Mid-Cycle Assessment Letter for Callaway Plant (Report 05000483/2014006)
ML14239A604
Person / Time
Site: Callaway Ameren icon.png
Issue date: 09/02/2014
From: O'Keefe N F
NRC/RGN-IV/DRP/RPB-B
To: Diya F M
Union Electric Co
O'Keefe N F
References
IR-2014-006 IR-2014-006
Download: ML14239A604 (6)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E LAMAR BLVD ARLINGTON, TX 76011

-4511 September 2, 2014 Mr. Fadi Diya, Senior Vice President and Chief Nuclear Officer Union Electric Company P.O. Box 620 Fulton, MO 65251

SUBJECT: MID-CYCLE ASSESSMENT LETTER FOR CALLAWAY PLANT (REPORT 0500483/2014006

)

Dear Mr. Diya:

O n August 1 2 , 20 14 , t h e NRC co m p l e t ed i t s mid-c y c l e p e r f o rm a n ce r e v i e w of Calla w a y Pl a n t. T he NR C r e v i e w e d t he m o s t rece n t q u a rt e r l y p e r f o r m a n ce i n di ca t o r s (P Is) i n ad di t i on t o inspec t i on resu l t s and e n f o r c e ment a c t i ons f r o m July 1, 2 0 1 3 , t h r o u g h June 30, 20 14. T h i s l e tt e r i n f o rm s y ou o f t he N RC's a sses s ment o f Calla w a y Pl a n t d u r i n g t h i s pe r i od and it s p lans f o r f u t u r e inspe c t ions at your f a c ili t y. The NRC determined that overall, Calla w a y Pl a n t was operated in a manner that preserved public health and safety and met all cornerstone objectives.

T he NR C de t e r m i n ed t he p e r f o r mance at Call a w a y Plant d u r i n g t h e m o s t r e ce n t q u a rt e r w as w i t h i n t he L icensee Response C o l u m n o f the NRC's R eac tor O v e r s i g h t P r ocess (R O P) A c ti on M atri x because a l l insp e c t i on f i n di n g s had v e r y l o w (i.e., Gr e e n) s a f e t y s i g n i f icanc e , and a l l P I s i n d i ca t ed t h a t y our p e r f o r mance w as w i t h i n t he n o m i n al , e x pec t ed r a n g e (i.e., Gr ee n). T h e r e f o r e , t he NR C p l ans t o con d u ct R OP base line inspec t i ons at y our f ac il i t y. As a result of the Safety Culture Common Language Initiative, the terminology and coding of cross-cutting aspects were revised. All cross

-cutting aspects identified during inspections conducted in calendar year 2014 reflect this revision to Inspection Manual Chapter (IMC) 0310. Cross-cutting aspects identified in 2013 using the 2013 terminology were converted to the latest revision in accordance with the cross

-reference in IMC 0310 during the mid

-cycle assessment review and evaluated for cross

-cutting themes and potential substantive cross

-cutting issues in accordance with IMC 0305.

T he enc losed insp e c ti on p l an li s t s t he i nspec t i ons sched ul ed t h r o u g h December 31, 2 01 5. R o u t i ne inspec t i ons p e r f o r m ed b y r es i de n t insp e c t o r s a r e not i nc l uded i n t he i ns p e c t i on p l an. The inspec t ions li s t ed du r i n g t he last n i ne m o nt h s of t h e inspec t i on p l an a r e t e n t a t i v e and m ay be r e v ised at t he end-of-c y c l e p e r f o rmance r e v i e w. T h e NR C p r o v i des t he i ns p ec t i on p l an t o a ll ow f o r t he reso l u t i on o f any sc h eduli ng co n f li c t s and p e rsonnel a v a il abili t y issues. T he NR C w ill co n tact y ou as soon as poss i b l e t o d i scu s s ch a nges t o t he i nspec t i on p l an sho ul d c i r cu m s tances w a rr ant a ny cha n g e s. T h i s insp e c t i on p l an does not i nc l u d e secu r i t y r e l a t ed inspec t ions, w h i ch w i ll be sent v i a sep a r a t e , n o n-p u b li c l y a v a il a bl e co rr e s p ondence. In response to the accident at Fukushima, the Commission issued Order EA

-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond

-Design-Basis External Events," which requires licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond

-design-basis external event.

Additionally, the Commission issued Order EA

-12-051, "Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," which requires licensees to have a reliable means of remotely monitoring wide-range Spent Fuel Pool levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event.

The NRC is conducting audits of licensee efforts towards compliance with these Orders.

This audit includes an onsite component in order for the NRC to evaluate licensee plans for complying with the Orders, as described in site-specific submittals, and to receive and review information relative to associated open items.

This onsite activity will occur in the months prior to a declaration of compliance for the first unit at each site, and will aid staff in development of an ultimate Safety Evaluation for the site. The date for the onsite component at your site is being coordinated with your staff.

A site-specific audit plan for the visit will be provided in advance to allow sufficient time for preparations.

I n acc o rdance w i t h 10 CFR 2.390 o f t he NRC's R u l es o f P r ac t i c e , a copy o f t h i s l e tter w i ll be a v a il a bl e e l ec tr o ni ca ll y f o r publi c insp e c t i on i n t he NR C P ubli c Docu m e n t R oom o r f r o m t he P ubli c l y A v a il a bl e Reco r ds (PAR S) co m pon en t o f NRC's doc u m en t s y s t e m (A DA M S). ADA M S i s access i b l e f r om t he N R C W e b s i t e a t h tt p://w w w.n r c.g o v/r ead i ng-r m/a d a m s.h tm l (t he P u blic El ec tr o ni c R ea d i n g R o o m).

Please co n t a c t m e a t 8 1 7-2 0 0-1141 w i t h any q u e s t i ons y ou h a v e r e g a r d i n g t h i s l e tt e r.

Sincerely,

/RA/ Neil F. O'K e e f e , C hi e f P r o j e c t B ranch B Di v i s i on of R ea c t o r P r o j e c t s Docket No.: 50-483 License No.:

NPF-30 Enclosure:

Callaway Plant Inspection/

Activity Plan

SUNSI Review By: NOKeefe ADAMS Yes No Publicly Available Non-Publicly Available Non-Sensitive Sensitive OFFICE RIV/BC/DRP RIV/D/DRS RIV/D/DRP NAME OKeefe/dll AVegel TPruett SIGNATURE /RA/ /RA/VGaddy for /RA/ DATE 8/21/14 8/25/14 8/22/14 Letter to Fadi Diya from Neil F. O'Keefe dated September 2, 2014

SUBJECT: MID-CYCLE ASSESSMENT LETTER FOR CALLAWAY PLANT (REPORT 05000483/2014006

) DISTRIBUTION

Regional Administrator (Marc.Dapas@nrc.gov) Deputy Regional Administrator (Steven.Reynolds@nrc.gov)

Acting DRP Director (Troy.Pruett@nrc.gov) Acting DRP Deputy Director (Michael.Hay@nrc.gov) DRS Director (Anton.Vegel@nrc.gov) DRS Deputy Director (Jeff.Clark@nrc.gov) Senior Resident Inspector (Tom.Hartman@nrc.gov) Resident Inspector (Zachary.Hollcraft@nrc.gov

) Administrative Assistant (Dawn.Yancey@nrc.gov)

Branch Chief (Neil.O'Keefe@nrc.gov) Senior Project Engineer (David.Proulx@nrc.gov) Project Engineer, (Fabian.Thomas@nrc.gov) Public Affairs Officer (Victor.Dricks@nrc.gov) Public Affairs Officer (Lara.Uselding@nrc.gov

) RIV State Liaison Officer (Bill.Maier@nrc.gov)

Project Manager (Fred.Lyon@nrc.gov) Branch Chief, DRS/TSB (Geoffrey.Miller@nrc.gov) R4DRPBC@nrc.gov R4DRSBC@nrc.gov Director, DIRS, NRR (Scott.Morris@nrc.gov)

Deputy Director, DIRS, NRR (Allen.Howe@nrc.gov)

Acting Director, DORL, NRR (Louise.Lund@nrc.gov)

Acting Deputy Director, DORL (Michael.Markley@nrc.gov)

Director, NSIR/DPR (Rob.Lewis@nrc.gov)

Chief, PLB IV, DORL, NRR (Eric.Oesterle@nrc.gov) Regional Counsel (Karla.Fuller@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

Technical Support Assistant (Loretta.Williams@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

RIV/ETA: OEDO (Anthony.B owers@nrc.gov)

ROPassessment Resource@nrc.gov ROPreports@nrc.gov OEMail Resource@nrc.gov Electronic Distribution for Callaway Plant Page 1 of 2 08/22/2014 13:57:44 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on SiteCallawayInspection / Activity Plan 09/01/2014

-12/31/2015EXAM-INITIAL OPERATOR EXAM 4 1 INITIAL EXAM-CALLAWAY (02/01/2015)

X0253511/03/201411/07/2014 1 INITIAL EXAM-CALLAWAY (02/01/2015)

X02535 12/08/2014 12/12/2014 ISFSI-PAD POUR INSPECTION (MULTIPLE VISITS)

1 1 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 08/01/201411/30/2014HEAD-REP-REACTOR HEAD REPLACEMENT P1 2 1 IP Reactor Vessel Head Replacement Inspection 71007 08/17/2014 09/27/201471111.08-CALLAWAY INSERVICE INSPECTION 2 1 IP Inservice Inspection Activities - PWR7111108P 10/13/2014 10/24/2014HEAD-REP-REACTOR HEAD REPLACEMENT-P2 2 1 IP Reactor Vessel Head Replacement Inspection 71007 10/19/201411/22/2014 1 IP Problem Identification and Resolution71152 10/19/2014 12/27/2014 RS 13 PI-RADIATION SAFETY 2 1 IP Radiological Hazard Assessment and Exposure Controls71124.01 10/27/2014 10/31/2014 1 IP In-Plant Airborne Radioactivity Control and Mitigation71124.03 10/27/2014 10/31/2014 1 IP71151-OR01 10/27/2014 10/31/2014 1 IP71151-PR01 10/27/2014 10/31/2014 ISFSI-DRY RUN INSPECTIONS (MULTIPLE VISITS)

1 1 IP Operation Of An ISFSI 60855 02/01/2015 05/01/2015 ISFSI-DRY RUN INSPECTION (MULTIPLE VISITS)

1 1 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 02/01/2015 06/01/2015 EB2-05T-TRIENNIAL FIRE PROTECTION INSPECTION 4 1 IP Fire Protection - NFPA 805 (Triennial)7111105x 04/27/2015 05/01/2015 1 IP Fire Protection - NFPA 805 (Triennial)7111105x05/11/2015 05/15/2015 EP-2-HAB EXERCISE INSPECTION 2 1 IP Emergency Action Level and Emergency Plan Changes7111404 05/04/2015 05/08/2015 1 IP Exercise Evaluation - Hostile Action (HA) Event7111407 05/04/2015 05/08/2015 EP-3-EP PERFORMANCE INDICATORS 2 1 IP71151-EP01 05/04/2015 05/08/2015 1 IP71151-EP02 05/04/2015 05/08/2015 1 IP71151-EP03 05/04/2015 05/08/2015 INSP-OPERATOR REQUAL INSPECTION 3 1 IP Licensed Operator Requalification Program7111111B 06/15/2015 06/19/2015 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.

Page 2 of 2 08/22/2014 13:57:44 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on SiteCallawayInspection / Activity Plan 09/01/2014

-12/31/2015 RS 5678-RADIATION SAFETY - TEAM 4 1 IP Radiation Monitoring Instrumentation71124.05 07/13/2015 07/17/2015 1 IP Radioactive Gaseous and Liquid Effluent Treatment71124.06 07/13/2015 07/17/2015 1 IP Radiological Environmental Monitoring Program71124.07 07/13/2015 07/17/2015 1 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation71124.08 07/13/2015 07/17/2015 RS 12 PI-RADIATION SAFETY 2 1 IP Radiological Hazard Assessment and Exposure Controls71124.01 10/26/2015 10/30/2015 1 IP Occupational ALARA Planning and Controls71124.02 10/26/2015 10/30/2015 1 IP71151-OR01 10/26/2015 10/30/2015 1 IP71151-PR01 10/26/2015 10/30/2015 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.