The Resources aspect is in the area of human performance.
Definition
Leaders ensure that personnel, equipment, procedures, and other resources are available and adequate to support nuclear safety.
|
|---|
Current trends: |
|
Count H.1 0 Since 12-08-2023 | |
|---|
Findings list | - 05000275/FIN-2018003-02 (Diablo Canyon, 2018Q3, 4 kV Vital Switchgear Room Ventilation Degraded or Non-Conforming Condition and Associated Compensatory Measure Not Corrected in a Timely Manner)
- 05000410/FIN-2018003-01 (Nine Mile Point, 2018Q3, Failure to Ensure that Thermal Power is Less Than or Equal to the Licensed Power Limit)
- 05000366/FIN-2018003-01 (Hatch, 2018Q3, Inoperability of 2A EDG Due to Inadequate Acceptance Criteria for Determining Cleaning Requirements of Emergency Diesel Generator Day Tanks)
- 05000220/FIN-2018002-02 (Nine Mile Point, 2018Q2, Inadequate Procedure Causes Water Hammer Condition Resulting in Isolation and Inoperability of the 12 Train of the Emergency Condenser System)
- 05000354/FIN-2018002-01 (Hope Creek, 2018Q2, Inadequate Instructions for Station Service Water Pump Maintenance)
- 05000348/FIN-2018002-05 (Farley, 2018Q2, Failure of a Main Steam Isolation Valve on the C Steam Line)
- 05000348/FIN-2018002-01 (Farley, 2018Q2, High vibrations on the 1B Charging pump)
- 05000390/FIN-2018002-01 (Watts Bar, 2018Q2, Inadequate Procedure Results in Exceeding the Design Pressure of the RHR Piping)
- 05000331/FIN-2018002-01 (Duane Arnold, 2018Q2, Inappropriate Procedural Guidance Resulted in Loss of Scram Function and Failure to Enter Technical Specification Limiting Condition for Operation)
- 05000336/FIN-2018410-01 (Millstone, 2018Q2, Security)
... further results |
|---|
|