IR 05000352/2009002
Download: ML091270824
Text
May 7, 2009
Mr. Charles Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Rd. Warrenville, IL 60555
SUBJECT: LIMERICK GENERATING STATION - NRC INTEGRATED INSPECTION REPORT 05000352/2009002 AND 05000353/2009002
Dear Mr. Pardee:
On March 31, 2008, the U. S. Nuclear Regulatory Commission (NRC) completed an inspection at your Limerick Generating Station Units 1 and 2. The enclosed integrated inspection report documents the inspection results which were discussed on April 10, 2009, with Mr. C. Mudrick and other members of your staff. The inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel. This report documents two NRC-identified findings of very low safety significance (Green).
The findings were determined to involve violations of NRC requirements. Additionally, a licensee-identified violation which was determined to be of very low safety significance is listed in this report. However, because of the very low safety significance and because they are entered into your corrective action program (CAP), the NRC is treating these findings as non-cited violations (NCVs), consistent with Section VI.A.1. of the NRC Enforcement Policy. If you contest any NCV in this report, you should provide a response within 30 days of the date of this inspection report, with basis for your denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administration, Region I; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-001; and the NRC Resident Inspector at the Limerick facility. In addition, if you disagree with the characterization of the cross-cutting aspect of any finding on this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the Regional Administrator, Region 1 and the NRC Senior Resident Inspector at the Limerick facility. The information you provide will be considered in accordance with Inspection Manual Chapter 0305. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,/RA/
Paul G. Krohn, Chief Projects Branch 4 Division of Reactor Projects Docket Nos: 50-352, 50-353 License Nos: NPF-39, NPF-85
Enclosure:
Inspection Report 05000352/2009002 and 05000353/2009002
w/Attachment:
Supplemental Information cc w/encl: C. Crane, President and Chief Operating Officer, Exelon Corporation M. Pacilio, Chief Operating Officer, Exelon Nuclear C. Mudrick, Site Vice President, Limerick Generating Station E. Callan, Plant Manager, Limerick Generating Station R. Kreider, Regulatory Assurance Manager, Limerick J. Grimes, Acting Senior Vice President, Mid-Atlantic Operations K. Jury, Vice President, Licensing & Regulatory Affairs P. Cowan, Director, Licensing D. Helker, Licensing B. Fewell, Associate General Counsel, Exelon Correspondence Control Desk D. Allard, Director, PA Dept of Environmental Protection J. Johnsrud, National Energy Committee, Sierra Club Chairman, Board of Supervisors of Limerick Township
SUMMARY OF FINDINGS
......................................................................................................... 3
REPORT DETAILS
REACTOR SAFETY
.............................................................................................................. 5 1R01 Adverse Weather Protection ................................................................................... 5 1R04 Equipment Alignment ............................................................................................. 5 1R05 Fire Protection ........................................................................................................ 6 1R07 Heat Sink Performance .......................................................................................... 7 1R11 Licensed Operator Requalification Program ........................................................... 7 1R12 Maintenance Effectiveness ..................................................................................... 7 1R13 Maintenance Risk Assessments and Emergent Work Control ................................ 8 1R15 Operability Evaluations ........................................................................................... 8 1R18 Plant Modifications ................................................................................................. 9 1R19 Post-Maintenance Testing .................................................................................... 12 1R20 Refueling and Other Outage Activities .................................................................. 12 1R22 Surveillance Testing ............................................................................................. 13 1EP2 Alert and Notification System (ANS) Evaluation ................................................... 15 1EP3 Emergency Response Organization (ERO) Staffing and Augmentation System ... 16 1EP4 Emergency Action Level (EAL) and Emergency Plan Changes ............................ 16 1EP5 Correction of Emergency Preparedness (EP) Weaknesses
RADIATION SAFETY
.......................................................................................................... 17 2OS1 Access Control to Radiologically Significant Areas ............................................... 17 2OS2 ALARA Planning and Controls .............................................................................. 19 2OS3 Radiation Monitoring Instrumentation and Protective Equipment .......................... 20 2PS3 Radiological Environmental Monitoring Program and Radioactive Material Control Program ..................................................................................... 20
4. OTHER ACTIVITES ............................................................................................................. 22
4OA1 Performance Indicator (PI) Verification
................................................................ 22
4OA2 Identification and Resolution of Problems
............................................................ 23
4OA3 Event Follow-up .................................................................................................... 25 4OA5 Other Activities ...................................................................................................... 27 4OA6 Meetings, Including Exit......................................................................................... 28 4OA7 Licensee-Identified Violations ................................................................................ 28
ATTACHMENT:
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
.................................................................................................. A-1
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
....................................................... A-2
LIST OF DOCUMENTS REVIEWED
...................................................................................... A-2
LIST OF ACRONYMS
............................................................................................................ A-9
Enclosure
- OF [[]]
- FINDIN [[]]
GS IR 05000352/2009002, 05000353/2009002; 01/01/2009 - 03/31/2009; Limerick Generating Station, Units 1 and 2; Surveillance Testing and Permanent Plant Modifications.
The report covered a three-month period of inspection by resident inspectors and announced inspections by regional reactor inspectors. Two Green findings which were determined to be non-cited violations (NCVs) were identified. The significance of most findings is indicated by their color (Green, White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609,
"Significance Determination Process (SDP)." Findings for which the
- NRC 's program for overseeing the safe operation of commercial nuclear power reactors is described in
- NUREG -1649, "Reactor Oversight," Revision 4, dated December 2006. Cornerstone: Barrier Integrity * Green. The inspectors identified a Green
III, "Design Control," for the failure to translate minimum room temperatures assumed in an isolation actuation instrumentation setpoint calculation into Unit 1 and 2 procedures such that reactor building room temperatures were maintained above the minimum assumed. As a result, the reactor enclosure and refueling area ventilation systems were not
operated to assure that room temperatures were maintained above the minimum assumed in design basis calculations. Exelon entered the issue into the Corrective Action Program (CAP) for resolution. This finding was more than minor because it was associated with the Design Control
attribute of the Barrier Integrity cornerstone, and affected the Barrier Integrity cornerstone objective to provide reasonable assurance that physical design barriers, including containment, protect the public from radionuclide releases caused by accidents or event. This finding was determined to be of very low safety significance because it did not represent an actual open pathway in the physical integrity of reactor containment,
containment isolation system, and heat removal components. This finding has a cross-cutting aspect in Human Performance, Decision Making, because the licensee did not make a safety significant decision using a systematic process to ensure safety was maintained H.1(a). Specifically, the decision to operate the reactor buildings at lower temperatures was made using an informal process within operations, therefore
interdisciplinary input and a review by engineering and other support organizations was not obtained (Section 1R22). Cornerstone: Mitigating Systems * Severity Level
- IV [[]]
- CFR 50.59, "Changes, Test, and Experiment," for failing to obtain a Technical Specification (TS) license amendment for a change made to the
TS Bases 3/4.8.1 required a change in the TS, because
the change caused the bases to be in direct conflict with the requirements of
CAP and issued night orders to operators which required declaring an offsite power supply
Enclosure inoperable when an offsite power supply feeder breaker became unavailable to an emergency bus.
Because this was a violation of
- 10 CFR [[50.59, it was considered to be a violation which potentially impedes or impacts the regulatory process. Therefore, such violations are characterized using the traditional enforcement process. In this case, the licensee failed to perform an adequate safety evaluation in accordance with 10]]
CFR 50.59 because the
approved change to the technical specification basis was in conflict with the
- NRC approval would have been required. The inspectors completed a Significance Determination Review using
- NRC [[]]
- IMC [[0609, Attachment 4, Phase 1 - Initial Screening and Characterization of Findings. Using the Phase I Screening worksheet the finding was determined to be of very low safety significance (Green) since the finding did not represent an actual loss of safety function for greater than the]]
- CFR 50.59 that result in conditions evaluated as having very low safety significance (i.e., Green) by the
- TS [[Bases change was made in 2000, the inspectors determined that this finding was not reflective of current licensee performance and, therefore, did not have a cross-cutting aspect. (Section 1R18) Other Findings A violation of very low safety significance, which was identified by the licensee has been reviewed by the inspectors. Corrective actions taken or planned by the licensee have been entered into the licensee's corrective action program. This violation and corrective actions are listed in Section 4]]
OA7 of this report. .
Enclosure
- REPORT [[]]
DETAILS Summary of Plant Status Unit 1 began the inspection period operating at full rated thermal power (RTP). On January 19, operators reduced power to approximately 65 percent to facilitate scram time testing, a control rod sequence exchange, and condenser waterbox cleaning. The unit was restored to full power
later that day. On March 13, a planned downpower to approximately 80 percent was performed for main turbine valve testing, main steam isolation valve testing, and fuel channel bow testing. The unit was restored to 100 percent power on March 14. Unit 1 operated at full RTP for the remainder of the inspection period.
Unit 2 began the inspection period operating at full
- RTP. [[On January 16, Unit 2 entered coastdown and feedwater temperature reduction operations, as planned, in advance of the Unit 2 refueling outage. On January 31, an unplanned downpower to approximately 72 percent was performed due to a loss of drywell cooling caused by a fault on a 480V motor control center (]]
MCC). Unit 2 was restored to 100 percent power on February 1. On February 21, operators performed a planned downpower to approximately 80 percent to facilitate fuel channel bow testing. On February 22, the Unit was returned to its maximum attainable power of 99 percent.
On March 19, Unit 2 experienced an unplanned downpower from 90 percent to 63 percent power when the 'B' reactor recirculation pump motor generator slowed to its minimum speed setting due to a power supply inverter inadvertently being switched off. The unit was restored to maximum attainable power later that day. On March 22, operators performed a reactor shutdown from 89 percent power to commence refueling outage 2R10. Unit 2 remained in the
refueling outage for the remainder of the inspection period. 1.
SAFETY Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity 1R01 Adverse Weather Protection (71111.01 - 1 sample) External Flooding
a. Inspection Scope The inspectors assessed the design and material condition of the Unit 2 emergency diesel generator (EDG) building to determine its ability to mitigate external flood conditions. The inspectors reviewed the licensee's Updated Final Safety Analysis Report
(UFSAR) and Individual Plant Examination for External Events (IPEEE) to determine the requirements for the
EDG building roof to ensure the drains were free of debris, there was no low-lying equipment that could be impacted by a maximum precipitation event, and the structure appeared sound. The inspectors also conducted a walkdown of the exterior walls of the EDG building to ensure there were no cracks in the structure or caulking that could allow water to enter the building.
b. Findings No findings of significance were identified. 1R04 Equipment Alignment (71111.04Q - 3 samples)
Enclosure Partial Walkdown a. Inspection Scope The inspectors performed partial walkdowns of the plant systems listed below to verify their operability when safety-related equipment in the opposite train was either
inoperable, undergoing surveillance testing, or potentially degraded. The inspectors used
- UFS [[]]
AR as guidance for conducting partial system walkdowns. The inspectors reviewed the alignment of system valves and electrical breakers to ensure proper in-service or standby configurations as described in plant procedures and drawings. During the walkdowns, the inspectors
evaluated the material condition and general housekeeping of the systems and adjacent spaces. The documents reviewed are listed in the Attachment. The inspectors performed walkdowns of the following areas: *
- EDG D14 return to standby lineup following monthly slow start test; * Unit 1 High Pressure Coolant Injection (
HPCI) system when Reactor Core Isolation Cooling System (RCIC) system was inoperable for planned maintenance; and * Unit 2 'B' Loop of Residual Heat Removal (RHR) while in shutdown cooling. b. Findings
No findings of significance were identified. 1R05 Fire Protection (71111.05Q - 5 samples) Fire Protection - Tours a. Inspection Scope The inspectors conducted a tour of the five areas listed below to assess the material condition and operational status of fire protection features. The inspectors verified that combustible materials and ignition sources were controlled in accordance with Exelon's administrative procedures. Fire detection and suppression equipment was verified to be
available for use, and passive fire barriers were verified to be maintained in good material condition. The inspectors also verified that station personnel implemented compensatory measures for out of service (OOS), degraded, or inoperable fire protection equipment in accordance with the station's fire plan. The documents reviewed are listed in the Attachment. The inspectors toured the following areas: *
- EDG D14 Room, Fire Area 82; * Unit 2 Safeguard System Access Area Room 370, Elevation 217', Fire Area 67; * Unit 1
HPCI Pump Room,109, Elevation 177', Fire Area 34; * Unit 2 Drywell, Fire Area 53; and * Unit 2 Main Steam and Feedwater Pipe Tunnel, Fire Area 69.
Enclosure 1R07 Heat Sink Performance (71111.07 - 1 sample)
a. Inspection Scope The inspectors reviewed the results of Exelon's thermal performance testing on the Unit 2 'B'
- RHR Heat Exchanger to assess the capability of the heat exchanger to function as designed. The inspectors reviewed the
UFSAR, supporting design
calculations, thermal performance calculations, and historical trend information to ensure the heat exchanger was capable of removing the required heat load during accident conditions. The inspectors verified that issues identified during the performance test were entered into the licensee's
- CAP [[for evaluation. Documents reviewed are listed in the Attachment. b. Findings No findings of significance were identified. 1R11 Licensed Operator Requalification Program (71111.11 - 1 sample) Resident Inspector Quarterly Review a. Inspection Scope On February 3, 2009, the inspectors observed licensed operator simulator requalification training on the 'E' operating crew. Simulator Training Scenario]]
LSTS-2053 tested the
operators' ability to respond to failures of secondary plant equipment as well as a steam leak in the drywell with equipment OOS and emergency core cooling system failures. In addition, the inspectors observed refueling operations training on an operations staff crew on February 5, 2009. The training involved various refueling mode potential failures including lowering level in the reactor vessel cavity and spent fuel pool and a
dropped fuel bundle. The inspectors observed licensed operator performance including operator critical tasks, which are required to ensure the safe operation of the reactor and protection of the nuclear fuel and primary containment barriers. The inspectors also assessed crew dynamics and supervisory oversight to verify the ability of operators to properly identify and implement appropriate TS actions, regulatory reports, and
notifications. The inspectors observed training instructor critiques and assessed whether appropriate feedback was provided to the licensed operators. b. Findings No findings of significance were identified. 1R12 Maintenance Effectiveness (71111.12 - 1 sample) a. Inspection Scope The inspectors evaluated Exelon's work practices and follow-up corrective actions for issues identified in Issue Report (IR) 721408 which described an
- EDG D23 undervoltage condition experienced during surveillance testing, to assess the effectiveness of Exelon's maintenance activities. The inspectors reviewed the performance history of
EDG D23 and assessed Exelon's extent-of-condition determination for potential common
cause or generic implications to evaluate the adequacy of the station's corrective actions. The inspectors assessed Exelon's problem identification and resolution actions
Enclosure for these issues to evaluate whether Exelon had appropriately monitored, evaluated, and dispositioned the issue in accordance with Exelon procedures and the requirements of
- CFR 50.65, "Requirements for Monitoring the Effectiveness of Maintenance." In addition, the inspectors reviewed
EDG classifications, performance criteria and goals, and Exelon's corrective actions that were taken or planned, to evaluate whether the actions were reasonable and appropriate. a. Findings No findings of significance were identified. 1R13 Maintenance Risk Assessments and Emergent Work Control (71111.13 - 5 samples) a. Inspection Scope The inspectors evaluated the effectiveness of Exelon's maintenance risk assessments required by 10 CFR 50.65(a)(4). This inspection included discussion with control room operators and risk analysis personnel regarding the use of Exelon's on-line risk monitoring software. The inspectors reviewed equipment tracking documentation, daily
work schedules, and performed plant tours to gain assurance that the actual plant configuration matched the assessed configuration. Additionally, the inspectors verified that Exelon's risk management actions, for both planned and emergent work, were consistent with those described in Exelon procedure,
AA-600-1042, "On-Line Risk Management." The documents reviewed are listed in the Attachment. Inspectors
reviewed the following samples: *
- EDG D24 indicated speed oscillations; * Replace Unit 1 recirculation motor generator set generator brushes (production risk activity) while one offsite power source was unavailable; *
- IR 891128, Unable to reset one-half scram on Unit 2 due to failure of reactor protection system relay C71A-K14H; and *
ELS-XX-219 inadvertently shut off resulting in 'B' recirculation pump speed reduction.
b. Findings No findings of significance were identified. 1R15 Operability Evaluations (71111.15 - 6 samples) a. Inspection Scope The inspectors assessed the technical adequacy of a sample of six operability evaluations to ensure that Exelon properly justified TS operability and verified that the
subject component or system remained available such that no unrecognized increase in risk occurred. The inspectors reviewed the
- UFS [[]]
AR to verify that the system or component remained available to perform its intended safety function. In addition, the inspectors reviewed compensatory measures implemented to ensure that the measures worked and were adequately controlled. The inspectors also reviewed a sample of issue reports to verify that Exelon identified and corrected deficiencies associated with
Enclosure operability evaluations. The documents reviewed are listed in the Attachment. The inspectors performed the following evaluations: *
- IR 874596, Drywell mixing fan 2B2-V212 failed to start in automatic when drywell mixing fan 2B1-V212 failed; *
- IR 885367, Unit 1 'A' reactor enclosure recirculation fan tripped during post maintenance test run; and *
TS minimum. b. Findings No findings of significance were identified. 1R18 Plant Modifications (71111.18 - 1 sample)
.1 Temporary Modifications a. Inspection Scope The inspectors reviewed the temporary plant modification to provide an alternate method
of monitoring for a reactor cavity well seal leak during the Unit 2 2R10 refueling outage. The alternate method was necessary due to degraded operation of the normal method which is via a flow detector monitoring leakby to the radioactive waste system. The inspectors reviewed the associated Safety Evaluation
UFSAR described function. The
inspectors ensured that station personnel implemented the modification in accordance with the temporary configuration change process. The inspectors verified that modification preparation, staging, and implementation did not impair emergency/ abnormal operating procedure actions and key safety functions. Post-installation testing was reviewed to confirm that the modification could fulfill the intended function. The inspectors confirmed that supplemental checks for leakby using the alternate method were performed, as indicated in operator logs, when reactor cavity flood-up operations
were ongoing during the Unit 2 2R10 refueling outage. Documents reviewed are listed in the Attachment. b. Findings
No findings of significance were identified. .2 Permanent Modifications (Closed) URI 05000352,05000353/2008005-01, Changes to Technical Specification 3.8.1 Bases a. Inspection Scope
Enclosure In inspection report 2008005, dated January 30, 2009, the inspectors opened a
TS 3.8.1. The inspectors identified
that the changes made by Exelon appeared to be in conflict with the requirements of
- TS [[]]
- TS [[]]
NRC approval. On February 24, 2009, Exelon provided additional
information to the
- NRC. The information was reviewed by the resident inspectors as well as several technical experts in
- NRC determined that the information did not provide any new information that would cause the agency to change its position. Therefore, the
- IV [[]]
- TS surveillance requirements to be misinterpreted. As a result, Limerick failed to enter the appropriate
TS Action Statement
on numerous occasions between 2000 and 2008 for an Emergency AC power source being inoperable. Description: On September 30, 2008, operators racked out one of the two offsite power supply feeder breakers to 4kV Emergency Bus D11 (201-D11) for maintenance. The
inspectors noted that although one of the two offsite power sources was not available to Emergency Bus D11, operators did not declare the associated offsite power circuit inoperable and enter into the associated 72-hour action statement per
- TS [[]]
- LCO 3.8.1.1, "AC Sources - Operating." The inspectors noted that one of the associated surveillance requirements,
- TS [[]]
SR 4.8.1.1.1.b, could not be met with one of the two offsite power
source breakers racked out. The
- SR states "Each of the above required independent circuits between the offsite transmission network and the onsite Class 1E distribution system shall be demonstrated
OPERABLE in accordance with the Surveillance Frequency Control Program by transferring, manually and automatically, unit power supply from the normal circuit to the alternate circuit." With an offsite power supply
feeder breaker racked out, manual and automatic transfer between the normal and alternate circuit was not possible. The inspectors further noted that Limerick
- TS [[]]
SR 4.0.1 states, in part, that, "Failure to meet a surveillance, whether such failure is experienced during the performance of a
Surveillance or between performances of the Surveillance, shall be failure to meet the Limiting Condition for Operation." The inspectors determined that because Limerick could not meet the requirements of
- SR 4.8.1.1.b with one of the offsite breakers racked out, they should have declared the offsite power source inoperable and entered
- TS [[]]
TS Bases 3/4.8.1, and found that the bases described
that an offsite circuit was to be considered inoperable if it was not capable of supplying at least three Unit 1 4kV emergency buses. Recognizing that the
SR, the inspectors questioned the history of the bases. Exelon informed the inspectors that the bases were modified in 2000 to define an operable offsite source as one capable of supplying power to three of the four
emergency buses in the unit, through Engineering Change Request (ECR)
- LGS [[]]
- LGS [[]]
TS bases change concluded that the change was
considered an enhancement, and therefore a formal
- TS [[]]
TS was contrary to 10 CFR 50.59
(c)(1)(i) which states that "a licensee may make changes in the facility as described in the final safety analysis report-without obtaining a license amendment pursuant to [paragraph] 50.90 only if a change to the technical specifications incorporated in the license is not required." Exelon entered this issue into the
IR 825317. Night orders were issued to operators, which required declaring an offsite power supply
inoperable when an offsite power supply feeder breaker became unavailable to an emergency bus. Analysis: The performance deficiency associated with this finding is that the change to
- TS incorporated in the license, because it caused the bases to be in direct conflict with the requirements of
- TS [[]]
- CFR [[50.59, it was considered to be a violation which potentially impedes or impacts the regulatory process. Therefore, such violations are characterized using traditional enforcement process. In this case, the licensee failed to perform an adequate safety evaluation in accordance with 10]]
CFR 50.59 because the approved change to the technical specification basis was in conflict with the TS surveillance requirements. Thus,
the
- TS surveillance requirement to demonstrate operability. This change required prior approval from the
- NRC approval would have been required. The inspectors completed a Significance Determination Review using
NRC IMC 0609, Attachment 4, Phase 1 - Initial Screening and Characterization of Findings. Using the Phase I Screening worksheet for the Mitigating System Cornerstone, the finding was determined to be of very low safety significance (Green) since the finding did not
represent an actual loss of safety function for greater than the
- CFR 50.59 that result in conditions evaluated as having very low safety significance (i.e., green) by the
- TS Bases change was made in 2000, the inspectors determined that this finding was not reflective of current licensee performance and, therefore, did not have a cross-cutting aspect. Enforcement: 10
CFR 50.59 (c)(1)(i) requires, in part, that a licensee may make changes in the facility as described in the final safety analysis report without obtaining a
license amendment pursuant to
- TS incorporated in the license is not required. Contrary to the above, on December 6, 2000, Exelon made a change to
- TS [[]]
TS license amendment as required.
Enclosure This violation was of very low safety significance and did not represent a condition where the licensee failed to restore compliance within a reasonable time; was not repetitive; did
not appear to have any willful aspects; and was entered into the licensee's
VI.A.1 of the Enforcement Policy. (NCV 05000352, 353/2009002-02, Failure to Obtain License Amendment for TS Bases Change) 1R19 Post-Maintenance Testing (71111.19 - 6 samples) a. Inspection Scope The inspectors reviewed six post-maintenance tests to verify that procedures and test
activities ensured system operability and functional capability. The inspectors reviewed Exelon's test procedures to verify that the procedures adequately tested the safety functions that may have been affected by the maintenance activity, and that the acceptance criteria in the procedures were consistent with information in the licensing and design basis documents. The inspectors also witnessed the test or reviewed test data to verify that the results adequately demonstrated restoration of the affected safety functions. The inspectors performed the following samples:
FD-C-076-192-A-OP; * C0227323, Investigate oscillating speed indication on EDG D24; * C0226265, Volatile chemical evaluation of reactor enclosure recirculation and standby gas treatment charcoal trains following painting of Unit 2 reactor building 253' elevation; and * C0227874 Replace reactor protection system relay; C71A-K14H. b. Findings No findings of significance were identified. 1R20 Refueling and Other Outage Activities (71111.20 - 1 partial sample) a. Inspection Scope The inspectors reviewed the station's work schedule and outage risk plan for the
Limerick Unit 2 maintenance and refueling outage (2R10), which commenced on March 23, 2009. The inspectors reviewed Exelon's development and implementation of outage plans and schedules to verify that risk, industry experience, previous site-specific problems, and defense-in-depth were considered. At the end of the inspection period,
Unit 2 was in Operational Condition (OPCON) 5, Refueling with the reactor cavity flooded. This sample will be completed in the second quarter after the unit returns to
- OPC [[]]
ON 1. Documents reviewed are listed in the Attachment. During the outage, the inspectors observed portions of the shutdown and cooldown processes and monitored Exelon controls associated with the following outage activities:
Enclosure * Configuration management, including maintenance of defense-in-depth, commensurate with the outage plan for the key safety functions and compliance with the applicable
- TS [[when taking equipment out of service; * Post shutdown primary containment walkdown to identify any abnormal conditions that may have existed during the previous operating cycle; * Implementation of clearance activities and confirmation that tags were properly hung and that equipment was appropriately configured to safely support the associated work or testing; * Installation and configuration of reactor coolant pressure, level, and temperature instruments to provide accurate indication and instrument error accounting; * Status and configuration of electrical systems and switchyard activities to ensure that]]
- TS [[were met; * Monitoring of decay heat removal operations; * Impact of outage work on the ability of the operators to operate the spent fuel pool cooling system; * Reactor water inventory controls, including flow paths, configurations, alternative means for inventory additions, and controls to prevent inventory loss; * Activities that could affect reactivity; * Maintenance of secondary containment as required by]]
- TS [[; * Refueling activities, including fuel handling and fuel receipt inspections; and * Identification and resolution of problems related to refueling outage activities. b. Findings No findings of significance were identified. 1R22 Surveillance Testing (71111.22 - 6 samples) a. Inspection Scope The inspectors either witnessed the performance of, or reviewed test data for, six surveillance tests (]]
STs) associated with risk-significant structure, system, components (SSC). The reviews verified that Exelon personnel followed TS requirements and that
acceptance criteria were appropriate. The inspectors also verified that the station established proper test conditions, as specified in the procedures, that no equipment preconditioning activities occurred, and that acceptance criteria were met. The inspectors reviewed
- ST -6-107-590, Daily Surveillance Log/OPCONS 1, 2, 3, Revision 147, performed during the week of January 12, 2009; *
LLR-061-2, Local Leak Rate Testing for 'A-D' Main Steam Isolation Valves, Revision 8. b. Findings
Enclosure Introduction: The inspectors identified a Green
CFR50, Appendix B, Criterion III, "Design Control," for the failure to translate minimum room temperatures assumed in
an isolation actuation instrumentation setpoint calculation into Unit 1 and 2 procedures such that such that reactor building room temperatures were maintained above the minimum assumed. As a result, in December 2008, temperatures in several reactor building rooms fell below the minimum design basis temperature. Description: On December 26, 2008,
CRD) accumulator nitrogen pressures. The pressures were low due to low ambient reactor building temperatures in Units 1 and 2. The inspector reviewed the issue and determined that there were no operability issues with the low out-of-specification accumulator pressures. This was because pressures
were being maintained greater than 1000 psig, which was above
- SR ) minimum pressure of 955 psig, and there was a low pressure alarm set at 970 psig to alert operators prior to exceeding the
IR 860165, Exelon began maintaining reactor building temperatures at higher values. The inspectors reviewed the history of reactor building temperatures. The inspectors
noted that
- ST [[-6-107-590-1 and -2, Daily Surveillances Log/OpCons 1, 2, and 3, recorded lower than normal temperatures in several rooms in Units 1 and 2 during the December 2008 time frame. The inspectors noted that the lowest temperature recorded in Unit 1 was 44ûF in the Reactor Water Cleanup (]]
- 2 RW [[]]
CU Pump Room 'B' on December 12, 2008. Prior to the onset of seasonably cold weather in 2008, Limerick Operations personnel performed an informal review to determine if any operating restrictions would preclude lower reactor building temperatures. Having found no procedural restrictions, informal
guidance for operating the reactor enclosure and refueling area ventilation system was conveyed to operators, which resulted in operating the Units 1 and 2 at lower than normal temperatures. Operations did not consult with engineering or other support organizations prior to changing the operating guidance for this system. The inspectors noted that ST-6-107-590-1 and -2 did not specify a minimum allowed temperature; only
a normal band was given. The inspectors discovered that the
- UFSAR Section 9.4.2 describes the Reactor Enclosure and Refueling Area Ventilation System as being designed to maintain space temperatures so that the minimum temperature is not below 65ûF. The inspectors identified that Calculation
- MISC -22, "Leak Detection System Setpoint Bases," Revision 6, specified 65ûF as the assumed minimum initial temperature in reactor building rooms.
TS LCO 3.3.2, "Isolation Actuation System." The inspectors noted that initial room temperatures less than 65ûF would have a non-conservative effect on isolation system operation due to room high temperature. This is because room heatup to the specified high temperature instrument setpoint would take longer for any given size pipe break in
the room. This issue was within Exelon's ability to foresee and prevent, because the temperatures in those room were significantly below the normal bands and there were several opportunities to identify this abnormal condition and question if system operability was
affected by this abnormal condition.
Enclosure Analysis: The performance deficiency associated with this issue is that both the ST-6-107-590-1 and -2, Daily Surveillances Log/OpCons 1, 2, and 3 and the reactor enclosure and refueling area ventilation system operating procedures did not contain minimum temperature limits to ensure design basis limits were maintained. As a result, in December 2008, the reactor enclosure and refueling area ventilation systems were not operated to assure that room temperatures were maintained above the minimum
assumed in design basis calculations. This resulted in rooms associated with the Unit 1 and Unit
MISC-22, "Leak Detection System Setpoint Bases." This finding was more than minor because it was associated with the Design Control attribute of the Barrier Integrity cornerstone, and affected the Barrier Integrity cornerstone objective to
provide reasonable assurance that physical design barriers, including containment, protect the public from radionuclide releases caused by accidents or event. In accordance with
- NRC [[]]
IMC 0609, Attachment 4, Phase 1 - Initial Screening and Characterization of Findings, the inspectors determined the finding to be of very low safety significance (Green) because it did not represent an actual open pathway in the physical integrity of reactor containment, containment isolation system, and heat removal components. This finding has a cross-cutting aspect in Human Performance, Decision Making, because the licensee did not make a safety significant decision using a systematic process to ensure safety was maintained. Specifically, the decision to operate the reactor buildings at lower temperatures was made using an informal process within
operation, therefore, interdisciplinary input and a review by engineering and other support organizations was not obtained. H.1(a) Enforcement:
III, "Design Control," requires that measures shall be established to assure that applicable regulatory requirements and the
design basis - those structures, systems, and components to which this appendix applies are correctly translated into specifications, drawings, procedures, and instructions. Contrary to the above, minimum room temperatures assumed in Calculation
- MI [[]]
SC-22 for isolation actuation instrumentation setpoints were not translated into procedures such that Units 1 and 2 reactor building room temperatures were
maintained above the minimum assumed in design basis calculations. As a result,
- RWCU System rooms in Units 1 and 2 were operated below the minimum temperature assumed in Calculation
- MISC -22 for Technical Specification isolation activation systems during several periods in December 2008. Because this issue is of very low safety significance and has been entered into the
- ANS ) Evaluation (71114.02 - 1 sample) a. Inspection Scope An onsite review was conducted to assess the maintenance and testing of the Limerick
- ANS. During this inspection, the inspectors interviewed the Exelon Facility and Equipment Coordinator, who is responsible for implementation of
ANS testing and maintenance. The inspector discussed with the Coordinator the performance of the
ANS issues. The inspector reviewed the
- ANS Enclosure procedures and the ANS design report to ensure Exelon's compliance with those commitments for system maintenance and testing. The inspector observed a complete
- ANS siren test. Additionally, the inspector reviewed changes to the design report and how the licensee incorporated the changes into the
CFR 50, Appendix E, were used as reference criteria. Documents reviewed are listed in the
Attachment. b. Findings No findings of significance were identified.
ERO) Staffing and Augmentation System (71114.03 - 1 sample) a. Inspection Scope The inspector conducted a review of Limerick's ERO augmentation staffing requirements
and the process for notifying and augmenting the
- ERO. This was performed to ensure the readiness of key staff to respond to an event and to ensure timely emergency response facility activation. The inspector reviewed procedures and
- ERO notification system and drills, and reviewed records from call-in drills. The inspector interviewed personnel responsible for testing the
ERO augmentation process,
and reviewed the training records for the
- ERO to ensure training and qualifications were current. The inspector further verified a sampling of
- ERO participation in exercises and drills in 2008 and 2009. The inspection was conducted in accordance with
- NRC [[]]
CFR 50, Appendix E, were used as reference criteria. Documents
reviewed are listed in the Attachment. b. Findings No findings of significance were identified.
- EAL ) and Emergency Plan Changes (71114.04 - 1 sample) a. Inspection Scope Prior to this inspection, the
- NRC had received and acknowledged changes made to the Limerick Emergency Plan and its implementing procedures. Exelon developed these changes in accordance with 10
- CFR 50.54(q), and determined that the changes did not result in a decrease in effectiveness of the Plan. The licensee also determined that the Plan continued to meet the requirements of
- EAL s, and for a sample of the changes made to the Plan, from August 2008 through March 2009, that could have potentially resulted in a decrease in effectiveness. This review of the
NRC approval of the changes and, as such, the changes remain subject to future NRC inspection. The inspection was conducted in accordance
with
- NRC [[]]
IP 71114, Attachment 4. The requirements in 10 CFR 50.54(q) were used as reference criteria. Documents reviewed are listed in the Attachment.
Enclosure b. Findings No findings of significance were identified.
EP) Weaknesses (71114.05 - 1 sample)
a. Inspection Scope The inspector reviewed a sampling of self-assessment procedures and reports to assess Exelon's ability to evaluate their
- EP [[]]
IRs, from January 2008 through March 2009,
initiated by Exelon at Limerick from drills, self-assessments, and audits. Additionally, the inspector reviewed Limerick's Quality Assurance audits and reports, and the 2007 and 2008
- NRC [[]]
- 10 CFR 50 Appendix E were used as reference criteria. Documents reviewed are listed in the Attachment. b. Findings No findings of significance were identified. 2.
- SAFE [[]]
TY
2OS1 Access Control to Radiologically Significant Areas (71121.01 - 10 samples) a. Inspection Scope During the period January 12 - 16, 2009, the inspector conducted the following activities to verify that the licensee was properly implementing physical, administrative, and engineering controls for access to locked high radiation areas and other radiologically controlled areas, and that workers were adhering to these controls when working in these areas. Implementation of these controls was reviewed against the criteria
contained in 10 CFR 20, Technical Specifications, and the licensee=s procedures. This inspection activity represents completion of ten samples relative to this inspection area. The documents reviewed are listed in the Attachment.
Plant Walkdown and
- RWP Reviews * The inspector identified exposure significant work areas in the Unit 1 and Unit 2 reactor buildings, refuel floor, and waste processing building. Specific work activities included Unit 1 hydraulic control unit (
HCU) maintenance, Unit 2 scaffolding erection, reactor cavity work platform (RCWP) maintenance, and waste sludge tank inspection. The inspector reviewed radiation survey maps and radiation work
permits (RWP) associated with these areas to determine if the associated controls were acceptable.
LG-0-09-00003 (Open/Inspect Waste Sludge Tank). * The inspector toured the accessible radiological controlled areas in both units, including the reactor buildings, waste processing building, and refuel floor, and with
Enclosure the assistance of a radiation protection technician performed independent surveys of selected areas to confirm the accuracy of survey data and the adequacy of postings. * In evaluating the
- RWP [[s, the inspector reviewed electronic dosimeter dose/dose rate alarm set points to determine if the set points were consistent with the survey indications and plant policy. The inspector verified that the workers were knowledgeable of the actions to be taken when the dosimeter alarms, or malfunctions, for tasks being performed under selected]]
RWPs. * The inspector reviewed RWPs and associated instrumentation and engineering controls for potential airborne radioactivity areas located in the reactor buildings, waste processing building, and fuel floor. The inspector reviewed dose assessment records related to evaluating airborne radioactivity concentrations and personnel
contaminations and confirmed that no worker received an internal dose, in excess of 50 mrem, when performing radiological significant tasks. The inspector reviewed the dose assessment methodology for an internal exposure that was less than 50 mrem to confirm the accuracy of the results. Problem Identification and Resolution * A review of Nuclear Oversight objective evidence reports, Common Cause Analyses, and an Apparent Cause Evaluation, was performed to determine if identified problems and negative performance trends were entered into the corrective action program and evaluated for resolution. * Relevant IRs, associated with radiation protection control access, initiated between January 2008 through January 2009 were reviewed and discussed with the licensee staff to determine if the follow-up activities were being conducted in an effective and
timely manner, commensurate with their safety significance. High Radiation Area and Very High Radiation Area Controls * Procedures for controlling access to High Radiation Areas (HRA) and Very High Radiation Areas (VHRA) were reviewed to determine if the administrative and physical controls were adequate. The inspector also reviewed the physical and procedural controls for securing and removing highly contaminated/activated materials stored in the spent fuel pool. The inspector discussed with radiation
protection management, the adequacy of current locked high radiation areas (LHRA)/VHRA controls, including prerequisite communications and authorizations, and verified that any changes made to relevant procedures did not substantially reduce the effectiveness and level of worker protection. Keys to
- LH [[]]
RAs were verified to be properly secured and
posted during plant tours in both units. Radiation Worker Performance and Radiation Protection Technician Performance * The inspector observed and questioned radiation workers and radiation protection technicians regarding radiological controls applied to various tasks, including waste sludge tank inspections,
HCU maintenance, and Unit 2
scaffolding erection. The inspector performed these activities to determine whether the workers were aware of current RWP requirements, radiological conditions, access controls, and that the skill level was appropriate with respect to the potential radiological hazards and the work involved.
Enclosure * The inspector reviewed
- IR s, related to radiation worker and radiation protection technician errors, and personnel contamination event reports to determine if an observable pattern traceable to a similar cause was evident. b. Findings No findings of significance were identified. 2
- ALA [[]]
RA Planning and Controls (71121.02 - 7 samples)
a. Inspection Scope During the period January 12 - 16, 2009, the inspector conducted the following activities to verify that the licensee was properly implementing operational, engineering, and administrative controls to maintain personnel exposure as low as is reasonably
achievable (ALARA) for tasks performed during 2008 and in making preparations for the Unit 2 refueling outage (2R10). Implementation of these controls was reviewed against the criteria contained in 10 CFR 20, applicable industry standards, and the licensee=s procedures. The documents reviewed are listed in the Attachment. This inspection represents completion of seven samples relative to this inspection area. Radiological Work Planning * The inspector reviewed pertinent information regarding the 2008 1R12 outage exposure history, current exposure trends, and ongoing activities to assess current performance and 2R10 outage exposure challenges. A review of 2008 outage
performance was conducted to compare actual exposures with forecasted estimates to determine if differences were properly addressed in Work-In-Progress and Post-Job
- ALARA Council. * The inspector reviewed the 2R10 outage work scheduled during the upcoming spring refueling outage period and the associated work activity dose estimates and
- ALA [[]]
RA Plans. Scheduled work includes the in-service inspection of the Unit 2 reactor pressure vessel nozzles and the associated hydrolazing and installation of temporary
shielding. Additional projects included suppression pool inspections, core shroud weld examinations, and jet pump repairs. * The inspector evaluated the departmental interfaces between radiation protection, operations, maintenance crafts, and engineering to identify missing
- ALARA program elements and interface problems. The evaluation was accomplished by attending a pre-job briefing for opening and inspecting a waste sludge tank; reviewing recent Station
- ALA [[]]
RA reviews,
Nuclear Oversight Objective Evidence Reports; and interviewing the site Radiation Protection Manager. Verification of Dose Estimates * The inspector reviewed the assumptions and basis for the annual (2009) site collective exposure projections for the 2R10 outage and for routine power operations. * The inspector reviewed the licensee=s procedures associated with monitoring and re-evaluating dose estimates when the forecasted cumulative exposure for tasks differed from the actual exposure received. The inspector reviewed the dose/dose
Enclosure rate alarm reports, work-in-progress evaluations, and exposure data for selected individuals receiving the highest Total Effective Dose Equivalent (TEDE) for 2008 to
confirm that no individual exposure exceeded the regulatory limit, or met the performance indicator reporting guideline. Jobs-In-Progress * The inspector observed various jobs-in-progress to evaluate the effectiveness of dose control measures. Jobs observed included a waste sludge tank inspection, scaffolding installation,
- HCU maintenance, and reactor cavity work platform maintenance. As part of this evaluation, the inspector reviewed the
RWP, survey maps, and contamination control measures. The inspector attended the pre-job briefing for the waste sludge tank inspection. The inspector also determined that workers were properly wearing dosimetry and were knowledgeable of
- RWP requirements. Problem Identification and Resolution * The inspector reviewed elements of the licensee=s corrective action program related to implementing
- ALARA program controls, including Issue Reports, Nuclear Oversight Objective Evidence reports, dose/dose rate alarm reports, and Station
ALARA Committee meeting minutes to determine if problems were being entered at a conservative threshold and resolved in a timely manner. b. Findings No findings of significance were identified. 2OS3 Radiation Monitoring Instrumentation and Protective Equipment (71121.03 - 2 samples)
a. Inspection Scope During the period January 12 - 16, 2009, the inspector conducted the following activities to evaluate the operability and accuracy of radiation monitoring instrumentation that was used for the protection of workers. The criteria contained in 10 CFR 20, applicable
industry standards, and the licensee=s procedures were used to evaluate the adequacy of these instruments. The documents reviewed are listed in the Attachment. The calibration procedures, related records, and quality control checks for the Canberra
FastScan and AccuScan whole body counting systems were reviewed. The inspector reviewed the training materials for recently purchased hand held portable survey instruments including the Eberline
- RAM [[]]
PS3 Radiological Environmental Monitoring Program and Radioactive Material Control Program (71122.03 - 10 samples)
Enclosure a. Inspection Scope During the period March 9 - 17, 2009, the inspector conducted the following activities to verify that the licensee implemented the radiological environmental monitoring program (REMP) consistent with the Site Technical Specifications and the Off-Site Dose Calculation Manual (ODCM) to validate that radioactive effluent releases met the design objectives of Appendix I to
- 10 CFR [[50. Additionally, the inspector verified that radiological surveys and controls were adequate to prevent the inadvertent release of radioactive material into the public domain. Implementation of these controls was reviewed against the criteria contained in 10]]
- CFR 20 & 50, relevant Technical Specifications, and the licensee=s procedures. This inspection activity represents completion of ten samples relative to this inspection area.
- REMP Inspections: * The inspector reviewed the 2007 Annual Radiological Environmental Operating Report and the 2008 Land Use Census Report to verify that the environmental monitoring programs were implemented as required by the
- ODCM [[(Revision 24). * The inspector walked down six (6) air particulate/iodine sampling stations (Nos. 10S3, 11S1, 11S2, 13C1, 14S1, 22G1), five (of 5) cow=s milk sampling stations (Nos.10F4, 18E1, 19B1, 23F1, 25C1), four (of 4) drinking water stations (Nos. 15F4, 15F7, 16C2, 28F3 ), two (of 2) surface water sampling stations (24S1, 13B1), and seven (of 40) thermoluminescent (TLD) monitoring stations (10S3, 11S1, 13C1, 14S1, 21S2, 19D1, 34S2). The inspector determined if sampling locations were as described in the]]
- OD [[]]
CM, and evaluated the sampling equipment material condition. * As part of the walk down, the inspector observed the technician collect and prepare for analysis cow=s milk samples, demonstrate water and air sample collection techniques, and verified that sampling techniques were performed in accordance
with procedures. * Based on direct observation and review of records, the inspector verified that the meteorological instrumentation was operable, calibrated, and maintained in accordance with the guidance contained in the
NRC Safety Guide 23, and the
licensee/vendor procedures. The inspector verified that the meteorological data readout and recording instruments in the control room and at the primary and backup towers were operable for wind direction, wind speed, temperature, and delta temperature. The inspector observed calibration of the instrumentation on the primary tower and on the backup tower, on March 17 and 18, 2009, respectively.
The inspector confirmed that redundant instrumentation was operable and that the annualized recovery rate for meteorological data was greater that 90%. * During walkdowns, the inspector had technicians demonstrate the air and water sampling equipment was properly operating. The inspector reviewed maintenance records and operating parameter trending records for air samplers and water compositors. * The inspector reviewed Issue Reports, Nuclear Oversight Audit/Assessment Reports, management evaluations of sample collection,
ODCM requirements, to
evaluate the threshold for which issues are entered into the corrective action
Enclosure program, the adequacy of subsequent evaluations, and the effectiveness of the resolution * The inspector reviewed the results of the licensee=s quarterly laboratory cross-check program to verify the accuracy of the licensee=s environmental air filter, charcoal cartridge, water, biota, and milk sample analyses. * The inspector reviewed any significant changes made by the licensee to the
- ODCM [[as a result of changes to the land use census or sampler station modifications since the last inspection. The inspector also reviewed technical justifications for any change in sampling location (or frequency) and verified the licensee performed the reviews required to ensure that the changes did not affect its ability to monitor the radiological condition of the environment. Unrestricted Release of Material from the Radiologically Controlled Area (]]
- RCA ) * The inspector reviewed the contamination control procedures and guidance provided to personnel for monitoring potentially contaminated material leaving the
- RCA [[for unrestricted use. During the inspection, the inspector determined that contamination monitoring was performed at appropriate locations within the facility to preclude release of material into the public domain. * The inspector verified that the radiation monitoring instrumentation (]]
- SAM [[-11, Frisker) was appropriate for the radiation types potentially present and was calibrated with appropriate radiation sources. The inspector reviewed the licensee=s criteria for the survey and release of potentially contaminated material; verified that there was guidance on how to respond to an alarm which indicates the presence of contamination; and reviewed instrument alarm set points to ensure that radiation detection sensitivities are consistent with the]]
- HPP [[]]
OS-221 for volumetrically contaminated material. The inspector also reviewed the licensee=s procedures and records to verify that the radiation detection instrumentation was used at its typical sensitivity level based on appropriate counting parameters, and verified that the licensee has not established a release limit by altering the instruments sensitivity through such methods as raising the energy discrimination level or locating the instrument in a high radiation background area. With the assistance of a technician, the inspector verified that in-use monitors appropriately
responded to a radioactive source check. b. Findings No findings of significance were identified. 4.
- OTHER [[]]
PI) Verification (71151 - 9 samples)
.1 Initiating Event and Mitigating Systems Cornerstone PIs a. Inspection Scope The inspectors sampled Exelon's submittal of the Mitigating Systems and Barrier
Integrity cornerstone PIs listed below to verify the accuracy of the data recorded from January 2008 though December 2008, except as noted below. The inspectors utilized
Enclosure performance indicator definitions and guidance contained in Nuclear Energy Institute (NEI) 99-02, "Regulatory Assessment Performance Indicator Guidelines," Revision 5, to
verify the basis in reporting for each data element. The inspectors reviewed various documents, including portions of the main control room logs, issue reports, power history curves, work orders, and system derivation reports. The inspectors also discussed the method for compiling and reporting performance indicators with cognizant engineering personnel and compared graphical representations from the most recent PI report to the
raw data to verify that the report correctly reflected the data. The documents reviewed are listed in the Attachment. Cornerstone: Initiating Events (2 samples) * Units 1 and 2 Unplanned Power Changed per 7000 critical hours (IE03) Cornerstone: Mitigating Systems (4 samples) * Units 1 and
MS08) (April 2008-December 2008) b. Findings No findings of significance were identified.
.2 Emergency Preparedness Performance Indicator Verification a. Inspection Scope The inspector reviewed the Limerick
- PI data, its supporting documentation, and the information Exelon reported from the third and fourth quarters of 2008, to verify the accuracy of the reported data. The review of these
PIs was conducted in accordance
with
- NRC [[]]
- NEI 99-02, Revision 5, "Regulatory Assessment Performance Indicator Guidelines." The documents reviewed are listed in the Attachment. Cornerstone: Emergency Preparedness (3 samples) * Common Drill and Exercise Performance (EP01) * Common
EP03) b. Findings No findings of significance were identified. 4OA2 Identification and Resolution of Problems (71152 - 2 annual samples)
.1 Review of Items Entered into the Corrective Action Program a. Inspection Scope
Enclosure As required by IP 71152, "Identification and Resolution of Problems," and in order to help identify repetitive equipment failures or specific human performance issues for
follow-up, the inspectors screened all items entered into Limerick's corrective action program. The inspectors accomplished this by reviewing each new condition report, attending management review committee meetings, and accessing Exelon's computerized database. Documents reviewed are listed in the Attachment.
b. Findings and Observations No findings of significance were identified. .2 Annual Sample: Review of
- RCIC Pump Suction Alignment Issue and Areas for Improvement for Limerick Generating Station's Fire Protection Program a. Inspection Scope The inspectors selected
PI&R) samples for a detailed follow-up review. IR 843591 documented on November 11, 2008, an engineer participating in senior reactor operator certification
training in the simulator observed that the remote shutdown procedure,
- SE -1, "Remote Shutdown," did not agree with the supporting design calculations for the fire safe shutdown method being implemented by the procedure. The calculations assumed that the
- RC [[]]
IC pump suction is aligned to the condensate storage tank
(CST) during normal operation. The remote shutdown procedure did not contain the steps necessary to align the
IR 859194 identified areas of improvement in Limerick Generating Station's fire protection program. Focus areas included fire safe-shutdown procedures and guidelines, control transient combustibles, and fire protection backlog issues.
The inspectors assessed Exelon's problem identification threshold, cause analyses, extent-of-condition reviews, operability determinations, and the prioritization and timeliness of corrective actions to determine whether Exelon was appropriately identifying, characterizing, and correcting problems associated with these issues and
whether the planned or completed corrective actions were appropriate to prevent recurrence. Additionally, the inspectors interviewed cognizant plant personnel regarding the identified issues. The documents reviewed are listed in the Attachment. b. Findings and Observations No findings of significance were identified. The inspectors determined that Exelon properly implemented their corrective action process regarding the initial discovery of the above issues. The IR packages were complete and included cause evaluations, operability determinations, extent-of-condition reviews, corrective actions, and planned corrective actions. Additionally, the elements of
the
- IR [[packages were detailed and thorough. Corrective actions were timely and appeared appropriate to prevent recurrence of the above issues. Corrective actions addressed immediate procedure concerns. The inspectors determined that corrective actions included revising]]
SE-1, "Remote
Shutdown," to add the appropriate steps to align the
- RC [[]]
IC pump suction to the
Enclosure suppression pool as analyzed in the fire safe shutdown analysis. However, the licensee determined that additional extent of condition reviews were necessary to ensure all fire
areas that credit
- RCIC alignment to the suppression pool were captured. Additionally, the licensee had to complete an additional revision of
- RCIC pump suction from the suppression pool. This was a correction to a valve identification number that was added to the
- EDG D23 Overvoltage and Subsequent Engineered Safety Feature Actuation a. Inspection Scope The inspectors reviewed Limerick's causal analysis, extent-of-condition, and corrective actions associated with
RHR pump loading. Operators manually tripped the EDG output breaker per procedure which caused actuation of the bus' undervoltage logic. The inspectors evaluated Exelon's actions against the requirements of the corrective action program and applicable regulatory requirements.
The documents reviewed are listed in the Attachment. b. Findings and Observations No findings of significance were identified.
The inspectors assessed that Exelon's final causal analysis and corrective actions were appropriate and reasonable. However, the inspectors observed that there were some delays in completing the final causal analysis and establishing comprehensive corrective actions. This was primarily due to delays in removing the inactivated suspect voltage
regulator rectifier from the D23
- EAG. [[Although the failure occurred in January 2008 the rectifier was not removed and sent to the vendor for failure analysis until June 2008. Because the failure analysis revealed a different failure mechanism than originally suspected, a revision to the licensee event report (]]
LER) describing the event was necessary. Following receipt of the failure analysis from the vendor, comprehensive
corrective actions were promptly determined and implemented to assure that the same failure mechanism did not exist on the site's other
OA3 Event Follow-up (71153 - 6 samples) .1 Plant Event Review a. Inspection Scope For the three plant events listed below, the inspectors reviewed and/or observed plant parameters, reviewed personnel performance, and evaluated performance of mitigating systems. The inspectors communicated the plant events to appropriate regional personnel and compared the event details with criteria contained in IMC 0309, "Reactive Inspection Decision Basis for Reactors," for consideration of potential reactive inspection
activities. The inspectors reviewed Exelon's follow-up actions related to the events to assure that appropriate corrective actions were implemented commensurate with their safety significance. The documents reviewed are listed in the Attachment.
Enclosure * Unit 2 Loss of Motor Control Center D224-R-G and subsequent load drop to 72 percent power on January 31, 2009; * Water discovered leaking from Units 1 and 2 Turbine Building blowout panels found to contain tritium; and * Unit 2 unplanned downpower to 65 percent caused by 'B' recirculation pump speed reduction to minimum on March 19, 2009. b. Findings No findings of significance were identified. .2 (Closed) Licensee Event Report (LER) 05000353/2008-001-01: Valid Actuation of the D23 Emergency Diesel Generator Bus Undervoltage Logic. A valid actuation of the D23
- EDG bus undervoltage minimum actuation logic occurred following manual operator action to mitigate a bus overvoltage condition during
EDG post maintenance testing. The EDG overvoltage condition was caused by an intermittent failure of the #1 rectifier bank in the voltage regulator. The failure was
caused by looseness at a bolted connection and corrosion at the rectifier flyback diode causing a high resistance. The high resistance caused a silicon controlled rectifier to fail to return to the "off" state which caused an overvoltage condition of the
- LER 05000352/2008-003: High Pressure Coolant Injection System Instrument Power Supply Failure. On November 2, 2008, the Unit 1
HPCI system was rendered inoperable due to observed oscillations in the system flow indication. The condition was corrected by recalibration of a flow transmitter, replacement of a square root converter, and
replacement of a degraded inverter in the
- HP [[]]
CI turbine control system. A failure analysis determined the most probable cause of the inverter component failure to be age-related degradation. Corrective actions included replacement of the inverter, increased monitoring of inverter performance, and increased replacement frequency of the inverter model in plant systems. The event was documented in Exelon's corrective
action program as
- LER 05000352, 05000353/2008-004: Remote Shutdown Procedure Error. On November 11, 2008, an engineer participating in senior reactor operator certification training in the simulator observed that the remote shutdown procedure,
- SE -1, "Remote Shutdown," did not agree with the supporting design calculations for the fire safe-shutdown method being implemented by the procedure. The calculations assumed that the
- RC [[]]
IC pump suction would be aligned to the suppression pool during the remote
shutdown event. The
- CST during normal plant operation. The remote shutdown procedure did not contain steps necessary to align the
TS 6.8.1.g, "Procedures and Programs," the licensee did not establish a safe shutdown procedure that was consistent with the fire safe shutdown analysis. The
licensee determined that the condition was caused by a failure to include the required steps in the safe-shutdown procedure that were consistent with the fire safe-shutdown
Enclosure analysis. Corrective actions included revising the remote shutdown procedure to include the necessary steps to align the
- RC [[]]
IC pump suction to the suppression pool while
operating the system from the remote shutdown panel. The deficiency was documented in Exelon's corrective action program as
OA5 Other Activities .1 Quarterly Resident Inspector Observations of Security Personnel and Activities a. Inspection Scope During the inspection period the inspectors conducted observations of security force
personnel and activities to ensure that the activities were consistent with licensee security procedures and regulatory requirements relating to nuclear plant security. These observations took place during both normal and off-normal plant working hours. These quarterly resident inspector observations of security force personnel and activities
did not constitute any additional inspection samples. Rather, they were considered an integral part of the inspectors' normal plant status review and inspection activities. b. Findings
No findings of significance were identified. .2
- TI 2515/173, Review of the Implementation of the Industry Ground Water Protection Voluntary Initiative (1 sample) a. Inspection Scope An
NRC assessment was performed the week of March 9, 2009, of the licensee's implementation of the Nuclear Energy Institute - Voluntary Ground Water Protection Initiative (NEI 07-07, dated August 2007, ML072610036). The inspector verified that the licensee had evaluated work practices that could lead to leaks and spills, and has performed an evaluation of systems, structures, and components that contain licensed
radioactive material to determine potential leak or spill mechanisms. The licensee has completed a site characterization of geology and hydrology to determine the predominant ground water gradients and potential pathways for ground water migration from on-site locations to off-site locations. Monitoring wells have been
installed at the appropriate locations and an on-site ground water sampling program has been implemented to monitor for potential licensed radioactive leakage into groundwater. The ground water monitoring results were being reported in the annual radiological environmental operating report.
The licensee has prepared procedures for the decision making process for potential remediation of leaks and spills, including consideration of the long term decommissioning impacts. Records of leaks and spills are being recorded in the licensee's decommissioning files in accordance with 10 CFR 50.75(g).
The licensee has identified the appropriate local and state officials and has conducted briefings on the licensee's ground water protection initiative. Protocols have been
Enclosure established for notification to these local and state officials regarding detection of leaks and spills. b. Findings and Observations No findings of significance were identified. .3 (Closed) Unresolved Item (URI) 05000352,05000353/2001014-01, Reliance on an Assumption of a Single Spurious Malfunction of Safe Shutdown Equipment for Any Single Fire During the 2001 triennial fire protection inspection, the NRC identified an unresolved item concerning an issue that a single fire in some plant areas could potentially cause
multiple fire induced spurious actuations of safe shutdown components to occur, as documented in Generic Letter 86-10. The Limerick Generating Station
- IPEEE [[were based on the assumption that only a single fire-induced spurious action could occur at a time. The potential of multiple fire-induced spurious actuations in a single fire and whether the accumulated effects of these spurious actuations should be addressed in the licensees' fire protection programs is a generic industry issue to be resolved between the]]
NRR) and the nuclear industry. Any further corrective
actions required to resolve this issue will be addressed in future guidance to be issued by the
- NRC. [[The licensee will be expected to identify and address any corrective actions following the issuance of the guidance, and those corrective actions will be reviewed in future triennial fire protection inspections. The licensee has captured this issue in their]]
CAP (IR 00888803) to track issuance of NRC guidance regarding multiple
spurious actuation assumptions. Therefore, this item is administratively closed. 4OA6 Meetings, Including Exit Exit Meeting Summary On April 10, 2009, the resident inspectors presented the inspection results to
Mr.
- C. Mudrick and other members of his staff. The inspectors confirmed that proprietary information was not included in the inspection report. 4
- OA 7 Licensee-Identified Violations The following violation of very low safety significance (Green) was identified by Exelon and is a violation of
VI of the
- NCV [[). * Technical Specification 6.8.1.g, "Procedures and Programs," requires that written procedures shall be established, implemented, and maintained covering fire protection program implementation. Contrary to this requirement, Exelon failed to establish an adequate remote shutdown procedure to align]]
- RC [[]]
IC pump suction to the suppression pool as assumed and analyzed in the fire safe-
shutdown analysis. Specifically, Exelon did not ensure that procedure
RCIC pump suction to the suppression pool while operating the system at the remote shutdown panel for a fire in the main control room or the cable spreading room. The issue was entered into Exelon's corrective action program as IR 843591. The finding was
more than minor because it is associated with the procedural quality attribute of the Mitigating Systems Cornerstone and affects the cornerstone objective of
Enclosure ensuring the availability and reliability of the
- RC [[]]
IC system under postulated fire safe-shutdown conditions. The inspectors determined that the finding was of
very low safety significance (Green), based on
- IMC 0609, Appendix F, "Fire Protection Significance Determination Process," Phase 2 screening, Task Number 2.3.5, because no credible fire ignition source scenarios were identified.
- ATTACH [[]]
- MENT [[:]]
- SUPPLE [[]]
- MENTAL [[]]
- INFORM [[]]
- SUPPLE [[]]
- MENTAL [[]]
- INFORM [[]]
- ATION [[]]
- KEY [[]]
- POINTS [[]]
- OF [[]]
CONTACT
Exelon Generation Company C. Mudrick, Site Vice President
- E. Callan, Plant Manager D. DiCello, Manager, Radiation Protection R. Dickinson, Director, Engineering P. Gardner, Director, Operations R. Kreider, Manager, Regulatory Assurance
- M. [[Jesse, Manager, Nuclear Oversight S. Bobyock, Manager, Plant Engineering D. Palena, Manager, Electrical Engineering Systems E. Dennin, Shift Operations Superintendent C. Gray, Manager, Radiological Engineering R. Harding, Engineer, Regulatory Assurance J. Berg, System Manager,]]
- HPCI [[]]
- RHR [[]]
EDG R. Gosby, Radiation Protection Technician, Instrumentation D. Malinowski, Simulator Instructor
J. Sprucinski, Senior Radiation Protection Technician R. Harding, Regulatory Assurance J. Risteter, Radiation Protection Manager D. Wahl, Environmental Scientist C. Rich, Manager of Nuclear Training
J. Hunter, Operations Training Manager D. Malinowski, Supervisor Requalification Training W. Ward, Exam Developer D. Monahan, Simulator Operator/Instructor R. Harding, Licensing
J. Mihm, Instructor/Evaluator S. Cohen, Instructor/Evaluator C. Bruce, Fire Protection Engineer R. George, Manager, Electrical Design C. Pragman, Exelon, Corporate Fire Protection Engineer
P. Tarpinian, Probability Risk Assessment K. Ferich, Limerick Emergency Planning Manager M. Crim, Emergency Prepardness Coordinator R. Rogers, Exelon Facility and Equipment Coordinator E. Bell, Senior Radiation Protection Technician D. Kern, Senior radiation Protection Technician M. Lyate, Radiation Protection Supervisor, Field Operations
T. Moore, Director Work management J. Risteter, Radiation Protection Supervisor, Technical Support
Attachment
- LIST [[]]
- OF [[]]
- ITEMS [[]]
- AND [[]]
- DISCUS [[]]
SED
Opened None
Closed 2515/173
- TI Review of the Implementation of the Industry Ground Water Protection Voluntary Initiative (Section 4
- URI Reliance on an Assumption of a Single Spurious Malfunction of Safe Shutdown Equipment for Any Single Fire (Section 4
OA3.2)
- NCV Failure to Maintain Design Control for Reactor Building Temperatures (Section 1R22) 05000352, 353/2009002-02
- LIST [[]]
- OF [[]]
- REVIEW [[]]
- ED Section 1R04: Equipment Alignment Procedures 1592.1N (OL-4), Equipment Alignment for D14 Diesel Generator Operation, Revision 24 1S57.1.A(COL), Equipment Alignment for Automatic Operation of
- HP [[]]
CI System, Revision 15
Attachment S51.8.B, Shutdown Cooling-Reactor Coolant Circulation Operation Startup and Shutdown, Revision 66 Section 1R05: Fire Protection Procedures F-D-311D, D14 Diesel Generator Room and Fuel Oil and Lube Oil Tank Rooms; 311D and 312D, Elevation 217, Fire Area 82, Revision 5 F-R-370, Unit 2 Safeguard System Access Area Room 370, Elevation 217, Fire Area 67, Revision 7 Section 1R07: Heat Sink Performance Procedures
- RHR Heat Exchanger Transfer Test, Revision 6 Section 1R13: Maintenance Risk Assessments and Emergent Work Control Procedures
- LG -104-1001, Guidelines for the Review, Screening and Execution of Production Risk Activities, Revision
AA-101, On-line Work Control Process, Revision 15 S43.7.A, Manual Operation of Scoop Tube Positioners, Revision 32 S43.D.A, Resetting A Scoop Tube Lock-up, Revision 18
Section 1R15: Operability Evaluations
Procedures ST-6-107-760-2, Volt 2 Control Rod exercise Test, Revision 42
Drawings Drawing E-0476 Electrician Schematic Diagram, Drywell Area Unit Coolers, Revision 22 Section 1R18: Plant Modifications Procedures S53.0.A, Normal Makeup/Response to Low Level in Fuel Storage Pool or Reactor Well, Revision
- 22 UFS [[]]
AR Section 9.1.3.5, Instrumentation Applications Section 1R20: Refueling and Other Outage Activities
Procedures
- AA -330-1001, Core Verification Guideline, Revision 4 GP-3, Normal Plant Shutdown, Revision 127 Limerick 2R10, Shutdown Safety Plan, 3/6/2009
LG-104, Limerick Shutdown Safety Management Program, Revision 7
Attachment
- OPCON 5) System Preparation, Revision 20 S53.3.B, Filling Reactor Well and Dryer/Separator Storage Pool from Condensate System, Revision 13 Section
EP-MA-121-1005, Exelon East ANS Preventive Maintenance, Revision 5 Sample of maintenance records for 2007, 2008, and 2009
Section
- AA -112, Emergency Response Organization (ERO)/Emergency Response Facility (ERF) Activation and Operation, Revision
AA-113, ERO Training and Qualification, Revision 12
Section
- 2008 NOS [[]]
- LGS Emergency Preparedness Comprehensive Performance Assessment, dated September 19, 2008 Focused Area Self-Assessment, Readiness Assessment for the
ASSA#636075-32 Focused Area Self-Assessment, NRC Baseline Inspection Readiness Assessment,
Attachment
- AS [[]]
SA#840707-03 Emergency Preparedness Drill Reports, dated between January 2008 and March 2009 Emergency Preparedness-related Issue Reports and Action Requests, dated between January 2008 and March 2009 Section 20S1, 20S2, 20S3: Radiation Safety
Procedures:
- AA -222, Revision 3, Methods for Estimating Internal Exposure from In Vivo and In Vitro Bioassay Data
- LG -300-102, Revision 2, Removing Items from the Spent Fuel Pool, Reactor Cavity, Equipment Pit, or Cask Pit
- ALA [[]]
- RT -0-100-460-0, Revision 3,High Radiation and Locked High Radiation Door Preventative Maintenance Inspection Issue Reports (Access Control/
ALARA related (71121.01/02):) 865581, 845162, 740616, 764772, 753194, 786036, 753069, 753254, 764072, 764070, 764064,
764051, 764040. 764035, 764024, 764020, 864642, 856932, 839478, 863398, 790161 Cause Analyses: Apparent Cause Report (IR 790161), Improving Fleet Dose Projections Common Cause Analysis (IR 748277), Personnel Contamination Events during 1R12
Common Cause Analysis (IR748276), Floor Drains backup causing contamination Common Cause Analysis (IR 764772), Emergent Radiation Dose Issues
- ISI [[]]
RPV Nozzle & Skirt AP08-009, Installation/Removal of Scaffolding
AP08-037, Reactor Cavity Work Platform Activities
Attachment Station
- ALARA Council Meeting Minutes Meeting Nos.:2008-01 through 2008-23 Nuclear Oversight Objective Evidence Reports Comprehensive Performance Assessment,
- LG -08-13, regarding High Radiation Area Controls, Contamination Controls, Management Oversight of Radworker Performance, and On-Line Dose Control
- NOSPA [[-LG-08-1Q, Control of Radioactive Sources Miscellaneous Reports Dose and Dose Rate Alarm Report for period May 2008 through January 12, 2009 Business Plan Performance Report November 2008 2008 Calibration Records for the Canberra FastScan and AccuScan Whole Body Counting Systems Training Materials for using the Eberline]]
- RAM [[]]
GAM, and Bicron RSO-50E. 1R!2 Radiation Protection Outage Report
Section
- 2PS 3: Radiological Environmental Monitoring Program and Radioactive Material Control Program Procedures:
- AA -170-1000, Rev 2, Radiological Environmental Monitoring Program and Meteorological Program Implementation
- LG -120-11012, Rev 19, Outside Chemistry/NPDES Sampling & Analysis Schedule RT-5-104-800-0, Rev 6, Tritium Analysis of Non-Contaminated Systems
- MET. [[]]
- AA -170-4100, Rev 1, Radiological Ground water Protection Program Environmental Sample Collection and Implementation
- LG -170-4160, Rev 1, Radioactive Groundwater Protection Program Scheduling and Notification for the Limerick Generating Station
AA-1120, Rev 10, Reportable Event RAD 1.34
- ER - 5, Rev 12, Collection of Water Samples for Radiological Analysis
Attachment *ER - 8, Rev 12, Collection of Air Particulate and Air Iodine Samples for Radiological Analysis *ER - 9, Rev 7, Collection of
ER-10, Rev 11, Collection of Milk Samples for Radioactive Analysis *Normandeau Associates, Inc. Procedures
Sampling Sites: Cow=s Milk Nos. 10F4, 18E1, 19B1, 23F1, 25C1 Air Particulate/Iodine: 10S3, 11S1, 11S2, 13C1, 14S1,22G1 Drinking Water: Nos. 15F4, 15F7, 16C2, 28F3
Surface Water Nos. 13B1, 24S1 Thermolumeniscent Dosimeters Nos. 10S3, 11S1, 14S1, 21S2, 23S2, 19D1 Nuclear Oversight (NO)/Self-Assessment Reports:
LG-08-13, Contamination Controls Assessment
Self-Assessment 567519, Tritium Monitoring-Radiological Groundwater Protection Plan Implementation Chemistry
- REMP Self Assessment 859249-02 Issue Reports: 880363, 889095, 882759, 848385, 801327, 700944, 739108, 798054, 752414, 842009, 881821, 880716, 567519, 864773, 808357, 802070, 773982, 680121, 654269, 625154, 591087, 615724 Calibration Records
SAM Nos. 334213, 334829, 332533, 334219, 334212, 334828, 334827
Miscellaneous Reports: - 2007 Annual Radioactive Effluent Release Report, No. 33 - 2007 Annual Radiological Environmental Operating Report, No. 23 - Evaluation of the LGS Onsite Radioactive Materials Storage Area: A vendor prepared decommissioningCost Estimate Report - Air Particulate Monitoring System Maintenance Records (Normandeau Associates, Inc)
- Water Sampling Equipment Maintenance Logs - Hydro-geologic Investigation Report, No. 045136 - 2008 Land Use Survey - Analytics Inter-laboratory Cross Check Program Results, January - September 2008 - Fall 2008 Routine Groundwater and Surface Water Monitoring Program Results
- P1009 Meteorological Monitoring Program, Equipment Servicing and Data Recovery Manual, Rev 26 - Monthly Report on the Meteorological Monitoring Program, December 2008
Section
ANS) Reliability, Revision 5 Data records for the three EP performance indicators, July 2008 - December 2008
Attachment Issue Reports and Action Requests
- HP [[]]
CI System Availability
Section
SE-1, Remote Shutdown, Revision 61
S49.1.C, Recovery from
- ID s 8031-M-49, U1 Reactor Core Isolation Cooling, Revision 53 8031-M-49, U1 Reactor Core Isolation Cooling, Revision 48 8031-M-50, U1 & U2
- RC [[]]
IC Pump Turbine, Sheets 1 - 4 8031-M-55, U2 High Pressure Coolant Injection, Revision 55
8031-M-55, U2 High Pressure Coolant Injection, Revision 51 Drawings M-1-E51-1040-E-001, U1 Elementary Diagram Reactor Core Isolation Cooling, Revision 16 M-1-E51-1040-E-003, U1 Elementary Diagram Reactor Core Isolation Cooling, Revision 30 M-1-E51-1040-E-008, U1 Elementary Diagram Reactor Core Isolation Cooling, Revision 26 M-1-E51-1040-E-012, U1 Elementary Diagram Reactor Core Isolation Cooling, Revision 26 M-1-E51-1040-E-017, U1 Elementary Diagram Reactor Core Isolation Cooling, Revision 7
M-1-E51-1040-E-019, U2 Elementary Diagram Reactor Core Isolation Cooling, Revision 26 M-1-E51-1040-E-020, U2 Elementary Diagram Reactor Core Isolation Cooling, Revision 10 M-1-E51-1040-E-021, U2 Elementary Diagram Reactor Core Isolation Cooling, Revision 0 M-1-E51-1040-E-027, U2 Elementary Diagram Reactor Core Isolation Cooling, Revision 5 M-1-E51-1040-E-033, U2 Elementary Diagram Reactor Core Isolation Cooling, Revision 11
Action Request A1351836 Issue Reports 00843591 00859194 00855503 Apparent Cause Evaluations 00843591,
- NOS [[]]
ID Potential Areas for Improvement FP.1-1 Fire Protection Program Issues
Miscellaneous LER 2008-004, Remote Shutdown Procedure Error Limerick Generating Station, Technical Specifications Limerick Generating Station, Updated Final Safety Analysis Evaluation Report
T-112 Bases, Emergency Blowdown, Revision 9
Attachment Risk Assessment of
- LIST [[]]
- OF [[]]
- HP [[]]
TEDE total effective dose equivalent
Attachment
- VH [[]]