1 24 Month Fuel Cycle Pre-Submittal Meeting March 4, 2015 1:00 to 3:00 PM Robinson Nuclear Plant
Agenda 2
Opening Remarks/Meeting Objectives Project Update/LAR Submittal Schedule LAR Content Closing Remarks
3 Duke Attendees Jim Kammer RNP Engineering General Manager Gary Swider RNP 24 Month Fuel Cycle Project Lead Tim Tully RNP 24 Month Fuel Cycle Project Lead Eng Jeff Mungo RNP 24 Month Fuel Cycle Project Lead Eng Scott Connelly RNP Licensing
Opening Remarks 4
Introductions
Meeting Objectives :
Common understanding of the proposed scope of the Robinson LAR Understanding of the detail of information expected in the LAR Gain an understanding regarding regulatory positions on specific issues Discuss LAR schedule from submittal to NRC approval
LAR Content 5
Requirements of Generic Letter 91-04 Surveillances Extensions Calibration Surveillances Non-calibration Surveillances Steam Generator Inspections Appendix J
LAR Content (continued)
Methodology Used to Evaluate Acceptability of Change to 24 Month Fuel Cycle Engineering Evaluation will document changes and acceptability TS Surveillances
- Calibrations
- Non-calibrations Programs 6
LAR Content (continued)
Methodology Used to Evaluate Acceptability of Change to 24 Month Fuel Cycle Engineering Evaluation for Time Dependent Analyzed Drift (AD)
Utilization of EPRI TR-103335 Rev 1 and 2 Addresses seven items identified in Enclosure 2 of GL 91-04 Use of Industry experts in Drift analysis Methodology similar to Oconee 7
LAR Content (continued) 8 Drift Analysis/Failure Review Methodology Review of 10+ years of Previous Calibrations Statistical analysis to demonstrate extended interval acceptable.
Review of 10+ years of Corrective maintenance.
Document that all found failures would not go undetected due to a longer Technical Specification interval
9 Additional Analyses AST analysis approach in accordance with RG 1.183 Core Design Removal of partial length shield assemblies (PLSAs) and implementation of mid-enriched blankets Fuel Design Change to standardized design with larger pellet diameter Criticality Analyses May need to be revised to support fuel design changes LAR Content (continued)
10 Precedent LARs -
Oconee 1,2,3 -
Adams ML101330499 LAR Submittal Adams ML110480489 RAI response Adams ML11124A126 RAI Response Adams ML11203A018 RAI Response Adams ML091620074 Information Adams ML101330499 Amendment Issuance Indian Point 2,3 - Adams ML100320955 LAR Submittal 27 associated Adams documents LAR Content (continued)
Project Timeline/LAR Submittal Date 11 RNP 24 Month Fuel Cycle Project started May 2014 RNP LAR Submittal Summer 2016 Seeking NRC Approval Date Late Summer 2018 24 Month Fuel Cycle Implementation Fall 2018 RO32
Closing Remarks 12 Any near term rulemaking that may affect the project?
LAR submittal (s) - NRC preference for one or multiple LAR time table acceptability