ML18102B550

From kanterella
Jump to navigation Jump to search
Insp Repts 50-272/97-14 & 50-311/97-14 on 970622-0726. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support
ML18102B550
Person / Time
Site: Salem  PSEG icon.png
Issue date: 08/14/1997
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML18102B548 List:
References
50-272-97-14, 50-311-97-14, NUDOCS 9709020259
Download: ML18102B550 (49)


See also: IR 05000272/1997014

Text

-*

Docket Nos:

License Nos:

Report No.

Licensee:

Facility:

Location:

Dates:

Inspectors:

Approved by:

U. S. NUCLEAR REGULATORY COMMISSION

50-272, 50-311

DPR-70, DPR-75

REGION I

50-272/97-14, 50-311/97-14

Public Service Electric and Gas Company

Salem Nuclear Generating Station, Units 1 & 2

P.O. Box 236

Hancocks Bridge, New Jersey 08038

June 22, 1997 - July 26, 1997

M. G. Evans, Senior Resident Inspector

C. S. Marschall, Senior Resident Inspector

J. G. Schoppy, "senior Resident lnsplctor .

R. K. Lorson, Resident Inspector

T. J. Kenny, Senior Reactor Engineer

F. J. Laughlin, Resident Inspector

James C. Linville, Chief, Projects Branch 3

Division of Reactor Project:

9709020259 970814

PDR

ADOCK 05000272

G

PDR

.....

EXECUTIVE SUMMARY

Salem Nuclear Generating Station

NRC Inspection Report 50-272/97-14, 50-311/97-14

This integrated inspection included aspects of licensee operations, engineering,

maintenance, and plant support. The report covers a 5-week period of resident inspection.

  • In .addition, it includes the results of announced inspections by regional engineering and

emergency preparedness inspectors.

Operations

The inspectors observed professional and safety-conscious operations. (Section 01 . 1)

A control room supervisor's lack of attention to detail resulted in a missed entry into the

Technical Specification limiting condition for operation action statement for the Unit 2

control room intake duct radiation monitor. This was considered a non-cited violation

(NCV 50-311/97-14-01). Plant management promptly identified the operator performance

issue and took appropriate corrective actions. (Section 01.2)

Plant and operations management took timely and appropriate actions to address an

increase in operator errors that occurred in the early to middle part of the report period.

Since July 16, 1997, the number and frequency of operator performance issues has

decreased significantly and the control of activities by the control room supervisors has *

improved. The inspectors will continue to monitor operations performance prior to and

during the Unit 2 startup as part of normal inspection activities. In addition, for those

issues identified which require a Licensee Event Report (LER), the inspectors will further

review licensee corrective actions upon issuance of the LERs. (Section 07. 1)

Maintenance

A retest group operator and a maintenance supervisor demonstrated good questioning

attitudes in identifying that operators failed to perform adequate post maintenance tests of

main steam check valves. The failure to perform an adequate retest was considered a non-

cited violation (NCV 50-311197-14-02). Operators took prompt and appropriate corrective

actions to ensure the turbine-driven auxiliary feedwater pu!Tlp operability after the testing

deficiencies were identified. (Section M1 .2)

The operator's decision not to remove test equipment from the emergency diesel gen.erator

control cabinet during restoration from surveillance test procedure S2.0P-ST.DG-0001 was

improper and a violation of Technical Specification 6.8.1. (NOV 50-311197-14-03) (Section

M1 .3)

The attempt to test the feedwater stop check valves in a manner not defined by the ASME

Code demonstrated a weakness in implementation of the in-service test program.

Operations management's decision to leave these valves isolated while the issue was

under review was appropriate. (Section M1 .4)

ii

Engineering

Operations management implemented adequate interim actions to address the control of

entry into the control room envelope instrument backpanels. Licensee management

indicated that a detailed plan to correct this condition would be available by September 1 ,

1997. (Section E2. 1)

The licensee adequately investigated an unexpected control room ventilation alignment that

occurred during a maintenance activity. (Section E2.1 l

Plant Support

Recent licensee changes to the emergency plan and its implementing procedures did not

reduce the effectiveness of the emergency plan. The plan changes are subject to future

inspection. (Section P3.1)

iii

TABLE OF CONTENTS

EXECUTIVE SUMMARY

ii

TABLE OF CONTENTS .............................................. iv

I. Operations ................ * ...........................

~. . . . . . . . . .

1

01

Conduct of Operations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

1

01 . 1 General Comments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

1

01.2 Missed Technical Specification LCO Action for R1 B lnoperability . . . . . .

1

03

Operations Procedures and Documentation . . . . . . . . . . . . . . . . . . . . . . . . . .

2

03.1

(Closed} Inspector Followup Item 50-272&311 /96-0B-09 . . . . . . . . . . .

2

07

Quality Assurance in Operations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

2

  • 07. 1 . Human Performance Issues in Operations

. . . . . . . . . . . . . . . . . . . . . .

2

OB

Miscellaneous Operations Issue

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

OB.1

(Closed) Unresolved Items 50-311/96-B1-01 & 02 and LER 50-

272/96-037-00 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

OB.2

(Closed) Unresolved Item 50-311/96-B1-03 . . . . . . . . . . . . . . . . . . . . .

4

OB.3 (Closed) Unresolved Item 50-311/96-B1-10 . . . . . . . . . . . . . . . . . . . . .

5

II. Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6

M 1

Conduct of Maintenance .............. ; . . . . . . . . . . . . . . . . . . . . . . . . 6

M1 .1

General Comments ............................. * . . . . . . . . . 6

M1 .2 Post Maintenance Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6

M1 .3 2A Emergency Diesel Generator Post-Test Restoration . . . . . . . . . . . . . 7

M1 .4 Feedwater Stop Check Valve In-Service Testing

. . . . . . . . . . . . . . . . . B

M1 .5 Reactor Coolant System Pressure Isolation Valve Testing . . . . . . . . . .

10

MB

Miscellaneous Maintenance Issues . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

10

MB.1

(Closed) Unresolved Item 50-311/96-B1-05 . . . . . . . . . . . . . . . . . . . .

10

MB.2 (Closed} Unresolved Item 50-311/96-B1-06 . . . . . . . . . . . . . . . . . . . .

10

MB.3 (Closed) Unresolved Item 50-311/96-B1-0B . . . . . . . . . . . . . . . . . . . .

11

MB.4 (Closed) Unresolved Item 50-311/96-B1-09 . . . . . . . . . . . . . . . . . . . .

13

Ill. Engineering

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

14

E2

Engineering Support of Facilities and Equipment . . . . . . . . . . . . . . . . . . . . . .

14

E2.1

Control Room Emergency Ventilation System Design Issues . . . . . . . .

14

EB

Miscellaneous Engineering Issues . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

16

EB. 1

(Closed) Unresolved Item 50-311/96-B1-11 . . . . . . . . . . . . . . . . . . . .

16

EB.2

(Closed) Unresolved Item 50-311/96-B1-12 .................... 16

EB.3

(Closed) Unresolved Item 50-311/96-B1-15 . . . . . . . . . . . . . . . . . . . .

17

iv

IV. Plant Support . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

18

P3

EP Procedures and Documentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

1 8

P3. 1

In-Office Review of Licensee Procedure Changes . . . . . . . . . . . . . . . .

18

F8

Miscellaneous Fire Protection Issues . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

18

F8.1

Appendix R Post-Fire Alternative Shutdown; (Closed) Unresolved Item

50-27 2&311 /93-80-08 .......................... ; . . . . . . .

18

V. Management Meetings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

18

X 1

Exit Meeting Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

18

X2

Pre-Decisional Enforcement Conference Summary . . . . . . . . . . . . . . . . . . . .

18

v

Report Details

Summary of Plant Status

Unit 1 remained defueled for the duration of the inspection period.

Unit 2 began the inspection period in Mode 4. On July 3, operators increased average

coolant temperature above 350°F and entered Mode 3. On July 24, operators commenced

a cooldown of Unit 2 and entered Mode 5 on July 26.

I. Operations

01

Conduct of Operations

01 . 1 General Comments (71707)

Using Inspection Procedure 71707, the inspectors conducted frequent reviews of

ongoing plant operations. In general, the conduct of operations was professional

and safety-conscious; specific events and noteworthy observations are detailed in

the sections below.

01.2 Missed Technical Specification LCO Action for R1 B lnoperability

a.

Inspection Scope (71707)

The licensee identified that operators missed a Technical Specification action

requirement for control room radiation monitors for Salem Unit 2. The inspector

reviewed the licensee's corrective actions to address this deficiency.

b.

Observations and Findings

The Salem Unit 1 and Unit 2 Technical Specifications require two operable radiation

monitoring instrumentation channels for each control room ventilation intake. For

the Unit 2 intake duct, the radiation monitor instrumentation channels are 1 R 1 B-2

and 2R1 B-1.

On July 15, 1997, operators failed to complete the action required by Technical

Specification limiting condition for operation (LCO) action statement for the Unit 2

control room ventilation intake duct. Specifically, control room operators allowed

channel 2R 1 B-1 to being taken out of service for a channel count per procedure

S2.IC-CC.RM-0002, while the redundant channel, 1 R1 B-2, was inoperable. On

July 13, 1997, 1R1 B-2 had elevated counts due to a pin hole leak in the Mylar foil

and had been declared inoperable.

Both channels were inoperable for about three

hours. Per Technical Specification 3.3.3.1, with less than the required channels

operable, the control room emergency air condition system (CREASl must be placed

in service. This was not done immediately, because the senior reactor operators

(SROs) did not immediately recognize that both channels were inoperable.

2

The cause of this issue appears to be a weakness in personnel performance on the

part of the control room supervisor (CRS) who did not take the time to fully

understand which radiation monitor channels were already considered inoperable

when he allowed 2R 1 B-1 to be taken out of service. There were also weaknesses

in logging the condition of the radiation monitor channels in the Technical

Specification Action Statement (TSAS) log and the nomenclature for identification of

the radiation monitor channels.

The licensee's immediate corrective action included discipline of the SRO involved

and the addition of independent reviews for all entries and exits from the TSAS log .

. The licensee is developing longer term corrective actions such as changes in the

nomenclature for the radiation monitor channels and additional operator training on

the system. These actions will be detailed in the Licensee Event Report for this

missed Technical Specification action requirement.

The failure to compelte the action required by the LCO action statement is a

violation of Technical Specification 3.3.3.1. However, this licensee-identified and

corrected violation is being treated as a Non-cited Violation, consistent with Section

Vll.B.1 of the NRC Enforcement Policy. (NCV 311/97-14-01)

c.

Conclusions

Although a control room supervisor's lack of attention to detail resulted in a missed

entry into the LCO action statement for the Unit 2 control room intake duct

radiation monitor, the licensee promptly identified the condition and took

appropriate corrective action.

03

  • Operations Procedures and Documentation

03.1

!Closed) Inspector Followup Item 50-272&311 /96-08-09: procedures for cross

connecting Salem Unit 1 &2 spent fuel cooling systems.

Section 9.1.3.2 of the Updated Final Safety Analysis Report (UFSAR) states that

the Unit 1 &2 spent fuel cooling systems can be cross-connected if required. In

March 1996 an NRC inspection identified that no operating procedure existed to

operate in this configuration.

The inspector reviewed procedure S2.0P-SO.SF-0002(Z), Spent Fuel Cooling

System Operation, and found that the procedure was revised to provide instructions

for cross-connected operation. Inspector followup item 96-08-09 is closed.*

07

Quality Assurance in Operations

07.1

Human Performance Issues in Operations

On July 16, 1997, plant management implemented actions to address a series of

operational errors that had occurred since May 1997. A majority of the errors

occurred during the period June 30 through July 15, 1997. Although, individually,

3

the issues were not considered significant by the licensee or the NRC, taken as a

whole, they reflected an overall decline in performance in Salem operations

department. For example, in May 1 997; the NRC identified that the operations staff

did not document and pursue the root cause of recurring configuration control

deficiencies (Violation 50-272&311 /97-12-02). During the period June 30 through

July 15, 1997, licensee identified issues included: a Unit 1 effluent release

performed without performing the Technical Specification required independent

verification of the tank valve line-up; the surveillance requirement to perform a

channel check of all 4 loss of power event (LOOP) average temperatures was not

performed as required upon raising temperature above 543 degrees Fahrenheit;

operators failed to perform a required post-maintenance test following a main steam

check valve packing adjustment and did not ensure operability of the 23 auxiliary

feedwater pump (discussed in Section M1 .2 of this report); and a CRS missed a

Technical Specification action requirement for control room radiation monitors for

Salern Unit 2 (discussed in Section 01.2 of this report).

As of July 16, 1997, the corrective actions implemented by licensee management

included: independent verification of all entries and exits from the Technical

Specification Action Statement log; the use of the NAP-5 brief sheet for all

evolutions; and improved control and enforcement of the work schedule. Licensee

management briefed NRC Region I management on these issues, including the

corrective actions, on July 17, 1997. The licensee implemented a level 1 Condition

Report (AR #970717297) to provide additional review of the potential common

causes of these human performance issues following completion of the root cause

evaluations for the individual issues.

c.

Conclusions

The inspectors found that the actions that licensee management took to address the

increase in operations errors were appropriate and very good. Management

responded to the indication of a decline in operator performance in a timely manner.

Since July 16, 1997, the number and frequency of operations human performance

issues has decreased and control of activities by the control room supervisors has

improved. In addition, for those issues identified above which require a Licensee

Event Report (LER), the inspectors will further review licensee corrective actions

upon issuance of the LERs.

08

Miscellaneous Operations Issue

08.1

(Closed) Unresolved Items 50-311 /96-81-01 & 02 and LER 50-272/96-037-00: As

an interim measure, in 1995, PSE&G initiated a policy to ensure that at least two

component cooling (CC) pumps were operable during plant operation, but failed to

appropriately account for a single failure of CC pump room ventilation. The failure

of the 22/23 CC pump room cooler, when the 21 CC pump was out of service,

could have resulted in no available CC pumps during some postulated accident

conditions. PSE&G properly notified the NRC in LER 96-037-00 on

December 26, 1996.

4

The effect of the failure of the 22/23 CC pump room cooler on the operability of the

equipment within the room had not previously been considered. Specifically, the

22/23 CC room cooler failure would result in reduced *air flow for room cooling and

could lead to the failure of the CC pumps, and other equipment, due to unanalyzed

high temperatures. PSE&G implemented the following actions to ensure that

current Emergency Operating Procedures (EOPs) are not adversely affected by

failure of the room cooler to the 22/23 CC pump room:

1 .

The door to the 22/23 CC pump room was removed to allow increased air

flow into the pump room with the room cooler failed.

2.

The air flow to the CC pump rooms was re-balanced to redirect a portion of

flow from the 21 CC room cooler.

3.

Based on new calculations, the 22/23 CC pump room temperature remains

below 130°F under design basis accident conditions, including failure of the

22/23 CC pump room cooler.

4.

Electrical equipment in the 22/23 CC pump room is acceptable to 132°F,

with the exception of seven relays that were subsequently replaced.

5.

Mechanical equipment in the 22/23 CC pump room (e.g. pumps, lubricants,

bearings, MOVs, etc.) was evaluated as satisfactory up to 132°F.

6.

FSAR change request No. 97-05 was approved to revise Section 9.4.2 to

address the room cooler failure.

The inspectors independently reviewed the calculation "CC Pump Room

Temperature Following a Room Cooler Failure" and verified that the adjusted flow

from the 21 CC pump room cooler was included in the calculation. The inspector

verified that an electrical relay evaluation appeared complete, regarding the seven

relays that were not rated to perform at the calculated maximum temperature of

132 ° F and reviewed completed work orders to verify that the seven relays were

replaced. The inspector verified that various components were properly evaluated

for* 132 ° F and visually verified that the doors between the 22/23 CC pump room

and the hallway were removed.

Based on the above, the unresolved items and LER are closed.

(Closed) Unresolved Item 50-311 /96-81-03: Emergency Operating Procedures had

previously allowed a CC pump to operate at flow rates beyond its documented

design limits for a short period of time. The failure to provide a technically sound

basis for operating a CC pump in this manner was unresolved.

An engineering analysis had been prepared by MPR Associates, Inc. that determined

the CC pumps could operate reliably during and after the run-out condition, which

lasts approximately 10 to 15 minutes. The NRC inspector had reviewed the MPR

analysis and questioned the conclusion because ( 1) the evaluated run-out flow of

5

5600 gpm was less than flows being predicted by the current system flow model

(around 6300 gpm) and (2) the pump manufacturer (Goulds Pump Co.) had not

provided input to the evaluation.

PSE&G arranged and conducted two pump tests, one at the manufacturer's test

facility and the other at Salem Unit 1 . The insp.ector reviewed documentation

related to both pump tests and concluded that the test flow rate exceeded the

previously calculated system flow rate for the run-out condition. The testing

confirmed the MPR analysis, that the CC pumps will perform adequately during and

after run-out conditions.

Based on the above, the unresolved item is closed.

08.3 !Closed) Unresolved Item 50-311/96-81-10: This unresolved item was identified

during the review of the technical basis for assuring that adequate CC water flow

will be provided to emergency core cooling system coolers following the initiation of

an accident. The licensee's operations staff indicated that the EOPs would direct

the operators to manually start a CC pump in less than 20 minutes after the

initiation of any accident event. However, PSE&G was unable to provide

documentation to support this assessment.

The inspector reviewed CR 950814345, Condition Report Corrective Action (CRCA)

No. 3 which documented that the operations staff confirmed, through simulator

training scenarios, that a CC pump can be started in less than ten minutes. With an

SI signal and loss-of-power, the CC pump was started by the operators using the

EOPs regardless of the initiating event (i.e. large-break LOCA, small-break LOCA,

etc.) in less than ten minutes. Consequently, under post accident conditions, a CC

pump could be started and provide cooling to emergency core cooling system

(ECCS) seal coolers within the 15 to 20 minute requirement of the 1980

Westinghouse letter. The inspector had discussions with an operation supervisor

and confirmed that several different crews performed the scenarios with the same

acceptable results stated above.

In addition to the above, the inspector noted that the CC pump was started during

the injection phase of a LOCA. In this case, the injection water (from the refueling

water storage tank (RWST)) will typically be 80°F or below (with maximum

temperatures in the mid-90s). Since CC temperatures can approach 100°F under

design basis conditions, the seals are effectively self-cooled (by the cooler RWST

water) throughout the injection phase. Consequently, with a CC pump starting prior

to the recirculation phase (where pumped fluids approach containment accident

temperatures and begin heating the seals), the ECCS pumps are effectively never

without cooling under post-accident conditions.

Based on the above, the unresolved item is closed.

6

II; Maintenance

M1

Conduct of Maintenance

M 1 . 1 General Comments

a.

Inspection Scope (61726)

The inspectors observed all or portions of the following surveillances:

  • 52.0P-ST.SJ-0020:
  • 52.0P-ST.DG-0003:
  • 52.RE-ST.ZZ-0002:
  • 52.0P-ST.RC-0008
  • 52.0P-ST.AF-0006:
  • 52.0P-ST.CBV-0003:

Periodic Leakage Test RCS Pressure Isolation Valves -

Mode 4

2C Diesel Generator Surveillance Test

Shutdown Margin Calculation

Reactor Coolant System Water Inventory Balance

lnservice Testing Auxiliary *Feedwater Valves

Containment Systems Cooling Systems

The inspectors observed that plant staff did the surveillances safely, effectively

proving operability of the associated system.

M1 .2 Post Maintenance Testing

a.

Inspection Scope (71707)

The licensee identified that operators failed to perform a required post maintenance

test (PMT) following a main steam check valve packing adjustment and did not

ensure operability of the no. 23 auxiliary feedwater pump. The inspector reviewed

the licensee's corrective actions to address this deficiency.

b.

Observations and Findings

On July 4, 1997, maintenance technicians adjusted the packing on 21 MS46, "no.

21 main steam header check valve to no. 23 turbine-driven auxiliary feedwater

(TDAFW) pump." On July 6, maintenance technicians adjusted the packing on

23MS46, "no. 23 main steam header check valve to no. 23 TDAFW pump." In

both cases, operators did not perform a PMT to ensure continued TDAFW pump

operability.

On July 14, an operator in the retest group identified that operators did not perform

the PMT following the work on 21 MS46. Operators declared the TDAFW pump

inoperable and entered TS LCO 3.7.1.2.B. Within 5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />, operators performed

S2.0P-ST.AF-0006, lnservice Testing Auxiliary Feedwater Valves, to demonstrate

operability of 21 MS46 and declared the TDAFW pump operable. Operators initiated

a significance level 1 AR (970714384) to address the root cause of their failure to

perform the required PMT.

c.

7

On July 15, a maintenance supervisor identified that operators failed to perform a

PMT following 23MS46 maintenance on July 6. Operators declared the TDAFW

pump inoperable, performed S2.0P-ST.AF-0006 to restore operability and initiated

another level 1 AR (970715183) to address this failure as some of the contributing

factors appeared different from the 21 MS46 inadequate PMT. The inspector noted

that the retest group operator and the maintenance supervisor demonstrated good

questioning attitudes in identifying the missed PMTs. In both cases, operators

appropriately considered the TDAFW pump inoperable and promptly completed the

applicable surveillance test. The missed PMTs resulted in no safety consequence as

the successful surveillance tests demonstrated continued operability of the TDAFW

pump despite the main steam check valve maintenance. Failure to perform an

adequate PMT is a violation of NC.NA-AP.ZZ-0009, Work Control Process. This

non-repetitive, licensee-identified and corrected violation is being treated as a Non-

Cited Violation, consistent with Section Vll.B.1 of the NRC Enforcement Policy.

(NCV 50-311197-14-02)

Conclusions

A retest group operator and a maintenance supervisor demonstrated good

questioning attitudes in identifying that operators failed to perforn:i adequate post

maintenance tests of main steam check valves. Operators took prompt and

appropriate corrective action to ensure turbine-driven auxiliary feedwater pump

operability and root cause evaluation of the identified deficiencies.

M1 .3 2A Emergency Diesel Generator Post-Test Restoration

a.

Inspection Scope (61726/71707)

The inspectors reviewed an observation that electrical test equipment remained

connected to the 2A emergency diesel generator (EOG) for about nine hours on July

2 while the 2A EOG was considered operable.

b.

Observations and Findings

The 2A EOG was tested early on July 2 in accordance with surveillance test

procedure, S2.0P-ST.DG-0001, 2A Diesel Generator Surveillance Test. The

operators completed the test and declared the EOG operable at 0545. The

inspector subsequently observed that the 2A EOG control cabinet door was partially

open and that electrical test equipment installed for the test remained connected

inside the 2A EOG control cabinet.

The CRS indicated that the test equipment had not been removed in order to

support additional EOG testing scheduled for later that day. The CRS also indicated

that the step in ST.OP-ST.DG-0001 that directed removal of the test equipment had

been marked as not applicable, and the second test procedure had been initiated up

to the step that installed the equipment. The operators, however, were unable to

immediately perform this test since the EOG lubricating oil system had to cooldown

in order to meet the initial test conditions.

8

The inspector questioned whether leaving the EOG control cabinet in this condition

affected its operability and also whether this condition had been previously

evaluated. The inspector discussed this question with operations management who

agreed to review the issue and also implemented interim guidance to declare the

EOG inoperable anytime the control cabinet door was opened.

The EOG system manager's initial operability review focused on electrical separation

of the EOG control circuitry from the non-1 E test equipment and associated power

supply, and also on the impact of a seismic event on relays mounted on the EOG

control panel door. The final assessment had not been provided prior to the end of

this report period.

The inspector also reviewed an evaluation that had been performed in 1993 to

justify installation of the test equipment, and noted that it did not provide a basis

for concluding that the EOG could remain operable while the test equipment was

installed. The inspector concluded that the operator's decision not to remove the

EOG test equipment as required by step 5.11.5 of S2.0P-ST.OG-0001 before

completing the procedure and declaring the EOG operable was improper since this

condition had not been previously analyzed.

Technical Specification 6.8.1 requires, in part, that written procedures be

implemented to perform surveillance testing of safety-related equipment. Contrary

to the above surveillance test procedure S2.0P-ST.OG-0001 was not properly

implemented on July 2 since test equipment was not removed from the 2A EOG

control cabinet as required by step 5.11.5 of the procedure. This constitutes a

violation of TS 6.8.1. (VIO 50-311/97-14-03)

c.

Conclusions

The operator's decision not to remove the test equipment from the EOG control

cabinet before completing surveillance test procedure S2.0P-ST.OG-0001 was

improper and a violation of Technical Specification 6.8.1.

M1 .4 Feedwater Stop Check Valve In-Service Testing

a.

Inspection Scope (61726)

b.

The inspector reviewed the licensee's response to the failure of two feedwater stop

check valves (22BF22 and 23BF22) to meet their in-service test (IST) performance

requirements.

Observations and Findings

The BF22 valves are normally open piston stop check valves that have an active

safety function to close for: 1) containment isolation, and 2) to prevent the

diversion of auxiliary feedwater flow through a feedwater line break upstream of

these valves. The BF22 valves are designed to close automatically upon reversal of

flow and are provided with a motor operator to minimize seat leakage through the

valve.

9

Technical specification 4.0.5 requires the valves be tested in accordance with the

American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code

unless granted specific relief. The IST program requires the check valve feature to

be tested to support operability of the auxiliary feedwater system. The applicable

ASME Code provides two methods for testing the check valve function. The first

method involves observation that the valve disc travels to its seat upon the

cessation or reversal of flow. The observation can be either direct (i.e. position

indicator) or indirect such as observing a system pressure change. The second

method for testing the check valve function would be to disassemble and inspect

the check valve.

The BF22 valves were tested on July 1 per test procedure S2.0P-ST.MS-0002,

lnservice Testing Main Steam And Main Feedwater Valves, which involved

establishing reverse flow through the valves while the steam generators were

press1,Jrized to about 90 psig. The valves failed to establish the required 50 psig

differential pressure specified by the test procedure to confirm the valve closure.

The licensee subsequently revised the test procedure to require that the motor

operator be used to shut the check valves during the testing. Salem engineering

personnel stated that use of the motor operator was technically acceptable since

the motor operator developed only about 50% of the seating force that the valve

would experience at full steam generator operating pressures.

The inspector questioned this test method since it was not defined in the applicable

ASME Code or in NUREG 1482 which contained general guidance for testing stop

check valves. The inspector reviewed this issue with a Region I specialist inspector

and with a NRR technical specialist who indicated that use of the motor 'operator to

test the valve had not been defined by the ASME Code or NUREG 1482.

Operations management maintained the 22BF22 and the 23BF22 valves isolated

while this issue was being reviewed.

The licensee reviewed this information and subsequently decided to test the BF22

valves using a reverse flow method with the steam generator at a higher initial

pressure. The BF22 valves were observed to change position by either

establishment of the required differential pressure or by acoustic monitoring.

c.

Conclusions

The inspector concluded that the final BF22 valve test method met the ASME Code

test requirements. The inspector considered the operations management decision to

leave these valves isolated while the issue was being reviewed appropriate. The

attempt to test the BF22 valves in a manner not previously defined by the ASME

Code demonstrated a weakness in implementation of the IST program .

10

M1 .5 Reactor Coolant System Pressure Isolation Valve Testing

The inspector observed the operators test the reactor coolant system pressure

isolation check valves specified by Technical Specification surveillance requirement 4.4.7.2.2d. The inspector noted that the testing was performed in accordance with

surveillance procedure S2.0P-ST.SJ-0020, Periodic Leakage Test RCS Pressure

Isolation Valves Mode 4, and the valve performance satisfied the test acceptance

limits. The inspector also reviewed the test flowpath against the system drawing

and concluded that the test lineup was acceptable.

MS

Miscellaneous Maintenance Issues

M8.1 (Closed) Unresolved Item 50-311 /96-81-05: This item was opened because the

NRC concluded that the computerized model used to predict component cooling

heat ~xchanger (CCHX) performance, based on test data, may not be conservative.

PSE&G was in contact with the heat exchanger manufacturer to resolve this issue.

The NRC concluded that the lack of a specific documented technical basis for the

five percent instrument measurement uncertainty assumption used in CC heat

exchanger performance calculations was an unresolved item.

The inspector reviewed calculation S-C-CC-MDC-1686 Rev 0, performed to .

determine the instrument measurement uncertainty. The calculation documented

the technical basis for instrument uncertainty associated with heat exchanger

performance testing. The results of the calculation showed the instrument

measurement uncertainty for 21 CCHX to be plus or minus 2.42 percent and plus or

minus 4:83 percent for 22CCHX. These percentages are within the acceptance

criteria stated above. Therefore, the inspector determined that the calculation

supported the five percent uncertainty assumption used in calculating the heat

transfer rate.

Based on the above, the unresolved item is closed.

(Closed) Unresolved Item 50-311 /96-81-06: The lack of acceptance criteria for

assessing the as-found condition of the CC room coolers and the lack of criteria for

establishing adequate service water and air flow rates in CC room cooler

maintenance procedures were considered to be unresolved items.

The inspector reviewed the procedures for inspecting service water room cooler

internals and for performing service water biofouling monitoring of room coolers.

The procedure for inspecting service water room cooler internals does not provide

specific criteria for assessing the as found condition of the heat exchanger.

However, PSE&G has taken actions to reduce the amount of material deposited in

the heat exchangers. Through interviews with the system engineer, the inspector

verified that the service water is continuously chlorinated to eliminate biofouling.

Further, the inspector verified through photos that PSE&G had applied an epoxy

lining to the heat exchanger internals. According to the system engineer, this

epoxy lining has* not demonstrated failures and was installed to prevent pitting and

corrosion. The "as found" photos, taken after opening the coolers did not show

11

any excessive debris. Finally, the inspector verified that the room cooler heat

exchangers are scheduled to be cleaned and inspected every refueling outage, and

the cleaning procedure includes both the water and air sides of the heat

exchangers.

The inspector reviewed and verified that the procedure for performing service water

biofouling monitoring of room coolers was revised to include a periodic room cooler

service water differential pressure test. This procedure provides criteria for

determining unacceptable differential pressures by including a methodology for

determining the differential pressure limit. According to the system engineer, the

periodic differential pressure tests for the room coolers are scheduled to be

performed every 90 days, however, this frequency is subject to change depending

on the initial trended data.

In order to verify acceptable air flow rates through the room cooler heat exchangers,

the inspector reviewed the results of the flow balance tests and verified that the

measured flow rates for cooling room ventilation, correlated to the design flow rates

as depicted in the current design basis. Further, in order to ensure proper

ventilation to the CC pump rooms, PSE&G is in the process of establishing a

procedure and recurring task to periodically verify the adequacy of the auxiliary

building ventilation supply and exhaust flows for CC pump room cooling. These

procedures are not considered essential to re-start efforts, and are scheduled to be

completed by August 1, 1997.

Based on the above, the unresolved issue is closed.

M8.3 (Closed) Unresolved Item 50-311196-81-08: This item was identified during the

review of the ventilation system to determine its capability and readiness in

supporting the operability of the CC system.

The NRC had observed three design and configuration deficiencies during plant walk

downs:

1 .

The louvered fire damper in the fire door (Door C8-2) for 21 CC pump room

was closed and design information concerning this damper was not available.

The impact of this closed louvered fire damper on return air flow and room

temperature had not been determined, thus the closed louvered fire damper

may have prevented the CC room coolers from performing their design basis

function.

PSE&G concluded that due to leakage around the damper and the door, the

closed louvered fire damper in the 21 CC pump room did not adversely affect

the flow balance. The fire damper was determined to be inoperable and was

subsequently replaced. The auxiliary building ventilation flow balance for

this area was re-performed.

12

The inspectors reviewed the Performance Improvement Requests (PRs) for

the closed louvered fire damper in Door C8-2 (fire door for 21 CC pump

room). The PRs indicate that the fire protection group performs daily visual

inspections of fire doors, however, inspection of fire dampers on these doors

was not included. The inspector verified that the Fire Protection daily

inspection procedures were revised to include the position of the louvered

fire dampers as part of the daily inspection. In addition, the inspector-

reviewed the results of the flow balance tests and v*erified that the measured

flow rates for the 21 CC pump room ventilation correlated to the design flow

rates as depicted in the design basis.

The inspector questioned PSE&G personnel regarding the available design

information concerning the louvered fire damper in door C8-2. No air flow

calculation existed to determine if the louver in the fire door was adequately

sized. PSE&G determined a calculation was not necessary based on the

results of the flow balance tests, which indicated proper design flows were

achievable. The inspector reviewed the results of the flow balance tests and

verified that the measured flow rates for the 21 CC pump room ventilation,

correlated to the design flow rates as depict~d in the design basis.

In order to ensure proper ventilation to the CC pump rooms, PSE&G is in the

process of establishing a procedure and recurring task to periodically verify

the adequacy of the auxiliary building ventilation supply and exhaust flows

for CC pump room cooling. These procedures are not essential to re-start

efforts, and are scheduled to be complete by August 1 , 1997.

2.

The manual (2-VHE-747) damper, which supplies ventilation air to the 21

and 22/23 CC pump .rooms, and the manual (2-VHE-749) damper, which

supplies ventilation air to the 22/23 CC pump room, were closed.

The inspectors reviewed the Performance Improvement Request that

indicated the room cooler ducts were re-balanced upon verification that the

ventilation dampers were open. The inspector reviewed the results of the

flow balance tests and verified that the measured flow rates for the room

cooler dampers correlated to the design flow rates as depicted in the design

basis. In addition, the inspector visually verified that the ventilation dampers

were in the open position.

3.

PSE&G could not account for the position of the dampers described above

and indicated that there were no existing administrative controls regarding

ventilation damper positions to support equipment operability of safety-

related systems.

The inspectors verified that PSE&G has issued an action request to establish

programmatic controls associated with damper positions. These

programmatic controls were not essential for restart efforts and will be

complete post-restart.

13

PSE&G has completed actions to ensure adequate ventilation air flow to the CC

pump rooms by verifying proper damper and louver positions, and by periodically

performing flow balance tests.

Based on the above, the unresolved item is closed.

M8.4 (Closed) Unresolved Item 50-311196-81-09: This unresolved item was identified

during the review of the maintenance and surveillance test procedures required to

support the CC system. The 125 Volt batteries support control of the CC system

pumps, the on-site power supply, and power the pilot solenoid valves. The EDGs

supply power for the CC system pumps and motor operated valves. The NRC

concluded that the failure to incorporate the latest technical specification

surveillance criteria in the battery surveillance performance test procedure was a

procedure weakness. The NRC also concluded that the licensee had previously

failed to follow their battery performance test procedure for calculating the capacity

of batteries 2A and 2B in 1993 because of the inadequate test procedure.

The inspector reviewed condition report (CR) 961 206169 which indicated that the

1993 testing met technical specification requirements for battery capacity but failed

to provide a reference to determine battery degradation for the test in 1998. The

inspector verified by reviewing the test (1.SC.MD-FT.125-0002(0)) performed in

1993 that the calculation, required by the test, was not performed. This calculation

documents the battery's capacity and should be greater than 80 percent of the

manufacturers rating when subject to a performance discharge test as stated in

Technical Specification (TS) 4.8.2.3.2.g.

Technical Specification 4.8.2.3.2.h requires the current battery capacity to be at

least 80 percent of manufacturer's rating if the battery shows signs of degradation

as compared to the previous test (degradation is defined as ten percent). The

inspector verified that the results have been extrapolated to establish capacities of

115% (battery 2Al and 112.5% (battery 2B) and have been documented as

reference points for the 1 998 test. The extrapolated values are scheduled to be

added to the test procedure in accordance with CRCA No. 1 to CR 961206169 with

a completion date November 11, 1997. The inspector verified that revision 5, to

procedure SC.MD-FT.125-0002(0) has now included additional wording to ensure

compliance with TSs.

Based on the above, the unresolved item is closed.

. '

14

Ill. Engineering

E2

Engineering Support of Facilities and Equipment

E2.1

Control Room Emergency Ventilation System Design Issues

a.

Inspection Scope

The inspector reviewed two issues associated with the design and operation of the

control room emergency ventilation system. The first issue involved an unexpected

system lineup that occurred following a momentary loss of power to the control

room radiation monitoring instruments. The second issue involved the necessity to

.enter TS 3.7.6.c upon opening the control room envelope instrument backpanel

doors.

b.

Observations and Findings

Control Room Emergency Ventilation System Response To An Unexpected Electrical

Transient On July 20

On July 20, a momentary electrical spike occurred on the 1 B vital instrument bus

during a maintenance activity. The electrical spike caused a momentary loss of

power to the control room radiation monitors ( 1 R 1 B-1 (Unit 1) and 1R1 B-i (Unit 2)

that automatically shifted the control room ventilation system to an unexpected

configuration. The resultant ventilation lineup was equivalent to the "accident

pressurized" mode of operation with the exception that both the Unit 1 and the Unit

2 control room emergency ventilation intake dampers were open. The normal

accident pressurized mode of operation would have aligned the control room

ventilation intake to the "non-accident" unit intake dampers while the intake

dampers on the "accident" unit remained shut. The intake dampers are located

external to the auxiliary building of each unit.

The control room operators recognized the abnormal system lineup, aligned the

system to the defined accident pressurized mode of operation, and made the 4 hour4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />

non-emergency event notification per 10 CFR 50. 72. The licensee reviewed the

event and determined that the system functioned properly per the installed plant

design, and also that the "as founq" system lineup would not have resulted in

exceeding the 10 CFR 50 Appendix A Design Criterion 19 control room personnel

exposure limits.

The inspector questioned the expected system response to a loss of offsite power

(LOOP). The licensee indicated that the radiation monitors would remain powered

during a LOOP event since they had a dual power supply with a battery backup.

The inspectors concluded that the licensee performed an adequate followup of this

event and that it had minimal significance .

15

Entry Into The Back Of The Control Room Envelope Instrument Panels

The licensee installed magnetic strips to seal the back of the normally shut control

room instrument panels (which form a portion of the control room envelope), and

also cut ventilation openings into the front and tops of the panels. This modification

was required to limit air leakage through the panels to allow the control room

emergency ventilation system to develop the required positive pressure ( + 1 /8 in.) in

the control room envelope relative to the adjacent spaces.

Salem also installed manually operated louvers to seal the front and top ventilation

openings to support transfer of the control room envelope to the front of the

instrument panels when the backpanel doors were opened. Salem operations and

maintenance personnel enter the panels weekly for log readings, and to perform

preventive and corrective maintenance activities. The licensee identified during

post-installation testing that shutting the louvers did not adequately seal the

instrument panels for the limiting design condition. Salem management decided, in

the interim, to declare the control room envelope inoperable and enter TS 3.7.6.c

anytime the back panel doors are open.

The resident inspectors observed this practice and questioned the frequency and

control of entries into the backpanels and also the planned corrective actions to

eliminate the need to enter TS 3. 7 .6.c. Operations management responded to these

concerns by reducing the number of planned entries into the backpanels, and also

by implementing tighter controls for opening the backpanel doors. The control room

envelope can be restored by shutting the backpanel door and by re-installing the

magnetic strips. The licensee is developing permanent corrective actions to address

this problem.

'

The inspectors noted that although the number of planned entries has decreased

there are still frequent entries into the backpanels for corrective maintenance

activities. For instance during a two week period, (June 27 to July 9) the inspector

noted that the backpanels were entered for four different corrective maintenance

activities. The inspector noted improved controls during the recent backpanel

entries. The inspector concluded that the licensee's interim actions were adequate.

This issue was discussed during a conference call between Region I management

and Salem plant and engineering management. Salem management indicated that a

detailed plan to correct this condition would be available by September 1, 1997.

c.

Conclusions

The licensee implemented adequate interim actions to address the control of entry

into the control room envelope back panels. Licensee management indicated that a

detailed plan to correct this condition would be available by September 1, 1997 .

ES

16

Miscellaneous Engineering Issues

!Closed) Unresolved Item 50-311196-81-11 : The NRC concluded that there were

significant weaknesses in the calculation for the selection of the thermal overload

relays (TOLs) for the CC system MOVs. The design change to place the TOLs

inservice resulted in the installation of TOLs without a documented design basis.

The NRC concluded that the licensee had not maintained document control of the

TOLs associated with the CC system and other safety-related systems, because

heater sizes existed in MOV circuits that were not based on the existing calculated

basis. The NRC also concluded the change document to the design calculation did

not provide any documented basis to accept the installed TOL heaters for 30 safety-

related MOVs.

The inspector confirmed that during the process of implementing design change

packC!ge (DCP) 2EC-3249 (design change to remove jumpers from around the TOL

contacts and replace them with resized TOLs), the licensees' storeroom expended

the designated TOLs and issued similar ones in their place. After the design

engineer evaluated the newly issued TOLs and had them installed instead of the

original, the DCP was not properly updated to reflect the change. For example; the

single line diagram was updated to reflect the substituted (C3.01 A) TOL, however,

the revised calculation (E18.006) that showed the substitute relay would perform

the same as the original (C3.56A) TOL was l')Ot placed in the completed DCP

paperwork.

A total of 32 TOLs that were installed in MOVs were not documented properly. The

inspector reviewed design evaluation workbook-5 (1 EA-1260) that was performed

to document the acceptability of the as built configuration. Workbook-5 used the

same method of calculating point of trip for the TOLs that was used in the original

time concurrent characteristic (TCC) curves. The inspector verified that the TCC

curves, developed by workbook-5, showed that the MOVs would be capable of

performing their safety function without experiencing spurious trips with the

installed TOLs. The inspector verified that the Maintenance Management

Information System (MMIS) was updated to reflect the correct as installed TOLs.

The inspector concluded that the licensee took adequate actions to address this

issue. This unresolved item is closed.

E8.2

(Closed) Unresolved Item 50-311196-81-12: The NRC concluded that the design

basis documentation for the CC system radiation monitors was inconsistent. The

NRC also determined that the CC radiation monitor setpoints may be inappropriately

set high. These radiation monitors are not safety-related and are not used to

calculate offsite radioactive releases. The NRC also identified that the design basis

setpoint calculation for the surge tank level alarms contained missing information

identified in the body of the calculation, but had not been included in a system to

track its resolution .

17

The inspector reviewed CRCA No. 2 to CR961125133 that contained a workbook-4

calculation that showed the present R-1 7 radiation monitor set-point was

acceptable. The calculation showed that the R17 alarm setpoint would alarm in less

than 30 seconds with the reactor coolant leakage above one gpm with the worst

case bounding reactor coolant activity concentrations. The inspector reviewed 10

CFR 20 Appendix B table 2 and table 11 .1-8 of the UFSAR, and verified that the

chosen isotope "Iodine 131" was the bounding isotope, because it requires the

most dilution (2E-10 mCi/ml of air and 1 E-6 mCi/ml of water). Therefore, the

inspector concluded that the present setpoint provides an adequate barrier against .

exceeding 10 CFR limits for the limiting isotope Iodine 131, chosen for the

calculation. CRCA No. 2 to CR9611 25133 was issued to update the set-point basis

in the "Radiation Monitoring Configuration Basis Document" (CBD) and the vendor

manuals. The CBD and vendor manuals are scheduled to be up-dated, post-restart.

The scheduled completion date is December 30, 1997.

Based on the above, the unresolved item is closed.

E8.3

(Closed) Unresolved Item 50-311196-81-15: The NRC concluded that providing post

accident sampling system (PASS) heat exchanger cooling water from the

demineralized water system was inconsistent with the UFSAR. This issue was

unresolved pending the completion of the licensee's evaluation and assessment for

using demineralized water instead of CC.

The inspector reviewed UFSAR Section 9.3.6.2 that stated 10 gpm of CC ~ater is

supplied to the sample cooler rack to cool reactor coolant samples. Since CC to the

PASS sample cooler is provided from the Unit 2 CC system and is physically

connected to CC piping feeding the boric acid evaporator coolers, the Unit 2 CC

must be operating and the CC valves to the boric acid evaporator must be open, in

order to supply cooling water to PASS. However, under post-accident conditions,

the boric acid evaporator will* be manually isolated to reduce CC flow to non-safety

related components. Therefore, the alternative method of cooling the PASS sample

cooler was sµpplied from the Demineralized Water System.

The inspector reviewed Procedure SC.CH-AB.CC-1155(0), "Temporary Cooling of

PASS Cooler Rack 811 " that provides the steps necessary to install temporary

cooling (via demineralized water) when Unit 2 CC is not available to the PASS

cooler rack. Previously, this configuration was not delineated in the UFSAR. *

PSE&G initiated an action request, BP 961212177, to track completion of an

UFSAR change notice.

The inspector verified that the appropriate changes to Procedure SC.CH-SA.PAS-

1001 (0) "Pass Start-up" and SC.CH-AB.CC-1155(0) "Temporary Cooling of PASS

Cooler Rack 811" were implemented.

Based on the above, the unresolved item is closed .

P3

f 8

18

IV. Plant Support

EP Procedures and Documentation

In-Office Review of Licensee Procedure Changes

An in-office review of revisions to the emergency plan and its implementing

procedures submitted by the licensee was completed. A list of the specific

revisions reviewed are included in Attachment 1 to this report. Based on the

licensee's determination that the changes do not decrease the overall effectiveness

of the emergency plan, and that it continues to meet the standards of 10 CFR

50.47(b) and the requirements of Appendix E to Part 50, NRC approval is not

required for those changes.

Miscellaneous Fire Protection Issues

Appendix R Post-Fire Alternative Shutdown: (Closed) Unresolved Item 50-

272&311 /93-80-08

NRC Inspection Report 97-09 Section F8.1 discussed several unresolved items

involving Appendix R Alternative Shutdown requirements. Unresolved Item 93-80-

08 should have bee.n closed out in 97-09, but was not included due to an

administrative oversight. Unresolved Item 93-80-08 is closed, based on discussion

in section F.8.1.b of that report.

V. Management Meetings

X1

Exit Meeting Summary

The inspectors presented the inspection results to members of licensee management at the

conclusion of the inspection on July 31, 1997. The licensee acknowledged the findings

presented. The inspectors asked the licensee whether any materials examined during the

inspection should be considered proprietary. No proprietary information was identified.

X2

Pre-Decisional Enforcement Conference Summary

On July 8, a pre-decisional enforcement conference was held at the NRC Region I office to

discuss potential enforcement issues identified in Inspection Reports 50-272&311 /97-09

and 97-11. The issues related to Appendix R concerns as discussed in Inspection Report

97-09 and emergency core cooling system operation outside the plant design basis .as -

discussed in Inspection Report 97-11. Slides used in the licensee's presentation at the

conference have been included as Attachment 2 to this report .

18

IV. Plant Support

P3

EP Procedures and Documentation

P3.1

In-Office Review of Licensee Procedure Changes

An in-office review of revisions to the emergency plan and its implementing

procedures submitted by the licensee was completed. A list of the specific

revisions reviewed are included in Attachment 1 to this report. Based on the

licensee's determination that the changes do not decrease the overall effectiveness

of the emergency plan, and that it continues to meet the standards of 10 CFR

50.47(b) and the requirements of Appendix E to Part 50, NRC approval is not

required for those changes.

F8

Miscellaneous Fire Protection Issues

F8.1

Appendix R Post-Fire Alternative Shutdown: !Closed) Unresolved Item 50-

272&311 /93-80-08

NRC Inspection Report 97-09 Section F8.1 discussed several unresolved items

involving Appendix R Alternative Shutdown requirements. Unresolved Item 93-80-

08 should have been closed out in 97-09, but was not included due to an

administrative oversight. Unresolved Item 93-80-08 is closed.

V. Management Meetings

X 1

Exit Meeting Summary

The inspectors presented the inspection results to members of licensee management at the

conclusion of the inspection on July 31, 1997. The licensee acknowledged the findings

presented. The inspectors asked the licensee whether any materials examined during the

inspection should be considered proprietary. No proprietary information was identified.

X2

Pre-Decisional Enforcement Conference Summary

On July 8, a pre-decisional enforcement conference was held at the NRC Region I office to

discuss potential enforcement issues identified in Inspection Reports 50-272&311 /97-09

and 97-11. The issues related to Appendix R concerns as discussed in Inspection Report

97-09 and emergency core cooling system operation outside the plant design basis as

discussed in Inspection Report 97-11. Slides used in the licensee's presentation at the

conference have been included as Attachment 2 to this report .

19

ATTACHMENT 1

REVIEWED LICENSEE DOCUMENTS

NUCLEAR BUSINESS UNIT

EMERGENCY PLAN IMPLEMENTING PROCEDURES

EPIP 102S

EPIP 103S

EPIP 104S

EPIP 105S

EPIP 201 S

EPIP 202S

EPIP 204S

EPIP 301 S

EPIP 302S

EPIP 309S

Alert - SNSS/EDO

Site Area Emergency - SNSS/EDO

General Emergency - SNSS/EDO

Upgrading Protective Action Recommendations

TSC-lntegrated Engineering Team Response

OSC Activation and Operations

Emergency Response Callout/Personnel Recall

Radiation Protection Technician On-Shift Response

Radiological Assessment Coordinator Response

Dose Assessment

12

13

13

7,8

9

16

35,36

19

20

11

EVENT CLASSIFICATION GUIDE

Section iii

Attachment 6

Attachment 7

Attachment 9

Attachment 1 5

Attachment 18

Attachment 19

Attachment 24

Critical Function Status Trees (CFSTs), Unit 2

22

Primary Communicator Log

1, 2

Primary Communicator Log (GE)

1, 2

Non-Emergency Notifications Reference

1 , 2

Environmental Protection Plan

1

4 Hr Report-Radiological Transportation Accident

1

24 Hr Report-Fitness For Duty (FFD) Program Events

1

UNUSUAL EVENT (Common Site)

1

EVENT CLASSIFICATION GUIDE TECHNICAL BASIS

Section 11 . 2

Section 11 . 7

EMERGENCY PLAN

Document

Section 3

Section 5

Section 8

Section 9

Section 16

Design Basis/Unanalyzed Condition

Security/Emergency Response Capabilities

COMMON SITE

Document Title

Emergency Organization

Emergency Classification System

Public Information

Emergency Facilities and Equipment

Radiological Emergency Response Training

1

1

Revision

8, 9

5

5

6

6, 7

.. {

ADMINISTRATIVE

EPIP 1006

EPIP 1007

EPIP 1008

EPIP 1013

EPIP 1016

EPIP 404

EPIP 602

SECURITY

EPIP 902

20

Emergency Equipment Inventory (Radiation Protection)

EOF/ENC Supply & Locker Inventory

Emergency Communications Drills

Emergency Response Personnel Telephone List

Test Procedures for EOF Backup Generator,

Vent System and HVAC Filter Replacement

Protective Action Recommendations

Radiological Dose Assessment

Accountability/Evacuation

18

17

14

36,37

3

8,9

19

14

EMERGENCY NEWS CENTER

NC.EP-EP.ZZ-0801 (Q)

NC. EP-EP .ZZ-006(0)

EPIP 801

EPIP 802

EPIP 803

EPIP 804

EPIP 805

EPIP 806

EPIP 807

Emergency News Center Operation

0

ENC Evacuation and Activation of Back-up ENC 0, 1

Void

10

Void

9

Void

8

Void

. 6

Void

8

Void

5

Emergency News Center Telephone Directory

9, 10 .

21

INSPECTION PROCEDURES USED

IP 61726:

IP 62707:

IP 71707:

Surveillance Observations

Maintenance Observations

Plant Operations

IP 92903:

Followup - Engineering

Opened

50-311197-14-03

Closed

50-272&311 /93-80-08

50-311196-81-01

50-311 /96-81-02

50-311196-81-03

50-311196-81-05

50-311196-81-06

50-311196-81-08

50-311196-81-09

50-311196-81-10

50-311196-81-11

50-311/96-81-12

50-311196-81-15

50-311/97-14-01

50-311/97-14-02

ITEMS OPENED, CLOSED, AND DISCUSSED

VIO

Improper restoration of a diesel generator following testing

URI

URI

URI

URI

URI

URI

URI

URI

URI

URI

URI

URI

NCV

NCV

Appendix R post-fire alternative shutdown

CC pump room ventilation deficiency prior to 1995

Current EOPs are inconsistent with single CC pump room

ventilation failure

Current EOPs allow CC pump to runout which is not supported

by pump design documentation

No documented basis for CC heat exchanger performance test

assumptions and analysis

Lack of acceptance criteria for CC room ventilation coolers

CC pump room ventilation damper position is not controlled

Battery surveillance test inadequacies

CC supply to pump seal water cooling heat exchangers

Inadequacy in TOL heater calculation and control

Inadequacy in setpoint calculations for radiation monitors and

surge tank level alarm

. PASS operation inconsistent with UFSAR

  • Failure to enter Technical Specification Action Statement for

inoperable control radiation monitors

Failure to perform an adequate retest following main steam

system check valve maintenance

ASME

CBD

cc

CCHX

CR

CRCA

CREAS

CRS

DCP

ECCS

EDG

EOPs

LCO

LER

LOCA

LOOP

MMIS

MOV

NRC

PASS

PDR

PMT

PR

PSE&G

RWST

SR Os

TCC

TDAFW

TOL

TS

TSAS

UFSAR

URI

22

LIST OF ACRONYMS USED

American Society of Mechanical Engineers

Configuration Basis Document

Component Cooling Water System

Component Cooling Heat Exchanger

Condition Report

Condition Report Corrective Action

Control Room Emergency Air Condition System

Control Room Supervisor

Design Change Package

Emergency Core Cooling System

Emergency Diesel Generator

Emergency Operating Procedures

Limiting Condition for Operation

Licensing Event Report

Loss of Coolant Accident

Loss of Power

Maintenance Management Information System

Motor Operated Valve

Nuclear Regulatory Commission

Post Accident Sampling System

Public Document Room

Post Maintenance Test

Performance Improvement Request

Public Service Electric & Gas

Refueling Water Storage Tank

Senior Reactor Operators

Time Concurrent Characteristics

Turbine-Driven Auxiliary Feedwater

Thermal Overload Relay

Technical Specification

Technical Specification Action Statement

Updated Final Safety Analysis Report

Unresolved Issue

  • . -

.

ATTACHMENT 2

The Power of Commitment

  • ,

PUBLIC SERVICE ELECTRIC AND GAS

PREDECISIONAL ENFORCEMENT CONFERENCE

INSPECTION REPORT 50-272/311-97-09

JULY 8, 1997

E. C. SIMPSON

FIRE PROTECTION

REPAIR ISSUES

L

1983

1985

  • PSE&G ASSUMES APPROVAL

1987

The Power of Commitment

CURRENT ST_ATUS

&:~~,,~.*.. PS~G

fa*

-~

&

",.

. ,.,

~;.,

'<:..'"ff!

~b~}Sf

  • Unit 2 Modifications Installed
  • Unit 1 Modifications Scheduled
  • Procedure Streamlined

No Repairs Needed for Alternate Shutdown

I

4

The Power of Commitment ~

FIRE WRAP

6

The Power of Commitment. ,

UNDERSTANDING THE ISSUE

  • Safety Significance
  • Generic Issues Throughout the Industry

7

c.o

.....J

())

.....

c.o

.....J

cc

.....

c.o

CX>

0

.....

c.o

CX>

.....

.....

c.o

CX>

C)

CD

cc

0

.....

c.o

c.o

w

_.

c.o

c.o

01

.....

c.o

c.o

.....J

  • KAOWOOL

"'C z

~~

~ )>

_n

zn

en m

-; "'C

)> -l

r- en

r ?"

en )>

7' 0

)> ~

Do

~o

0 r-

0

r

COMPE

INITIA~

COMPE

DOWN1

NRC INSPEC

COMPENSA

PLANDEVE

FS-195

E-50

"'CZ II

en ;;n en

m n..:...

$20 )> c.o

G)

(J1

-

(")-;

zn

en m m

-; -o en

)> -; -;

r- en m

I

II 0

en en

I .....

c.o

(J1

-l m

m'

en CJ1

-l 0

m

0

NSATORYMEASURE s

ED

NSATORYMEASURE s

rRADED

lr'ION

ORY MEASURES UP ~RADED

[,OPED

-m

z,

en CJ1

-l 0

)>

r r m

0

J*

rit-!'<~.

---X'

'~

-:....L

0

.,C)., ~

"0,,.c.,_ 1'

~ "<

OA f-,

. '\\fl '.(-*

,,(0. 1<l-*

~ ~'

./%

<r'-0.

"'!~

~/I . ':/

()9*

/f

0

~-&

G,.;

<o

~

?'&, o.

~Jo.

<:c~

,/;-.

'0V

Oo

~-6

~~~

o~

'::,./

  • . -_

-- :

The Power of Commitment

NEXT STEPS

.. *. PS~G

.

. '

.: ..... * .. *. ' .... *:::--. *.

... *: **::*.'.*:: ... *: ..

..

.

  • Re-analysis of Safe Shut down
  • Identify required cables -
  • Develop resolution -
  • Implement resolution

8

The Power of Commitment

FIRE BARRIER MATERIALS

USED AT SALEM

_j?:/!fi"!h:.

PS~G

(J

~.

  • Kaowool - About 500 Feet of Cable Trays -

accepted - resolution per 1OCFR50.109

  • FS-195 - About 14,000 Feet of Cable Trays -

accepted - resolution per 1OCFR50.109

  • E-50 - About 5000 Feet of Cable Trays

9

~

-

-

.

,

The Power of Commitment .

TECHNICAL ISSUES

9 RHR Pump Flow During Recirculation

a Net Positive Sucti.on Head (NPSH) for RHR

Pumps

'J Switchover From Injection to Recirculation

  • .. ~.

The Power of Commitment

RESIDUAL HEAT REMOVAL (RHR) ISSUES

July 8, 1997

David R. Powell

CURRENT STATUS

J RHR Pump Flows. Acceptable

J NPSH Requirements Met

~ Credit for Containment Pressure

Not Required

.

-

,

The Power of Commitn1ent .

.*. :**" PS~G

~ ECCS Pumps Not Stopped During Switchover

..,_. ___

...,... T.1 SMIN

COLD LEG RECIRCULATION

INJECTION

.,.__v .... o ...

L...,UM

..... E..__. lcm

SWJTCHOVER

....,.._v .... o...,L_UM_E_-t tG'N-lOW

..__ ___

"""'. CONTAJNMENT

SPRAY PUMPS

Sjl

CONTA!NMtNl

s~

RHR

SJ44

CS36

I

..,._ _______

_.._ __

_,COLD LEGS (41

CS36

HOT LEGS (1)

I

COLD LfGS (~)

I

HOT LEGS (2)

I

COLD LEGS (2)

,

.,_... ___

......,.T .' S MIN

INJECTION

.,..__v_o ....

L.U_M_E...._..,. Lc)w

swrTCHOVER

...__v_o_t_UM_.E-. .... lOVV-lO~'w'

____ .,.

COLD LEG RECIRCULATION

ONE RHR PUMP FAILS

CONTAINMENT

CS36

SPRAY PUMPS

CS36

LOOP AROUND

FLOW---

to-----------__,, COLD LfGS (4~

.,____.,...._.,__-1CHARGING PUMPS

2

Sj2

HOT LEGS (2)

I

COLD LfGS (4,

HOT LEGS (2)

I

(ON'<AJNMcNT

s~

f

COLD LtGS {I)

SJ44

.,__ ___

... r r S f'"JN

INJECnON

,__v_ol_U_M_E --.LOW'

SWITCHOVER

HOT LEG RECIRCULATION

PRIOR TO 1994 CHANGES

,.__v_oL_U_M_E _..,.LOW'-lOW .-----..-1

CS36

CONTAINMENT

.._ __ _...

SPRAY PUMPS

CS36

I

.----------..,COLD LEGS {4)

t---'f"lll~--.CHARGING PUMPS

~2-... " ...... -

I I

HOT LE.GS (l)

COLD LEGS (4)

I

HOT LEGS (2)

CONTAJNMENT

Slff

I

COLD LEGS {2)

SJ44

HOT LEGS (2)

,. ...

...,._ ___

__..I* S MIN

lhJJECTION

.,__v_o_L_UM_i.= __ LO\\/

S\\VITCHOVfR

VOLUME

, r)'.'~-l0'N

HOT LEG RECIRCULATION

AFTER 1994 CHANGES

____

...,. CONTAiNMfNT

CS36

SPRAY PUMPS

CS36

1--------------.;- COLD LfGS (4l

cor...:1A1t*H1c.-.n

SL."'.'"'

Sj2

r.--....-~1~--tCHARGING PUMPS

2

SI PUMPS

< "I

_J

HEAD

. (FT.)

Salem Unit 2

RHR Pumps

Original Design Basis (19BO SER)

Available NPSH

(w/ Overpressure)

Available NPSH

(w/o Overpressure)

Required

NPSH

34.9'

28.7

1

48::10

FLOW (GPM)

I

34.3':

I

I

28.1' :

Current Design Basis

(1994: No Rt-1R He..! Leg)

Maximum Estimated

(Pre*1994: w/ RHR Hot Leg)

Pump Test Data

Vend'Jr

Extension

'I

I

I

...... ~o*

/

,"

4980

5040 5185 5250

5500

    • AVAILABLE NPSH GREATER THAN REQUIRED NPSH**

~-------------------- ---

(,_

~ *

J

~IBP I

p

s

E

&

G

SEMI-AUTOMATIC SWITCHOVER

FROM RWST TO CONTAINMENT SUMP

rj

1/83

(POST-LOCA)

5/B9 I

1/87

\\

(l)

'O \\ ,,..

~ \\ ii'

'J/97

5197

I I

-*

SEMI-AUTOMATIC SWITCHOVER

Time

Training

Issue

Analysis

18 minutes (SER

13 minutes

Non conservative

Did not account for

May 1989

Amendment 69)

basis

Small Break LOCA

8.5 minutes

. and worse case

(submitted for Large

single failure

Break LOCA)

11.8 minutes

March 1996

11.8 minutes (actual

50.59 evaluation

Inappropriate credit

(credited 1.8 min

<11 minutes)

missed USQ

for downcomer flow

downcomer flow

w/o NRC approval

considering SB*

LOCA)

In compliance with

Appropriate reviews

May 1997

11.2 minutes

11.2 minutes (actual

Licensing and Design

performed

(removed credit for

<9 minutes)

Basis

downcomer flow)

EOPs changed

Corrections made to

Amendment 69

SEMI-AUTOMATIC SWITCHOVER

Safety Li1nit

Desired State

--

I

I

Current

Operator

Times

  • Current

1996

Training Training

RWST Water Volume

,

'-----------------'

Downcomer Water Volun1e

Peak Clad Temperature Lin1its

--

_,

~

'

' '

-*

The Power of Commitment.

ACTIONS TAKEN

Improvements to Corrective Action Program

-~ Operability Assessments

  • ~ Integrated Corrective Action Program

-~ Lower Threshold for ldentificatlon

~Improved Rep,ortability Review

3 SORC Expectations for Licensing Basis

,~ Design and Licensing Basis Review Project

7:;) Improvements to 50.59 Program

I~

., ;. '

i:.~ .

'

~

The Power of Commitment,

CONCLUSIONS

u Technical Issues Resolved Timely

-~ Regulatory Compliance - No Safety

Consequences

0) Issues Similar to Civil Penalty of October

1995 for Appendix B Criterion XVI

L'