ML18058B004
| ML18058B004 | |
| Person / Time | |
|---|---|
| Site: | Palisades |
| Issue date: | 08/05/1992 |
| From: | Masciantonio A Office of Nuclear Reactor Regulation |
| To: | Slade G CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.) |
| References | |
| REF-GTECI-A-46, REF-GTECI-SC, TASK-A-46, TASK-OR GL-87-02, GL-87-2, GL-88-20, TAC-M83653, NUDOCS 9208130245 | |
| Download: ML18058B004 (4) | |
Text
,
~po.fl flEG(J~
"1>-.
August 5, 1992
"'~~01).L
'~
d~
~
g 1-*
'1. s:
<JI
,.*:ff:
~
<f o'
1)
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555 Dock~l..,..... o. 50-255
~~-~~--
Mr. Gerald B. Slade Plant General Manager Palisades Plant Consumers Power Company 27780 Blue Star Memorial Highway Covert, Michigan 49043
Dear Mr. Slade:
SUBJECT:
PALISADES PLANT - REVIEW OF RESPONSE TO GENERIC LETTER 88-20, SUPPLEMENT NO. 4 - INDIVIDUAL PLANT EXAMINATIONS FOR EXTERNAL EVENTS (TAC NO. M83653)
Supplement 4 to Generic Letter 88-20 was issued on June 28, 1991, to require each licensee and each Construction Permit holder to conduct an individual plant examination of external events (IPEEE).
Guidance was provided with the generic letter supplement in the form of NUREG-1407, 0 Procedural and Submittal Guidance for the Individual Plant Examination of External Events (IPEEE) for Severe Accident Vulnerabilities.
11 The supplement requested a 180-day response (December 26, 1991) that would (1) identify the method and approach selected for the IPEEE, (2) describe the method to be used if it has not previously been submitted for staff review, and (3) identify the milestones and schedule for performing the IPEEE and submittal of the results to the NRC.
Licensees were requested in the supplement to submit the IPEEE results to the NRC for review by June 28, 1994, (three years after issuance of the supplement) to ensure that the intent of the Commission's Severe Accident Policy Statement will be met by mid-1995.
We have reviewed your letter dated December 20, 1991, submitted in response to Generic Letter 88-20, Supplement 4.
We find that your selected IPEEE methods are acceptable.
However, your submittal did not provide projected milestones and schedules.
The reason given in your submittal for not providing this inform~tion was that the staff had not issued the Supplemental Safety Evalua-tion Report (SSER) approving the USI A-46 Generic Implementation Procedure (GIP). This SSER was issued by the staff on May 22, 1992, via Supplement 1 to Generic Letter 87-02. Therefore, we request that you update your IPEEE plans and provide your projected milestones and schedules to the NRC no later than September 18, 1992.
The basis for that response date is that those plants covered under USI A-46 are required to respond by September 18, 1992, with their USI A-46 program.
Most licensees for these plants have linked their -
If your IPEEE submittal date is not consistent with the NRC's requested date of June 1994, you should forward your justification with sufficient discussion to provide the NRC staff with a basis for determining the acceptability of your schedules.
However, we request that your IPEEE submittal be provided no later than mid-1995.
By doing so, your efforts will more closely reflect the level of safety significance attributed to this effort by the Commission when the goal of closing severe accident issues by June 1995 was established.
9208130245 920805 PDR ADOCK 05000255 r#\\
P PDR
Mr. G. Note that, through your IPE process, we expect that you are now familiar with Level l Probabilistic Risk Assessment (PRA) technology.
The information you obtained and expertise you acquired through the IPE process should be used and built upon to fulfill part of the IPEEE requirements.
The staff believes that, with the safety systems and equipment being identified through the IPE process, you should be able to complete the IPEEE within the requested time frame.
The information requested by this letter is within the scope of the overall burden estimated in Supplement 4 to Generic Letter 88-20 for the IPEEE program, which was a maximum of 6 person-years per licensee response over a 3-year period. This request is covered by Office of Management and Budget Clearance Number 3150-0011, which expires May 31, 1994.
cc: See next page Sincerely, Armando Masciantonio, Project Manager Project Directorate 111-1 Division of Reactor Projects 111/IV/V Office of Nuclear Reactor Regulation
Mr. Gerald B. Slade Consumers Power Company cc:
M. I. Miller, Esquire Sidley l Austin 54th Floor One First National Plaza Chicago, Illinois 60603 Mr. Thomas A. McNish, Secretary Consumers Power Company 212 West Michigan Avenue Jackson, Michigan 49201 Judd L. Bacon, Esquire Consumers Power Company 212 West Michigan Avenue Jackson, Michigan 49201 Regional Administrator, Region Ill U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137 Jerry Sarno Township Supervisor Covert Township 36197 M-140 Highway Covert, Michigan 49043 Office of the Governor Room 1 - Capitol Building Lansing, Michigan 48913 Mr. Patrick M. Donnely, Director Safety and Licensing Palisades Plant 27780 Blue Star Memorial Highway Covert, Michigan 49043 U.S. Nuclear Regulatory Commission Resident Inspector Office Palisades Plant 27782 Blue Star Memorial Highway Covert, Michigan 49043 Palisades Plant Nuclear Facilities and Environmental Monitoring Section Office Division of Radiological Health Department of Public Health 3423 N. Logan Street P. o. Box 30195 Lansing, Michigan 48909 Gerald Charnoff, Esquire Shaw, Pittman, Potts and Trowbridge 2300 N Street, N.. W.
Washington DC 20037 Mr. David L. Brannen, Vice President Palisades Generating Company c/o Bechtel Power Corporation 15740 Shady Grove Road Gaithersburg, Maryland 20877 Roy W. Jones, Manager Strategic Program Development Westinghouse Electric Corporation 4350 Northern Pike Monroeville, Pennsylvania 15146
Mr. G. Note that, through your IPE process, we expect that you are now familiar with Level 1 Probabilistic Risk Assessment (PRA) technology.
The information you obtained and expertise you acquired through the IPE process should be used and built upon to fulfill part of the IPEEE requirements.
The staff believes that, with the safety systems and equipment being identified through the IPE process, you should be able to complete the IPEEE within the requested time frame.
The information requested by this letter is within the scope of the overall burden estimated in Supplement 4 to Generic Letter 88-20 for the IPEEE program, which was a maximum of 6 person-years per licensee response over a 3-year period. This request is covered by Office of Management and Budget Clearance Number 3150-0011, which expires May 31, 1994.
cc: See next page DISTRIBUTION Docket File NRC & LPDRs PD31 Rdg File Palisades p/f BBoger JZwolinski LMarsh AMasciantonio MGamberoni MShuttleworth OGC ACRS(IO)
WShafer Rill RHernan 14/C/7 JChan NLS-324 CAder NLS-324 OFFICE LA:PD31
./ 4 NAME MShuttl eworth l DATE 712~
OFFICIAL RECORD COPY PE:PD31 MGamberJf i :
jkd m 8 /S/92 Sincerely, Original signed by:
Armando Masciantonio, Project Manager Project Directorate 111-1 Division of Reactor Projects 111/IV/V Office of Nuclear Reactor Regulation PM: PD3 l dM11 D:PD31 It AMasciantonio LMarsh fl f' f.>.f92
~6/92 FILENAME: C:\\WP\\WPDOCS\\PALISADE\\IPEEE.BOL