ML20058C899
| ML20058C899 | |
| Person / Time | |
|---|---|
| Site: | Hatch |
| Issue date: | 06/09/1982 |
| From: | Beckham J GEORGIA POWER CO. |
| To: | James O'Reilly NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| Shared Package | |
| ML20058C883 | List: |
| References | |
| NUDOCS 8207260474 | |
| Download: ML20058C899 (2) | |
Text
,
,h>>.s(a p
r,,
p 3 ! j f' r y^t 4
.m, A u~a (i < r ; a 1:w,"
r
,y
,..to t i ;r, ', :n r
~
pf a : yAje f[
rq g
Georgia Power
=,[ j [} [ b
~
'e ect-
,1 J. T. Beckham, Jr.
y P1
( r-4 5, rm ' &,
- n..
,a.
June 9, 1982 U. S. Nuclear Regulatory Commission
REFERENCE:
Office of Inspection and Enforcement RII: HCD Region II - Suite 3100 50-321/50-366 101 Marietta Street, NW Inspection Report Atlanta, Georgia 30303 82-08 ATTENTION: Mr. James P. O'Reilly GENTLEMEN:
Georgia Power Company hereby submits the following information as a supplemental response to Inspection Report 82-08 concerning the inspection conducted by Mr. B. R. Crowley of your office on March 2-5 and 16-19,1982.
This supplcaent specifically addresses the response to the " admission or denial of alleged violation" submitted by our letter dated May 12, 1982.
Mr.
B.
R.
Crowley has requested a clarification of our response to the admission / denial of violation statement.
The clarification is offered as follows for your review and consideration:
REASON FOR THE VIOLATION - The violation occurred because the CB&I Welding Inspector accepted a weld joint fit-up which was not in conformance with the drawing.
The drawing showed a joint with a 15-degree double bevel.
The joint, as fit-up, had a 15-degree single bevel.
Georgia Power Company agrees with C8&I's response that the degree of beval in this particular instance was not a critical factor in the integrity of the weld joint.
The fact remains that the violation was due to failure to comply with the design drawing which shows a specific weld bevel.
8207260474 820716 PDR ADOCK 05000321 G
]
Georgia Power A U. S. Nuclear Regulatory Commission Office of Inspection and Enforcement Region II - Suite 3100 June 9, 1982 Page Two j
If you have any questions in this regard, please contact this office.
J. T. Beckham, Jr. states that he is Vice President of Georgia Power Company and is authorized to execute this oath on behalf of Georgia Power Company, and that to the best of his knowledge and belief the facts set forth in this letter are true.
l GEORGIA POWER COMPANY 0 cy"m AJ u 1L By:
e
--g
(/J.T.Beckham,Jr.
Sworn to and subscribed fore me this 9th day of June, 1982 jj//
Notary Puth, Georgia. State at Large C N.
h My Cmwnssm Expires Sept. 20,1983 Notary Public yac
-JAE/ DAM /mb Enclosure xc:
H. C. Nix R. F. Rogers, III t