March 3, 2008
SUBJECT:
ANNUAL ASSESSMENT LETTER - SURRY POWER STATION (NRC INSPECTION REPORT 05000280/2008001 AND 05000281/2008001)
Dear Mr. Christian:
On February 6, 2008, the NRC staff completed its performance review of the Surry Power Station. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from January 1 through December 31, 2007. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only--Security Related Information" will include the security cornerstone review and resultant inspection plan.
Overall, Surry Power Station Units 1 and 2 operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter, as well as for the first three quarters of the assessment cycle, was within the Licensee Response column of the NRC=s Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility. We also plan on conducting several non-ROP inspections which include: TI 2515/166, Pressurized Water Reactor Containment Sump Blockage; TI 2515/171, Verification of Site Specific Implementation of B.5.b Phase 2 & 3 Mitigating Strategies; and TI 2515/172, Reactor Coolant System Dissimilar Metal Butt Welds.
The enclosed inspection plan details the inspections, less those related to physical protection scheduled through June 30, 2009. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature.
The inspections in the last nine months of the inspection plan are tentative and may be revised at the mid-cycle review.
In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (404) 562-4662 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Eugene Guthrie, Chief Reactor Projects Branch 5 Division of Reactor Projects
Docket Nos.: 50-280, 50-281 License Nos.: DPR-32, DPR-37
Enclosure:
Surry Inspection/Activity Plan (03/01/08 - 06/30/09)
cc w/encl.:
(See page 3)
_________________________
OFFICE RII:DRP RII:DRP RII:DRP RII:DRP
SIGNATURE
/RA/
/RA/
/RA/
/RA/
NAME JDodson DArnett LGarner EGuthrie
DATE 2/28/08 2/27/08 3/3/08 3/3/08 3/ /2008 3/ /2008 3/ /2008 E-MAIL COPY?
YES NO YES NO YES NO YES NO YES NO YES NO YES NO
cc w/encl.:
Chris L. Funderburk Director Nuclear Licensing and Operations Support Virginia Electric and Power Company Electronic Mail Distribution
Donald E. Jernigan Site Vice President Surry Power Station Virginia Electric & Power Company Electronic Mail Distribution
Virginia State Corporation Commission Division of Energy Regulation P.O. Box 1197 Richmond, VA 23209
Lillian M. Cuoco, Esq.
Senior Counsel Dominion Resources Services, Inc.
Millstone Power Station Electronic Mail Distribution
Letter to Jeffrey B. Archie from Eugene F. Guthrie dated March 3, 2008
SUBJECT:
ANNUAL ASSESSMENT LETTER - SURRY POWER STATION NRC INSPECTION REPORT 05000280/2008001 AND 05000281/2008001
Distribution w/encl.:
C. Evans, RII EICS (Part 72 Only)
L. Slack, RII EICS OE Mail (email address if applicable)
S. P. Lingam, NRR Richard Jervey, NRR RIDSNRRDIRS PUBLIC
Surry Inspection / Activity Plan 03/01/2008 - 06/30/2009 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 03/03/2008 08:13:27 Report 22
OL EXAM
- INITIAL EXAM Not Applicable SURRY/MARCH 2008 EXAM AT POWER FACILITIES 03/17/2008 03/28/2008
V23279
EB1-SUMP
- TI 2515/166 CONTAINMENT SUMP INSPECTION Safety Issues Pressurized Water Reactor Containment Sump Blockage [NRC GENERIC LETTER 2004-02]
05/05/2008 05/09/2008
2515/166 IP
EB3-ISI
- UNIT 2 - ISI Baseline Inspections Inservice Inspection Activities - PWR 05/05/2008 05/09/2008
7111108P IP
EB3TI172
- TI-172 Generic Safety Inspection Reactor Coolant System Dissimiliar Metal Butt Welds 05/05/2008 05/09/2008 1, 2 2515/172 IP
EB3SGISI
- U2 SG ISI Baseline Inspections Inservice Inspection Activities - PWR 05/12/2008 05/16/2008
7111108P IP
PSB1-RP
- RADIATION PROTECTION PREINSPECTION VISIT Baseline Inspections Access Control to Radiologically Significant Areas 06/23/2008 06/25/2008 1, 2 7112101 IP
EB3-HS
- HEAT SINK Baseline Inspections Heat Sink Performance 06/23/2008 06/27/2008 1, 2 7111107B IP
PSB1-EP
- EP INSP EP Baseline Inspection Alert and Notification System Testing 07/14/2008 07/18/2008 1, 2 7111402 IP EP Baseline Inspection Emergency Response Organization Augmentation Testing 07/14/2008 07/18/2008 1, 2 7111403 IP EP Baseline Inspection Emergency Action Level and Emergency Plan Changes 07/14/2008 07/18/2008 1, 2 7111404 IP EP Baseline Inspection Correction of Emergency Preparedness Weaknesses and Deficiencies 07/14/2008 07/18/2008 1, 2 7111405 IP Baseline Inspections Drill/Exercise Performance 07/14/2008 07/18/2008 1, 2 71151-EP01 IP Baseline Inspections ERO Drill Participation 07/14/2008 07/18/2008 1, 2 71151-EP02 IP Baseline Inspections Alert & Notification System 07/14/2008 07/18/2008 1, 2 71151-EP03 IP
PSB1-RP
- RADIATION PROTECTION PUBLIC BASELINE Baseline Inspections Access Control to Radiologically Significant Areas 07/28/2008 08/01/2008 1, 2 7112101 IP Baseline Inspections Radiation Monitoring Instrumentation and Protective Equipment 07/28/2008 08/01/2008 1, 2 7112103 IP Baseline Inspections Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 07/28/2008 08/01/2008 1, 2 7112201 IP Baseline Inspections Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program 07/28/2008 08/01/2008 1, 2 7112203 IP Baseline Inspections Occupational Exposure Control Effectiveness 07/28/2008 08/01/2008 1, 2 71151-OR01 IP Baseline Inspections RETS/ODCM Radiological Effluent 07/28/2008 08/01/2008 1, 2 71151-PR01 IP
TI-171
- B.5.B PHASE 2&3 Generic Safety Inspection Verification of Site Specific Implementation Of B.5.b Phase 2 & 3 Mitigating Strategies 08/04/2008 08/08/2008 1, 2 2515/171 IP
- REQUAL INSPECTION Baseline Inspections Licensed Operator Requalification Program 04/06/2009 04/10/2009 1, 2 7111111B IP
EB3ISI
- UNIT 1 ISI Baseline Inspections Inservice Inspection Activities - PWR 04/27/2009 05/01/2009
7111108P IP This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Surry Inspection / Activity Plan 03/01/2008 - 06/30/2009 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 03/03/2008 08:13:27 Report 22
TFPI
- TFPI Baseline Inspections Fire Protection [Triennial]
06/08/2009 06/12/2009 1, 2 7111105T IP Baseline Inspections Fire Protection [Triennial]
06/22/2009 06/26/2009 1, 2 7111105T IP This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.