Nuclear Reactor Regulation
Shared Package
ML20031G928 List:
References
TAC-42508, NUDOCS 8110260226
Download: ML20031G927 (1)


Text

- - - - - - - - - -

TOLEDO O

%mm EDISON x

/

Docket No. 50-346 Rcano P. CnouSE vc. Penident License No. NPF-3 NWWF (4191259-5221 Serial No. 750 October 12, 1981 Director of Nuclear Reactor Regulation Attention:

Mr. John F. Stolz Operating Reactor Branch No. 4 Division of Operating Reactors United States Nuclear Regulatory Commission Washington, D.C.

20555

Dear Mr. Stolz:

The Safety Evaluation Report (SER) for the Environmental Qualification of Safety Related Electrical Equipment was issued June 5, 1981 (Log No.

737).

The report addressed cnly the safety related electrical equipment potentially exposed to a harsh environment resulting from postulated

[

}

Loss of Coolant Accident (LOCA) or high energy line break (HELB). A (j

NRC meeting followed on the issues with all utilities July 7-10, 1981.

This letter (10 copies) constitutes the response to the SER and the meeting activities for the Davis-Besse Nuclear Power Station Unit No. 1.

This submittal is divided into two parts.

The first is " Equipment Qualificaticn Manual Diset 1sion Highlighting Methodology and SER Descrepanciea".

This document describes the details of the equipment review as well as responding to the SER deficiencies.

A cross reference system is provided to ease the transition from the SER deficiency to the specific response. The second part of the submittal includes six (6) volumes of the DB-1 Environmental Qualification Manual.

This updates in its entirely all systems and component information submitted tmder the 1E Bulletin 79-01B effort on this subject.

As a result of our detailed evaluation, several actielties will be continuing to finalize certified qualification on some equipment as identified on the appropriate equipment summary works'ect.

However, aone of the NF-defined deficiencies has altered our overall finding supporting the continued safe operation at Davis-Besse.

Very truly yours, i

6%f

\\

f C'

RPC:TJM: lab I

^

cc:

DB-1 NRC Resident Inspector

/

THE TOLEDO EDISON COMPANY EDISON PLAZA 300 MADISON AVENUE TOLEDO, OHIO 43652 3

8110260226 811012 PDR ADOCK 05000346 4

rp PDR

-.__-__ - _________-