{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION uly 23, 2018
{{#Wiki_filter:July 23, 2018


==SUBJECT:==
==SUBJECT:==
SURRY POWER STATION - NUCLEAR REGULATORY COMMISSION INTEGRATED INSPECTION REPORT 05000280/2018002 AND 05000281/2018002
SURRY POWER STATION - NUCLEAR REGULATORY COMMISSION  
 
INTEGRATED INSPECTION REPORT 05000280/2018002 AND  
 
05000281/2018002


==Dear Mr. Stoddard:==
==Dear Mr. Stoddard:==
Line 37: Line 41:


Sincerely,
Sincerely,
/RA/
/RA/  
Steven D. Rose, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket Nos.: 50-280, 50-281 License Nos.: DPR-32, DPR-37
 
Steven D. Rose, Chief  
 
Reactor Projects Branch 4  
 
Division of Reactor Projects  
 
Docket Nos.: 50-280, 50-281 License Nos.: DPR-32, DPR-37  


===Enclosure:===
===Enclosure:===
IR 05000280/2018002, 05000281/2018002
IR 05000280/2018002, 05000281/2018002  


==Inspection Report==
==Inspection Report==
Docket Numbers: 50-280, 50-281 License Numbers: DPR-32, DPR-37 Report Numbers: 05000280/2018002 and 05000281/2018002 Enterprise Identifier: I-2018-002-0046 Licensee: Virginia Electric and Power Company (VEPCO)
Docket Numbers:
Facility: Surry Power Station, Units 1 and 2 Location: 5850 Hog Island Road Surry, VA 23883 Inspection Dates: April 1, 2018 - June 30, 2018 Inspectors: P. McKenna, Senior Resident Inspector C. Read, Resident Inspector A. Butcavage, Reactor Inspector (71111.08)
50-280, 50-281  
R. Carrion, Senior Reactor Inspector (71111.08)
 
C. Fontana, Emergency Preparedness Inspector (71114, 71151)
License Numbers:
S. Sanchez, Senior Emergency Preparedness Inspector (71114, 71151)
DPR-32, DPR-37  
J. Tornow, Physical Security Inspector (EP Trainee)
 
J. Walker, Emergency Preparedness Inspector (Trainee)
Report Numbers:
Approved By: S. Rose, Chief Reactor Projects Branch 4 Division of Reactor Projects Enclosure
05000280/2018002 and 05000281/2018002  
 
Enterprise Identifier: I-2018-002-0046  
 
Licensee:
Virginia Electric and Power Company (VEPCO)  
 
Facility:
Surry Power Station, Units 1 and 2  
 
Location:
5850 Hog Island Road  
 
Surry, VA 23883  
 
Inspection Dates:
April 1, 2018 - June 30, 2018  
 
Inspectors:
P. McKenna, Senior Resident Inspector  
 
C. Read, Resident Inspector  
 
A. Butcavage, Reactor Inspector (71111.08)  
 
R. Carrion, Senior Reactor Inspector (71111.08)  
 
C. Fontana, Emergency Preparedness Inspector (71114, 71151)  
 
S. Sanchez, Senior Emergency Preparedness Inspector (71114, 71151)  
 
J. Tornow, Physical Security Inspector (EP Trainee)  
 
J. Walker, Emergency Preparedness Inspector (Trainee)  
 
Approved By:
S. Rose, Chief  
 
Reactor Projects Branch 4  
 
Division of Reactor Projects  
 
Enclosure  


=SUMMARY=
=SUMMARY=
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring licensees performance by conducting a quarterly integrated inspection at Surry Power Station, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. NRC and self-revealed findings, violations, and additional items are summarized in the table below.
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring licensees performance by conducting a quarterly integrated inspection at Surry Power Station, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. NRC and self-revealed findings, violations, and additional items are summarized in the table below.


List of Findings and Violations Failure to Follow Preventative Maintenance Procedure Results in Additional Failures of Emergency Bus Undervoltage and Degraded Voltage Relays Cornerstone Significance                     Cross-cutting Aspect               Report Section Initiating       Green NCV                   P.3 - Resolution                  71152 Events            05000281/2018002-01 Opened/Closed An NRC-identified Green NCV of Surry Technical Specification (TS) 6.4.D was identified for the failure to follow procedure ER-AA-102, Preventative Maintenance Program, which resulted in the Unit 2 H emergency bus degraded voltage (DV) relay failure on March 13, 2018, and the Unit 2 J emergency bus under voltage (UV) relay failure on May 21, 2018, while the unit was operating at rated thermal power (RTP).
===List of Findings and Violations===
Failure to Follow Preventative Maintenance Procedure Results in Additional Failures of Emergency Bus Undervoltage and Degraded Voltage Relays Cornerstone Significance Cross-cutting Aspect Report Section Initiating Events Green NCV 05000281/2018002-01 Opened/Closed P.3 - Resolution 71152 An NRC-identified Green NCV of Surry Technical Specification (TS) 6.4.D was identified for the failure to follow procedure ER-AA-102, Preventative Maintenance Program, which resulted in the Unit 2 H emergency bus degraded voltage (DV) relay failure on March 13, 2018, and the Unit 2 J emergency bus under voltage (UV) relay failure on May 21, 2018, while the unit was operating at rated thermal power (RTP).


=PLANT STATUS=
=PLANT STATUS=
Line 68: Line 122:


==REACTOR SAFETY==
==REACTOR SAFETY==
==71111.01 - Adverse Weather Protection==
===Summer Readiness (1 Sample)===
The inspectors evaluated summer readiness of offsite and alternate alternating current (AC) power systems.


==71111.01 - Adverse Weather Protection Summer Readiness==
==71111.04 - Equipment Alignment==
{{IP sample|IP=IP 71111.01|count=1}}
===Partial Walkdown (4 Samples)===
 
The inspectors evaluated summer readiness of offsite and alternate alternating current (AC)power systems.
 
==71111.04 - Equipment Alignment Partial Walkdown==
{{IP sample|IP=IP 71111.04|count=4}}
 
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
: (1) Alternative alternating current (AAC) diesel prior to planned #2 emergency diesel generator (EDG) monthly performance test, on April 9, 2018
: (1) Alternative alternating current (AAC) diesel prior to planned #2 emergency diesel generator (EDG) monthly performance test, on April 9, 2018
Line 83: Line 134:
: (4) Unit 1 auxiliary feedwater (AFW) system valves inside containment, on May 22, 2018
: (4) Unit 1 auxiliary feedwater (AFW) system valves inside containment, on May 22, 2018


==71111.05AQ - Fire Protection Annual/Quarterly Quarterly Inspection==
==71111.05AQ - Fire Protection Annual/Quarterly==
{{IP sample|IP=IP 71111.05AQ|count=5}}
===Quarterly Inspection (5 Samples)===
 
The inspectors evaluated fire protection program implementation in the following selected areas:
The inspectors evaluated fire protection program implementation in the following selected areas:
: (1) AAC Diesel Building, on April 9, 2018
: (1) AAC Diesel Building, on April 9, 2018
Line 93: Line 143:
: (5) Fuel Building, on June 21, 2018
: (5) Fuel Building, on June 21, 2018


==71111.06 - Flood Protection Measures Internal Flooding==
==71111.06 - Flood Protection Measures==
{{IP sample|IP=IP 71111.06|count=1}}
===Internal Flooding (1 Sample)===
 
The inspectors evaluated internal flooding mitigation protections in the Unit 1 and Unit 2 turbine buildings with the component cooling heat exchanger (CCHX) service water (SW)jumper modification in place between the two turbine buildings.
The inspectors evaluated internal flooding mitigation protections in the Unit 1 and Unit 2 turbine buildings with the component cooling heat exchanger (CCHX) service water (SW)jumper modification in place between the two turbine buildings.


Line 108: Line 157:


UT-18-006, 4/24/18 (Observed)d) Summary No. S1.LSS.0006, Work Order No. 38103811311/NDER17-203, Component ID 11448-WMKS-1105B13 / 3-CH-4 / 0-19, Pipe to Elbow, Report No. UT-18-007, 4/24/18 (Observed)e) Summary No. S1.LSS.0020, Work Order No. 38203874699/NDER18-109, Component ID 11448-WMKS-1105B13 / 3-CH-4 / 0-18A, Elbow to Pipe, Report No. UT-18-008, 4/24/18 (Observed)
UT-18-006, 4/24/18 (Observed)d) Summary No. S1.LSS.0006, Work Order No. 38103811311/NDER17-203, Component ID 11448-WMKS-1105B13 / 3-CH-4 / 0-19, Pipe to Elbow, Report No. UT-18-007, 4/24/18 (Observed)e) Summary No. S1.LSS.0020, Work Order No. 38203874699/NDER18-109, Component ID 11448-WMKS-1105B13 / 3-CH-4 / 0-18A, Elbow to Pipe, Report No. UT-18-008, 4/24/18 (Observed)
: (3) Visual (VT)a) Summary No. S1.B15.80.001, Component ID, 11448-WMKS-RC-R-1.1/N/A/1-RC-R-1, Reactor Bottom Mounted Instrumentation Penetration Nozzles, 4/24/18 (Reviewed)b) Summary No. S1.F1.30.193, VT-3 Visual Inspection of Component Support ID111448-WMKS-0112E1/18-CC-19/1-CC-H018, 4/25/18 (Reviewed)c) Summary No. S1.F1.30.272, VT-3 Visual Inspection of Component Support ID
: (3) Visual (VT)a) Summary No. S1.B15.80.001, Component ID, 11448-WMKS-RC-R-1.1/N/A/1-RC-R-1, Reactor Bottom Mounted Instrumentation Penetration Nozzles, 4/24/18 (Reviewed)b) Summary No. S1.F1.30.193, VT-3 Visual Inspection of Component Support ID111448-WMKS-0112E1/18-CC-19/1-CC-H018, 4/25/18 (Reviewed)c) Summary No. S1.F1.30.272, VT-3 Visual Inspection of Component Support ID  


===11448-WMKS-0112L1/6-CC-101/1-CC-H015 (Reviewed)
===11448-WMKS-0112L1/6-CC-101/1-CC-H015 (Reviewed)
Line 115: Line 164:
The Inspectors evaluated the licensees boric acid control program performance, performed a walk-down inspection of the reactor containment building and completed a sample review of the latest inspection results for the lower reactor vessel head penetration area.
The Inspectors evaluated the licensees boric acid control program performance, performed a walk-down inspection of the reactor containment building and completed a sample review of the latest inspection results for the lower reactor vessel head penetration area.


==71111.11 - Licensed Operator Requalification Program and Licensed Operator Performance Operator Requalification==
==71111.11 - Licensed Operator Requalification Program and Licensed Operator Performance==
{{IP sample|IP=IP 71111.11|count=1}}
Operator Requalification===
{{IP sample|IP=IP 11448|count=1}}


The inspectors observed and evaluated a simulator scenario involving a failed open pressurizer relief valve, tornado in the switchyard which caused a loss of offsite power, a large break loss of coolant accident (LOCA) with the failure of the low head safety injection (LHSI) pumps to auto start, and a loss of SW flow through the recirculation spray heat exchangers (RSHXs) due to the failure of all RSHX SW inlet isolation valves to open with an alert declaration, on June 6, 2018.
The inspectors observed and evaluated a simulator scenario involving a failed open pressurizer relief valve, tornado in the switchyard which caused a loss of offsite power, a large break loss of coolant accident (LOCA) with the failure of the low head safety injection (LHSI) pumps to auto start, and a loss of SW flow through the recirculation spray heat exchangers (RSHXs) due to the failure of all RSHX SW inlet isolation valves to open with an alert declaration, on June 6, 2018.


Operator Performance ===
===Operator Performance (1 Sample)===
{{IP sample|IP=IP 11448|count=1}}
The inspectors observed and evaluated licensed operator performance in the main control room during 1-GOP-2.7, Unit Shutdown Power Decrease from Allowable Power to Unit Offline for Refueling Outage, on April 20, 2018; and 1-OP-RX-009, Dilution to Critical Conditions Following Refueling, on May 30, 2018.
The inspectors observed and evaluated licensed operator performance in the main control room during 1-GOP-2.7, Unit Shutdown Power Decrease from Allowable Power to Unit Offline for Refueling Outage, on April 20, 2018; and 1-OP-RX-009, Dilution to Critical Conditions Following Refueling, on May 30, 2018.


==71111.12 - Maintenance Effectiveness Quality Control==
==71111.12 - Maintenance Effectiveness==
{{IP sample|IP=IP 71111.12|count=1}}
===Quality Control (1 Sample)===
 
The inspectors evaluated maintenance and quality control activities associated with the following equipment performance issues:
The inspectors evaluated maintenance and quality control activities associated with the following equipment performance issues:
: (1) Machinery equipment room (MER) - 3 charging (CH) SW piping replacement
: (1) Machinery equipment room (MER) - 3 charging (CH) SW piping replacement
Line 174: Line 222:
The inspectors evaluated refueling outage 1R28 activities from April 21, 2018 to May 31, 2018.
The inspectors evaluated refueling outage 1R28 activities from April 21, 2018 to May 31, 2018.


==71111.22 - Surveillance Testing The inspectors evaluated the following surveillance tests:
==71111.22 - Surveillance Testing==
Routine==
The inspectors evaluated the following surveillance tests:  
 
===Routine===
{{IP sample|IP=IP 71111.22|count=4}}
{{IP sample|IP=IP 71111.22|count=4}}
: (1) 1-OSP-SW-008, "SW Flow Test of RSHXs 1-RS-E-1B and 1-RS-E-1C," Revision 6 (OTO1), on April 21, 2018
: (1) 1-OSP-SW-008, "SW Flow Test of RSHXs 1-RS-E-1B and 1-RS-E-1C," Revision 6 (OTO1), on April 21, 2018
: (2) 1-OPT-ZZ-001, ESF Actuation with Undervoltage and Degraded Voltage 1H Bus, Revision 42, on April 23, 2018
: (2) 1-OPT-ZZ-001, ESF Actuation with Undervoltage and Degraded Voltage 1H Bus, Revision 42, on April 23, 2018
: (3) 1-OPT-SI-009, Refueling Test of the LHSI Check Valves to the Hot Legs, Revision 17, on April 27, 2018
: (3) 1-OPT-SI-009, Refueling Test of the LHSI Check Valves to the Hot Legs, Revision 17, on April 27, 2018
: (4) 1-OPT-SI-026, Safety Injection Train A Master Relay and Reset Timer Test, Revisions 3 and 4, on May 8, 2018
: (4) 1-OPT-SI-026, Safety Injection Train A Master Relay and Reset Timer Test, Revisions 3 and 4, on May 8, 2018  


===In-service (1 Sample)===
===In-service (1 Sample)===
: (1) 0-OPT-SW-002, Emergency Service Water Pump 1-SW-P-1B Performance Test, Revision 65, on May 31, 2018
: (1) 0-OPT-SW-002, Emergency Service Water Pump 1-SW-P-1B Performance Test, Revision 65, on May 31, 2018  


===Containment Isolation Valve (1 Sample)===
===Containment Isolation Valve (1 Sample)===
Line 208: Line 258:
The inspectors evaluated the maintenance of the emergency preparedness program, on April 9, 2018 through April 13, 2018.
The inspectors evaluated the maintenance of the emergency preparedness program, on April 9, 2018 through April 13, 2018.


==71114.06 - Drill Evaluation Emergency Planning (EP) Drill==
==71114.06 - Drill Evaluation==
{{IP sample|IP=IP 71114.06|count=1}}
===Emergency Planning (EP) Drill (1 Sample)===
 
The inspectors evaluated a licensee EP drill involving a dropped fuel assembly in the fuel building, a loss of all feedwater, and a steam generator tube rupture concurrent with failed fuel and a stuck open main steam safety valve resulting in a General Emergency declaration, on June 19,
The inspectors evaluated a licensee EP drill involving a dropped fuel assembly in the fuel building, a loss of all feedwater, and a steam generator tube rupture concurrent with failed fuel and a stuck open main steam safety valve resulting in a General Emergency declaration, on June 19,


==OTHER ACTIVITIES - BASELINE==
==OTHER ACTIVITIES - BASELINE==
===71151 - Performance Indicator Verification


===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below for the period from April 1, 2017 through March 31, 2018. ===
The inspectors verified licensee performance indicators submittals listed below for the period from April 1, 2017 through March 31, 2018.===
{{IP sample|IP=IP 71151|count=6}}
{{IP sample|IP=IP 71151|count=6}}
: (1) Unit 1 and Unit 2 Safety System Functional Failures
: (1) Unit 1 and Unit 2 Safety System Functional Failures
: (2) Unit 1 and Unit 2 Reactor Coolant System (RCS) Specific Activity
: (2) Unit 1 and Unit 2 Reactor Coolant System (RCS) Specific Activity
: (3) Unit 1 and Unit 2 RCS Leak Rate The inspectors verified licensee performance indicators submittals listed below for the period from April 1, 2017 through December 31, 2017. (3 Samples)
: (3) Unit 1 and Unit 2 RCS Leak Rate  
 
The inspectors verified licensee performance indicators submittals listed below for the period from April 1, 2017 through December 31, 2017. (3 Samples)
: (1) EP01: Drill & Exercise Performance
: (1) EP01: Drill & Exercise Performance
: (2) EP02: Emergency Response Organization Drill Participation
: (2) EP02: Emergency Response Organization Drill Participation
: (3) EP03: Alert & Notification System Reliability
: (3) EP03: Alert & Notification System Reliability


==71152 - Problem Identification and Resolution Annual Follow-up of Selected Issues==
==71152 - Problem Identification and Resolution==
{{IP sample|IP=IP 71152|count=1}}
===Annual Follow-up of Selected Issues (1 Sample)===
 
The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:
The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:
: (1) Emergency Bus Degraded and Under Voltage Relays (CRs 1009999, 1030874, and 1084436)
: (1) Emergency Bus Degraded and Under Voltage Relays (CRs 1009999, 1030874, and 1084436)


==INSPECTION RESULTS==
==INSPECTION RESULTS==
Observation                                       71152 The inspectors performed a detailed review of the corrective action from the following condition reports:
Observation 71152 The inspectors performed a detailed review of the corrective action from the following condition reports:
* CR 1009999, Unanticipated Starting of EDG #2 During Undervoltage (UV) Degraded Voltage (DV) Testing Procedure
* CR 1009999, Unanticipated Starting of EDG #2 During Undervoltage (UV) Degraded Voltage (DV) Testing Procedure
* CR 1030874, 1J Emergency Bus UV/DV Panel Light Out
* CR 1030874, 1J Emergency Bus UV/DV Panel Light Out
* CR 1084472, Evaluation Required of Emergency Bus UV/DV Relays The inspectors chose this sample because of two additional failures of emergency bus UV/DV relays. A Unit 2 H emergency bus DV relay failed during 2-PT-2.33A, Emergency Bus Undervoltage and Degraded Voltage Test H Train on March 13, 2018 (CR 1091928) and a Unit 2 J emergency bus UV relay failed during 2-PT-2.33B on May 21, 2018. The inspectors identified a Non-cited Violation (NCV) during this sample which is detailed in the next section of this report.
* CR 1084472, Evaluation Required of Emergency Bus UV/DV Relays  
 
The inspectors chose this sample because of two additional failures of emergency bus UV/DV relays. A Unit 2 H emergency bus DV relay failed during 2-PT-2.33A, Emergency Bus Undervoltage and Degraded Voltage Test H Train on March 13, 2018 (CR 1091928) and a Unit 2 J emergency bus UV relay failed during 2-PT-2.33B on May 21, 2018. The inspectors identified a Non-cited Violation (NCV) during this sample which is detailed in the next section of this report.
 
Failure to follow Preventative Maintenance Procedure Results in Additional Failures of Emergency Bus Undervoltage and Degraded Voltage Relays Cornerstone Significance Cross-cutting Aspect Report Section Initiating Events


Failure to follow Preventative Maintenance Procedure Results in Additional Failures of Emergency Bus Undervoltage and Degraded Voltage Relays Cornerstone            Significance                            Cross-cutting      Report Aspect            Section Initiating Events      Green NCV                               P.3 - Resolution 71152 05000281/2018002-01 Opened/Closed An NRC-identified Green NCV of Surry Technical Specification (TS) 6.4.D was identified for the failure to follow procedure ER-AA-102, Preventative Maintenance Program, which resulted in the Unit 2 H emergency bus degraded voltage (DV) relay failure on March 13, 2018, and the Unit 2 J emergency bus under voltage (UV) relay failure on May 21, 2018, while the unit was operating at rated thermal power (RTP).
Green NCV 05000281/2018002-01 Opened/Closed P.3 - Resolution 71152 An NRC-identified Green NCV of Surry Technical Specification (TS) 6.4.D was identified for the failure to follow procedure ER-AA-102, Preventative Maintenance Program, which resulted in the Unit 2 H emergency bus degraded voltage (DV) relay failure on March 13, 2018, and the Unit 2 J emergency bus under voltage (UV) relay failure on May 21, 2018, while the unit was operating at rated thermal power (RTP).


=====Description:=====
=====Description:=====
Line 253: Line 308:
Corrective Actions: The licensees immediate corrective action was to replace the Unit 2 B phase H emergency bus DV relay. Additionally, the licensee made a CA assignment for engineering to review previous corrective actions associated with emergency bus UV and DV relays to determine if actions taken were timely and if additional actions were required based on this issue.
Corrective Actions: The licensees immediate corrective action was to replace the Unit 2 B phase H emergency bus DV relay. Additionally, the licensee made a CA assignment for engineering to review previous corrective actions associated with emergency bus UV and DV relays to determine if actions taken were timely and if additional actions were required based on this issue.


Corrective Action Reference: CR 1091928
Corrective Action Reference: CR 1091928  


=====Performance Assessment:=====
=====Performance Assessment:=====
Line 294: Line 349:
1-OP-SI-001A, Safety Injection System Alignment, Rev. 19
1-OP-SI-001A, Safety Injection System Alignment, Rev. 19
Condition Reports (*NRC Identified)
Condition Reports (*NRC Identified)
1094952*       1095732*     1096350*       1097151*       1097647     1097650
1094952*
1098085*       1098224*     1099074*       1100035*
1095732*
1096350*
1097151*
1097647
1097650
1098085*
1098224*
1099074*
1100035*
Drawings
Drawings
11448-FB-046D Sh. 2, Flow/Valve Operating Numbers Diagram Lube Oil System - Station
11448-FB-046D Sh. 2, Flow/Valve Operating Numbers Diagram Lube Oil System - Station
Line 317: Line 380:
1-FS-FP-137, Containment Unit 1 Elevation (-)27 Feet - 7 Inches, Rev. 1
1-FS-FP-137, Containment Unit 1 Elevation (-)27 Feet - 7 Inches, Rev. 1
1-EPT-0902-01, Fire Protection Low Pressure CO2 System Puff Test, Rev. 31
1-EPT-0902-01, Fire Protection Low Pressure CO2 System Puff Test, Rev. 31
0-FS-FP-225, Alternate AC Diesel Room - Construction Site Elevation 35 Ft, Rev. 1
0-FS-FP-225, Alternate AC Diesel Room - Construction Site Elevation 35 Ft, Rev. 1  


IP 71111.06: Flood Protection
IP 71111.06: Flood Protection
Line 366: Line 429:
WM-4372, Work Order 38103811311 Weld Map, Charging System Line No. 3-CH-251-1502,
WM-4372, Work Order 38103811311 Weld Map, Charging System Line No. 3-CH-251-1502,
Design Change No. SU-17-00109, 4/20/18
Design Change No. SU-17-00109, 4/20/18
WM-4166, Work Order 38103611539 Weld Map, Line No. 3/4 RC-67-1502, 9/26/16
WM-4166, Work Order 38103611539 Weld Map, Line No. 3/4 RC-67-1502, 9/26/16  


Work Orders/Work Requests:
Work Orders/Work Requests:
Line 413: Line 476:
Framatome Inc. Engineering Information Record, 51-9282567-000, Surry Unit 1 - 1R28 ECT
Framatome Inc. Engineering Information Record, 51-9282567-000, Surry Unit 1 - 1R28 ECT
Inspection Plan
Inspection Plan
Framatome Inc. Engineering Information Record, 51- 9282741- 000 - Qualified Eddy Current
Framatome Inc. Engineering Information Record, 51-9282741- 000 - Qualified Eddy Current
Examination Techniques for Surry Unit 1, 1R28
Examination Techniques for Surry Unit 1, 1R28  


NDE Personnel Qualification and Certification Records for 15 individuals
NDE Personnel Qualification and Certification Records for 15 individuals
Line 428: Line 491:
Weld Data Record, Work Order 38103611539, Weld No. 3, Valve 01-RC-139, 11/8/16
Weld Data Record, Work Order 38103611539, Weld No. 3, Valve 01-RC-139, 11/8/16
Weld Data Record, Work Order 38103611539, Weld No. 5, Valve 01-RC-139, 11/8/16
Weld Data Record, Work Order 38103611539, Weld No. 5, Valve 01-RC-139, 11/8/16
Welder Performance Qualification (WPQ), for Rev. 8 of Technique 801- one person
Welder Performance Qualification (WPQ), for Rev. 8 of Technique 801-one person
IP 71111.11: Licensed Operator Requalification Program
IP 71111.11: Licensed Operator Requalification Program
Procedures
Procedures
Line 437: Line 500:
IP 71111.12: Maintenance Effectiveness
IP 71111.12: Maintenance Effectiveness
Condition Reports
Condition Reports
1091963       1098836
1091963
1098836
Work Orders
Work Orders
203874980           38203875045
203874980
203875045
Other Documents
Other Documents
DC SU-18-00112, Charging SW Fire Protection Pipe Replacement, Rev. 0
DC SU-18-00112, Charging SW Fire Protection Pipe Replacement, Rev. 0
Line 458: Line 523:
IP 711111.15: Operability Determinations and Functionality Assessments
IP 711111.15: Operability Determinations and Functionality Assessments
Procedures
Procedures
0-FS-FP-211, Emergency Service Water Pump House - Low Level Elevation 18 Feet, Rev. 3
0-FS-FP-211, Emergency Service Water Pump House - Low Level Elevation 18 Feet, Rev. 3  


DNES-AA-MOV-1001, Motor Operated Valve Diagnostic Test Preparation and Evaluation,
DNES-AA-MOV-1001, Motor Operated Valve Diagnostic Test Preparation and Evaluation,
Line 464: Line 529:
OP-AA-102, Operability Determination, Rev. 15
OP-AA-102, Operability Determination, Rev. 15
Condition Reports
Condition Reports
1091963       1094780         1097862
1091963
1094780
1097862
Drawings
Drawings
11448-FM-071B, Flow/Valve Operating Numbers Diagram Circulating and Service water
11448-FM-071B, Flow/Valve Operating Numbers Diagram Circulating and Service water
Line 471: Line 538:
Rev. 53
Rev. 53
Work Orders
Work Orders
38102221431           38203874699          38203874700          38203874701
38102221431
203874699
203874700
203874701
Other Documents
Other Documents
Calculation ME-0166, Appendix R Fire SWSOPA, Rev. 2
Calculation ME-0166, Appendix R Fire SWSOPA, Rev. 2
Line 492: Line 562:
Cabinets, Rev. 0
Cabinets, Rev. 0
Condition Reports
Condition Reports
1097528       1097542         1098226       1098566
1097528
1097542
1098226
1098566
Drawings
Drawings
11448-ESK-6BY, Elementary Diagram 480V Circuits Motor Operated Valves 01-FW-MOV-
11448-ESK-6BY, Elementary Diagram 480V Circuits Motor Operated Valves 01-FW-MOV-
Line 501: Line 574:
Rev. 0
Rev. 0
Work Orders
Work Orders
38103835060           38103786256           38103862320           38203874701
38103835060
203874745
38103786256
38103862320
203874701
203874745  


Other Documents
Other Documents
Line 523: Line 599:
Rev. 58
Rev. 58
1-OPT-ZZ-001, ESF Actuation with Undervoltage and Degraded Voltage 1H Bus, Rev. 42
1-OPT-ZZ-001, ESF Actuation with Undervoltage and Degraded Voltage 1H Bus, Rev. 42
DNES-AA-MOV-1001, Motor Operated Valve Diagnostic Test Preparation and Evaluation, Rev.
DNES-AA-MOV-1001, Motor Operated Valve Diagnostic Test Preparation and Evaluation, Rev.  
 
Condition Reports
Condition Reports
1095507       1096445       1096973         1097129     1097208       1098022
1095507
1098650
1096445
1096973
1097129
1097208
1098022
1098650  
 
Work Orders
Work Orders
203874699           38203874700          38203874701        38203877019
203874699
38103753291           38103753299           38103753307       38103753315
203874700
38103753323           38103753331           38103775433       38103771661
203874701
38103788540           38103867760           38103863466       38103629393
203877019
38103753291
38103753299
38103753307
38103753315
38103753323
38103753331
38103775433
38103771661
38103788540
38103867760
38103863466
38103629393
Drawings
Drawings
11448-FM-088B, Flow/Valve Operating Numbers Diagram Chemical & Volume Control System,
11448-FM-088B, Flow/Valve Operating Numbers Diagram Chemical & Volume Control System,
Line 547: Line 642:
IP 71111.20: Refueling and Other Outage Activities
IP 71111.20: Refueling and Other Outage Activities
Procedures
Procedures
1-GOP-1.8, Unit Startup, Hot Shutdown to Max Allowable Power, Rev. 40
1-GOP-1.8, Unit Startup, Hot Shutdown to Max Allowable Power, Rev. 40  


1-GOP-2.7, Unit Shutdown, Power Decrease from Allowable Power to Unit Offline for Refueling
1-GOP-2.7, Unit Shutdown, Power Decrease from Allowable Power to Unit Offline for Refueling
Line 557: Line 652:
MA-AA-102, Foreign Material Exclusion, Rev. 22
MA-AA-102, Foreign Material Exclusion, Rev. 22
Condition Reports
Condition Reports
1095133         1095607       1095784       1096592       1096323       1096319
1095133
1097151         1096349       1096386       1096874       1096989       1097149
1095607
1096810         1096339       1096350       1097304       1098578       1098605
1095784
1098650         1098758       1098933
1096592
1096323
1096319
1097151
1096349
1096386
1096874
1096989
1097149
1096810
1096339
1096350
1097304
1098578
1098605
1098650
1098758
1098933
IP 71111.22: Surveillance Testing
IP 71111.22: Surveillance Testing
Procedures
Procedures
Line 591: Line 703:
FEMA Analysis of the Prompt Alert & Notification System for Surry Power Station, dated 12/8/87
FEMA Analysis of the Prompt Alert & Notification System for Surry Power Station, dated 12/8/87
Notification System Quality Assurance Verification Final Report, dated 9/30/87
Notification System Quality Assurance Verification Final Report, dated 9/30/87
Sample of 2017 & 2018 siren testing results
Sample of 2017 & 2018 siren testing results  


Condition Reports
Condition Reports
Line 615: Line 727:
EPIP-4.03, Dose Assessment Team Controlling Procedure, Rev. 21
EPIP-4.03, Dose Assessment Team Controlling Procedure, Rev. 21
EAL Technical Basis Document, Rev. 4
EAL Technical Basis Document, Rev. 4
Corporate Emergency Plan, Rev. 16
Corporate Emergency Plan, Rev. 16  
 
Records and Data
Records and Data
Assessment of On-Shift Emergency Response Organization Staffing Capabilities, NEI 10-05,
Assessment of On-Shift Emergency Response Organization Staffing Capabilities, NEI 10-05,
Line 637: Line 750:
CR 1072620, Unsuccessful Drill and Exercise Performance (DEP) opportunity
CR 1072620, Unsuccessful Drill and Exercise Performance (DEP) opportunity
CR 1090846, CR not submitted when ERO staff positions dropped below five
CR 1090846, CR not submitted when ERO staff positions dropped below five
CR 1094415, Discrepancies identified with ERO response times (NRC-identified)
CR 1094415, Discrepancies identified with ERO response times (NRC-identified)  


71114.04: Emergency Action Level and Emergency Plan Changes
71114.04: Emergency Action Level and Emergency Plan Changes
Line 684: Line 797:
Records and Data
Records and Data
Surry Power Station, ACE #: CA 3060983, CR 1072620, Unsuccessful Drill and Exercise
Surry Power Station, ACE #: CA 3060983, CR 1072620, Unsuccessful Drill and Exercise
Performance (DEP) opportunity, dated 6/29/17
Performance (DEP) opportunity, dated 6/29/17  


Radiological Status Form, CERC run based on MIDAS projection for Surry Drill, run #4 (K run)
Radiological Status Form, CERC run based on MIDAS projection for Surry Drill, run #4 (K run)
Line 734: Line 847:
CR 1072416, SJUN17DR DEP potentially incorrect IAW EP-AA-103 related to PAR
CR 1072416, SJUN17DR DEP potentially incorrect IAW EP-AA-103 related to PAR
CR 1074327, TSC communication equipment issues
CR 1074327, TSC communication equipment issues
CR 1074436, SJUL17BE ERDS data from simulator not visible to NRC
CR 1074436, SJUL17BE ERDS data from simulator not visible to NRC  


CR 1074531, SJUL17BE Objective 20 was upgraded as NOT MET overall for the exercise
CR 1074531, SJUL17BE Objective 20 was upgraded as NOT MET overall for the exercise
Line 762: Line 875:
EPIP-2.01, Notification of State and Local Governments, Rev. 44
EPIP-2.01, Notification of State and Local Governments, Rev. 44
Condition Reports
Condition Reports
1099973         1100214         1100460       1101008
1099973
1100214
1100460
1101008
IP 71151: Performance Indicator Verification
IP 71151: Performance Indicator Verification
Procedures
Procedures
Line 780: Line 896:
CR 1051157, ARCOS wed-based callout unavailable due to internet outage
CR 1051157, ARCOS wed-based callout unavailable due to internet outage
CR 1058590, Operations personnel NRC Communicator qualifications delayed
CR 1058590, Operations personnel NRC Communicator qualifications delayed
CR 1074339, ARCOS activation notifications received 12 minutes after declaration of Alert
CR 1074339, ARCOS activation notifications received 12 minutes after declaration of Alert  


Other Documents
Other Documents
Line 797: Line 913:
WM-AA-101, Work Order Planning, Rev. 14
WM-AA-101, Work Order Planning, Rev. 14
Condition Reports
Condition Reports
1000999       1030874     1084436       1084472       1091928     1097966
1000999
1030874
1084436
1084472
1091928
1097966
1098297
1098297
Work Orders
Work Orders
3810359162           38103658614         38103660563         38103843782
3810359162
38103658614
38103660563
38103843782
Other Documents
Other Documents
ACE CA3009200, Unanticipated Starting of EDG #2 during Undervoltage/Degraded Voltage
ACE CA3009200, Unanticipated Starting of EDG #2 during Undervoltage/Degraded Voltage
Line 807: Line 931:
RTE P-SURR-343477, Create Preventative Maintenance for Unit 2 H Bus UV/DV Two out of
RTE P-SURR-343477, Create Preventative Maintenance for Unit 2 H Bus UV/DV Two out of
Three Relays, 01/29/2016
Three Relays, 01/29/2016
Enclosure
}}
}}

Latest revision as of 17:14, 5 January 2025

Nuclear Regulatory Commission Integrated Inspection Report 05000280/2018002 and 05000281/2018002
ML18204A019
Person / Time
Site: Surry  Dominion icon.png
Issue date: 07/23/2018
From: Steven Rose
NRC/RGN-II/DRP/RPB4
To: Stoddard D
Virginia Electric & Power Co (VEPCO)
References
IR 20180002
Download: ML18204A019 (26)


Text

July 23, 2018

SUBJECT:

SURRY POWER STATION - NUCLEAR REGULATORY COMMISSION

INTEGRATED INSPECTION REPORT 05000280/2018002 AND

05000281/2018002

Dear Mr. Stoddard:

On June 30, 2018, the United States Nuclear Regulatory Commission (NRC) completed an inspection at your Surry Power Station, Units 1 and 2. On July 11, 2018, the NRC inspectors discussed the results of this inspection with Mr. F. Mladen and other members of your staff.

The results of this inspection are documented in the enclosed inspection report.

NRC inspectors documented one finding of very low safety significance (Green) in this report.

This finding involved a violation of NRC requirements. The NRC is treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2.a of the NRC Enforcement Policy.

If you contest the violations or significance of any of this NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN.: Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at the Surry Power Station.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; and the NRC Resident Inspector at the Surry Power Station. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Steven D. Rose, Chief

Reactor Projects Branch 4

Division of Reactor Projects

Docket Nos.: 50-280, 50-281 License Nos.: DPR-32, DPR-37

Enclosure:

IR 05000280/2018002, 05000281/2018002

Inspection Report

Docket Numbers:

50-280, 50-281

License Numbers:

DPR-32, DPR-37

Report Numbers:

05000280/2018002 and 05000281/2018002

Enterprise Identifier: I-2018-002-0046

Licensee:

Virginia Electric and Power Company (VEPCO)

Facility:

Surry Power Station, Units 1 and 2

Location:

5850 Hog Island Road

Surry, VA 23883

Inspection Dates:

April 1, 2018 - June 30, 2018

Inspectors:

P. McKenna, Senior Resident Inspector

C. Read, Resident Inspector

A. Butcavage, Reactor Inspector (71111.08)

R. Carrion, Senior Reactor Inspector (71111.08)

C. Fontana, Emergency Preparedness Inspector (71114, 71151)

S. Sanchez, Senior Emergency Preparedness Inspector (71114, 71151)

J. Tornow, Physical Security Inspector (EP Trainee)

J. Walker, Emergency Preparedness Inspector (Trainee)

Approved By:

S. Rose, Chief

Reactor Projects Branch 4

Division of Reactor Projects

Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring licensees performance by conducting a quarterly integrated inspection at Surry Power Station, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. NRC and self-revealed findings, violations, and additional items are summarized in the table below.

List of Findings and Violations

Failure to Follow Preventative Maintenance Procedure Results in Additional Failures of Emergency Bus Undervoltage and Degraded Voltage Relays Cornerstone Significance Cross-cutting Aspect Report Section Initiating Events Green NCV 05000281/2018002-01 Opened/Closed P.3 - Resolution 71152 An NRC-identified Green NCV of Surry Technical Specification (TS) 6.4.D was identified for the failure to follow procedure ER-AA-102, Preventative Maintenance Program, which resulted in the Unit 2 H emergency bus degraded voltage (DV) relay failure on March 13, 2018, and the Unit 2 J emergency bus under voltage (UV) relay failure on May 21, 2018, while the unit was operating at rated thermal power (RTP).

PLANT STATUS

Unit 1 operated at or near rated thermal power from the beginning of the inspection period until April 21, 2018, when it was shut down to begin a planned refueling outage (RFO). It remained offline until May 31, 2018, when the main turbine was synchronized to the grid. On June 2, 2018, the unit reached rated thermal power and operated there for the remainder of the inspection period.

Unit 2 operated at or near rated thermal power for the entire inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Summer Readiness (1 Sample)

The inspectors evaluated summer readiness of offsite and alternate alternating current (AC) power systems.

71111.04 - Equipment Alignment

Partial Walkdown (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Alternative alternating current (AAC) diesel prior to planned #2 emergency diesel generator (EDG) monthly performance test, on April 9, 2018
(2) Unit 1 A train residual heat removal (RHR) system after pump and motor replacement, on May 17, 2018
(3) Unit 1 C safety injection (SI) accumulator after check valve repairs, on May 22, 2018
(4) Unit 1 auxiliary feedwater (AFW) system valves inside containment, on May 22, 2018

71111.05AQ - Fire Protection Annual/Quarterly

Quarterly Inspection (5 Samples)

The inspectors evaluated fire protection program implementation in the following selected areas:

(1) AAC Diesel Building, on April 9, 2018
(2) Carbon dioxide suppression system testing for Unit 1 Cable Vault and Cable Tunnel, on April 11, 2018
(3) Unit 1 Containment Building, on May 9, 2018
(4) Auxiliary Building 27 foot elevation, on June 21, 2018
(5) Fuel Building, on June 21, 2018

71111.06 - Flood Protection Measures

Internal Flooding (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the Unit 1 and Unit 2 turbine buildings with the component cooling heat exchanger (CCHX) service water (SW)jumper modification in place between the two turbine buildings.

71111.08 - Inservice Inspection Activities

The inspectors evaluated pressurized water reactor non-destructive testing by reviewing the following examinations from April 23 - 27, 2018:

(1) Liquid Penetrant Test (PT)a) PT-18-020, Work Order 38103811311/NDER17-203, Weld Number 0-17, ASME Code Class 2, Pipe to Tee, Charging Crosstie 5/3/18 (Reviewed)b) BOP-PT-18-046, Work Order 38103811311, Final Weld Number 017, ASME Code Class 2, 3-CH-251-1502, 4/26/18 (Observed)c) BOP-PT-16-193, Work Order 38103611539, Final Welds 3&5, Valve 01-RC-139, 11/8/16 (Reviewed)
(2) Ultrasonic (UT)a) Summary No.17-203, Work Order No. 3810311311, Weld 0-17 In Area Ground for ISI Prep, UT Thickness Examination, ASME Class 2, 4/25/18 (Observed)b) Summary No. S1.LSS.0003, Work Order No. 38103811311/NDER17-203, Component ID 11448-WMKS-1105B5 / 3-CH-3 / 2-E, Tee to Pipe, Report No.

UT-18-005, 4/24/18 (Observed)c) Summary No. S1.LSS.0005, Work Order No. 38103811311/NDER17-203, Component ID 11448-WMKS-1105B13 / 3-CH-4 / 0-20, Tee to Pipe, Report No.

UT-18-006, 4/24/18 (Observed)d) Summary No. S1.LSS.0006, Work Order No. 38103811311/NDER17-203, Component ID 11448-WMKS-1105B13 / 3-CH-4 / 0-19, Pipe to Elbow, Report No. UT-18-007, 4/24/18 (Observed)e) Summary No. S1.LSS.0020, Work Order No. 38203874699/NDER18-109, Component ID 11448-WMKS-1105B13 / 3-CH-4 / 0-18A, Elbow to Pipe, Report No. UT-18-008, 4/24/18 (Observed)

(3) Visual (VT)a) Summary No. S1.B15.80.001, Component ID, 11448-WMKS-RC-R-1.1/N/A/1-RC-R-1, Reactor Bottom Mounted Instrumentation Penetration Nozzles, 4/24/18 (Reviewed)b) Summary No. S1.F1.30.193, VT-3 Visual Inspection of Component Support ID111448-WMKS-0112E1/18-CC-19/1-CC-H018, 4/25/18 (Reviewed)c) Summary No. S1.F1.30.272, VT-3 Visual Inspection of Component Support ID

===11448-WMKS-0112L1/6-CC-101/1-CC-H015 (Reviewed)

(4) Eddy Current Testing (ECT)a) Steam Generator A; Tubes R038/C027, R016/C068, R017/C068, R016/C069, and R017/C069 (Reviewed.)

The Inspectors evaluated the licensees boric acid control program performance, performed a walk-down inspection of the reactor containment building and completed a sample review of the latest inspection results for the lower reactor vessel head penetration area.

71111.11 - Licensed Operator Requalification Program and Licensed Operator Performance

Operator Requalification===

The inspectors observed and evaluated a simulator scenario involving a failed open pressurizer relief valve, tornado in the switchyard which caused a loss of offsite power, a large break loss of coolant accident (LOCA) with the failure of the low head safety injection (LHSI) pumps to auto start, and a loss of SW flow through the recirculation spray heat exchangers (RSHXs) due to the failure of all RSHX SW inlet isolation valves to open with an alert declaration, on June 6, 2018.

Operator Performance (1 Sample)

The inspectors observed and evaluated licensed operator performance in the main control room during 1-GOP-2.7, Unit Shutdown Power Decrease from Allowable Power to Unit Offline for Refueling Outage, on April 20, 2018; and 1-OP-RX-009, Dilution to Critical Conditions Following Refueling, on May 30, 2018.

71111.12 - Maintenance Effectiveness

Quality Control (1 Sample)

The inspectors evaluated maintenance and quality control activities associated with the following equipment performance issues:

(1) Machinery equipment room (MER) - 3 charging (CH) SW piping replacement

71111.13 - Maintenance Risk Assessments and Emergent Work Control

The inspectors evaluated the risk assessments for the following planned and emergent work activities:

(1) Unit 1 and Unit 2 risk while the "A" main control room (MCR) and emergency switchgear room (ESGR) chilled water system was tagged out for an emergent modification and compensatory fire watches where in place in MER-3 for unprotected CHSW fiberglass piping, on April 18, 2018.
(2) Unit 1 and Unit 2 risk with "A" reserve station service transformer (RSST) planned maintenance, unplanned maintenance on the "C" RSST tap changer motor, and Unit 1 in refueling outage (RFO), on April 23, 2018.
(3) Unit 2 risk during #1 EDG 18 month maintenance outage during the Unit 1 RFO, on April 30, 2018.
(4) Unit 2 risk while the Unit 1 "B" station battery was being replaced, the ESGR flood dike was not installed, and Unit 1 was in a RFO, on May 14, 2018.
(5) Unit 1 and Unit 2 risk with one service air (SA) compressor out for planned maintenance and both of the remaining SA compressors tripped due to high temperatures, and the site in a hot weather alert, on June 19, 2018.

71111.15 - Operability Determinations and Functionality Assessments

The inspectors evaluated the following operability determinations and functionality assessments:

(1) CRs 1094780 and 1091963, Unprotected Appendix "R" CHSW piping in MER-3
(2) Unit 1 charging cross-connection modification performed in three phases during Unit 1 RFO
(3) CR 1071016, Unit 1 Anchor Darling double disc gate valves after RFO testing and modifications
(4) Low level intake structure fire protection
(5) CR1097862, 1-SW-MOV-104B, RSHX SW inlet isolation valve degrading trend after valve seat and valve operator replacement

71111.18 - Plant Modifications

The inspectors evaluated the following permanent modifications:

(1) Design Change Package (DCP) SU-16-00109, Surry Unit 1 AFW MOV Hot Short Resolution
(2) DCP SU-17-00109, Surry Unit 1 Hot Short Resolution Charging Cross-tie Relocation

71111.19 - Post Maintenance Testing

The inspectors evaluated the following post maintenance tests:

(1) 0-OPT-ZZ-008, ASME System Pressure Test, Revision 11, and radiography film review after the completion of the charging cross-tie modification, on April 29, May 14, and May 18, 2018
(2) 1-OPT-EG-009, Number 1 Emergency Diesel Generator Major Maintenance Operability Test, Revision 58, following the completion of the #1 EDG 18 month maintenance package, on May 3, 2018
(3) DNES-AA-MOV-1001, Motor-Operated Diagnostic Test Preparation and Evaluation, Revision 1, following stem and disc arm replacement on 1-SI-MOV-1863A, Low Head SI to Alternative High Head SI isolation valve, on May 9, 2018
(4) 1-EPT-0106-07, Main Station Battery 1B Performance Test, Revision 21, following the Unit 1 "B" Main battery cell replacement, on May 16, 2018
(5) 1-OPT-SI-002, Refueling Test of the Low Head Safety Injection Check Valves to the Cold Legs, Revision 25, following maintenance on 1-SI-79, Loop A Cold Leg Injection Downstream Check Valve, on May 17, 2018
(6) 1-OPT-FW-002, Motor Driven Auxiliary Feedwater Pump 1-FW-P-3B Performance Test, Revision 36, following motor replacement, on May 21, 2018
(7) 1-PT-8.2, Reactor Protection Logic, Revision 25, following the replacement of reactor protection system relay 1-RLY-P10-XA, on May 29, 2018

71111.20 - Refueling and Other Outage Activities

The inspectors evaluated refueling outage 1R28 activities from April 21, 2018 to May 31, 2018.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Routine

(1) 1-OSP-SW-008, "SW Flow Test of RSHXs 1-RS-E-1B and 1-RS-E-1C," Revision 6 (OTO1), on April 21, 2018
(2) 1-OPT-ZZ-001, ESF Actuation with Undervoltage and Degraded Voltage 1H Bus, Revision 42, on April 23, 2018
(3) 1-OPT-SI-009, Refueling Test of the LHSI Check Valves to the Hot Legs, Revision 17, on April 27, 2018
(4) 1-OPT-SI-026, Safety Injection Train A Master Relay and Reset Timer Test, Revisions 3 and 4, on May 8, 2018

In-service (1 Sample)

(1) 0-OPT-SW-002, Emergency Service Water Pump 1-SW-P-1B Performance Test, Revision 65, on May 31, 2018

Containment Isolation Valve (1 Sample)

(1) Type C leak rate testing on Penetration 112, Containment Instrument Air Compressor Suction Piping, on May 11, 2018

71114.02 - Alert and Notification System Testing

The inspectors evaluated the maintenance and testing of the alert and notification system, on April 9, 2018 through April 13, 2018.

71114.03 - Emergency Response Organization Staffing and Augmentation System

The inspectors evaluated the readiness Emergency Response Organization, on April 9, 2018 through April 13, 2018.

71114.04 - Emergency Action Level and Emergency Plan Changes

The inspectors evaluated submitted Emergency Action Level and Emergency Plan changes, on April 9, 2018 through April 13, 2018. This evaluation does not constitute NRC approval.

71114.05 - Maintenance of Emergency Preparedness

The inspectors evaluated the maintenance of the emergency preparedness program, on April 9, 2018 through April 13, 2018.

71114.06 - Drill Evaluation

Emergency Planning (EP) Drill (1 Sample)

The inspectors evaluated a licensee EP drill involving a dropped fuel assembly in the fuel building, a loss of all feedwater, and a steam generator tube rupture concurrent with failed fuel and a stuck open main steam safety valve resulting in a General Emergency declaration, on June 19,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below for the period from April 1, 2017 through March 31, 2018.===

(1) Unit 1 and Unit 2 Safety System Functional Failures
(2) Unit 1 and Unit 2 Reactor Coolant System (RCS) Specific Activity
(3) Unit 1 and Unit 2 RCS Leak Rate

The inspectors verified licensee performance indicators submittals listed below for the period from April 1, 2017 through December 31, 2017. (3 Samples)

(1) EP01: Drill & Exercise Performance
(2) EP02: Emergency Response Organization Drill Participation
(3) EP03: Alert & Notification System Reliability

71152 - Problem Identification and Resolution

Annual Follow-up of Selected Issues (1 Sample)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Emergency Bus Degraded and Under Voltage Relays (CRs 1009999, 1030874, and 1084436)

INSPECTION RESULTS

Observation 71152 The inspectors performed a detailed review of the corrective action from the following condition reports:

  • CR 1009999, Unanticipated Starting of EDG #2 During Undervoltage (UV) Degraded Voltage (DV) Testing Procedure
  • CR 1030874, 1J Emergency Bus UV/DV Panel Light Out
  • CR 1084472, Evaluation Required of Emergency Bus UV/DV Relays

The inspectors chose this sample because of two additional failures of emergency bus UV/DV relays. A Unit 2 H emergency bus DV relay failed during 2-PT-2.33A, Emergency Bus Undervoltage and Degraded Voltage Test H Train on March 13, 2018 (CR 1091928) and a Unit 2 J emergency bus UV relay failed during 2-PT-2.33B on May 21, 2018. The inspectors identified a Non-cited Violation (NCV) during this sample which is detailed in the next section of this report.

Failure to follow Preventative Maintenance Procedure Results in Additional Failures of Emergency Bus Undervoltage and Degraded Voltage Relays Cornerstone Significance Cross-cutting Aspect Report Section Initiating Events

Green NCV 05000281/2018002-01 Opened/Closed P.3 - Resolution 71152 An NRC-identified Green NCV of Surry Technical Specification (TS) 6.4.D was identified for the failure to follow procedure ER-AA-102, Preventative Maintenance Program, which resulted in the Unit 2 H emergency bus degraded voltage (DV) relay failure on March 13, 2018, and the Unit 2 J emergency bus under voltage (UV) relay failure on May 21, 2018, while the unit was operating at rated thermal power (RTP).

Description:

On March 13, 2018, the licensee was testing DV relay, 2-EP-27BX-2HDUP-2H, B phase H emergency bus DV relay as part of procedure 2-PT-2.33A, Emergency Bus Undervoltage and Degraded Protection Test H Train. When the relay was tested as part of the procedure, it failed to fully change state. The relay was declared inoperable and Unit 2 entered an unplanned TS limiting condition for operation (LCO) to place the affected reactor protection system (RPS) channel in trip within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. The relay was replaced with Unit 2 operating at RTP on March 14, 2018.

Additionally, on May 21, 2018, the licensee tested UV relay, 2-EP-27BX-2JDUP-2J2, the B phase J emergency bus UV relay as part of procedure 2-PT-2.33B, Emergency Bus Undervoltage and Degraded Protection Test J Train. This relay failed to re-energize as expected during the test. The relay was declared inoperable and Unit 2 entered an unplanned TS LCO to place the affected reactor protection system (RPS) channel in trip within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. The relay was replaced with Unit 2 operating at RTP on May 22, 2018.

The DV and UV relays that failed were Westinghouse, Model ARD440UR relays which are normally energized. The licensee had a previous failure of this type of relay on September 16, 2015 when a Unit 2 H bus UV relay failed during 2-PT-2.33A testing (CR 1009999).

This failure caused a loss of the Unit 2 H bus and the auto start of the number 2 EDG. As part of the corrective action for this failure, the licensee conducted an apparent cause evaluation (ACE) and concluded that all emergency bus UV and DV relays had no preventative maintenance (PM) to periodically replace the relays. The installed relays were five years past their Electrical Power Research Institute (EPRI) Guide 3002000541 end of life of 20 years. Independent lab testing of the failed relay indicated prolonged thermal damage as the cause of the failure.

As part of the corrective actions to the ACE, the licensee created a corrective action (CA) to create a PM for the UV and DV relays on the Unit 1 and Unit 2 emergency buses. The PM was created as part of a request for technical evaluation (RTE) and determined that the initial relay replacement activities needed to be performed at the next scheduled opportunity and that the normally energized relays need to be replaced on a 20-year frequency. The PM approval date was November 25, 2015. A work order (WO) (38103660563) was written prior to completion of the ACE to replace all of the Unit 2 normally energized UV relays during the fall 2015 refueling outage (RFO). The work order status was listed as completed, but only the remaining two UV relays on the Unit 2 H bus were replaced. The J bus UV relays were not replaced and the H and J bus DV relays were not replaced. New work orders were created for the UV and DV relays that were not replaced, but no UV or DV relays were replaced during the Unit 1 fall 2016 RFO and no UV or DV relays were replaced during the Unit 2 spring 2017 RFO. There were no notes in the work orders discussing the delay in replacing the relays and there were no RTEs for PM evaluations to evaluate if the relays could operate for additional cycles without replacement.

Dominion procedure ER-AA-102, Preventative Maintenance Program, section 3.4 discusses the scheduling and reviewing of PM tasks. Section 3.4.11 states to Annotate in the description field of first work order for new PM tasks First Time PM (FTPM) or FTPM-Past Initial Frequency (PIF) prior to PM task description. All of the WOs to replace the UV and DV relays should have been annotated FTPM-PIF, but none were noted as such. Some of the WOs did have FTPM in the description field, but were missing PIF. Failure to annotate PIF on the WO failed to relay critical information for the work planning process. Additionally, the initial WOs that were created, were not updated with language that recommended replacement of the relays at the next scheduled opportunity.

Corrective Actions: The licensees immediate corrective action was to replace the Unit 2 B phase H emergency bus DV relay. Additionally, the licensee made a CA assignment for engineering to review previous corrective actions associated with emergency bus UV and DV relays to determine if actions taken were timely and if additional actions were required based on this issue.

Corrective Action Reference: CR 1091928

Performance Assessment:

Performance Deficiency: The inspectors determined that failure of the licensee to follow procedure ER-AA-102, Preventative Maintenance Program, and properly annotate a past initial frequency PM was a performance deficiency (PD) that was within the licensees ability to foresee and correct. Specifically, the licensee did not annotate the emergency bus UV and DV relay replacement WOs as Past Initial Frequency and as a result, these relays were not scheduled to be replaced at the next scheduled opportunity in accordance with the RTE that established the PM.

Screening: The inspectors determined that the PD was more than minor because it adversely affected the equipment performance attribute of the Initiating Events Cornerstone and the cornerstone objective to limit the likelihood of events that upset plant stability and challenge critical safety functions during shutdown as well as power operations. Specifically, the failure of the Unit 2 B phase H and J emergency bus DV and UV relays while at RTP necessitated the high risk replacement to prevent a loss of an emergency bus and unnecessarily challenging safety systems.

Significance: The inspectors assessed the significance of the finding using IMC 0609.04, Initial Characterization of Findings, Table 2, dated October 7, 2016, and the finding was determined to adversely affect the Initiating Events Cornerstone. The inspectors screened the finding using Manual Chapter 0609, Appendix A, Significance Determination Process (SDP) for Findings at-Power, dated June 19, 2012, and determined that it screened as Green because the deficiency did not cause a reactor trip and the loss of mitigation equipment relied upon to transition the plant to a stable shutdown condition.

Cross-cutting Aspect: This finding has a cross-cutting aspect in the resolution component of the problem identification and resolution area, P.3, because the organization did not take effective corrective actions to address issues in a timely manner commensurate with their safety significance. Specifically, the replacement of the Unit 1 and Unit 2 emergency bus UV and DV relays were not scheduled at the next scheduled opportunity in accordance with the RTE that established the PM frequency after the September 2015 failure of an UV relay.

Enforcement:

Violation: Surry Technical Specification 6.4.D requires, in part, that procedures described in section 6.4.A shall be followed. Surry Technical Specification 6.4.A.7 requires, in part, that detailed written procedures with appropriate instructions shall be provided for conditions that include: preventative maintenance operations which would have an effect on the safety of the reactor. These requirements are implemented, in part, by Dominion procedure, ER-AA-102, Preventative Maintenance Program.

Contrary to the above, on November 25, 2015, the licensee failed to follow their Preventative Maintenance Program procedure and did not properly annotate the work orders to replace the emergency bus UV and DV relays as Past Initial Frequency. As a result, the UV and DV relays were not replaced at their next scheduled opportunity and subsequently the Unit 2 B phase H emergency bus DV relay failed on March 13, 2018 and Unit 2 B phase J emergency bus UV relay failed on May 21, 2018.

Disposition: This violation is being treated as a Non-Cited Violation, consistent with Section 2.3.2.a of the NRC Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On July 11, 2018, the inspector presented the quarterly resident inspector inspection results to Mr. F. Mladen, and other members of the licensee staff.

DOCUMENTS REVIEWED

IP 71111.01: Adverse Weather Protection

Procedures

0-AP-10.18, Response to Grid Instability, Rev. 23

0-AP-37.01, Abnormal Environmental Conditions, Rev. 71

0-OP-ZZ-021, Severe Weather Preparation, Rev. 20

0-OSP-ZZ-003, Hot Weather Preparation, Rev. 8

1-OP-26.5, 230 KV Switchyard Voltage, Rev. 19

2-OP-26.5, 500 KV Switchyard Voltage, Rev. 23

Work Orders

38103849456

IP 71111.04: Equipment Alignment

Procedures

0-OP-AAC-001A, AAC Diesel Generator Systems Alignment, Rev. 13

1-OP-RH-001A, RHR System Alignment, Rev. 6

1-OP-FW-001A, Auxiliary Feedwater System Valve Alignment, Rev. 7

1-OP-SI-001A, Safety Injection System Alignment, Rev. 19

Condition Reports (*NRC Identified)

1094952*

1095732*

1096350*

1097151*

1097647

1097650

1098085*

1098224*

1099074*

1100035*

Drawings

11448-FB-046D Sh. 2, Flow/Valve Operating Numbers Diagram Lube Oil System - Station

Blackout, Rev. 3

11448-FB-046D Sh. 3, Flow/Valve Operating Numbers Diagram Cooling Water System -

Station Blackout, Rev. 3

11448-FB-046D Sh. 4, Flow/Valve Operating Numbers Diagram Starting Air System - Station

Blackout, Rev. 11

IP 71111.05: Fire Protection

Procedures

0-LPT-FP-011, Fire Hose Hydrostatic Test, Rev. 4

1-LPT-FP-009, Inspection of Containment Hose Stations, Rev. 4

1-LPT-FP-013, Inspection of Containment Fire Hoses, Rev. 3

1-LPT-FP-023, Flow Test of containment Hose Station Valves, Rev. 8

0-FS-FP-161, Auxiliary Building Elevation 27 Feet - 6 Inches, Rev. 2

0-FS-FP-163, Fuel Building Elevation 6 Feet - 10 Inches and 15 Feet - 10 Inches, Rev. 1

0-FS-FP-164, Fuel Building Elevation 27 Feet - 6 Inches and 45 Feet - 10 Inches, Rev. 3

1-FS-FP-134, Containment Unit 1 Elevation 47 Feet - 4 Inches, Rev. 1

1-FS-FP-135, Containment Unit 1 Elevation 18 Feet - 4 Inches, Rev. 1

1-FS-FP-136, Containment Unit 1 Elevation (-)3 Feet - 6 Inches, Rev. 1

1-FS-FP-137, Containment Unit 1 Elevation (-)27 Feet - 7 Inches, Rev. 1

1-EPT-0902-01, Fire Protection Low Pressure CO2 System Puff Test, Rev. 31

0-FS-FP-225, Alternate AC Diesel Room - Construction Site Elevation 35 Ft, Rev. 1

IP 71111.06: Flood Protection

Procedures

0-AP-13.00, Turbine Building or MER 3 Flooding, Rev. 30

0-MOP-SW-002, Operation of Unit 1 to Unit 2 Service Water Jumper, Rev. 7

0-MOP-SW-003, Preparation of Unit 1 to Unit 2 Service Water Jumper, Rev. 2

0-OP-ZZ-008, Assessment of Maintenance Activities for Potential Flooding of Turbine Building &

Associated Areas, Rev. 13

GMP-C-107, Rigging and Lifting, Rev. 34

MA-AA-101, Fleet Lifting and Material Handling, Rev. 22

Other Documents

DC SU-13-00012, CCHX SW Outlet Jumper

IP 71111.08: Inservice Inspection Activities

Procedures:

ER-AA-NDE 140, Nondestructive Examination (NDE) Procedure, Processing of Dominion NDE

Data, Rev. 5

ER-AA-NDE-PT-300, SME Section XI Liquid Penetrant Examination Procedure, Rev. 7

ER-AA-NDE-PT-301, NDE Procedure, Balance of Plant, Liquid Penetrant Examination

Procedure, Rev. 7

ER-AA-NDE-PT-301, NDE Procedure, Balance of Plant (BOP) Liquid Penetrant Examination

Procedure, Rev. 7

ER-AA-NDE-UT-701, NDE Procedure, Ultrasonic Thickness Measurement Procedure, Rev. 6

ER-AA-NDE-UT-706, NDE Procedure, Ultrasonic Examination for the detection of Laminar

Indications, Rev. 1

ER-AA-NDE-UT-802, NDE Procedure, Ultrasonic Examination of Austenitic Piping Welds in

Accordance with ASME Section XI, Appendix VIII, Rev. 5

ER-AA-NDE-VT-603, NDE Procedure, VT-3 Visual Examination Procedure, Rev. 6

ER-AA-NDE-VT-604, NDE Procedure, Visual Examination for Leakage of PWR Reactor Head

Penetrations, (Code Case N729-4), Rev. 3

ER-AA-NDE-VT-607, NDE Procedure, Visual Examination Procedure, Examination of Pressure

Retaining Welds in Class 1 Components Fabricated with Alloy 600/82/182 Materials, Rev. 2

ER-AP-SGP-10, Steam Generator Program Description, Rev. 8

ER-AP-SGP-101, Steam Generator Program, Rev. 12

ER-AP-SGP-102, Steam Generator Degradation Assessment, Rev. 8

ER-AP-SGP-103, Steam Generator Condition Monitoring and Operational Assessments, Rev. 7

ER-SU-AUG-101, Administrative Procedure, Surry Augmented Inspection Program, Rev. 16

0-NSP-RC-003, Engineering Surveillance Procedure, Visual Examination of Reactor Pressure

Vessel Bottom Mounted Instrumentation (BMI), Rev. 3

Drawings:

11448-CBM-087A-5, ISI Classification Boundary Drawing, Interval-5, Residual Heat Removal

System, Surry Power Station Unit-1, Virginia Power, Rev. 0

11448-FM-087A, Sht. 1, Flow/Valve Operating Numbers Diagram, Residual Heat Removal

System, Rev. 23

11448-FP-12B, Sht. 2, Residual Heat Removal System, Rev. 11

11448-WMKS-RC-R-1.1, Inservice Inspection Detail Drawing, Reactor Vessel Welds, Surry

Power Station, Unit-1, Rev. 4

WM-4372, Work Order 38103811311 Weld Map, Charging System Line No. 3-CH-251-1502,

Design Change No. SU-17-00109, 4/20/18

WM-4166, Work Order 38103611539 Weld Map, Line No. 3/4 RC-67-1502, 9/26/16

Work Orders/Work Requests:

38103611539, Valve Replacement In Accordance with Design Change SU-15-01046, Replace

Valve 01-RC-139, 11/5/16

38103775582, RHR Pump 01-RH-P-1A, Pump Swap Out, 4/24/18

Condition Reports:

1051211, 1-RH-P-1A Has Seal Leakage

1051336, Boric Acid on 1-RH-P-1A (Pump Seal)

1052226, Possible Foreign Material in the Secondary Side of the Steam Generator

1053709, U1 S/G Pressures Lower Than Expected after Refueling Outage

1062048, U-1 Steam Generator Elevated Sodium

1063848, Boric Acid Identified on 1-SI-61, Low Head Safety Injection Pump 1A Recirculation

Check Valve

1069494, Unit 1 Steam Generator Sodium Concentration Increasing

1073523, PCS Primary to Secondary Leak Rate Program Requires Update

1076596, U-1 Steam Generator Sodium Spiked when Placing 1-CP-DM-1F in Service for 2-hr

Run

1089827, 1-OP-RC-015 Data Incorrectly Entered

1095256, Surry Unit-1, R28, Cold Shutdown Walk-down, Boric Acid Inspection, Below

Screening Threshold Leaks

1095383, Pipe Support 1-CC-H015, Unable to Determine Cold Load Setting on Spring Support

1095388, Pipe Support 1-CC-H018, Unacceptable Gaps Noted Condition, Improper Thread

Engagement

1095485, ASME Section XI, IWE Inspection Procedure ER-AA-NDE-VT-605 Requires Update

1095636, Foreign Material (FM) Identified during As-Found Inspections in "C" Steam Generator

Primary Side

1095775, UT Indication Found during MRP-146 Thermal Fatigue Examination

1095586, Boric Acid Leak at Pipe Cap Downstream of 1-CH-433

1095587, NRC Identified Boric Acid at 1-CH-344 at ASME Class 1 Tee Connection

1096048, Possible Loose Parts in U1 SG A

Miscellaneous Documents:

Certificate of Certification, Spotcheck Penetrant, SKL-SP-2, 5/14/17

Certificate of Calibration, Thermometer Certificate No. 180854030900376, 3/26/18

Certificate of, Thermometer Certificate No. 180854030900380, 3/26/18

CAL-18-004, UT Thickness Calibration Report, 4/25/18

Document Number 180-9264066-000, Surry S1R27 Bare Metal Visual Examination, 11/10/16

ETE-SU-2015-0011, Steam Generator Condition Monitoring and Operational Assessment -

Surry Unit 1, Rev. 0

ETE-SU-2016-0031, Steam Generator Condition Monitoring and Operational Assessment -

Surry Unit 1, Rev. 0

ETE-SU-2018-0009, Surry Unit 1, Spring 2018 Steam Generator Degradation Assessment,

Rev. 0

Figure 15.5-1, Reactor Containment Waterproofing Elevation View, Surry UFSAR, Rev 49.01,

1/31/18

Framatome Inc. Engineering Information Record, 51-9282567-000, Surry Unit 1 - 1R28 ECT

Inspection Plan

Framatome Inc. Engineering Information Record, 51-9282741- 000 - Qualified Eddy Current

Examination Techniques for Surry Unit 1, 1R28

NDE Personnel Qualification and Certification Records for 15 individuals

Personnel Certification Records for one Independent Data Analyst

RR 2016-093, ASME Section XI Repair /Replacement Plan for Work Order 38103611539,

11/8/16

Self-Assessment PIR1030006, Steam Generator Program Quality and Implementation

SRY-SGPMS-002, Surry Site Specific Eddy Current Analysis Guidelines, Surry 1R28, Rev. 26

Surry Power Station, Unit-1, Inservice Inspection Plan for Components and Component

Supports, Fifth 10-Year Inservice Inspection Interval, Dec.14, 2013 - October 13, 2023, Rev. 3

TB-07-2, Westinghouse Technical Bulletin, Reactor Vessel Head Adapter Thermal Sleeve Wear

Rev. 3

Weld Data Record, Work Order 38103611539, Weld No. 3, Valve 01-RC-139, 11/8/16

Weld Data Record, Work Order 38103611539, Weld No. 5, Valve 01-RC-139, 11/8/16

Welder Performance Qualification (WPQ), for Rev. 8 of Technique 801-one person

IP 71111.11: Licensed Operator Requalification Program

Procedures

1-GOP-1.8, Unit Startup, Hot Shutdown to Max Allowable Power, Rev. 40

1-GOP-2.7, Unit Shutdown, Power Decrease from Allowable Power to Unit Offline for Refueling

Outage, Rev. 38

1-OP-RX-009, Dilution to Critical Conditions Following Refueling, Rev. 26

IP 71111.12: Maintenance Effectiveness

Condition Reports

1091963

1098836

Work Orders

203874980

203875045

Other Documents

DC SU-18-00112, Charging SW Fire Protection Pipe Replacement, Rev. 0

GMP-035, Sealing of Fire Barriers with Mortar or Caulking Compound, Rev. 15

IP 71111.13: Maintenance Risk Assessments and Emergent Work Control

Procedures

NF-AA-PRA-370, Probabilistic Risk Assessment Procedures and Methods: MRule (a)(4) Risk

Monitor Guidance, Rev. 19

WM-AA-20, Risk Assessment of Maintenance Activities, Rev. 2

WM-AA-100, Work Management, Rev. 31

WM-AA-301, Operational Risk Assessment, Rev. 19

Other Documents

EOOS Schedulers Risk Evaluation for Surry Power Station, April 18, 2018

EOOS Schedulers Risk Evaluation for Surry Power Station, April 24, 2018

EOOS Schedulers Risk Evaluation for Surry Power Station, April 30, 2018

EOOS Schedulers Risk Evaluation for Surry Power Station, May 14, 2018

Surry Unit 2 2017 Outage Shutdown Risk Review Report, Dated 4/21/2018

IP 711111.15: Operability Determinations and Functionality Assessments

Procedures

0-FS-FP-211, Emergency Service Water Pump House - Low Level Elevation 18 Feet, Rev. 3

DNES-AA-MOV-1001, Motor Operated Valve Diagnostic Test Preparation and Evaluation,

Rev. 1

OP-AA-102, Operability Determination, Rev. 15

Condition Reports

1091963

1094780

1097862

Drawings

11448-FM-071B, Flow/Valve Operating Numbers Diagram Circulating and Service water

System, Rev. 61

11448-FM-088B, Flow/Valve Operating Numbers Diagram Chemical & Volume Control System,

Rev. 53

Work Orders

38102221431

203874699

203874700

203874701

Other Documents

Calculation ME-0166, Appendix R Fire SWSOPA, Rev. 2

ETE-CME-2017-0014, Surry Power Station Anchor-Darling Double Disk Gate Valve Part 21

Applicable Valve Prioritizations, 06/11/18

Prompt Operability Determination for Unit 1 and Unit 2 Anchor-Darling Double Disk Gate

Valves, 05/22/18

Static Test Evaluation Review Checklist for 1-SW-MOV-104B, 05/19/18

SU-17-00137, Unit 1 Stem and Pin Replacements on Anchor-Darling Double Disk Gate Valves,

Rev. 0

IP 71111.18: Plant Modifications

Procedures

1-OSP-ZZ-001, Auxiliary Shutdown Panel Functional Surveillance, Rev. 15

1-OSP-ZZ-006, Operational Check of the Auxiliary Shutdown Panel and Transfer Relay

Cabinets, Rev. 1

0-NAT-E-003, Control Circuitry Checkout/Initial Energization of Electrical Equipment, Rev. 2

0-NAT-FC-001, Functional Loop Checkout, Rev. 2

0-FCA-1.00, Limiting MCR Fire, Rev. 54

1-OSP-ZZ-006, Operational Check of the Auxiliary Shutdown Panel and Transfer Relay

Cabinets, Rev. 0

Condition Reports

1097528

1097542

1098226

1098566

Drawings

11448-ESK-6BY, Elementary Diagram 480V Circuits Motor Operated Valves 01-FW-MOV-

151C&D, Revs. 23 and 24

11448-FM-088B, Sheet 2, Flow/Valve Operating Numbers Diagram, Chemical & Volume

Control System, Rev. 55

1700109-1-M-800, Sheet 001, Charging Cross Connection Piping, Surry Power Station - Unit 1,

Rev. 0

Work Orders

38103835060

38103786256

38103862320

203874701

203874745

Other Documents

DCP 79-067, Charging Pump Cross-Connect #1 and #2, 02/06/81

DCP SU-16-00109, Surry Unit 1 AFW MOV Hot Short Resolution, Rev. 0

DCP, SU-17-00109, Surry Power Station Unit 1 Hot Short Resolution Charging Cross-tie

Relocation, Rev. 0

IP 71111.19: Post Maintenance Testing

Procedures

0-OPT-ZZ-008, ASME System Pressure Test, Rev. 11

1-PT-2.33A, Emergency Bus Undervoltage and Degraded Protection Test H Train, Rev. 8

1-PT-8.2, Reactor Protection Logic, Rev. 25

1-OPT-SI-002, Refueling Test of the Low Head Safety Injection Check Valves to the Cold Legs,

Rev. 25

1-OPT-FW-002, Motor Driven Auxiliary Feedwater Pump 1-FW-P-3B, Rev. 36

VPAP-0812, Station Lubrication Program, Rev. 17

1-EPT-0106-07, Main Station 1B Performance Test, Rev. 21

1-EPT-1801-01, Bus 1H Protective Relay Testing, Rev. 16

1-OPT-EG-009, Number 1 Emergency Diesel Generator Major Maintenance Operability Test,

Rev. 58

1-OPT-ZZ-001, ESF Actuation with Undervoltage and Degraded Voltage 1H Bus, Rev. 42

DNES-AA-MOV-1001, Motor Operated Valve Diagnostic Test Preparation and Evaluation, Rev.

Condition Reports

1095507

1096445

1096973

1097129

1097208

1098022

1098650

Work Orders

203874699

203874700

203874701

203877019

38103753291

38103753299

38103753307

38103753315

38103753323

38103753331

38103775433

38103771661

38103788540

38103867760

38103863466

38103629393

Drawings

11448-FM-088B, Flow/Valve Operating Numbers Diagram Chemical & Volume Control System,

Rev. 53

Other Documents

DCP SU-17-00109, SPS U1 Hot Short Resolution Charging Cross-tie Relocation, Rev. 0

DCP SU-18-00116, Stem and Disc Arm Replacement for 1-SI-MOV-1863A, Rev. 0

ME-3330, JOG Calculation of Required Thrust Settings for MOV 1-SI-MOV-1863A, Rev. 4

Radiographic Film for RR-2018-084 Weld 3A, dated 4/29/18

Static Test Evaluation Review Checklist for 1-SI-MOV-1863A, 05/09/18

SU-CALC-MEC-2044498-C-033, Seismic/Weak Link Thrust Calculation for MOVs: 1-CH-MOV-

1115B, 1-CH-MOV-1115D, 1-SI-MOV-1863A, & 1-SI-MOV-1863B at Surry Unit 1, Rev. 2

VT-2 Visual Examination Report for ASME Pressure Test RR-2018-084, dated 5/14/18 and

5/18/18

IP 71111.20: Refueling and Other Outage Activities

Procedures

1-GOP-1.8, Unit Startup, Hot Shutdown to Max Allowable Power, Rev. 40

1-GOP-2.7, Unit Shutdown, Power Decrease from Allowable Power to Unit Offline for Refueling

Outage, Rev. 38

1-OP-FH-001, Controlling Procedure for Refueling, Rev. 41

1-OP-RC-004, Draining the RCS to Reactor Flange Level, Rev. 38

1-OP-RX-009, Dilution to Critical Conditions Following Refueling, Rev. 26

LI-AA-700, Fatigue Management and Work Hour Limits for Covered Workers, Rev. 13

MA-AA-102, Foreign Material Exclusion, Rev. 22

Condition Reports

1095133

1095607

1095784

1096592

1096323

1096319

1097151

1096349

1096386

1096874

1096989

1097149

1096810

1096339

1096350

1097304

1098578

1098605

1098650

1098758

1098933

IP 71111.22: Surveillance Testing

Procedures

0-OPT-SW-002, Emergency Service Water Pump 1-SW-P-1B, Rev. 65

0-MCM-0802-01, Recirculation Spray Heat Exchanger Inspection and Cleaning, Rev. 11

1-OPT-SI-026, Safety Injection Train A Master Relay and Reset Timer Test, Revs. 3 and 4

1-OPT-CT-201, Containment Isolation Valve Local Leak Rate Testing (Type C Containment

Testing), Rev. 25

1-OPT-SI-009, Refueling Test of the LHSI Check Valves to the Hot Legs, Rev. 17

1-OPT-ZZ-001, ESF Actuation with Undervoltage and Degraded Voltage 1H Bus, Rev. 42

1-OSP-SW-008, SW Flow Test of RSHXs 1-RS-E-1B and 1-RS-E-1C, Rev. 6 (OTO1)

Condition Reports

1096874

Work Orders

38103629393

71114.02: Alert and Notification System Evaluation

Procedures

Surry Power Station Emergency Plan, Rev. 64

0-LSP-EW-001, Early Warning System Polling Functional Test, Rev. 17

0-LSP-EW-002, Early Warning System Siren Activation Monitoring, Rev. 13

0-LSP-EW-003, Early Warning System Siren Quarterly Inspection, Rev. 2

0-LSP-EW-004, Early Warning System Siren Quarterly Remote Activation Panel Inspection,

Rev. 1

0-LSP-EW-007, Early Warning System Polling Functional Test (Innsbrook), Rev. 1

0-LSP-EW-008, Early Warning System Siren Annual Inspection, Rev. 2

Records and Data

Alert & Notification System Updated Design Report for Surry Power Station, Rev. 2, dated

3/12/18

Dominions Surry Siren Upgrade Propagation Study, Rev. 1, dated 10/24/14

FEMA Analysis of the Prompt Alert & Notification System for Surry Power Station, dated 12/8/87

Notification System Quality Assurance Verification Final Report, dated 9/30/87

Sample of 2017 & 2018 siren testing results

Condition Reports

CR 1035025, Potential trend for SPS EWS #51

CR 1044956, 00-EW-ESIR-49 Failed to Poll

CR 1055371, Siren 41 did not respond as expected during conduct of 0-LSP-EW-007

CR 1070454, SPS EWS Siren Polling (Corporate) 29 & 51 failed to Poll

CR 1071840, SPS scheduled EWS siren activation test

CR 1085925, Failed James County backup activation panel

CR 1088227, SPS Back-up EWS failed to Poll

CR 1094430, SPS EWS siren polling test 21A failed to respond to battery AC test (NRC-

observed)

71114.03: Emergency Response Organization Staffing and Augmentation System

Procedures

0-LSP-CO-005, EP Surveillance Procedure, Augmentation Capabilities, Rev. 0

CPIP-3.1, CERC and EOF Activation, Rev. 30

CPIP-3.3. Surry LEOF Activation, Rev. 21

CPIP-6.0, LEOF Recovery Manager Guidance, Rev. 14

EPIP-2.02, Notification of NRC, Rev. 24

EPIP-3.02, Activation of the Technical Support Center, Rev. 35

EPIP-3.03, Activation of the Operations Support Center, Rev. 22

EPIP-3.05, Augmentation of Emergency Response Organization, Rev. 12

EPIP-4.03, Dose Assessment Team Controlling Procedure, Rev. 21

EAL Technical Basis Document, Rev. 4

Corporate Emergency Plan, Rev. 16

Records and Data

Assessment of On-Shift Emergency Response Organization Staffing Capabilities, NEI 10-05,

dated 12/20/12

Augmentation Capability Assessment - Emergency Response Organization: dated 1/30/17,

2/01/17, 7/17/17, 9/28/17, 12/06/17

Emergency Response Organization Team Roster Assignments

Selected ERO Training Records

Surry Units 1&2 On-shift Analysis Record of Revision, Rev. 0

Condition Reports

CR 1047822, Adverse Trend in Corp ERO Availability

CR 1055786, Drill confidential material distributed to key ERO members prior to 12/13/16 EP

drill

CR 1055790, During SDEC16FS EP Drill, Accountability Reader Activation Took 8 Minutes

CR 1056052, EP drill conducted on 12/13/16, SDEC16FS objective 20 MET with Problems for

CRS

CR 1056054, EP Drill conducted on 12/13/16, SDEC16 FS overall 20 graded as MET with

Problems

CR 1061848, Surry ERO LMS roles do not align with the ERO Training Program Guide

CR 1062280, Communications Failures

CR 1072620, Unsuccessful Drill and Exercise Performance (DEP) opportunity

CR 1090846, CR not submitted when ERO staff positions dropped below five

CR 1094415, Discrepancies identified with ERO response times (NRC-identified)

71114.04: Emergency Action Level and Emergency Plan Changes

Procedures

EP-AA-101, 10 CFR 50.54(q) Change Evaluation, Rev. 7

EP-AA-102, Revision & Control of Emergency Plan, Emergency Action Levels (Technical Basis

and Matrix) & Reference Manual, Rev. 8

EP-AA-105, Emergency Preparedness Department Staff Training, Rev. 0

EPIP-4.03, Dose Assessment Team Controlling Procedure, Revs. 20 & 21

Surry Power Station Emergency Action Level Matrix, Rev. 4

Surry Power Station Emergency Action Level Technical Basis Document, Rev. 4

Surry Power Station Emergency Plan, Revs. 63 & 64

Change Packages

SU-17-06, 50.54(q)(3) Screening/Evaluation for Emergency Plan, Section 7.2.2.4, dated 2/27/18

SU-17-09A, 50.54(q)(2) Analysis for EPIP-4.03, Dose Assessment Team Controlling Procedure,

Rev. 20

SU-17-10A, 50.54(q)(2) Analysis for EPIP-2.02, Notification of NRC, Rev. 24

SU-18-025, 50.54(q)(3) Screening/Evaluation for Surry Emergency Plan, Rev. 64

Condition Reports (*NRC Identified)

CR 1061820, EPIP implementation has resulted in differences in current use revisions

CR 1062839, New calculations will affect future NEI 99.01 Rev. 6 EAL thresholds

CR 1071334, EPIP-2.01 enhancements required as discovered during training exercise

CR 1072420, Procedural deficiency in EPIP-4.03

CR 1072667, Question exists regarding most appropriate method of determining noble gas to

particulate ratio (NG/Part)

CR 1074400, Wrong revision numbers referenced in procedure package

CR 1074537, SJUL17BE - Additional 50.72 reporting when in continuous NRC communications

CR 1094413*, Benchmark the 10 CFR 50.54q process

71114.05: Maintenance of Emergency Preparedness

Procedures

0-HSP-EP-001, Health Physics Surveillance Procedure, Rev. 26

1-1PM-ER-REC-001, Seismic Instrumentation Status Check Recording, Rev. 6

EP-AA-100, Maintaining Emergency Preparedness, Rev. 8

EP-AA-303, Equipment Important to Emergency Response, Rev. 17

EP-AA-400, Drill & Exercise Program, Rev. 12

EPIP-303, Activation of the OSC, Rev. 22

EPIP-4.03, Dose Assessment Team Controlling Procedure, Revs. 19, 20, and 21

EPIP-8.02, Activation of the TSC, Rev. 35

OP-ZZ-026, Compensatory Measures for Category A Equipment Important to Emergency

Response, Rev. 1

PI-AA-100-1003, Self-Evaluation & Trending, Rev. 24

PI-AA-100-1004, Self-Assessments, Rev. 14

PI-AA-200, Corrective Action, Rev. 33

PI-AA-300, Cause Evaluation, Rev. 15

Surry Power Station Emergency Plan, Revs. 63 and 64

Records and Data

Surry Power Station, ACE #: CA 3060983, CR 1072620, Unsuccessful Drill and Exercise

Performance (DEP) opportunity, dated 6/29/17

Radiological Status Form, CERC run based on MIDAS projection for Surry Drill, run #4 (K run)

date/time: 6/27/17 at 10:38

Radiological Status Form, LEOF run based on MIDAS projection for Surry Drill, run # 3,

date/time: 6/27/17 at 10:05

Radiological Status Form, TSC run based on MIDAS projection for Surry Drill, run # 4,

date/time: 6/27/17 at 10:27

Self-Assessment, PIR 1039123, Emergency Response Facility Support Equipment, dated

2/21/16

Self-Assessment, PIR 1034876, Drill Development, dated 5/5/17

Self-Assessment, PIR 1058655, NRC Biennial Exercise Readiness, dated 6/26/17

Self-Assessment, PIR 1079700, Inspection Readiness, dated 3/15/18

Nuclear qualifications for selected ERO staff for respiratory protection, dated 4/9/18

Nuclear Oversight Audit report 17-02, Emergency Preparedness, dated 3/29/17

SDEC16FS, Full Scale Training Drill, Management Critique, dated 12/13/16

SFEB16FS, Full Scale Training Drill, Management Critique, dated 2/29/16

SJUN16FS, Full Scale Training Drill, Management Critique, dated 6/21/16

Surry Evacuation Time Estimates Report, dated December 2012

Surry 2017 Evacuation Time Estimate/Population Update Analysis, dated 12/7/17

0-LSP-CO-004, Emergency Response Data System (ERDS) Test, Rev. 8, dated 1/4/17

Work Orders

38103847993, Location 01-ER-REC-100-Panel, U1, PM: Perform Seismic Channel Check,

dated 2/22/18

38103854141, Location 01-ER-REC-100-Panel, U1, PM: Perform Seismic Channel Check,

dated 3/26/18

38103619942, Location 01-ER-REC-100-Panel, U1, PM: Perform Seismic Channel Check,

dated 10/23/16

38103444550, Location 01-ER-REC-100-Panel, U1, PM: Perform Seismic Channel Check,

dated 5/11/15

Corrective Action Documents

CR 1028317, Approver was not qualified to approve 10 CFR 50.54 (q) evaluations

CR 1035040, EP Baseline Inspection NRC observations

CR 1037165, Objective 4 offsite Notifications NOT MET

CR 1041302, NRC ENS line will not work for incoming or outgoing calls

CR 1041840, TSC AC unit not working

CR 1059998, 1-PT-26-2C completed UNSAT due to annunciator A3 will not illuminate

CR 1060458, Discrepancy in the minimum staffing requirements between the E-Plan and OP-

AA-100

CR 1061291, B.5b self-assessments have not been performed

CR 1063530, During drill SMAR 17 FS unable to complete EPIP-2.01 notification to all locations

within 145 minutes

CR 1064585, TSC Ping 38 communication error

CR 1068020, Main steam line Radiation Monitor cable damaged

CR 1068672, Surry backup EOF location different from NRC-approved location

CR 1069966, MIDAS not working properly

CR 1072399, Potential for ERO PAR vulnerability based on EPIP 4.03, NE-GL-0035

CR 1072405, SJUN17DR - Not Met objective 15 timely and accurate information to the public

CR 1072416, SJUN17DR DEP potentially incorrect IAW EP-AA-103 related to PAR

CR 1074327, TSC communication equipment issues

CR 1074436, SJUL17BE ERDS data from simulator not visible to NRC

CR 1074531, SJUL17BE Objective 20 was upgraded as NOT MET overall for the exercise

CR 1074753, SJUL17BE - Exercise Scenario package did not contain demonstration criteria

CR 1074790, Observations from NRC Biennial EP Inspection

CR 1077061, TSC Ping 3-B computer not functioning, the computer locked out

CR 1078651, Surry County ARD not working as designed

CR 1079349, MIDAS not automatically down-loading meteorological or radiation data

CR 1080249, Vent Stack 2 RM pump tripped

CR 1083260, TSC PCS components high temperature

CR 1084539, 1-VG-RI-131 B Vent-gas #2 failed

CR 1090066, Numerous outlets in the CP Control Room, including security card readers have

lost power

CR 1090297, Charles City Instaphone is not functional

CR 1090846, CR not submitted when ERO staff positions dropped below five

CR 1093227, 1-GW-R1-130B indicates a flow fault

CR 1094428, LEOF tripping hazard resulted in near-miss (NRC-identified)

CR 1094431, LEOF walk down (NRC-identified)

CR 1094499, Respirator inspection date not documented in EP go-kits

IP 71114.06: Emergency Preparedness Drills

Procedures

1-E-0, Reactor Trip or Safety Injection, Rev. 72

EPIP-1.03, Response to Alert, Rev. 23

EPIP-1.04, Response to Site Area Emergency, Rev. 23

EPIP-1.05, Response to General Emergency, Rev. 25

EPIP-1.06, Protective Action Recommendations, Rev. 12

EPIP-2.01, Notification of State and Local Governments, Rev. 44

Condition Reports

1099973

1100214

1100460

1101008

IP 71151: Performance Indicator Verification

Procedures

EP-AA-103, Emergency Preparedness Performance Indicators, Rev. 5

ER-AA-SPI-101, Implementation of the Consolidated Data Entry (CDE) Reporting for Mitigating

System Performance Index (MSPI), Rev. 0

NEI 99-02, Regulatory Assessment Performance Indicator Guideline, Rev. 7

PI-AA-200, Corrective Action, Rev. 33

SU-2014-0082, MSPI Basis Document, Rev. 0

Records and Data

DEP opportunities documentation for 2nd, 3rd, & 4th quarters 2017

Siren test data for 2nd, 3rd, & 4th quarters 2017

Drill & exercise participation records of ERO personnel for 2nd, 3rd, & 4th quarters 2017

Corrective Action Documents

CR 1046155, Incorrect value for EP KPI

CR 1047961, Loss of power to EAS system

CR 1051157, ARCOS wed-based callout unavailable due to internet outage

CR 1058590, Operations personnel NRC Communicator qualifications delayed

CR 1074339, ARCOS activation notifications received 12 minutes after declaration of Alert

Other Documents

1Q/2018 Performance Indicators - Surry 1 and 2 - Reactor Coolant System Activity, dated

05/01/18

1Q/2018 Performance Indicators - Surry 1 and 2 - Reactor Coolant System Leakage, dated

05/01/18

1Q/2018 Performance Indicators - Surry 1 and 2 - Safety System Functional Failures, dated

05/01/18

Unit 1 Control Room Narrative Log, 04/01/2017 - 03/31/2018

Unit 2 Control Room Narrative Log, 04/01/2017 - 03/31/2018

IP 71152: Identification and Resolution of Problems

Procedures

ER-AA-102, Preventative Maintenance Procedure, Rev. 11

WM-AA-10, Work Management, Rev. 1

WM-AA-101, Work Order Planning, Rev. 14

Condition Reports

1000999

1030874

1084436

1084472

1091928

1097966

1098297

Work Orders

3810359162

38103658614

38103660563

38103843782

Other Documents

ACE CA3009200, Unanticipated Starting of EDG #2 during Undervoltage/Degraded Voltage

Testing Procedure, 12/06/2015

EACE, CA3027045, The 1-EP-27-1JDUS-1J1A Relay was found to be Chattering, 07/30/2016

RTE P-SURR-343477, Create Preventative Maintenance for Unit 2 H Bus UV/DV Two out of

Three Relays, 01/29/2016