EPID:L-2020-LLM-0003, Post Shutdown Decommissioning Activities Report Including Site-Specific Decommissioning Cost Estimate for Palisades Nuclear Plant (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance
|
MONTHYEARML20358A2322020-12-23023 December 2020 Post Shutdown Decommissioning Activities Report Including Site-Specific Decommissioning Cost Estimate for Palisades Nuclear Plant Project stage: Request ML21028A0552021-01-27027 January 2021 NRR E-mail Capture - Palisades Nuclear Plant - Acceptance of License Transfer Application Project stage: Acceptance Review ML21012A0352021-02-0101 February 2021 And Big Rock Point Plant - Notice of Consideration of Approval of Transfer of Control of Licenses and Conforming Amendments and Opportunity for a Hearing (FRN) Project stage: Other ML21012A0312021-02-0101 February 2021 And Big Rock Point Plant - Notice of Consideration of Approval of Transfer of Control of Licenses and Conforming Amendments and Opportunity for a Hearing Project stage: Other ML21011A0672021-02-0101 February 2021 Proposed Post-Shutdown Decommissioning Activities Report with Site-Specific Decommissioning Cost Estimate Project stage: Other ML21055A9532021-02-24024 February 2021 Petition of Beyond Nuclear, Michigan Safe Energy Future and Dont Waste Michigan for Leave to Intervene, and Request for an Adjudicatory Hearing Project stage: Request ML21055A8882021-02-24024 February 2021 Petition of the Michigan Attorney General for Leave to Intervene and for a Hearing Project stage: Request ML21055A9142021-02-24024 February 2021 The Environmental Law & Policy Center Petition to Intervene and Hearing Request Project stage: Request ML21281A0022021-10-13013 October 2021 And Big Rock Point Plant - Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML21309A2982021-11-0505 November 2021 NRR E-mail Capture - Palisades Nuclear Plant and Big Rock Point Plant - Application for Order Consenting to Transfers of Licenses and Conforming License Amendments Project stage: Other ML21328A0062021-11-18018 November 2021 NRR E-mail Capture - (External_Sender) State of Michigan Response - Palisades Nuclear Plant and Big Rock Point Plant - Application for Order Consenting to Transfers of Licenses and Conforming License Amendments Project stage: Request ML21337A3022021-12-0303 December 2021 Notification of Significant Licensing Action Regarding Proposed Issuance of an Order Approving a License Transfer Application for Which a Hearing Has Been Requested Project stage: Approval ML21291A2372021-12-0303 December 2021 Proposed Issuance of an Order Approving a License Transfer Application for Which a Hearing Has Been Requested Project stage: Approval ML21292A1452021-12-13013 December 2021 And Big Rock Point Plant - Order Approving Transfer of Licenses and Draft Conforming Administrative License Amendments (EPID L-2020-LLM-0003) (Letter) Project stage: Draft Other ML21292A1462021-12-13013 December 2021 And ISFSI and Big Rock Point and ISFSI - Order Approving Direct and Indirect Transfers of Licenses and Draft Conforming Administrative License Amendments (EPID L-2020-LLM-0003) (Enclosure 1) Project stage: Draft Other ML21292A1492021-12-13013 December 2021 And Big Rock Nuclear Plant- Federal Register Notice Re Order Approving Transfer of Licenses and Draft Conforming Administrative License Amendments Project stage: Draft Other ML21292A1472021-12-13013 December 2021 Draft Conforming License Amendments - Palisades Nuclear Plant Renewed Facility Operating License DPR-20 and ISFSI and Big Rock Point Facility Operating License DPR-6 and ISFSI (EPID L-2020-LLM-0003) (Enclosure 2) Project stage: Draft Other ML21292A1482021-12-13013 December 2021 Safety Evaluation Related to Request for Direct and Indirect Transfers of Control of Facility Operating License DPR-6 for Big Rock Point and Renewed Facility Operating License DPR-20 for Palisades Nuclear Plant and ISFSI (EPID L-2020-LLM-00 Project stage: Approval ML21286A5812021-12-13013 December 2021 Holtec Dtf Exemption Project stage: Request ML21292A1552021-12-13013 December 2021 License Transfers Project stage: Request ML22173A1792022-06-23023 June 2022, 28 June 2022 Conforming Amendments for License Transfer to Holtec (L-2022-LLM-0002 and L-2020-LLM-0003) Project stage: Request ML22173A1782022-06-23023 June 2022 Enclosure 4 - Palisades Amendment to Indemnity Agreement No. B-40 - Amendment No. 13 Project stage: Other ML22173A1772022-06-23023 June 2022 Enclosure 3 - Big Rock Point Amendment to Indemnity Agreement No. B-22 - Amendment No. 20 Project stage: Other ML22178A0772022-06-24024 June 2022 (HDI) Satisfactory Documentary Evidence Required Before the Planned Closing Date of the Purchase and Sale Transaction of Palisades Nuclear Plant and Big Rock Point Plant Project stage: Request PNP 2022-019, & Big Rock Point - Notification of Expected Date of Transfer of Ownership of Nuclear Plants to Holtec Palisades, LLC; and Notification of Receipt of All Required Regulatory Approvals2022-06-24024 June 2022 & Big Rock Point - Notification of Expected Date of Transfer of Ownership of Nuclear Plants to Holtec Palisades, LLC; and Notification of Receipt of All Required Regulatory Approvals Project stage: Request ML22173A1762022-06-28028 June 2022 Enclosure 2 - Holtec Palisades, LLC and Holtec Decommissioning International, LLC - Palisades Nuclear Plant Amendment to Renewed Facility Operating License Project stage: Other ML22173A1752022-06-28028 June 2022 Enclosure 1 - Holtec Palisades, LLC and Holtec Decommissioning International, LLC - Big Rock Point Plant Amendment to Facility Operating License Project stage: Other ML22173A1732022-06-28028 June 2022 And Big Rock Point Plant - Issuance of Amendment Nos. 129 and 273 Order Approving Transfer of Licenses and Conforming License Amendments (EPIDs L-2022-LLM-0002 and L-2020-LLM-0003) Project stage: Approval ML22322A0722022-11-18018 November 2022 NRC-001 - Safety Evaluation Related to Request for Direct and Indirect Transfers of Control of Facility Operating License DPR-6 for Big Rock Point and Renewed Facility Operating License DPR-20 for Palisades Nuclear Plant and ISFSI Project stage: Approval 2021-12-03
[Table View] |
Text
December 13, 2021 EA-21-158 Mr. A. Christopher Bakken, III President, CEO Entergy Nuclear Operations, Inc.
1340 Echelon Parkway Jackson, MS 39213
SUBJECT:
PALISADES NUCLEAR PLANT AND BIG ROCK POINT PLANT - ORDER APPROVING TRANSFER OF LICENSES AND DRAFT CONFORMING ADMINISTRATIVE LICENSE AMENDMENTS (EPID L-2020-LLM-0003)
Dear Mr. Bakken:
By application dated December 23, 2020 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20358A075), as supplemented by information provided in letters from Holtec Decommissioning International, LLC (HDI) dated December 23, 2020, December 23, 2020, and October 29, 2021 (ADAMS Accession Nos. ML20358A232, ML20358A239, and ML21302A064, respectively), Entergy Nuclear Operations, Inc. (ENOI), on behalf of itself; Entergy Nuclear Palisades, LLC (ENP); Holtec International (Holtec); and HDI (collectively, the Applicants), submitted Application for Order Consenting to Transfers of Control of Licenses and Approving Conforming License Amendments. Specifically, the application requested that the U.S. Nuclear Regulatory Commission (NRC) consent to (1) the indirect transfer of control of Renewed Facility Operating License No. DPR-20 for the Palisades Nuclear Plant (Palisades), the general license for the Palisades independent spent fuel storage installation (ISFSI), Facility Operating License No. DPR-6 for Big Rock Point Plant (Big Rock Point), and the general license for the Big Rock Point ISFSI (referred to collectively as the Sites and the licenses) to Holtec and (2) the transfer of ENOIs operating authority (i.e., its authority to conduct licensed activities at the Sites) to HDI. In addition, the Applicants requested that the NRC approve conforming administrative amendments to the licenses to reflect the proposed transfer of the licenses from ENOI to HDI and the planned name change from ENP to Holtec Palisades, LLC.
The NRC published its notice of consideration of approval of the application in the Federal Register on February 4, 2021 (86 FR 8225). The supplemental information in the letter dated October 29, 2021, provided additional information that clarified the application and did not expand the scope of the application as originally noticed.
The NRC staff has completed its review of the application. Enclosure 1 is the order that consents to the license transfer, subject to the conditions described therein. The order also approves the draft conforming administrative license amendments in Enclosure 2, which the NRC will issue and make effective at the time the transfer is completed. Enclosure 3 is the NRC staffs safety evaluation related to the application.
The NRC forwarded the order to the Office of the Federal Register for publication.
If you have any questions concerning this action, please contact me at (301) 415-2855 or by e-mail to Scott.Wall@nrc.gov.
Sincerely,
/RA/
Scott P. Wall, Senior Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-155, 50-255,72-007, and 72-043
Enclosures:
- 1. Order Approving License Transfer (EA-21-158)
- 2. Draft Conforming Amendments
- 3. Safety Evaluation cc: Listserv
ENCLOSURE 1 ORDER APPROVING TRANSFER OF BIG ROCK POINT PLANT FACILITY OPERATING LICENSE NO. DPR-6 PALISADES NUCLEAR PLANT RENEWED FACILITY OPERATING LICENSE NO. DPR-20 BIG ROCK POINT PLANT INDEPENDENT SPENT FUEL STORAGE INSTALLATION PALISADES NUCLEAR PLANT INDEPENDENT SPENT FUEL STORAGE INSTALLATION DOCKET NOS. 50-155, 50-255,72-007, AND 72-043 (EA-21-158)
ENCLOSURE 2 DRAFT CONFORMING LICENSE AMENDMENTS PALISADES NUCLEAR PLANT RENEWED FACILITY OPERATING LICENSE NO. DPR-20 PALISADES NUCLEAR PLANT INDEPENDENT SPENT FUEL STORAGE INSTALLATION DOCKET NOS. 50-255 AND 72-007 AND BIG ROCK POINT PLANT FACILITY OPERATING LICENSE NO. DPR-6 BIG ROCK POINT PLANT INDEPENDENT SPENT FUEL STORAGE INSTALLATION DOCKET NOS. 50-155 AND 72-043
ENCLOSURE 3 SAFETY EVALUATION RELATED TO THE REQUEST FOR TRANSFER OF CONTROL OF FACILITY OPERATING LICENSE NO. DPR-6 FOR BIG ROCK POINT PLANT, RENEWED FACILITY OPERATING LICENSE NO. DPR-20 FOR PALISADES NUCLEAR
- PLANT, AND THE GENERAL LICENSES FOR THE INDEPENDENT SPENT FUEL STORAGE INSTALLATIONS FOR BIG ROCK POINT PLANT AND PALISADES NUCLEAR PLANT DOCKET NOS. 50-155, 50-255,72-007, AND 72-043
Package: ML21292A155 Letter: ML21292A145 Order: ML21292A146 Amendment: ML21292A147 Safety Evaluation: ML21292A148 FRN: ML21292A149 OFFICE NRR/DORL/LPL3/PM NRR/DORL/LPL3/LA Tech Editor NRR/DRO/IOLB/BC(A)
NAME SWall SRohrer JDougherty BGreen DATE 10/18/2021 10/20/2021 10/25/2021 11/02/2021 OFFICE NMSS/REFS/FAB NMSS/DFM/STLB/BC NMSS/DUWP/RDB/BC OGC - NLO NAME FMiller JMcKirgan BWatson JWachutka DATE 10/20/2021 11/02/2021 10/20/2021 11/23/2021 OFFICE OE/EB/BC NRR/DORL/LPL1/BC NRR/DORL/D NMSS/DFM/D NAME JPeralta (RFretz for)
NSalgado BPham (BWittick for)
SHelton DATE 11/24/2021 12/02/2021 12/03/2021 12/13/2021 OFFICE NRR/D NRR/DORL/LPL3/PM NAME AVeil (MKing for)
SWall DATE 12/13/2021 12/13/2021