| | Quarter | Site | Title |
|---|
| 05000390/FIN-2016501-01 | 2016Q4 | Watts Bar | Failure to Maintain Minimum On-Shift Emergency Response Staffing Levels |
| 05000244/FIN-2016003-01 | 2016Q3 | Ginna | Failure to Perform Drills Required by the Site Emergency Plan |
| 05000456/FIN-2015001-03 | 2015Q1 | Braidwood | Failure to Activate the ERO During an Actual Event |
| 05000461/FIN-2010003-04 | 2010Q2 | Clinton | Inadequate Emergency Preparedness Augmentation Call-In Drills |
| 05000461/FIN-2009502-01 | 2009Q4 | Clinton | Implementation of a Change which Decreased the Effectiveness of the Emergency Plan |
| 05000282/FIN-2009004-03 | 2009Q3 | Prairie Island | Potential Testing Emergency Response Organization Callout and Augmentation Process Performing Deficiency |
| 05000244/FIN-2008003-02 | 2008Q2 | Ginna | Failure to Maintain Timely ERO Augmentation of ON-SHIFT Staff |
| 05000461/FIN-2008002-05 | 2008Q1 | Clinton | Changes to ERO ON-SHIFT and Augmentation Staffing Levels and Position Titles |
| 05000219/FIN-2005011-02 | 2005Q3 | Oyster Creek | EAL Matrix Not Reviewed for Declaring an Alert |
| 05000341/FIN-2005012-01 | 2005Q2 | Fermi | Failure to Perform a 10CFR50/54(q) Review to Determine if Changing the Augmentation Process for the Station Nuclear Engineer Decreased the effectiveness of the Emergency Plan |