Letter Sequence Request |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Results
Other: L-MT-13-096, GE-MNGP-AEP-3304R1, Enclosure 4, NEDC-33435 Corrected Pages, L-MT-13-126, Enclosure 3, GE-MNGP-AEP-3306, Enclosure 2 GEH Response to Mella+ Eicb RAI and Affidavit, L-MT-14-023, Maximum Extended Load Line Limit Analysis Plus: Technical Specification Clarifications, L-MT-16-071, Submittal of 2016 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.46, ML100320229, ML100710787, ML100740044, ML110190204, ML11325A426, ML12340A430, ML13191B128, ML13282A142, ML14141A399
|
MONTHYEARML1002805572009-12-31031 December 2009 NEDO-33435, Revision 1, Safety Analysis Report for Monticello Maximum Extended Load Line Limit Analysis Plus, Attachment 5 of L-MT-10-003 Project stage: Request ML1002805582010-01-21021 January 2010 License Amendment Request: Maximum Extended Load Line Limit Analysis Plus Project stage: Request ML1003202292010-02-16016 February 2010 Determination That Attachment 3 Contains Proprietary Information and Is Withheld from Public Disclosure Project stage: Other L-MT-10-017, Mellla+: Supplemental Information Needed to Complete the Acceptance Review2010-03-0404 March 2010 Mellla+: Supplemental Information Needed to Complete the Acceptance Review Project stage: Supplement ML1007104442010-03-0404 March 2010 Enclosure 2, GE-MNGP-AEP-1687, Rev. 1, GEH Responses to NRC Supplemental Requests 1, 3, and 4 Project stage: Supplement ML1007400442010-03-15015 March 2010 Application for Mellla+ Amendment Acceptable for Review Project stage: Other ML1007107872010-03-19019 March 2010 Determination That Enclosure 1 of 3/4/10 Letter Contains Proprietary Information and Is Withheld from Public Disclosure Project stage: Other L-MT-10-049, Response to Request for Additional Information for the Monticello Proposed Maximum Extended Load Line Limit Analysis Plus (Mellla+) Amendment2010-09-28028 September 2010 Response to Request for Additional Information for the Monticello Proposed Maximum Extended Load Line Limit Analysis Plus (Mellla+) Amendment Project stage: Response to RAI ML1027903732010-09-28028 September 2010 Enclosure 2, GE-MNGP-AEP-1913 R1, GEH Responses to Reactor Systems RAIs Project stage: Request ML1101902042011-02-0808 February 2011 Request for Withholding for Proprietary Information from Public Disclosure Project stage: Other L-MT-11-066, Correction of 10 CFR 50.46 Analysis Error Applicable to Monticello Extended Power Uprate (TAC MD9990) and Monticello Maximum Extended Load Line Limit Analysis Plus (TAC ME3145) License Amendment Requests2011-11-11011 November 2011 Correction of 10 CFR 50.46 Analysis Error Applicable to Monticello Extended Power Uprate (TAC MD9990) and Monticello Maximum Extended Load Line Limit Analysis Plus (TAC ME3145) License Amendment Requests Project stage: Request ML11325A4262011-11-30030 November 2011 Letter Approving Withholding from Public Disclosure Two Documents Containing Proprietary Information Submitted in the Licensees 11/11/2011 Letter Project stage: Other ML12192A1042012-06-27027 June 2012 Supplement to Maximum Extended Load Line Limit Analysis Plus License Amendment Request Project stage: Supplement ML12279A2242012-10-0404 October 2012 NRR E-mail Capture - Monticello Nuclear Generating Plant - Draft Request for Additional Information Mellla+ License Amendment Review Project stage: Draft RAI ML12319A1792012-11-0808 November 2012 NRR E-mail Capture - Monticello Nuclear Generating Plant - Draft Requests for Additional Information Mellla+ License Amendment Request Review Project stage: Draft RAI L-MT-12-107, Extended Power Uprate and Maximum Extended Load Line Limit Analysis Plus License Amendment Requests: Supplement to Address Secy 11-0014 Use of Containment Accident Pressure, Sections 6.6.4 and 6.6.72012-11-30030 November 2012 Extended Power Uprate and Maximum Extended Load Line Limit Analysis Plus License Amendment Requests: Supplement to Address Secy 11-0014 Use of Containment Accident Pressure, Sections 6.6.4 and 6.6.7 Project stage: Supplement ML12340A4302012-11-30030 November 2012 Enclosure 2, Presentation Materials Used During the Course of the NRC Audit of General Electric - Hitachi Held on October 24-25, 2012 - Non-Proprietary Project stage: Other 05000263/LER-2012-004, Regarding High Pressure Coolant Injection Inoperable When Inverter Is Out of Service2012-11-30030 November 2012 Regarding High Pressure Coolant Injection Inoperable When Inverter Is Out of Service Project stage: Request L-MT-12-111, Maximum Extended Load Line Limit Analysis Plus License Amendment Request - General Electric - Hitachi Presentation Materials Discussed at the NRC Audit Held October 24 - 25, 20122012-11-30030 November 2012 Maximum Extended Load Line Limit Analysis Plus License Amendment Request - General Electric - Hitachi Presentation Materials Discussed at the NRC Audit Held October 24 - 25, 2012 Project stage: Request L-MT-12-108, Responses to Request for Additional Information for Trace/Tracg Differences - Maximum Extended Load Line Limit Analysis Plus License Amendment Request2012-12-21021 December 2012 Responses to Request for Additional Information for Trace/Tracg Differences - Maximum Extended Load Line Limit Analysis Plus License Amendment Request Project stage: Response to RAI L-MT-12-117, 10 CFR 50.46 Thirty-Day Report2012-12-26026 December 2012 10 CFR 50.46 Thirty-Day Report Project stage: Request ML13009A0122013-01-25025 January 2013 Request for Withholding of Proprietary Information from Public Disclosure Enclosure 1 of Letter Dated November 30, 2012 Project stage: Withholding Request Acceptance ML13009A0142013-01-25025 January 2013 Request for Withholding of Proprietary Information from Public Disclosure Enclosure 2 of Letter Dated December 21, 2012 Project stage: Withholding Request Acceptance L-MT-13-053, 0000-0146-5423-SRLR, Rev. 1, Supplemental Reload Licensing Report for Monticello, Reload 26 Cycle 27 Extended Power Uprate (EPU)2013-01-31031 January 2013 0000-0146-5423-SRLR, Rev. 1, Supplemental Reload Licensing Report for Monticello, Reload 26 Cycle 27 Extended Power Uprate (EPU) Project stage: Supplement ML13137A1022013-04-24024 April 2013 NRR E-mail Capture - Monticello Nuclear Generating Plant - Requests for Additional Information (Scvb) Supporting the EPU and Mellla+ Reviews Project stage: RAI L-MT-13-036, Extended Power Uprate and Maximum Extended Load Line Limit Analysis Plus License Amendment Requests: Supplement for Application of License Amendment 1722013-05-13013 May 2013 Extended Power Uprate and Maximum Extended Load Line Limit Analysis Plus License Amendment Requests: Supplement for Application of License Amendment 172 Project stage: Supplement ML13191B1282013-06-26026 June 2013 NEDO-33820, Revision 0, Monticello Nuclear Generating Plant Upper Shelf Energy Evaluation for Plate C2220 Material for 54 EFPY, Enclosure 5 Project stage: Other L-MT-13-059, Extended Power Uprate and Maximum Extended Load Line Limit Analysis Plus License Amendment Requests: Response to Request for Additional Information Reactor Systems Branch and Vessel & Internals Integrity Branch and Supplemental Informati2013-06-26026 June 2013 Extended Power Uprate and Maximum Extended Load Line Limit Analysis Plus License Amendment Requests: Response to Request for Additional Information Reactor Systems Branch and Vessel & Internals Integrity Branch and Supplemental Information Project stage: Supplement ML13191A5682013-07-0808 July 2013 Extended Power Uprate & Maximum Extended Load Line Limit Analysis Plus License Amendment Requests: Supplement for Analytical Methods Used to Address Thermal Conductivity Degradation & Analytical Methods Limitations Project stage: Supplement L-MT-13-070, Maximum Extended Load Line Limit Analysis Plus License Amendment Request - Request for Additional Information Responses2013-07-31031 July 2013 Maximum Extended Load Line Limit Analysis Plus License Amendment Request - Request for Additional Information Responses Project stage: Request L-MT-13-081, Maximum Extended Load Line Limit Analysis Plus License Amendment Request - Request for Additional Information Responses2013-08-14014 August 2013 Maximum Extended Load Line Limit Analysis Plus License Amendment Request - Request for Additional Information Responses Project stage: Request ML13282A1412013-10-0404 October 2013 Maximum Extended Load Line Limit Analysis Plus License Amendment Request - Request for Additional Information Responses Project stage: Request L-MT-13-096, GE-MNGP-AEP-3304R1, Enclosure 4, NEDC-33435 Corrected Pages2013-10-0404 October 2013 GE-MNGP-AEP-3304R1, Enclosure 4, NEDC-33435 Corrected Pages Project stage: Other ML13282A1422013-10-0404 October 2013 GE-MNGP-AEP-3304R1, Enclosure 2, GEH Response to Mella + RAI 2 Project stage: Other ML13239A0762013-10-0808 October 2013 Generation Plant - Request for Withholding of Proprietary Information from Public Disclosure Associated with Affidavit Executed on March 14, 2013, by Linda C. Dolan of GE-Hitachi Project stage: Withholding Request Acceptance ML13239A0842013-10-0808 October 2013 Generation Plant - Request for Withholding of Proprietary Information from Public Disclosure Associated with Affidavits Executed on March 14, 2013, by Linda Dolan and June 12, 2013, by Kurt Edsinger of Project stage: Withholding Request Acceptance ML13316B1072013-11-0101 November 2013 License Amendment Request Pursuant to 10 CFR 50.90: Maximum Extended Load Line Limit Analysis Plus Project stage: Request ML13337A2892013-11-26026 November 2013 NRR E-mail Capture - Monticello Nuclear Generating Plant - Draft Request for Additional Information Maximum Extended Load Line Limit Analysis Plus LAR Review Project stage: Draft RAI ML13358A3722013-12-20020 December 2013 Maximum Extended Load Line Limit Analysis Plus: Cycle 27 Safety Reload Licensing Report and Request for Additional Information Response Project stage: Request L-MT-13-126, Enclosure 3, GE-MNGP-AEP-3306, Enclosure 2 GEH Response to Mella+ Eicb RAI and Affidavit2013-12-20020 December 2013 Enclosure 3, GE-MNGP-AEP-3306, Enclosure 2 GEH Response to Mella+ Eicb RAI and Affidavit Project stage: Other ML13358A3732013-12-31031 December 2013 Enclosure 1, Reload 26 Cycle 27 Supplemental Reload Licensing Report, 000N0154-SRLR, Revision 5, Extended Power Uprate and Maximum Extended Load Line Limit Plus Project stage: Supplement L-MT-14-023, Maximum Extended Load Line Limit Analysis Plus: Technical Specification Clarifications2014-02-24024 February 2014 Maximum Extended Load Line Limit Analysis Plus: Technical Specification Clarifications Project stage: Other ML14087A0132014-03-28028 March 2014 Safety Evaluation Regarding the Maximum Extended Load Line Limit Plus (Mellla+) Review (non-proprietary Version) Project stage: Approval ML14035A2482014-03-28028 March 2014 Issuance of Amendment No. 180 to Implement Maximum Extended Load Line Limit Analysis Plus (Mellla+) Operating Domain Project stage: Approval ML14141A3992014-05-27027 May 2014 Correction Letter for License Amendment No. 180 Maximum Extended Load Line Limit Plus (Mellla+) Project stage: Other ML14169A0342014-06-13013 June 2014 License Amendment Request Pursuant to 10 CFR 50.90: Maximum Extended Load Line Limit Analysis Plus - Revision 1 Project stage: Request L-MT-16-071, Submittal of 2016 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.462016-12-19019 December 2016 Submittal of 2016 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.46 Project stage: Other 2013-01-31
[Table View] |
Text
@XcelEnergy Monticello Nuclear Generating Plant 2807 W County Rd 75 Monticello, MN 55362 December 20, 2013 L-MT-1 3-126 10 CFR 50.90 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Monticello Nuclear Generating Plant Docket 50-263 Renewed License No. DPR-22
Subject:
Maximum Extended Load Line Limit Analysis Plus: Cycle 27 Safety Reload Licensing Report and Request for Additional Information Response (TAC ME3145)
References:
1)
Letter from T J O'Connor (NSPM), to Document Control Desk (NRC),
"License Amendment Request: Maximum Extended Load Line Limit Analysis Plus," L-MT-10-003, dated January 21, 2010. (ADAMS Accession No. ML1100280558)
- 2)
NEDC-33006P-A, Revision 3, "Licensing Topical Report, General Electric Boiling Water Reactor, Maximum Extended Load Line Limit Analysis Plus," dated June 2009. (ADAMS Accession No. ML091800512)
- 3)
Email from T. Beltz (NRC) to J. Fields (NSPM), "Monticello Nuclear Generating Plant - Draft Request for Additional Information re:
Maximum Extended Load Line Limit Analysis Plus LAR Review (TAC No. ME3145)," dated November 26, 2013.
In Reference 1, Northern States Power Company, a Minnesota corporation (NSPM),
doing business as Xcel Energy, requested approval of an amendment to the Monticello Nuclear Generating Plant (MNGP) Renewed Operating License (OL) and Technical Specifications (TS). The proposed change would allow operation in the expanded Maximum Extended Load Line Limit Analysis Plus (MELLLA+) domain.
Document Control Desk Page 2 The purpose of this letter is to provide the NRC with the MNGP cycle 27 Supplemental Reload Licensing Report (SRLR) applicable to MELLLA+ conditions and evaluations and to provide a response to an NRC Request for Additional Information (RAI). to this letter provides the MNGP cycle 27 SRLR applicable to MELLLA+
conditions and evaluations. The cycle 27 SRLR is being submitted to the NRC to fulfill the requirements of the MELLLA+ topical report (Reference 2), Limitation and Condition 12.4, which specifies that the SRLR for the initial MELLLA+ implementation cycle shall be submitted for NRC staff confirmation.
The SRLR supports the licensing work performed for the MNGP MELLLA+ license.
This reload design was initiated prior to the PRIME transition commitment to utilize PRIME for reload analyses. The cycle-specific reload analyses are based on GESTR-M, with one exception, and the peak clad temperature (PCT) impact of PRIME was evaluated as part of 10 CFR 50.46 Error Notification 2012-01. The one exception is the Detect and Suppress Solution - Confirmation Density (DSS-CD) Backup Stability Protection (BSP) analysis, which was performed using PRIME. The use of PRIME for the DSS-CD BSP analysis is consistent with NEDO-33173 Supplement 4-A, Rev. 1, "Implementation of PRIME Models and Data in Downstream Methods," November 2012. provides a report from General Electric - Hitachi (GEH) letter, GE-MNGP-AEP-3306, "GEH Response to MELLLA+ EICB RAI," which provides a response to the NRC's RAI (Reference 3). Enclosure 2 contains proprietary information. provides a non-proprietary copy of the Enclosure 2 RAI response. The non-proprietary copy of the RAI response is being provided based on the NRC's expectation that the submitter of the proprietary information should provide, if possible, a non-proprietary version of the document with brackets showing where the proprietary information has been deleted. provides an affidavit executed to support withholding Enclosure 2 from public disclosure. Information in Enclosure 2 contains proprietary information as defined by 10 CFR 2.390. The affidavit sets forth the basis on which the information may be withheld from public disclosure by the NRC and addresses with specificity the considerations listed in 10 CFR 2.390(b)(4). Accordingly, NSPM respectfully requests that the proprietary information in Enclosure 2 be withheld from public disclosure in accordance with 10 CFR 2.390(a)4, as authorized by 10 CFR 9.17(a)4.
Correspondence with respect to the copyright or proprietary aspects of GEH information or the supporting GEH affidavit in Enclosure 4 should be addressed to Linda C. Dolan, Manager, Regulatory Compliance, GE-Hitachi Nuclear Energy Americas LLC, 3901 Castle Hayne Road, Wilmington, NC 28401.
Document Control Desk Page 3 The supplemental information provided herein does not change the conclusions of the No Significant Hazards Consideration and the Environmental Consideration evaluations provided in Reference 1 for the MELLLA+ license amendment request.
In accordance-with 10 CFR 50.91 (b), a copy of this application supplement, without enclosures is being provided to the designated Minnesota Official.
Summary of Commitments This letter makes no new commitments and no revisions to existing commitments.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on: Decemberq, 2013 Karen D. Fili Site Vice-President Monticello Nuclear Generating Plant Northern States Power Company-Minnesota Enclosures (4) cc:
Regional Administrator, Region III, USNRC (w/o enclosures)
Project Manager, Monticello Nuclear Generating Plant, USNRC Resident Inspector, Monticello Nuclear Generating Plant, USNRC (w/o enclosures)
Minnesota Department of Commerce (w/o enclosures)