Summary of December 1, 2022, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specification Conversion License Amendment Requests
ML22357A074
Person / Time
Site: Saint Lucie, Turkey Point  NextEra Energy icon.png
Issue date: 01/19/2023
From: Natreon Jordan
NRC/NRR/DORL/LPL2-2
To:
Florida Power & Light Co
References
EPID L-2021-LLI-0000, EPID L-2021-LLI-0002
Download: ML22357A074 (1)


Text

January 19, 2023 LICENSEE:

Florida Power and Light FACILITIES: St. Lucie Plant, Unit Nos. 1 and 2 Turkey Point Nuclear Generating, Unit Nos. 3 and 4

SUBJECT:

SUMMARY

OF DECEMBER 1, 2022, MEETING WITH FLORIDA POWER AND LIGHT ON ST. LUCIE AND TURKEY POINT IMPROVED TECHNICAL SPECIFICATION CONVERSION LICENSE AMENDMENT REQUESTS (EPID NOS. L-2021-LLI-0000 AND L-2021-LLI-0002)

On December 1, 2022, a virtual observation public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Florida Power and Light (FPL, the licensee). The purpose of the meeting was to discuss the license amendment requests (LARs) for St. Lucie Plant, Unit Nos. 1 and 2 (St. Lucie) to convert to improved standard technical specifications in accordance with NUREG-1432, Standard Technical Specifications -

Combustion Engineering Plants, Revision 5 (improved standard Technical Specifications (ISTS)) and Turkey Point Nuclear Generating Unit Nos. 3 and 4 (Turkey Point) to convert to improved standard technical specifications in accordance with NUREG-1431, Standard Technical Specifications - Westinghouse Plants, Revision 5. The meeting notice and agenda, dated October 31, 2022, are available in the Agencywide Documents Access and Management System (ADAMS) Accession No. ML22304A051. A list of attendees is provided in the Enclosure.

The following items for the St. Lucie review were discussed during the meeting:

NRC and licensee staff provided a current status of the review effort.

o NRC staff informed the licensee that questions were being developed related to Section 3.9.

Licensee staff provided a status of request for additional information responses related to the St. Lucie review effort.

The following items for the Turkey Point review effort were also discussed:

The licensee staff informed NRC staff of how they intend to address administrative changes related to Section 3.3.

A discussion was also held between NRC and licensee staff regarding the licensees plan to remove setpoints from the Technical Specifications to the licensee-controlled Technical Requirement Manual.

There were no members of the public in attendance for this meeting.

For questions or comments, please contact me at 301-415-7410, or Natreon.Jordan@nrc.gov.

/RA/

Natreon J. Jordan, Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-250, 50-251, 50-335, and 50-389

Enclosure:

List of Attendees cc: Listserv

Enclosure LIST OF ATTENDEES DECEMBER 1, PUBLIC MEETING WITH FPL/NEXTERA ST. LUCIE PLANT, UNIT NOS. 1 AND 2 TURKEY POINT NUCLEAR GENERATING UNIT NOS. 3 AND 4 IMPROVED STANDARD TECHNICAL SPECIFICATION CONVERSION Name Organization Natreon (Nate) Jordan U.S. Nuclear Regulatory Commission (NRC)

Clinton Ashley NRC Craig Harbuck NRC Ravi Grover NRC Khadijah West NRC Matthew Hamm NRC Vic Cusumano NRC Josh Wilson NRC Andrea Russell NRC Steve Smith NRC Michael Coen Florida Power and Light Company (FPL)

Michael Davis FPL Jarrett Mack FPL Gregg Ellis Excel Services Corporation (Excel)

Jerry Riste Excel Charles DeDeaux Excel Christina Long Excel Bruce Crabbs Excel David Bice Excel

Package: ML22357A044 Meeting Notice: ML22304A051 Meeting Summary: ML22357A074 OFFICE NRR/DORL/LPL2-2/PM NRR/DORL/LPL2-2/LA NRR/DORL/LPL2-2/BC NAME NJordan RButler DWrona DATE 12/21/2022 12/28/2022 1/19/2023