ML19344F295

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-445/78-05 & 50-446/78-05 on 780321-24. Noncompliance Noted:Vendor Quality Documentation Unavailable
ML19344F295
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 04/05/1978
From: Crossman W, Randy Hall, Renee Taylor
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML19344F268 List:
References
50-445-78-05, 50-445-78-5, 50-446-78-05, 50-446-78-5, NUDOCS 8009150093
Download: ML19344F295 (5)


See also: IR 05000445/1978005

Text

c

-@

, [*

.. U

O-

^

f,

.

.

,,

~ '[.(~

U. S. flVCLEAR REGULATORY COMMISSIO!!

.

OFFICE OF ItiSPECTI0il Atl0 EtiFORCEMEilT

REGI0ii IV.

Report tio.- 50-445/78-05; 56-446/78-05

Docket flo. S0-445; 50-446

Category A2

!

.

' Licensee: Texas Utilities Generating Company

. 2001 Bryan Tower

,

Dallas, Texas

75201

i,

Facility tiame: comanche Peak, Units 1 & 2

Inspection at: Comanche Peak Steam Electric Station, Glen Rose, Texas

.

-Inspection conducted: March 21-24,1978

h

.%.

Inspector:

/! Ib'u

/

  1. h7,F

R.'G.

lay

r, Reactor Inspector, Projects Section

Dat4

'

Other

Accompanying

m

Personnel:

R. E. Hall, Chief Engineering Support Section

.

.

R. J. Garcia, Engineering Aide, Engineering Support 3ection

Approved:

of/of/78

'

_

W. A. Crossman, Chief, Projects Section

Date

Inspection Summary:

inspection on March 21-24,1978 (Report tio. 50-445/78-05: 50-446/78-05)

,

Areas inspected:

Routine, unannounced inspection involving inspection of

reactor vessel storage; containment steel structures; and operations of

the on-site pipe fabrication shop. The inspection involved twenty-seven-

inspector-hours on' site by one tiRC inspector.

3esults:

Of the three areas inspected, no items of noncompliance or

.

deviations were found in t.o; ene apparent item of noncompliance was found

.

in one area (infraction

. failure to follow' pipe fabrication procedures -

paragraph 5).

-

!

=

ib *

oh

-

e

_

-

p

\\'

.__

__

,

_

..

.y..

g.=

-

.. ;

O

' e'~.

a-

P

1 67.

'

'

e .i

-DETAILS

<

.

1.

Pe~rsons Contacted

.

Principal Licensee Employees

  • J. B. George, TUSI Project General Manager
  • R. G. Tolson,.TUGC0 Site QA Supervisor

.

  • J.- T. Merritt, TUSI Resident Manager
  • B. J. Murray, TUSI Engineering Supervisor

'

  • R.~ V. Fleck, TUGC0/G&H QA Planner

-

-
  • J. V. Hawkins, TUGC0/G&H QA Site Representative

A. H. Boren, TUGC0 QA Engineer

.

A. Vega, TUGC0 Senior lA Engineer

C. Biggs, TUGC0 Lead QA Engineer-Systems Compliance

Other Personnel

'

,

  • U. D. Douglas, B&R Project Manager

t

  • B. C. Scott, B&R Site QA Manager
  • R. M. Osborne, B&R Senior QC Supervisor

K. Silverthorne, B&R QC Mechanical Engineer

,

G. Osborn, B&R QC Mechanical-Inspector

-

The inspector also interviewed other contractor ecployees during

"

the course of the inspection. They included-QA/QC and craft labor

personnel.

.

.

  • denotes those present at the exit interview.

,

l

2 .-

Reactor Vessel Storace

[

The HRC inspector inspected the Unit 1 stored reactor vessel to

l

,

determine whether requirements are being met as set forth by Brown

1

& Root Storage and Maintenance Requirement MEI-10-424 for " Reactor

. M.

Vessel and Associated Equipment," which in turn references Westing-

.

house fluclear Stear. System Component Receiving and Storage Criteria,

.

Mechanical Equipment Section, Shop Order 105. The vessel was found

1

to be sealed and the desiccant indicator showing a proper dry con-

dition.

-

,

.

l

'

The NRC inspector reviewed 507, of QC inspection records covering

reactor vessel storage to' ascertain conformance with Brown & Root

Quality Instruction CP-QCI-1.6-ll, " Safety Related Mechanical and

'

Electrical Equipment Storage Maintenance," which implements the

l

maintenance inspection requirements of Brown & Root Quality Pro-

)

cedure CP-QCP-1.6, "QC Surveillance of Mechanical, Electrical and

1

'

fpp

-.

-

-2-

.

...x.

. . _ . - -

.

..

-..

,

a

-

n

m

'

i, .

-,

'

.

,

Instrumentation Equipment Maintenance," and ANSI M45.2.2.

The

- -

-

,

recogds cover the period from receipt of the vessel on June 20,

1977._/ , to the current time.

No items of noncompliance or deviations were identified.

..

3.

Containment Steel Structures

Taa NRC inspector chose Valve. Isolation Tanks Cpl-RHATVT-02 and

cpl-CTATVT-02 as representative of steel containment structures

important to safety.

The two tanks are utilized with two addi-

tional like tanks to enclose the containment isolation valves

leading from the containment drain sumps to the residual heat

removal and containment spray systems, respectively and are an

extension of the containment pressure boundary although not with-

in the containment.

The tanks were purchased under order CP-0069A, with four supple-

.ments.

Engineering Specification 2323-M-69A (Revision 2) is a

part of the purchase document which in turn references the ASME

B&PV Code,Section III,1974 to the Summer 74 Addenda. .The Sub-

sections involved are NC for the vessel and NF for the support

s truc tures .

'

The NRC inspector reviewed vendor documentation for six selected

--

portions of each tank and +.he related support structure.

The

>===

. _ . .

certified material tast reoorts for each item of material satisfied

requirements of the applicable material specifications and the

nondestructive test repo; ts indicated acceptable weld quality for

the various welded joints involved.

The data package also included

the ASME Code certification and a " Quality Releace," signed by G&H

quality assurance vendor surveillance personnel.

It was noted that

the actual weld radiographs and vendor work process documents were

not available at the site as required by Engineering Specification

2323-M-69A although the " Quality Release" document indicated each

had been reviewed prior to release.

Brown & Root Material / Equip-

ment Control History Report No.1747, dated August 2,1976, ack-

nowledged receipt of the equipment, but noted that necessary quality

documentation had not been received.

The report was subsequently

cleared upon receipt of the documentation.

It could not be ascer-

tained from report 1747 whether the radiographs and work process

documents had been received and subsequently misfiled or never

received at all.

This will be considered an unresolved item pending an opportunity

to review the missing radiographs and documents.

,

i

1/ inspection Report No. 50-445/77-07

-3-

.

. . - . - .

- . . .

,

.

L...

p

n

m

~,

/

  • 4.

Potential 10 CFR 50.55(o) Itcm

-

.

,

During the course of the inspection, the licensee became aware

of an incident involving the Unit 1 pressurizer and so informed

the IE inspector.

The incident occurred in railroad yards near

Tallahassee, Florida when a wheel of the rail car transporting

the pressurizer broke causing the car to derail.

It is under-

stood that the pressurizer was not dislodged from the car and

appeared to suffer no damage. The licensee will inspect the

pressurizer upon receipt at the site and will furnish RIV with

information relative to its condition. The IE inspector will

follow up on this item during a subsequent inspection.

5.

Pipe Fabrication Shoo

The IE inspector conducted an examination of the activities of

the Brown & Root pipe fabrication shop observing material control,

documentation generation, welding, identification and temporary

' storage of partially and completely fabricated pipe spools.

The IE inspector noted that one partially fabricated pipe section

for a safety related system, consisting of three inch schedule

160 stainless steel material, had been counterbored preparatory

-

to welding. The transition between the counterbored diameter and

the original pipe inside diameter at the end of the counterbore

appeared to be unusually steep.

P""""

It was subsequently established that no prect'sion measuring equip-

ment was available at the site to measure the transition angle

and that complete reliance was being placed on the ccnfiguration

of the cutting tool to provide

,e correct angle.

Examination

of the cutting tool, coupled with simple computations, established

that the tool could not provide transition angles of 30 or less

as required by Construction Procedure 35-1195-MCP-7, Revision 1,

and the ASME B&PV Code except in a few nontypical instances where

very shallow counterbore cuts were, being made.

.

Failure to counterbore the pipe as required by Construction Proce-

dure 35-1195-MCP-7 represents noncompliance with the requirements

in Criterion V of Appendix B to 10 CFR 50.

6.

Unresolved Items

.

-

Unresolved items are matters about which more information is required

in order to ascertain whether they are acceptable items, items of non-

,

compliance, or deviations. An unresolved item disclosed during the

inspection is discussed in paragraph 3 and will hereafter be referred

to as " Unavailable Vendor Quality Documentation."

.

-4-

__

_

_

--

.

1

7

m

g.

7-3,

-

, ,

,

7

.

m

-

. .

. .

f.-

l$ <. . , . .

.

.

.

.

'

,

.

e **

7;

' Exit Interview

.

,

-The inspector met with. licensee representatives (denoted in para-

Ae

graph .1) at the conclusion of the inspection on !! arch 24, 1978.

The. inspector summarized the scope and findings of the inspection.

t

'

.The' licensee' representatives had no questions relative to the-

..p-

findings.

,

9

e

I

,

D

.

s

, *

.

O

-

I

.

.

.

eu.

h.iS i'

W

'

.

i

e

S

.4

e

h

b

!

e

6

[.

. ~ , -.

z t.ffb

-

-

.

1

-5-

'

-l

.)

=

...

..

.

-

...

. - _ -

.

.

. _ .

.,

-.

..

'

,

. , . _

_

m.-

.i. _

,