Letter Sequence Draft Other |
|---|
TAC:MD2341, RISK-INFORMED HPSI Aot/Ct Extension - WCAP-15773 (Approved, Closed) TAC:MD2342, RISK-INFORMED HPSI Aot/Ct Extension - WCAP-15773 (Approved, Closed) |
|
MONTHYEARML0604804392006-02-10010 February 2006 Response to NRC RAI on STPNOC Proposed Risk-Informed Technical Specifications Project stage: Request ML0612805912006-04-26026 April 2006 Response to NRC Requests for Additional Information on STPNOC Proposed Risk-Informed Technical Specifications Project stage: Response to RAI ML0700402472006-12-28028 December 2006 Revised Broad Scope Risk-Informed Technical Specification Amendment Request Project stage: Other NOC-AE-06002036, Revised Broad Scope Risk-Informed Technical Specification Amendment Request2006-12-28028 December 2006 Revised Broad Scope Risk-Informed Technical Specification Amendment Request Project stage: Other ML0713502482007-05-0909 May 2007 Response to Request for Additional Information on Risk-Informed Technical Specification Amendment Request Project stage: Response to RAI NOC-AE-07002163, Response to Request for Additional Information on Risk-Informed Technical Specification Amendment Request2007-05-0909 May 2007 Response to Request for Additional Information on Risk-Informed Technical Specification Amendment Request Project stage: Response to RAI ML0714503792007-05-17017 May 2007 Response to NRC Request for Additional Information, Supplement to Revised Broad Scope Risk-Informed Technical Specification Amendment Request Project stage: Supplement ML0714504982007-05-22022 May 2007 Notification of Meeting with South Texas Project Nuclear Operating Company to Present and Discuss Performance Results of the South Texas Station for Period of January 1 Through December 31, 2006 Project stage: Request ML0715502402007-06-0505 June 2007 Notice of Consideration of Issuance of Amendment Re Changes to Technical Specification Limiting Conditions for Operation to Permit Extension of Completion Times of Required Actions (TAC Nos. MD2341 & MD2342) - Ltr & FRN Project stage: Other ML0716201332007-06-11011 June 2007 6/11/07 E-Mail to A. Harrison & S. Head, STPNOC, from M. Thadani, NRR/DORL/LPL4 Re Request for Additional Information Re STPs Request for Spent Fuel Pool & Containment Storage Area Criticality Analysis (TAC MD2342 & MD2344) Project stage: RAI ML0716903342007-06-18018 June 2007 Letter Enclosing Draft Amendments Broad Scope Risk-informed Technical Specifications Project stage: Draft Other ML0716903522007-06-18018 June 2007 Draft, South Texas Project, Units 1 and 2, License Amendment, Issuance of Amendments Broad Scope Risk-informed Technical Specifications Project stage: Draft Approval ML0717801912007-07-13013 July 2007 Technical Specifications, Issuance of Amendment Nos. 179 and 166 Broad-Scope Risk-Informed Technical Specifications Amendments Project stage: Approval ML0717801862007-07-13013 July 2007 License Amendments, Issuance of Amendment Nos. 179 and 166 Broad-Scope Risk-Informed Technical Specifications Amendments Project stage: Approval ML0802200652008-02-0404 February 2008 Correction Letter, Revise License Pg 1 to Remove Owner Name for Amendment Nos. 172-181 for Unit 1 and 160-168 for Unit 2 (TAC Nos. MC4917/18, MC7258/59, MC8224/25, MD3852, MD0934/35, MD5268/69, MD2341/42, MD0333/34, MD4655/56) Project stage: Other ML0921806682009-07-29029 July 2009 License Amendment Request to Revise the Action Requirement for and Inoperable Control Room Envelope Boundary and to Revise the Application of Risk-Managed Technical Specifications to Technical Specification 3.7.7. Project stage: Request NOC-AE-09002441, License Amendment Request to Revise the Action Requirement for and Inoperable Control Room Envelope Boundary and to Revise the Application of Risk-Managed Technical Specifications to Technical Specification 3.7.7...2009-07-29029 July 2009 License Amendment Request to Revise the Action Requirement for and Inoperable Control Room Envelope Boundary and to Revise the Application of Risk-Managed Technical Specifications to Technical Specification 3.7.7... Project stage: Request ML1018701022010-06-28028 June 2010 License Amendment Request to Revise the Action Requirement for an Inoperable Control Room Envelope Boundary to Technical Specification 3.7.7, Control Room Makeup and Cleanup Filtration Systems Project stage: Request ML1021704702010-08-0505 August 2010 Acceptance Review E-mail, License Amendment Request, Revise Action Requirement in Technical Specification 3.7.7, Control Room Makeup and Cleanup Filtration Systems Project stage: Acceptance Review ML1033301722010-11-22022 November 2010 License Amendment Request to Revise the Application of Risk-Managed Technical Specifications to Technical Specification 3.7.7, Control Room Makeup and Cleanup Filtration System Project stage: Request NOC-AE-10002605, License Amendment Request to Revise the Application of Risk-Managed Technical Specifications to Technical Specification 3.7.7, Control Room Makeup and Cleanup Filtration System.2010-11-22022 November 2010 License Amendment Request to Revise the Application of Risk-Managed Technical Specifications to Technical Specification 3.7.7, Control Room Makeup and Cleanup Filtration System. Project stage: Request ML1109501462011-04-25025 April 2011 Issuance of Amendment Nos. 195 and 183, Revise Action Requirement in Technical Specification 3.7.7, Control Room Makeup and Cleanup Filtration Systems Project stage: Approval 2007-06-18
[Table View] |
Text
June 18, 2007 Mr. James J. Sheppard President and Chief Executive Officer STP Nuclear Operating Company South Texas Project Electric Generating Station P. O. Box 330 Wadsworth, TX 77483
SUBJECT:
SOUTH TEXAS PROJECT, UNITS 1 AND 2 - DRAFT AMENDMENTS RE:
BROAD SCOPE RISK-INFORMED TECHNICAL SPECIFICATIONS (TAC NOS.
MD2341 AND MD2342)
Dear Mr. Sheppard:
Enclosed please find the Nuclear Regulatory Commissions staffs draft of our response to your request for amendments to the Technical Specifications (TSs). The response is related to your application dated August 2, 2004, as supplemented by letters dated October 28, 2004, February 10, 2006, and April 26, 2006. You resubmitted your application in its entirety on June 6, 2006, and supplemented the resubmittal by letters dated December 28, 2006, February 28, 2007, May 9, 2007, and May 17, 2007.
The amendments would provide a new action for selected TS limiting conditions for operation to permit extending the completion times of action requirements subject to the requirement that the risk is assessed and managed. The proposed revised TS pages submitted by you are not included in the enclosed draft for comments.
As we discussed on the phone, you agreed to provide comments within 1 week of receipt of this letter. Therefore, we expect to receive your comments by June 27, 2007. If you have any questions, please contact me at (301) 415-1476.
Sincerely,
/RA/
Mohan C. Thadani, Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-498 and 50-499
Enclosure:
As stated cc w/encl: See next page
Pkg ML071690323 (Letter encl draft ML071690334, Draft Amdt. ML071690352)
OFFICE NRR/LPL4/PM NRR/LPL4/LA NRR/LPL4/BC NAME MThadani JBurkhardt THiltz DATE 6/18/07 6/18/07 6/18/07
March 2007 South Texas Project, Units 1 & 2 cc:
Senior Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 289 Wadsworth, TX 77483 C. M. Canady City of Austin Electric Utility Department 721 Barton Springs Road Austin, TX 78704 J. J. Nesrsta/R. K. Temple E. Alercon/Kevin Pollo City Public Service Board P.O. Box 1771 San Antonio, TX 78296 INPO Records Center 700 Galleria Parkway Atlanta, GA 30339-3064 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011 Steve Winn/Christie Jacobs Eddy Daniels/Marty Ryan NRC Energy, Inc.
211 Carnegie Center Princeton, NJ 08540 Judge, Matagorda County Matagorda County Courthouse 1700 Seventh Street Bay City, TX 77414 A. H. Gutterman, Esq.
Morgan, Lewis & Bockius 1111 Pennsylvania Avenue, NW Washington, DC 20004 E. D. Halpin Site Vice President STP Nuclear Operating Company South Texas Project Electric Generating Station P.O. Box 289 Wadsworth, TX 77483 S. M. Head, Manager, Licensing STP Nuclear Operating Company P.O. Box 289, Mail Code: N5014 Wadsworth, TX 77483 C. T. Bowman General Manager, Oversight STP Nuclear Operating Company P.O Box 389 Wadsworth, TX 77483 Marilyn Kistler Sr. Staff Specialist, Licensing STP Nuclear Operating Company P.O. Box 289, Mail Code 5014 Wadsworth, TX 77483 Environmental and Natural Resources Policy Director P.O. Box 12428 Austin, TX 78711-3189 Jon C. Wood Cox, Smith, & Matthews 112 East Pecan, Suite 1800 San Antonio, TX 78205 Director Division of Compliance & Inspection Bureau of Radiation Control Texas Department of State Health Services 1100 West 49th Street Austin, TX 78756
March 2007 South Texas Project, Units 1 & 2 cc:
Mr. Ted Enos 4200 South Hulen Suite 422 Ft. Worth, TX 76109 Brian Almon Public Utility Commission William B. Travis Building P.O. Box 13326 1701 North Congress Avenue Austin, TX 78701-3326 Susan M. Jablonski Office of Permitting, Remediation and Registration Texas Commission on Environmental Quality MC-122 P.O. Box 13087 Austin, TX 78711-3087 Ken Coates Plant General Manager STP Nuclear Operating Company South Texas Project Electric Generating Station P.O. Box 289 Wadsworth, TX 77483 Mr. Terry Parks, Chief Inspector Texas Department of Licensing and Regulation Boiler Division P.O. Box 12157 Austin, TX 78711
March 2007