IR 05000413/2010006

From kanterella
Revision as of 16:18, 21 August 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
IR 05000413-10-006, 05000414-10-006 on 04/26 - 30/2010 and 05/10/2010 - 14/2010 for Catawba Nuclear Station, Units 1 and 2, Fire Protection
ML102250119
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 08/10/2010
From: Nease R L
NRC/RGN-II/DRS/EB2
To: Morris J R
Duke Energy Carolinas
References
IR-10-006
Download: ML102250119 (27)


Text

August 10, 2010

Mr. J. Site Vice President Duke Energy Carolinas, LLC Catawba Nuclear Station 4800 Concord Road York, SC 29745-9635

SUBJECT: CATAWBA NUCLEAR STATION - NRC TRIENNIAL FIRE PROTECTION INSPECTION REPORT NO. 05000413/2010006 AND 05000414/2010006

Dear Mr. Morris:

On May 14, 2010, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Catawba Nuclear Station, Units 1 and 2. The enclosed inspection report documents the inspection results, which were discussed with you and other members of your staff. Following completion of additional review in the Region II office, another exit meeting was held by telephone with Mr. R. Ferguson and other members of your staff on June 28, 2010, to provide an update on changes to the preliminary inspection findings.

The inspection examined activities conducted under your licenses as they relate to safety and compliance with the Commission's rules and regulations and with the conditions of your licenses. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

This report documents one NRC-identified finding of very low safety significance (Green) which was determined to involve a violation of NRC requirements. However, because of the very low safety significance and because it was entered into your corrective action program, the NRC is treating this finding as a non-cited violation (NCV) consistent with Section VI.A.1 of the NRC Enforcement Policy. If you contest the NCV in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN.: Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, D.C. 20555-0001; and the NRC Resident Inspector at the Catawba facility.

In addition, if you disagree with the cross-cutting aspect assigned to the finding in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the Regional Administrator, RII, and the NRC Senior Resident Inspector at the Catawba Nuclear Station.

DEC, LLC. 2 In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response, if any, will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,/RA/ Rebecca L. Nease, Chief Engineering Branch 2 Division of Reactor Safety Docket Nos.: 50-413, 50-414 License Nos.: NPF-35, NPF-52

Enclosure:

Inspection Report 05000413/2010006 and 05000414/2010006

w/Attachment:

Supplemental Information

cc w/encl.: (See page 3)

DEC, LLC. 3 cc w/encl: Randy D. Hart Regulatory Compliance Manager Duke Energy Carolinas, LLC Electronic Mail Distribution

R. L. Gill, Jr. Manager Nuclear Regulatory Issues & Industry Affairs Duke Energy Carolinas, LLC Electronic Mail Distribution

Dhiaa M. Jamil Group Executive and Chief Nuclear Officer Duke Energy Carolinas, LLC Electronic Mail Distribution Kathryn B. Nolan Senior Counsel Duke Energy Corporation 526 South Church Street-EC07H Charlotte, NC 28202

Lisa F. Vaughn Associate General Counsel Duke Energy Corporation 526 South Church Street-EC07H Charlotte, NC 28202

Senior Resident Inspector U.S. Nuclear Regulatory Commission Catawba Nuclear Station U.S. NRC 4830 Concord Road York, SC 29745 David A. Repka Winston Strawn LLP Electronic Mail Distribution North Carolina MPA-1 Suite 600 P.O. Box 29513 Raleigh, NC 27525-0513

Susan E. Jenkins Director, Division of Waste Management Bureau of Land and Waste Management S.C. Department of Health and Environmental Control Electronic Mail Distribution R. Mike Gandy Division of Radioactive Waste Mgmt. S.C. Department of Health and Environmental Control Electronic Mail Distribution

W. Lee Cox, III Section Chief Radiation Protection Section N.C. Department of Environmental Commerce & Natural Resources Electronic Mail Distribution Vanessa Quinn Federal Emergency Management Agency 500 C Street, SW Room 840 Washington, DC 20472 Steve Weatherman, Operations Analyst North Carolina Electric Membership Corporation Electronic Mail Distribution County Manager of York County York County Courthouse P. O. Box 66 York, SC 29745-0066 Piedmont Municipal Power Agency Electronic Mail Distribution

Peggy Force Assistant Attorney General State of North Carolina P.O. Box 629 Raleigh, NC 27602

Letter to J. from Rebecca L.. Nease dated August 10, 2010.

SUBJECT: CATAWBA NUCLEAR STATION - NRC TRIENNIAL FIRE PROTECTION INSPECTION REPORT NO. 05000413/2010006 AND 05000414/2010006 Distribution w/encl:

RIDSNRRDIRS PUBLIC A. Adams, NRR RidsNrrPMCatawba Resource C. Evans, RII L. Slack, RII OE Mail RIDSNRRDIRS PUBLIC

(*) - SEE PREVIOUS PAGE FOR CONCURRENCES

X G PUBLICLY AVAILABLE G NON-PUBLICLY AVAILABLE G SENSITIVE X GNON-SENSITIVE ADAMS: X G Yes ACCESSION NUMBER:_________________________ X G SUNSI REVIEW COMPLETE (R. NEASE OFFICE RII:DRS RII:DRS RII:DRS RII:DRS RII:DRP RII:DRS RII:DRS SIGNATURE RA RA RA VIA EMAIL RA RA RA NAME MThomas NMerriweather KMiller LSuggs JBartley RNease DATE 6/ 28 /2010 6/ 24 /2010 6/ 25 /2010 6/ 24 /2010 7/ 22 /2010 8/10/2010 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NDOCUMENT NAME: S:\DRS\ENG BRANCH 2\REPORTS\CATAWBA\INSPECTION REPORTS\CAT TFPI 2010-006 RPT REV2.DOCdoc Enclosure U.S. NUCLEAR REGULATORY COMMISSION REGION II Docket Nos.: 50-413, 50-414 License Nos.: NPF-35, NPF-52

Report Nos.: 05000413/2010006 and 05000414/2010006 Licensee: Duke Energy Carolinas, LLC Facility: Catawba Nuclear Station, Units 1 and 2 Location: York, SC 29745

Dates: April 26 - 30, 2010 (Week 1) May 10 - 14, 2010 (Week 2)

Inspectors: M. Thomas, Senior Reactor Inspector (Lead Inspector) N. Merriweather, Senior Reactor Inspector K. Miller, Resident Inspector Watts Bar Unit 2 L. Suggs, Reactor Inspector (Week 1 only)

Approved by: Rebecca L. Nease, Chief Engineering Branch 2 Division of Reactor Safety Enclosure

SUMMARY OF FINDINGS

IR 05000413/2010-006, 05000414/2010-006; 04/26 - 30/2010 and 05/10 - 14/2010; Catawba Nuclear Station, Units 1 and 2; Fire Protection.

This report covers an announced two-week period of inspection by a triennial fire protection team composed of four regional inspectors. One Green non-cited violation was identified. The significance of most findings is indicated by their color (Green, White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609, ASignificance Determination Process

@ (SDP). Findings for which the SDP does not apply may be Green or be assigned a severity level after U.S.

Nuclear Regulatory Commission (NRC) management review. The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process," Revision 4, dated December 2006.

A. NRC-Identified and Self-Revealing Findings

Cornerstone: Mitigating Systems

  • Green: The inspectors identified a non-cited violation of Catawba Unit 1 Operating License Condition 2.C(5), in that the licensee failed to install emergency lighting units (ELUs) in accordance with the approved fire protection program. Specifically, ELUs were not installed in some areas in the Unit 1 turbine building for access/egress and where local operator manual actions were required to support post-fire safe shutdown for a fire in the main control room. The licensee initiated Problem Investigation Process C-10-2815 to address the ELU issue associated with the Procedure AP/1/A15500/017.

The licensee's failure to install ELUs for local operator manual actions, as required by the Catawba fire protection program, is a performance deficiency. The finding is more than minor because it is associated with the reactor safety Mitigating Systems cornerstone attribute of protection against external factors (i.e., fire), and it affects the objective of ensuring the reliability and capability of systems that respond to initiating events. Specifically, the finding could affect the licensee's ability to perform local operator actions required to achieve and maintain post-fire safe shutdown conditions following a main control room fire. The team completed a Phase 1 screening of the finding in accordance with IMC 0609, Appendix F, Fire Protection SDP Phase 1 Qualitative Screening Approach, Step 1.3, and concluded that the finding, given its low degradation rating, was of very low safety significance (Green), because the operators had a high likelihood of completing the tasks using flashlights or battery-powered portable hand lights. Consideration was given to the fact that operators normally carry flashlights and would have access to the portable hand lights to provide the necessary lighting. The cause of this finding has a cross-cutting aspect in the Resources component of the Human Performance area, in that the licensee did not ensure that equipment such as fixed 8-hour emergency lighting units were available to support post-fire safe shutdown actions (H.2 (d)). (Section 1R05.05)

B. Licensee Identified Violations

None

REPORT DETAILS

REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity

1R05 Fire Protection

This report documents the results of a triennial fire protection inspection of the Catawba Nuclear Station (CNS) Units 1 and 2. The inspection was conducted in accordance with NRC Inspection Procedure 71111.05TTP, "Fire Protection-National Fire Protection Association (NFPA) 805 Transition Period (Triennial)," dated December 24, 2009. The objective of the inspection was to review a minimum sample of 3 risk-significant fire areas to verify implementation of the fire protection program (FPP) and to verify site specific implementation of at least one B.5.b mitigating strategy as well as the storage, maintenance, and testing of B.5.b mitigating equipment. The three fire areas (FAs) and associated fire zones (FZs) were selected after reviewing available risk information as analyzed by a senior reactor analyst from Region II, previous inspection results, plant walk downs of fire areas, relational characteristics of combustible material to targets, and location of equipment needed to achieve and maintain safe shutdown (SSD) of the reactor. In selecting the B.5.b mitigating strategy sample, the team reviewed licensee submittal letters, safety evaluation reports, licensee commitments, B.5.b implementing procedures, and previous NRC inspection reports. Section 71111.05-05 of the IP specifies a minimum sample size of three fire areas and one B.5.b implementing strategy for addressing large fires and explosions. This inspection fulfilled the requirements of the procedure by selecting three fire areas, one fire zone and one B.5.b mitigating strategy. The specific FAs/FZs chosen for review were:

1. FA 15 - Unit 1 4160 Volt Switchgear Room A, Elev. 577 feet 2. FA 17 - Unit 1 Cable Spread Room, Elev. 574 feet 3. FA 21 - Units 1 and 2 Main Control Room, Elev. 594 feet 4. FZ - Unit 1 Turbine Bldg 6900 Volt Switchgear Room 1TA/1TB Elev. 594 feet The team evaluated the licensee

=s FPP against applicable requirements, including CNS Units 1 and 2 Renewed Operating License Condition 2.C(5), "Fire Protection Program"; Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix A, General Design Criteria 3, "Fire Protection"; 10 CFR 50.48, "Fire Protection"; Branch Technical Position Chemical Engineering Branch 9.5-1; Catawba Safety Evaluation Report (SER), NUREG 0954 with Supplements 2, 3, 4, and 5; commitments to Appendix A of Branch Technical Position Auxiliary and Power Conversion Systems Branch 9.5-1; CNS Updated Final Safety Analysis Report (UFSAR) Section 9.5.1, "Fire Protection System,"

and Section 16.9, "Auxiliary Systems; other related NRC safety evaluation reports; and plant Technical Specifications. The review of the B.5.b mitigating strategies was based on the CNS Units 1 and 2 Renewed Operating License Condition 2.C(6), "Mitigation Strategies;" licensee B.5.b submittals; and related NRC SERs.

. The team evaluated all 4 Enclosure areas of this inspection, as documented below, against these requirements. Specific licensing basis documents reviewed are listed in the Attachment.

.01 Protection of Safe Shutdown Capabilities

a. Inspection Scope

The objective of the inspection was to verify the licensee's ability to achieve hot and cold shutdown with and without the availability of offsite power. The inspection activities focused on ensuring the adequacy of systems selected for reactivity control, reactor coolant makeup, reactor heat removal, process monitoring instrumentation, and support system functions.

Methodology The team walked down the selected fire areas and examined the material condition of the fire detection and suppression systems and fire area boundaries. The team compared the post fire safe shutdown analysis (SSA) with the post fire Abnormal Procedure (AP) AP/0/A/5500/045, "Plant Fires," to verify that equipment required for post-fire safe shutdown was adequately protected from fire damage in accordance with the fire protection program. In cases where local operator manual actions (OMAs) were in place in lieu of cable protection of SSD components, the team verified that the OMAs were feasible and reliable based on the guidance in the IP.

Operational Implementation The team reviewed applicable sections of Abnormal Procedure AP/0/A/5500/045 utilized for post-fire SSD from the main control room (MCR) for a postulated fire in FA 15 and in the Unit 1 Turbine Building 6900 Volt Switchgear Room 1TA/1TB. The review was performed to verify that the shutdown methodology properly identified the components and systems necessary to achieve and maintain SSD conditions. The team performed a walk-through of procedure steps to ensure the implementation and human factors adequacy of the procedure. The team also reviewed selected operator actions to verify that the operators could reasonably be expected to perform the specific actions within the time required to maintain plant parameters within specified limits.

b. Findings

No findings were identified.

.02 Passive Fire Protection

a. Inspection Scope

For the selected FA/FZs, the team evaluated the adequacy of fire barrier walls, ceilings, floors, mechanical and electrical fire barrier penetration seals, fire doors, and fire dampers. The team compared the installed configurations to the approved construction details, and supporting fire endurance test data, which established the ratings of fire barriers. In addition, the team reviewed licensing bases documentation, such as NRC 5 Enclosure SERs and deviations from NRC regulations, to verify that passive fire protection features met license commitments.

The team walked down accessible portions of the selected FA/FZs to observe material condition and the design adequacy of fire area boundaries to assess if they were appropriate for the fire hazards in the area. Additionally, the team reviewed that as-built configurations met engineering design, standard industry practices, and were either properly evaluated or qualified by appropriate fire endurance tests. In addition, a sample of completed surveillance and maintenance procedures for selected fire doors, fire dampers, and fire barrier penetration seals were reviewed to ensure that these passive fire barrier features were properly inspected and maintained. The fire protection features included in the review are listed in the Attachment.

b. Findings

No findings were identified

.03 Active Fire Protection

a. Inspection Scope

The team performed in-plant observations of fire detection and manual suppression systems protecting the FA/FZs selected for review, reviewed design documents, and reviewed applicable NFPA codes and standards, to assess the material condition and operational lineup of fire detection and manual suppression systems. The appropriateness of detection and manual suppression methods for the category of fire hazards in the various areas was reviewed.

The team reviewed the fire detection and manual suppression surveillance instructions, as well as the most recently completed surveillance tests for each of the selected FA/FZs. The team reviewed the fire protection water supply system and operational valve lineups associated with the electric motor-driven fire pumps.

The team reviewed the fire detection system protecting the FA/FZs selected for review to assess the adequacy of the design and installation. The team also reviewed license documentation, such as NRC SERs and deviations from NRC regulations, to verify that active fire protection features met license commitments. The inspectors walked down the fire detection and alarm systems in the selected FA/FZs to evaluate the appropriateness of detection methods for the category of fire hazards in the areas relative to the NFPA 72E - 1974 location requirements.

During plant tours, the team observed placement of the fire hoses and extinguishers to verify they were not blocked and were consistent with the fire fighting pre-plan strategies and FPP documents.

The team reviewed the fire brigade staging and dress-out areas to asses the operational readiness of fire fighting and smoke control equipment. The fire brigade personal protective equipment, self-contained breathing apparatuses (SCBAs) and SCBA cylinder refill capability were reviewed for adequacy and functionality. The team also reviewed operator and fire brigade staffing, fire brigade response reports, offsite fire department communications and staging procedures, fire fighting pre-plan strategies, fire brigade 6 Enclosure qualification training, and the fire brigade drill program procedures. Fire brigade response-to-drill scenarios and associated brigade drill evaluations/critiques that transpired over the last 12 months for or in the vicinity of the selected FA/FZs were reviewed. The team also observed a fire brigade drill and post drill critique on May 12, 2010. The drill was conducted in a safety related area of the facility.

The team reviewed the fire fighting pre-plan strategies for the selected FA/FZs and fire response procedures to verify that pertinent information was provided to fire brigade members to identify potential effects to plant and personnel safety, and to facilitate suppression of an exposure fire that could impact SSD capability. The team walked down the selected FA/FZs to compare the associated fire fighting pre-plan strategy drawings with as-built plant conditions and fire response procedures. This was done to verify that fire fighting pre-plan strategies and drawings were consistent with the fire protection features and potential fire conditions described in the fire hazards analysis. The team also evaluated whether the fire response procedures and fire fighting pre-plan strategies for the selected FA/FZs could be implemented as intended. The documents included in the reviews are listed in the Attachment.

b. Findings

No findings were identified.

.04 Protection From Damage From Fire Suppression Activities

a. Inspection Scope

Through a combination of in-plant inspection and drawing reviews, the team evaluated the selected FAs/FZs to determine whether redundant trains of systems required for post-fire SSD could be subject to damage from fire suppression activities or from the rupture or inadvertent operation of fire suppression systems. The team considered the effects of water, drainage, heat, hot gasses, and smoke that could potentially damage redundant trains.

b. Findings

No findings were identified.

.05 Alternative Shutdown Capability

a. Inspection Scope

The team reviewed the systems and components credited for use during this shutdown method to verify that they would remain free from fire damage. The team reviewed the transfer logic for actuating the standby shutdown facility (SSF) to verify that the logic was tested and was in a periodic test program. The team reviewed surveillance test records for a sample of SSF hot standby instruments to verify that the instruments were periodically calibrated on a frequency consistent with the fire protection program requirements. The calibration records reviewed are listed in the Attachment. The team reviewed cable routing information by fire area for the Incore Nuclear Instrumentation Recorder ENCR9005 to verify that it would be available for use during a fire requiring the 7 Enclosure use of the SSF. Reviews also included verification that alternative shutdown could be accomplished with or without offsite power.

Operational Implementation The team reviewed selected job performance measures for licensed and non-licensed operators to verify that the training reinforced the shutdown methodology in the SSA and abnormal procedures for the selected FAs/FZs. The team also conducted interviews, reviewed shift turnover logs and shift manning to verify that personnel required for SSD using alternative shutdown systems and procedures were available onsite, exclusive of those assigned as fire brigade members.

The team performed a tabletop review of abnormal procedure AP/1/A/5500/017, "Loss of Control Room," and also performed a walk-through of procedure steps to ensure the implementation and human factors adequacy of the procedure. The team checked whether the SSD procedure included steps to prevent or mitigate the consequences of spurious operations. The team walked down the in-plant location of OMAs specified in the AP with operations personnel to evaluate the environmental conditions, relative difficulty and operator familiarization associated with each OMA. The team reviewed the systems and components credited for use during this shutdown method to verify that they would remain free from fire damage. The team reviewed selected operator actions to verify that the operators could reasonably be expected to perform the specific actions within the time required to maintain plant parameters within specified limits.

b. Findings

Introduction:

The team identified a Green non-cited violation (NCV) of Catawba Unit 1 Operating License Condition 2.C(5) and the FPP for the licensee

=s failure to install emergency lighting units (ELUs) in all areas where local OMAs were being performed to support post-fire safe shutdown. Specifically, ELUs were not installed in some areas in the Unit 1 turbine building for access/egress and where OMAs were specified by procedure AP/1/A/5500/017 to support post-fire safe shutdown for a fire in the MCR.

Description:

The team reviewed and walked down applicable sections of Abnormal Procedure AP/1/A/5500/017 to review the procedural guidance and assess the local operator actions in support of safe shutdown operation from the SSF in the event of a MCR fire. During the walkdown of procedure AP/1/A/5500/017, the team noted that ELUs were not installed along turbine building access/egress routes and in certain turbine building areas where local OMAs were being performed to support post-fire safe shutdown conditions. For example, there was no ELU installed in the vicinity of the main feedwater (CF) pump local control panels in the turbine building, where the AP directed operators to trip the CF pumps. The team determined that this OMA was added during a revision to procedure AP/1/A/5500/017 in February 2010.

The team concluded that the feasibility of this action would be challenged if normal lighting was lost and no ELUs were available. The team noted that the licensee

=s FPP (as referenced by UFSAR Section 9.5.1, "Fire Protection System," and described in design basis documents CNS-1435.00-00-0002, "Design Basis Specification for Post Fire Safe Shutdown," and CNS-1465.00-00-0006, "Design Basis Specification for the Plant Fire Protection") states that manual actions required within the initial eight hours must be provided with adequate battery-powered emergency lighting. This includes both 8 Enclosure the manual action location and the access/egress routes thereto. The team concluded that the failure to install ELUs to support the OMAs in the turbine building required by procedure AP/1/A/5500/017 did not comply with the FPP. The licensee initiated PIP C-10-2815 to address the ELU issue associated with the procedure.

Analysis:

The licensee's failure to install ELUs for local OMAs, as required by the CNS fire protection program, is a performance deficiency. The finding is more than minor because it is associated with the reactor safety Mitigating Systems cornerstone attribute of protection against external factors (i.e., fire) and it affects the objective of ensuring the reliability and capability of systems that respond to initiating events. Specifically, the finding could affect the ability to perform local OMAs required to achieve and maintain post-fire safe shutdown conditions following a MCR fire. The team completed a Phase 1 screening of the finding in accordance with IMC 0609, Appendix F, Fire Protection SDP Phase 1 Qualitative Screening Approach, Step 1.3, and concluded that the finding, given its low degradation rating, was of very low safety significance (Green), because the operators had a high likelihood of completing the tasks using flashlights or battery-powered portable hand lights. Consideration was given to the fact that operators normally carry flashlights and would have access to portable hand lights to provide the necessary lighting. The cause of this finding has a cross-cutting aspect in the Resources component of the Human Performance area, in that the licensee did not ensure that equipment such as fixed 8-hour ELUs were available to support post-fire safe shutdown local OMAs (H.2 (d)).

Enforcement:

Catawba Unit 1 Operating License Condition 2.C(5) requires the licensee to implement and maintain in effect all provisions of the approved FPP, as described in the UFSAR, and as approved in the NRC SER through Supplement 5. The approved FPP, as referenced by UFSAR Section 9.5.1, is contained in licensee design basis documents CNS-1435.00-00-0002, "Design Basis Specification for Post Fire Safe Shutdown," and CNS-1465.00-00-0006, "Plant Design Basis Specification for Fire Protection." The FPP states that manual actions required within the initial eight hours must be provided with adequate battery-powered emergency lighting. This includes both the OMA location and the access/egress routes thereto.

Contrary to the above, the licensee did not meet the requirements of the CNS FPP, in that 8-hour battery-powered ELUs were not installed in the Unit 1 turbine building where post-fire SSD OMAs were being performed. Specifically, there were no ELUs installed along the access/egress routes or in the vicinity of the CF pump local control stations in the turbine building where procedure AP/1/A/5500/017 directed operators to trip the CF pumps in the event of a MCR fire and MCR evacuation. The condition has existed since February 2010, when this OMA was added during a revision to procedure AP/1/A/5500/017. Because this finding is of very low safety significance and was entered into the licensee

=s corrective action program (PIP C-10-2815), this finding is being treated as a NCV, consistent with Section VI.A.1 of the NRC

=s Enforcement Policy. This finding is identified as NCV 05000413/2010006-01, Emergency Lighting Units Not Installed as Required by the Fire Protection Program.

Because the licensee committed, prior to December 31, 2005, to adopt NFPA 805 and change their fire protection licensing bases to comply with 10 CFR 50.48(c), the team evaluated this issue for enforcement and reactor oversight process discretion in accordance with the NRC Enforcement Policy, "Interim Enforcement Policy Regarding Enforcement Discretion for Certain Fire Protection Issues (10 CFR 50.48)." The team 9 Enclosure determined that enforcement discretion was not applicable to this finding, because it should have been previously identified by routine licensee efforts during review of the procedure change.

.06 Circuit Analyses

a. Inspection Scope

The team verified that a fire in the 6900 Volt Switchgear Room 1TA and 1TB in the turbine building, would not prevent SSD assuming a loss of offsite power. The inspectors reviewed design drawings to verify that the 125 volt direct current control power for the non-safety switchgear in the turbine building was electrically and physically separated from the control power for the safety-related switchgear in the auxiliary building, and that the protective relay logic would adequately protect the safety-related switchgear from electrical failures due to postulated fire damage in the 6900 volt switchgear room. This review was performed to confirm that a fire in a non-seismic category 1 structure should not affect seismic category 1 structures, systems, or components required for SSD. The inspectors also reviewed information showing the level of coordination between incoming supply breakers and feeder breakers of motor control center (MCC) 1EMXS. After reviewing cable routing information for all feeder cables from MCC 1EMXS, one associated circuit was found to be routed in an alternative shutdown area (FA 3) for which operation of the MCC is credited for SSD.

The cable was protected with a functional, but degraded fire barrier, for which the licensee had implemented appropriate compensatory measures. The inspectors verified that fuse and breaker coordination was appropriate to prevent loss of the MCC due to potential fire damage of the cable in the fire area. The inspectors verified this by reviewing a set of time current curves plotted for the types of protective devices used in MCC 1EMXS. Other documents reviewed are listed in the Attachment.

b. Findings

No findings were identified.

.07 Communications

a. Inspection Scope

The team reviewed plant communication capabilities to evaluate the availability of the communication systems to support plant personnel in the performance of local OMAs to achieve and maintain SSD conditions. The team also reviewed the communication systems available at different locations within the plant that would be relied upon to support fire event notification and fire brigade fire fighting activities to verify their availability at different locations.

b. Findings

No findings were identified.

10 Enclosure

.08 Emergency Lighting

a. Inspection Scope

The team performed plant walk down inspections with licensee staff of the post-fire safe shutdown procedures for the selected fire areas to observe if the placement and coverage area of fixed 8-hour battery pack emergency lights provided reasonable assurance of illuminating access and egress pathways and any equipment requiring local operation and/or instrumentation monitoring for post fire safe shutdown.

The team reviewed maintenance and design aspects, including manufacturer's information and vendor manuals, for the fixed emergency lighting units to verify that the battery power supplies were rated with at least an 8-hour capacity as described in fire protection safety evaluation reports. Preventive maintenance and surveillance testing records were reviewed to ensure adequate surveillance testing and periodic battery replacements were in place to ensure continued reliable operation of the fixed emergency lights. The team reviewed the completed 8-hour discharge test records for the fixed emergency lights to verify they met the minimum rating of at least eight-hour capacity. The team also discussed with the licensee the maintenance rule status of the emergency lighting systems. A list of documents reviewed is included in the Attachment.

b. Findings

Findings of significance involving emergency lighting are discussed in Section 1R05.05.b of this IR.

.09 Cold Shutdown Repairs

a. Inspection Scope

The licensee's SSA identified the need for post-fire repairs prior to achieving a cold shutdown condition. Thus, cold shutdown repair procedures and repair kits were reviewed during this inspection. The inspectors verified that the fire damage repair procedures were current and adequate and repair parts and equipment were being stored and maintained onsite. The inspectors toured the warehouse where the fire damage repair kits were stored, and examined the material condition of the parts being stored in the kits. The licensee annually inventories the repair kits in accordance with the inventory control procedure. The inspectors reviewed the inventory inspection check sheet records to verify that all required replacement parts were being accounted for and were available for use. The inspectors also verified by physical inspection that the special crimping tools required by the fire damage control procedure were readily available from the tool issue area for terminating new replacement electrical cables. The specific documents reviewed are listed in the Attachment.

b. Findings

No findings were identified.

11 Enclosure

.10 Compensatory Measures

a. Inspection Scope

The team reviewed the administrative controls for out-of-service, degraded, and/or inoperable fire protection features (e.g., detection and suppression systems and equipment, passive fire barriers, or pumps, valves or electrical devices providing SSD functions or capabilities). The team reviewed selected items on the fire protection impairment log and compared them with the FAs/FZs selected for inspection. The compensatory measures that had been established in these FAs/FZs were compared to those specified for the applicable fire protection feature to verify that the risk associated with removing the fire protection feature from service was properly assessed and adequate compensatory measures were implemented in accordance with the approved FPP. Additionally, the team reviewed the licensee's short term compensatory measures to verify that they were adequate to compensate for a degraded function or feature until appropriate corrective actions could be taken, and that the licensee was effective in returning the equipment to service in a reasonable period of time.

b. Findings

No findings were identified.

.11 B.5.b Inspection Activities

a. Inspection Scope

The team reviewed, on a sampling basis, the licensee's external spent fuel pool mitigation measures for large fires and explosions to verify that the measures were feasible, personnel were trained to implement the strategies, and equipment was properly staged and maintained. Through discussions with plant staff, review of documentation, and plant walk-downs, the team verified the engineering basis to establish reasonable assurance that the makeup capacity required by the strategy could be provided for the minimum time using the specified equipment and water sources.

The team reviewed the licensee's capability to provide a reliable and available water source and the ability to provide the minimum fuel supply. By review of records and physical inspection, the team verified that the B.5.b equipment required to support external spent fuel pool mitigation measures was being properly stored, maintained, and tested in accordance with the licensee's B.5.b program procedures. The team requested and reviewed maintenance records of required equipment. The team performed a walk-down of the storage and staging areas to verify that equipment identified for use in the current procedures were available and maintained. In the presence of licensee staff, the team conducted an independent audit and inventory of required equipment and a visual inspection of the dedicated credited power source.

The team also verified, by review of training records, that security, operations and emergency response personnel had received training on the strategy objectives and guidelines in accordance with the established training program.

b. Findings

No findings were identified.

OTHER ACTIVITIES

4OA2 Identification and Resolution of Problems

a. Inspection Scope

The team reviewed a sample of PIPs related to fire protection for detailed inspection to verify that the corrective actions were appropriate, timely and effective. The documents reviewed are listed in the Attachment.

b. Findings

No findings of significance were identified.

4OA6 Meetings, Including Exit

On May 13, 2010, the inspection team leader presented the preliminary inspection results to Mr. J. Morris, Site Vice President, and other members of the licensee's staff. Following completion of additional reviews in the Region II office, another exit meeting was held by telephone with Mr. R. Ferguson, Mechanical and Civil Engineering Manager, and other members of the licensee's staff on June 28, 2010, to provide an update on changes to the preliminary inspection findings. The license acknowledged the results.

Proprietary information is not included in this inspection report.

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee personnel

T. Arlow, Emergency Planning Manager
J. Brisson, Operations Support Group
B. Edmunds, Emergency Response Organization Training
G. Daniels, Operations Training
T. Daniels, Fire Brigade Coordinator
D. Davies, RF/RY System Engineer
A. Dickard, Breaker Coordination
R. Ferguson, Mechanical and Civil Engineering Manager
G. Hamrick, Station Manager
R. Hart, Regulatory Compliance Manager
M. Hogan, Fire Protection Engineer
T. Jackson, Regulatory Compliance
E. Madsen, Operations Training
J. Morris, Site Vice President Catawba Nuclear Station
A. Miller, Senior Reactor Operator
J. Oldham, Fleet-wide Fire Protection Engineer
T. Pasour, Regulatory Compliance
D. Peele, Emergency Lighting
B. Potter, Security Training
B. Price, B5b Engineer
T. Ray, Engineering Manager
M. Sawicki, Regulatory Compliance
S. Tripi, Operations Training

NRC personnel

R. Cureton, NRC Resident Inspector, CNS
A. Hutto, NRC Senior Resident Inspector, CNS

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened and Closed

05000413/2010006-01 NCV Emergency Lighting Units Not Installed as Required by the Fire Protection Program (Section 1R05.05.b)

Discussed

None

LIST OF FIRE BARRIER FEATURES INSPECTED (Refer to Report Section 1RO5.02- Passive Fire Barriers)

Fire Door Identification

Fire Door AX514B, Unit 1 Auxiliary Building SSF Disconnect, Elev. 577' Fire Door AX515, Unit 1 Auxiliary Building Cable Room, Elev. 574'

Fire Door AX516K, Unit 1 Auxiliary Building Cable Room, Elev. 574' Fire Door AX517C, Unit 1 Corridor to RCA Exit, Elev. 574' Fire Door AX536, Unit 1 Auxiliary Building Cable Room Area, Elev. 577'

Fire Damper Identification

Fire Damper 1CRA-FD-21, Control Room Area Fire Damper, Elev. 574' Fire Damper 1CRA-FD-22, Control Room Area Fire Damper, Elev. 574' Fire Damper 1CRA-FD-23, Control Room Area Fire Damper, Elev. 574' Fire Damper 2CRA-FD-19, Cable Room Area Fire Damper, Elev. 574'

Fire Damper 2CRA-FD-20, Cable Room Area Fire Damper, Elev. 574'

Fire Barrier Penetration Seal Identification

Penetration Firestop, H-AX-516-W-024, Type E-5 Electrical Cable Tray and Conduit Seal in Reinforced Concrete Wall, Auxiliary Building, Elev. 574' Penetration Firestop, H-AX-517-W-081, Type E-16 Armored Electrical Cable Seal in Masonry Block Wall, Auxiliary Building, Elev. 574' Penetration Firestop J-AX-515-W-005, Mechanical Seal in Masonry Block Wall, Auxiliary Building, Elev. 577' Penetration Firestop J-AX-536-F-004, Type M-2 Mechanical Seal in Reinforced Concrete Floor, Auxiliary Building, Elev. 577' Penetration Firestop, J-AX-514-W-027, Type E-12 Internal Conduit Seal in Electrical Conduit Embedded In Reinforced Concrete Wall, Auxiliary Building, Elev. 577'

LIST OF DOCUMENTS REVIEWED

Procedures

AP/0/A/5500/045, Plant Fires, Rev. 006 AP/0/A/5550/048, Extensive Damage Mitigation, Rev. 005
AP/1/A/5500/017, Loss of Control Room, Rev. 051
AP/1/A/5500/041, Loss of Spent Fuel Cooling or Level, Rev. 003 IP/0/A/3890/027C, Procedure for Inventory of Fire Damage Control (FDC) Kit, Rev. 014
IP/1/A/3890/027A, Fire Damage Control Procedure, Rev. 018
IP/0/B/3540/002, Emergency Battery Lighting (ELD) Periodic Maintenance and Testing,
Rev. 034 OP/0/B/6100/013, Standby Shutdown Facility Operations, Rev. 050 OP/0/B/6400/002E, Portable CAPT Sump Pump Operation, Rev. 002 CNS Addendum 7111.0, Catawba Nuclear Site Emergency Response Training Program Description, Rev. 12 PT/0/B/4600/032, Fire Brigade Equipment Inspection/Inventory, Rev. 005
RP/0/B/5000/029, Fire Brigade Response, Rev. 021
Nuclear System Directive: 104, Materiel Condition/Housekeeping, Foreign Material Exclusion and Seismic Concerns, Rev. 30 Nuclear System Directive: 313, Control of Combustible and Flammable Material, Rev. 7 Nuclear System Directive: 314, Hot Work Authorization, Rev. 7 Nuclear System Directive: 316, Fire Protection Impairment and Surveillance, Rev. 10
Calculations, Analyses and Evaluations
CNC-1435.00-00-0043, NFPA 805 Transition Expert Panel Report for Addressing Potential Catawba Multiple Spurious Operations, Rev. 0
CNS-1435.00-00-0002, Design Basis Specification for the Post Fire Safe Shutdown, Rev. 21
CNS-1465.00-00-0006, Design Basis Specification for the Plant Fire Protection, Rev. 16
CNS-1560.SS-00-0001, Design Basis Specification for the Standby Shutdown Facility, Rev. 26
DPC 1435.00-00-0006, Calculation for the Technical Evaluation of Fire Barrier Penetration Seals, Rev. 2

Drawings

CN-1100-02.03, Turbine Building Unit 1 General Arrangement Mezzanine Floor Elevation 594' + 0", Rev. 15
CN-1105-08, Architectural, Fire Boundary Walls, Plan at El. 574+0, Rev. 5
CN-1105-08.01, Rev. 8, Architectural, Fire Boundary Walls, Plan at El. 574+0, Rev. 8
CN-1105-09, Architectural, Fire Boundary Walls, Plan at El. 577+0, Rev. 10
CN-1105-08.02, Architectural, Fire Boundary Walls, Wall Elevations, El. 574+0, Rev. 19
CN-1105-09.05, Architectural, Fire Boundary Walls, Wall Elevations, El. 577+0, Rev. 16
CN-1105-09.08, Architectural, Fire Boundary Walls, Wall Elevations, El. 577+0, Rev. 16
CN-1105-10, Architectural, Fire Boundary Walls, Plan at El. 594+0, Rev. 23
CN-1105-10.03, Architectural, Fire Boundary Walls, Wall Elevations, El. 594+0, Rev. 17
CN-1105-10.04, Architectural, Fire Boundary Walls, Wall Elevations, Elevation 594+0, Rev. 11
CN-1105-10.05, Architectural, Fire Boundary Walls, Wall Elevations, El. 594+0, Rev. 13
CN-1105-16, Electrical Penetration Seal Firestop Details, Rev. 2
CN-1105-16.01, Electrical Penetration Seal Firestop Details, Rev. 1
CN-1105-17, Electrical Penetration Seal Firestop Details, Rev. 2
Attachment
CN-1105-17.01, Electrical Penetration Seal Firestop Details, Rev. 1
CN-1105-17.02, Electrical Penetration Seal Firestop Details, Rev. 1
CN-1200-9.4, Auxiliary Building, Units 1 & 2 - Floor El. 574+0, General Arrangement / Architectural, Cable Room Plan, Rev. 35
CN-1200-9.05, Auxiliary Building, Units 1 & 2 - Floor El. 577+0, General Arrangement / Architectural, Switchgear Room Plans, Rev. 75
CN-1200-10.04, Auxiliary Building, Units 1 & 2 - Floor El. 594+0, General Arrangement / Architectural, Control Room Plan, Rev. 69
CN-1201-4, Auxiliary Building Architectural, Concrete Block Wall Details, Rev. 59
CN-1201-4.1, Auxiliary Building Architectural, Concrete Block Wall Details, Rev. 13
CN-1201-4.2, Auxiliary Building Architectural, Concrete Block Wall Details, Rev. 17
CN-1201-4.3, Auxiliary Building Architectural, Concrete Block Wall Details, Rev. 30
CN-1201-4.4, Auxiliary Building Architectural, Concrete Block Wall Details, Rev. 25
CN-1201-4.5, Auxiliary Building Architectural, Concrete Block Wall Details, Rev. 17
CN-1201-4.6, Auxiliary Building Architectural, Fire Damper Details and Concrete Block Wall Details, Rev. 18
CN-1201-4.7, Auxiliary Building Architectural, Concrete Block Wall Details, Rev. 8
CN-1201-4.8, Auxiliary Building Architectural, Concrete Block Wall Details, Rev. 9
CN-1201-4.9, Auxiliary Building Architectural, Concrete Block Wall Details, Rev. 8
CN-1201-4.10, Auxiliary Building Architectural, Concrete Block Wall Details, Rev. 11
CN-1201-4.11, Auxiliary Building Architectural, Concrete Block Wall Details, Rev. 1
CN-1201-4.14, Auxiliary Building Architectural, Concrete Block Wall Details, Rev. 12
CN-1201-4.15, Auxiliary Building Architectural, "IVANY" Seismic Block Wall Details, Rev. 6
CN-1204-1, Auxiliary Building Architectural, Concrete Block Wall Details, El. 574+0 & El. 577+0, Rev. 27
CN-1204-2, Auxiliary Building Architectural, Concrete Block Wall Details, El. 577+0, Rev. 12
CN-1204-4, Auxiliary Building Architectural, Concrete Block Wall Elevations, El. 574+0 & El. 577+0, Rev. 44
CN-1204-5, Auxiliary Building Architectural, Concrete Block Wall Elevations, El. 577+0, Rev. 45
CN-1209-09, Fire Hose Houses, Rev. 4
CN-1209-10.10, Fire Protection Equipment, Auxiliary Building, Elevation 522+0, Rev. 3
CN-1209-10.11, Fire Protection Equipment, Auxiliary Building, Elevation 543+0, Rev. 14
CN-1209-10.12, Fire Protection Equipment, Auxiliary Building, Elevation 560+0, Rev. 20
CN-1209-10.13, Fire Protection Equipment, Auxiliary Building, Elevation 577+0, Rev. 18
CN-1209-10.14, Fire Protection Equipment, Auxiliary Building, Elevation 594+0, Rev. 16
CN-1209-10.15, Fire Protection Equipment, Auxiliary Building, Elevation 522+10 & 619+6,
Rev. 12
CN-1209-10.13, Fire Protection Equipment, Auxiliary Building, Elevation 577+0, Rev. 18
CN-1209-10.14, Fire Protection Equipment, Auxiliary Building, Elevation 594+0, Rev. 16
CN-1553-1.0, Flow Diagram of Reactor Coolant System (NC), Rev. 28
CN-1553-1.1, Flow Diagram of Reactor Coolant System (NC), Rev. 21
CN-1553-1.4, Flow Diagram of Reactor Coolant System (NC), Rev. 0
CN-1554-01.00, Flow Diagram of Chemical and Volume Control System (NV), Rev. 30
CN-1554-1.1, Flow Diagram of Chemical and Volume Control System (NV), Rev. 15
CN-1554-1.2, Flow Diagram of Chemical and Volume Control System (NV), Rev. 33
CN-1554-1.3, Flow Diagram of Chemical and Volume Control System (NV), Rev. 22
CN-1554-1.4, Flow Diagram of Chemical and Volume Control System (NV), Rev. 23
CN-1554-1.5, Flow Diagram of Chemical and Volume Control System (NV), Rev. 9
CN-1554-1.6, Flow Diagram of Chemical and Volume Control System (NV), Rev. 20
CN-1554-1.7, Flow Diagram of Chemical and Volume Control System (NV), Rev. 28
CN-1554-1.8, Flow Diagram of Chemical and Volume Control System (NV), Rev. 8
Attachment
CN-1554-1.9, Flow Diagram of Chemical and Volume Control System (NV), Rev. 0
CN-1599-1.0, Flow Diagram of Exterior Fire Protection System (RY), Rev. 37
CN-1599-1.1, Flow Diagram of Exterior Fire Protection System (RY), Rev. 6
CN-1599-1.2, Flow Diagram of Exterior Fire Protection System (RY), Rev. 14
CN-1599-2.0, Flow Diagram of Interior Fire Protection System (RF), Rev. 32
CN-1599-2.1, Flow Diagram of Interior Fire Protection System (RF), Rev. 31
CN-1599-2.2, Flow Diagram of Interior Fire Protection System (RF), Rev. 32
CN-1599-2.3, Flow Diagram of Interior Fire Protection System (RF), Rev. 30
CN-1599-2.4, Flow Diagram of Interior Fire Protection System (RF), Rev. 12
CN-1702-01.01, One Line Diagram 6900V Normal Auxiliary Power System (EPB) 6900V SWGR No. 1TA, Rev. 14
CN-1702-01.02, One Line Diagram 6900V Normal Auxiliary Power System (EPB) 6900V SWGR No. 1TB, Rev. 14
CN-1702-02.01, One Line Diagram 4160 Volt Essential Auxiliary Power System (EPC) 4160V Switchgear No. 1ETA, Rev. 17
CN-1702-02.02, One Line Diagram 4160 Volt Essential Auxiliary Power System (EPC) 4160V Switchgear No. 1ETB, Rev. 17
CN-1702-05.02, One Line Diagram Essential & Blackout Auxiliary Power Systems 4.16KV/600V Systems EPC, EPE, ETC, Rev. 8
CN-1703-03.24, One Line Diagram 600V Nonessential Load Center #1SLXG SSF, Rev. 3
CN-1705-01.01, One Line Diagram 125VDC Vital Instrumentation and Control Power System (EPL), Rev. 13
CN-1705-01.01-01, One Line Diagram 125 VDC Vital Instrumentation and Control Power System (EPL), Rev. 10
CN-1705-02.02, One Line Diagram 125VDC Auxiliary Control Power System (EPK) Distribution Center 1CDA, Rev. 22
CN-1716-03.02-01, Connection Diagram SSF Control Panel 0CNSL0001 (EOC System),
Rev. 32
CN-1716-03.02-02, Connection Diagram SSF Control Panel 0CNSL0001 (EOC System),
Rev. 26
CN-1716-03.02-03, Connection Diagram SSF Control Console 0CNSL0001 (EOC System), Rev. 36
CN-1716-03.02-04, Connection Diagram SSF Control Console 0CNSL0001 (EOC System), Rev. 20
CN-1716-03.02-05, Connection Diagram SSF Control Console 0CNSL0001 (EOC System), Rev. 14
CN-1762-01.01-04, Location Diagram, Fire Detection Sys (EFA), Detector Locations on El. 577+0 & 568+0, Rev. 7
CN-1762-01.01-05, Location Diagram, Fire Detection Sys (EFA), Detector Locations on El. 594+0, Rev. 22
CN-1767-01.09-07, Connection Diagram Reactor Building Penetrations Type K (Instrument) Penetration No. 1PENT0268, Rev. 18
CN-1783-02.02, Connection Diagram Incore Nuclear Instrumentation Sys (ENA) Control Cabinets C & D, Rev. 11
CN-1783-02.08, Connection Diagram Incore Instrumentation (ENA) Thermocouple System Reference Junction Box 2, Rev. 8
CN-1856-03, 8 Hour Battery Lighting Location Charts, Rev. 32
CN-1856-04, 8 Hour Battery Lighting Location Charts, Rev. 14
CN-1926-04, Electrical Equipment Layout Turbine Building Below Operating Floor Col.
IG-IN & 15 - 22 Plan, Rev. 21
Attachment
CNEE-0112-02.01, Elementary Diagram Standby Shutdown System (AD) SSF Transfer Scheme Essential Relaying Circuit, Rev. 3
CNEE-0112-02.01-01, Elementary Diagram Standby Shutdown System (AD) SSF Transfer Scheme Alarm and Monitoring Circuit, Rev. 3
CNEE-0112-02.01-02, Elementary Diagram Standby Shutdown System (AD) SSF Transfer Scheme Control Relays, Rev. 6
CNEE-0112-02.02, Elementary Diagram Standby Shutdown System (AD) SSF Transfer Scheme Non-Essential Control Circuit, Rev. 3
CNEE-0112-02.03, Elementary Diagram Standby Shutdown System (AD) SSF Transfer Scheme Alarms and Monitoring, Rev. 5
CNEE-0115-01.03, Elementary Diagram 4160V Switchgear 1ETA Unit 3 Normal Incoming Breaker Transfer 1ATC, Rev. 15
CNEE-0115-01.20, Elementary Diagram 4160V Switchgear 1ETA Breaker Failure, Mode Selector and Degraded Bus Voltage Circuits, Rev. 17
CNEE-0115-02.05, Elementary Diagram 4160V Blackout Switchgear 1FTA & 1GTA Potential, Breaker Failure, Heater Circuits, Rev. 8
CNEE-0116-01.04, Elementary Diagram 6900V Switchgear 1TA Unit #4 6900/4160V Transfer 1ATC, Rev. 9
CNEE-0116-01.18, Elementary Diagram 6900V Switchgear 1TA Breaker Failure, Residual Undervoltage and Undervoltage Circuits, Rev. 10
CNEE-0116-01.36, Elementary Diagram 6900V Switchgear 1TB Breaker Failure, Residual Undervoltage and Undervoltage Circuits, Rev. 9
CNEE-0160-02.21, Elementary Diagram Steam Turbine Driven Auxiliary Feedwater Pump #1 Sump Pump "1A" (1PMTR0196), Rev. 13
CNEE-0172-01.05, Elementary Diagram Incore Nuclear Instrumentation System (ENA) Monitor Points, Rev. 4
CNLD-0116-01.01, Logic Diagram 6.9KV Switchgear 1TA, 1TB, 1TC, 1TD Protective Relaying, Rev. 1
CNSF-1561-ND.01, Summary Flow Diagram Residual Heat Removal System (ND) Unit 1,
Rev. 3
CNSF-1573-KC.01, Summary Flow Diagram Component Cooling System (KC) Unit 1, Rev. 2
CNSF-1573-KC.02, Summary Flow Diagram Component Cooling System (KC) Unit 1, Rev. 1
CNSF-1553-NC.01, Summary Flow Diagram Reactor Coolant System (NC) Unit 1, Rev. 0
CNSF-1562-NI.01, Summary Flow Diagram Safety Injection System (NI) Unit 1, Rev. 0
CNSF-1592-CA.01, Summary Flow Diagram Auxiliary Feedwater System (CA) Unit 1, Rev. 5
Completed Surveillance Procedures, Test Records, & Work Orders
IP/0/A/3890/027C, Procedure for Inventory of Fire damage Control (FDC)
Kit, Rev. 013, Completed 11/5/09 IP/0/A/3890/027C, Procedure for Inventory of Fire Damage Control (FDC)
Kit, Rev. 013, Completed 2/5/08 PT/0/A/4400/002F, Extensive Damage Mitigation (EDM) Equipment Inspection, Rev. 000,
Completed 12/08/2008
PT/0/A/4400/002F, EDM Equipment Inspection, Rev. 000, Completed 11/06/2009
PT/0/A/4700/061, Time Critical Operator Action Review, Rev. 004, Completed 8/12/2008
PT/1/A/4350/022, CA Control from SSF Operability Test, Rev. 016, Completed 12/11/09
PT/2/A/4350/022, CA Control from SSF Operability Test, Rev. 014, Completed 4/11/09
PT/1/A/4600/003A, Monthly Surveillance Items Enclosure 13.6 - SSF Monitoring Instrumentation, Completed 4-30-10
Attachment
PT/1/A/4700/012, SSF Control Panel Functional Verification, Completed 10/30/2000
PT/2/A/4700/012, SSF Control Panel Functional Verification, Completed 4/4/2000
Work Order (WO) 0177945401: May Emergency Battery Lights PM, Completed 5-21-08
WO 0177548701: April Emergency Battery Lights PM, Completed 4-23-08
WO 0177034101: March Emergency Battery Lights PM, Completed 3-26-08
WO 0176473001: February Emergency Battery Lights PM, Completed 2-12-08
WO 0175963301: January Emergency Battery Lights PM, Completed 1-14-08
WO 0172200501: June Emergency Battery Lights PM, Completed 6-14-07
WO 0176422401: Perform Monthly Operability Test, Completed 8-22-07
WO 0187698901: January Emergency Battery Lights PM, Completed 1-25-10
WO 0188555701: February Emergency Battery Lights PM, Completed 2-25-10
WO 0188656701: March Emergency Battery Lights PM, Completed 3-31-10
WO 0184796601: July Emergency Battery Lights PM, Completed 7-28-09
WO 0184550101: June Emergency Battery Lights PM, Completed 6-24-09
WO 0183352901: April Emergency Battery Lights PM, Completed 5-4-09
WO 0183016101: March Emergency Battery Lights PM, Completed 3-27-09
WO 0182506301: February Emergency Battery Lights PM, Completed 3-4-09
WO 0181786001: January Emergency Battery Lights PM, Completed 1-19-09
WO 0186898701: November Emergency Battery Lights PM, Completed 11-29-09
WO 0187187901: December Emergency Battery Lights PM, Completed 12-17-09
WO 0184796601: July Emergency Battery Lights PM, Completed 7-28-09
WO 0185468301: August Emergency Battery Lights PM, Completed 8-31-09
WO 0186107701: September Emergency Battery Lights PM, Completed 9-23-09
WO 0186484801: October Emergency Battery Lights PM, Completed 11-2-09
WO 0183756201: May Emergency Battery Lights PM, Completed 5-18-09
WO 0191388801: Perform Monthly Operability Test, Completed 3-31-10
WO 0191042901: Perform Monthly Operability Test, Completed 2-15-10
WO 0181237901: Perform Monthly Operability Test, Completed 6-18-08
WO 0190534301: Perform Monthly Operability Test, Completed 1-25-10
WO 0181086001: Perform Monthly Operability Test, Completed 5-12-08
WO 0189843301: Perform Monthly Operability Test, Completed 1-05-10
WO 0180594801: Perform Monthly Operability Test, Completed 4-14-08
WO 0188964701: Perform Monthly Operability Test, Completed 11-02-09
WO 0180121101: Perform Monthly Operability Test, Completed 4-03-08
WO 0188642401: Perform Monthly Operability Test, Completed 9-23-09
WO 0179435701: Perform Monthly Operability Test, Completed 3-03-08
WO 0188297301: Perform Monthly Operability Test, Completed 8-31-09
WO 0179194101: Perform Monthly Operability Test, Completed 1-28-08
WO 0187847301: Perform Monthly Operability Test, Completed 8-03-09
WO 0178580401: Perform Monthly Operability Test, Completed 1-14-08
WO 0187353801: Perform Monthly Operability Test, Completed 7-08-09
WO 0178216501: Perform Monthly Operability Test, Completed 11-30-07
WO 0186853001: Perform Monthly Operability Test, Completed 5-19-09
WO 0177641601: Perform Monthly Operability Test, Completed 11-13-08
WO 0186353001: Perform Monthly Operability Test, Completed 5-05-09
WO 0177384501: Perform Monthly Operability Test, Completed 10-04-07
WO 0186041601: Perform Monthly Operability Test, Completed 3-23-09
WO 0175978401: Perform Monthly Operability Test, Completed 7-24-07
WO 0185087801: Perform Monthly Operability Test, Completed 3-04-09
WO 0176946701: Perform Monthly Operability Test, Completed 9-13-07
WO 0184850601: Perform Monthly Operability Test, Completed 1-19-09
WO 0184163701: Perform Monthly Operability Test, Completed 1-05-09
WO 0184163701: Perform Monthly Operability Test, Completed 1-05-09
Attachment
WO 0183647501: Perform Monthly Operability Test, Completed 11-12-08
WO 0183389901: Perform Monthly Operability Test, Completed 10-16-08
WO 0183028601: Perform Monthly Operability Test, Completed 9-29-08
WO 0182380201: Perform Monthly Operability Test, Completed 9-02-08
WO 0181703401: Perform Monthly Operability Test, Completed 7-22-08
WO 0185212301: 1CFLP5612
CC-SG A Wide Range Level - SSF, Completed 12-02-09
WO 0185215701: 1CFLP5622 1CF-CC-SG B Wide Range Level, Completed 11-30-09
WO 0185215801: 1CFLP5632
CC-SG C Wide Range Level - SSF, Completed 12-01-09
WO 0185212501: 1CFLP5642
CC-SG D Wide Range Level, Completed 11-30-09
WO 0185262601: 1NC - Calibrate NC Temperature Loops, Completed 11-15-09
WO 0185253401: 1NC - Calibrate Pressurizer Instrumentation, Completed 11-18-08
WO 0113045701: PT/0/A/4400/001 W, Rev. 019, SLC Fire Hose Station Flow Test, Completed 03/19/07
WO 0182193601: PT/0/A/4400/001 W, Rev. 019, SLC Fire Hose Station Flow Test, Completed 02/17/10
WO 0186865001: PT/0/A/4400/001 A, Rev. 047, Exterior Fire Protection Functional Capability Test, Completed 03/16/10
WO 0174878907: PT/0/A/4200/048 A, Rev. 002, Periodic Inspection of Fire Dampers, Completed 02/11/08
WO 0183800302: PT/0/A/4200/048 A, Rev. 003, Periodic Inspection of Fire Dampers, Completed 05/28/09
WO 0113186801: PT/0/A/4200/048, Rev. 021, Periodic Inspection of Fire Barriers and Related Structures, Completed 10/17/06
WO 0186389301: PT/0/A/4200/048, Rev. 023, Periodic Inspection of Fire Barriers and Related Structures, Completed 10/7/09
WO 0188292001: PT/0/A/4200/048, Rev. 023, Periodic Inspection of Fire Barriers and Related Structures, Completed 3/8/10
WO 0182014301: IP/0/A/3350/010, Rev. 020, EFA System Detector Test Procedure for DGP07, Completed 4/7/09
WO 0189904801: IP/0/A/3350/010, Rev. 020, EFA System Detector Test Procedure for DGP07, Completed 3/3/10
WO 0182054101: IP/0/A/3350/012, Rev. 017, EFA System Detector Test Procedure for DGP09, Completed 3/8/09
WO 0190522701: IP/0/A/3350/012, Rev. 018, EFA System Detector Test Procedure for DGP09, Completed 3/4/10
WO 0182013401: IP/0/A/3350/013, Rev. 017, EFA System Detector Test Procedure for DGP10, Completed 2/24/09
WO 0189898201: IP/0/A/3350/013, Rev. 017, EFA System Detector Test Procedure for DGP10, Completed 1/20/10
WO 0184746401: IP/0/A/3350/003, Rev. 029, Fire Detection System (EFA) Channel Operational Test Procedure, Completed 6/04/09
WO 0187417601: IP/0/A/3350/003, Rev. 029, Fire Detection System (EFA) Channel Operational Test Procedure, Completed 12/11/09
Applicable Codes, Specifications, & Standards
NFPA 10, Portable Fire Extinguishers, 1978 Edition NFPA 14, Standard for the Installation of Standpipe and Hose Systems, 1978 Edition NFPA 20, Standard for the Installation of Centrifugal Fire Pumps, 1978 Edition NFPA 24, Outside Protection, 1978 Edition Attachment
NFPA 30, Flammable and Combustible Liquids Code, 1977 Edition NFPA 72D - Proprietary Protective Signaling Systems, 1975 Edition NFPA 72E - Automatic Fire Detectors, 1974 Edition NFPA 80, Standard for Fire Doors and Windows, 1977 Edition NFPA 90A, Standard on Air Conditioning and Ventilating Equipment, 1981 Edition
NUREG-1552, Supplement 1, Fire Barrier Penetration Seals in Nuclear Power Plants, dated January 1999
Technical Manuals & Vendor Information
EMERGI-LITE Product Catalog - March 1994
Audits & Self-Assessments Audit Number 09-24 (INOS)(TFP)(CNS), Duke Energy Carolina, Catawba Nuclear Station, Triennial Fire Protection Audit, October 5 - October 15, 2009
License Basis Documents
CNS UFSAR, Section 9.5.1, "Fire Protection System"
CNS UFSAR Chapter 16, "Selected Licensee Commitments"
CNS Units 1 and 2 Renewed Operating License Condition 2.C (5), "Fire Protection Program"
CNS Units 1 and 2 Renewed Operating License Condition 2.C (6), "Mitigation Strategies"
CFR Part 50, Appendix A, GDC 3, "Fire Protection"
CFR 50.48, "Fire Protection" Branch Technical Position (BTP) Chemical Engineering Branch (CMEB) 9.5-1
Catawba Safety Evaluation Report (SER), NUREG 0954 with Supplements 2, 3, 4, and 5

Other Documents

CNS Addendum 7111.0, CNS Emergency Response Training Program Description, Rev. 12
SDQA-70322-COM, ST2122 Multiple Assigned Job Status Report (ODS)
ST2183, Simple Exception Report, CNEA49-N B.5.b/EDMG Training, Period 1/1/2008 -
4/13/2010
CNS-376.00-EFA-0001, Design Basis Specification for the EFA System, Rev. 4
CNS-1465.00-00-0006, Design Basis Specification for the Plant Fire Protection, Rev. 16,
CNS-1599.RF-00-0001, Design Basis Specification for the Fire Protection System (RF/RY), Rev. 18 CNS Fire Detection (EFA) Engineering Support Document, Rev. 7 Duke Power Company, CNS, Engineering Support Document, FPP, dated 11/2/2009 Duke Power Company, CNS, Interior/Exterior Fire Protection Systems (RF/RY), Engineering Support Document, Rev. 7 CNS Fire Brigade Response Strategies for Non-Safety Related Areas, Fire Strategy I & N, Rev.
CNS Fire Brigade Response Strategies for Safety Related Areas, Fire Strategy Fire Areas 13, 15, 16, 17, 19, 20, 21, 22, 35 & 45, Rev. 34 CNS Training Addenda, Addendum 7111.0, Catawba Nuclear Site Emergency Response (ER) Training Program Description, Rev. 12 Duke Energy Nuclear System Directive 112, Fire Brigade Organization, Training and Responsibilities, Rev. 8
Attachment
CNS 1435.00-00-0035, Rev. 0, CNS Penetration Seal Database and 86-10 Evaluations, Attachment 10, Fire Protection Evaluation for Penetrations That Do Not Conform to the Overlap Criteria of Typical Detail M-1, Rev. 0 Fire Detection System (EFA) System Health Report (1/1/2010 - 3/31/2010) Fire Protection System (RF/RY) System Health Report (1/1/2010 - 3/31/2010)
Impairment Log, dated 4/26/2010 JPM
OP-CN-CP-AD-001, Transfer Control to the Standby Shutdown System, Rev. 22 JPM
OP-CN-CP-AD-002, Establish NCP Seal Injection from the SSF, Rev. 27 JPM
OP-CN-CP-AD-003, Place SSF Diesel in Operation, Rev. 23 JPM
OP-CN-CP-AD-011, Perform a Unit 1 Partial Transfer to the SSF, Rev. 00
JPM
OP-CN-CP-ADS-002, Establish NC Pump Seal Injection from the SSF (Loss of RN),
Rev. 09
JPM
OP-CN-CP-RSS-004, Loss of Control Room NLO Actions, Rev. 02
LIST OF PROBLEM INVESTIGATION PROCESS (PIP) REPORTS REVIEWED DURING INSPECTION
C-00-05641
C-09-05931
C-01-03509
C-10-00672 C-09-01010
C-10-01527 C-09-01184
C-10-00518 C-09-06370
C-08-06488
C-09-06529
C-08-02042 C-09-01222
C-07-03911 C-04-01566
C-04-01574 C-06-03746
LIST OF PIPS GENERATED AS A RESULT OF THIS INSPECTION
C-10-02180
C-10-02323
C-10-02206
C-10-02815 C-10-00518

LIST OF ACRONYMS

AND [[]]
ABBREV IATIONS
AOV Air Operated Valve
AP Abnormal Procedure
APCSB Auxiliary and Power Conversion Systems Branch
BTP Branch Technical Position
CMEB Chemical Engineering Branch
CNS Catawba Nuclear Station
CFR Code of Federal Regulations
DC Direct Current
EDM Extensive Damage Mitigation
ELU Emergency Lighting Unit
FA Fire Area
FPP Fire Protection Program
FZ Fire Zone
IMC Inspection Manual Chapter
IP [[]]
NRC Inspection Procedure
MCC Motor Control Center
MCR Main Control Room
MOV Motor Operated Valve
NCV Non-cited Violation
NFPA National Fire Protection Association
NRC United States Nuclear Regulatory Commission
NUREG An explanatory document published by the
NRC [[]]
OMA Operator Manual Action
PIP Problem Identification Report
PORV Power Operated Relief Valve
REV Revision
ROP Reactor Oversight Program
SCBA Self-Contained Breathing Apparatus
SDP Significance Determination Process
SER Safety Evaluation Report
SSA Appendix R Safe Shutdown Analysis
SSD Safe Shutdown
SSF Standby Shutdown Facility
UFSAR Updated Final Safety Analysis Report
URI Unresolved Item
WO Work Order