MONTHYEARML0301606982002-01-15015 January 2002 Docket Information in Support of Staffs Review of H. B. Robinson, Unit 2 License Renewal Application Project stage: Approval ML0222804382002-08-16016 August 2002 Notice of Intent to Prepare an Environmental Impact Statement & Conduct Scoping Process for License Renewal for H. B. Robinson Steam Electric Plant, Unit No. 2 Project stage: Other ML0222801252002-08-29029 August 2002 Notice of Public Meeting at Coker College to Discuss Environmental Scoping Process for Robinson, Unit 2, License Renewal Application Project stage: Meeting ML0227402602002-09-25025 September 2002 Meeting Handouts to Discuss the Environmental Scoping Process for the LRA for Robinson, Unit 2 Project stage: Meeting ML0301706392003-01-16016 January 2003 Summary of Teleconference with National Marine Fishery Service and South Carolina Department of Natural Resources in Support of the Staffs Review of the H.B. Robinson, Unit 2 License Renewal Application Project stage: Meeting ML0303006192003-01-24024 January 2003 Summary of Teleconference with Carolina Power & Light in Support of Staffs Review of H.B. Robinson, Unit 2 License Renewal Application Project stage: Meeting ML0304301542003-02-11011 February 2003 Docket Information in Support of the Staffs Review of the H. B. Robinson, Unit 2, License Renewal Application Project stage: Approval ML0310804172003-02-28028 February 2003 Federal Fish & Wildlife Permit, Dated 02/28/2003 & Migratory Bird Depredation Permit Standard Conditions Project stage: Other ML0310703432003-03-0606 March 2003 /Data Cover Sheet Project stage: Other ML0310703512003-03-0606 March 2003 FW: Robinson Gross Generation 01 02 (Table) Project stage: Other ML0310703572003-03-11011 March 2003 F.W. Robinson Emailing: - Emailing: peedee2K1 Project stage: Other ML0310703682003-03-14014 March 2003 2003 Federal Bird Permit, Dated 2/28/03, E-mail Date: 3/14/03 (Cvr. Sheet) Project stage: Other ML0310703972003-03-19019 March 2003 Cost of Replacement of Yokes Project stage: Other ML0308701572003-03-19019 March 2003 Summary of Teleconference with Carolina Power and Light in Support of the Staffs Review of the H.B. Robinson, Unit 2 License Renewal Application Project stage: Meeting ML0310704102003-03-25025 March 2003 750 and 751 Cost Benefit Rev3.doc Dated 03/25/2003 (Data W/Table) (Robinson Nuclear Plant RHR Valves 750 and 751) Project stage: Other ML0310704212003-03-25025 March 2003 750 and 751 Cost Benefit Rev 3.doc (Cvr. Sheet) March 25, 2003 Project stage: Other ML0310704522003-03-26026 March 2003 Document 2 Dated 03/26/2003 Project stage: Other ML0310704632003-04-0303 April 2003 Radiant Energy Shield SAMA, Dated 4/3/03 Project stage: Other ML0310704722003-04-0808 April 2003 IPEEE Fire Analysis, Dated 04/08/2003 Project stage: Other ML0310702092003-04-15015 April 2003 Docket Information in Support of the Staffs Review of the H.B. Robinson, Unit 2, License Renewal Application Project stage: Approval ML0311304272003-04-22022 April 2003 (S. Bolden) - Biological Assessment for License Renewal at H.B. Robinson Steam Electric Plant, Unit 2 (Tac No. MB5226) Project stage: Other ML0311302502003-04-22022 April 2003 Biological Assessment for License Renewal at H.B. Robinson Steam Electric Plant, Unit 2 Project stage: Other ML0311400302003-04-30030 April 2003 Biological Assessment - H.B. Robinson Steam Electric Plant, Unit 2, (Nuclear) License Renewal Review Hartsville, South Carolina, April 2003 Project stage: Other ML0312600842003-05-0505 May 2003 Notice of Availability of the Draft Plant-Specific Supplement to the Generic Environmental Impact Statement Regarding H.B. Robinson Steam Electric Plant, Unit 2 Project stage: Draft Other ML0312604322003-05-0505 May 2003 Request for Comments on the Draft Plant-Specific Supplement 13 to the Generic Environmental Impact Statement Regarding H.B. Robinson Steam Electric Plant, Unit 2 (Tac No. MB5226) Project stage: Draft Other ML0322706002003-06-25025 June 2003 Corrected Transcript of Proceedings, U.S. Nuclear Regulatory Commission: H.B. Robinson Steam Electric Plant, Draft EIS Public Meeting - Afternoon, Hartsville, Sc ML0321604362003-06-25025 June 2003 E-Mail from L. England to Jan Kozyra Dam Releases Project stage: Other ML0322706012003-06-25025 June 2003 Corrected Transcript of Proceedings: U.S. Nuclear Regulatory Commission: H.B. Robinson Steam Electric Plant Draft EIS Public Meeting - Evening Session, Hartsville, Sc, Enclosure 3 ML0322706042003-08-15015 August 2003 Summary of Visit to Robinson Site in Support of the Staffs Review of the H.B. Robinson, Unit 2, License Renewal Application (Tac No. MB5226) Project stage: Approval ML0322706032003-08-15015 August 2003 Summary of Meeting Held in Support of the Environmental Review for the H.B. Robinson Steam Electric Plant, Unit 2, License Renewal Application (TAC No. Mb 5226) W/Encls. 1 & 4 Project stage: Meeting ML0333200662003-10-17017 October 2003 Comment (8) of Joseph F. Cockrell, U.S. Department of the Interior Regarding License Renewal at H.B. Robinson Steam Electric Plant, Unit 2 Project stage: Other ML0334303752003-12-12012 December 2003 Final Supplement 13 to the Generic Environmental Impact Statement for H.B. Robinson Steam Electric Plant, Unit 2 License Renewal Project stage: Other ML0334505172003-12-31031 December 2003 NUREG-1437 S13, Generic Environmental Impact Statement for License Renewal of Nuclear Plants. Project stage: Acceptance Review 2003-03-14
[Table View] |
Text
Kozyra, Jan From:
England, Louise Sent:
Wednesday, June 25, 2003 9:02 AM To:
Kozyra, Jan
Subject:
Dam releases The Water Pollution Control Authority issued a permit on 5-15-61 for the discharges from Robinson Plant (Unit 1) into Lake Robinson. At that time the "flow in Black Creek below the lake is to be maintained at or above normal rate at all times".
Permit (issued 6-24-64) was revised to state "Discharge from Lake Robinson dam to be maintained at or above 1.47 times flow measured by USGS gauge on Black Creek near McBee, South Carolina. Flow ratio subject to review at 5-year Intervals as data accumulates, or as major construction may Indicate a need."
First NPDES permit issued by EPA effective 2-18-75 had no verbiage concerning flow releases from Lake Robinson dam.
I could find no documentation that EPA was concerned with the flow releases from the dam.
First NPDES permit issued by SC DHEC effective in 1982 also had no verbiage concerning flow releases from Lake Robinson dam.
It appears that the limits within the Robinson Plant's operating procedure are a carryover from a gentleman's agreement with Sonoco. If you need more Information please let me know.