1 Duke Power NFPA-805 Transition Pilot Observation Project Status Oconee (ONS)
November 10, 2005 ATTACHMENT 11
2 Agenda
Reconstitution Project Status
NFPA-805 Contract Status
NFPA-805 Project Status
Fire PRA Status
Duke 3-Site Transition Schedule
Oconee Transition Schedule
NFPA-805 Project Organization
Near Term Tasks
3 Reconstitution Project Status
All three sites have funding approved with contracts in place
ONS Unit 2 /Common Reconstitution Analysis is complete
MNS currently has AREVA on site performing reconstitution for both units expected completion date of July 2006
ONS currently has AREVA performing reconstitution for ONS Unit 3 with expected completion date of September 2006
CNS currently has AREVA performing reconstitution for both units with expected completion date of July 2007
4 NFPA-805 Contract Status
ONS currently has Kleinsorg Group Risk Services, LLC assisting in performing the NFPA-805 Transition
ONS recently issued a contract to ERIN Engineering & Research, Inc. to assist in performing the Fire PRA in support of the transition to NFPA-805
5 Fire PRA Status
Sub-Task 5.1 - Plant Boundary Definition and Partitioning
Complete. Need to complete documentation. Will be included in the Fire Ignition Frequency Calculation
Sub-Task 5.2 - Fire Ignition Frequencies
95% complete.
Working on Transient Fire Calculation. EPRI/NRC Method is not clear on Categorizing Maintenance Tasks via work orders or hot work.
Comments to EPRI on Bus Bar Explosive Fires
Sub-Task 5.3 - Fire PRA Component Selection
In Progress. Completed BEMAP (PRA to Basic Event Mapping) for Unit 3, working on other 2 units and mapping to Appendix (ARTRAK) database.
Sub-Task 5.4 - Fire PRA Cable Selection
Will start in December. Database design is key.
Sub-Task 5.5 - Qualitative Screening
Not going to perform Qualitative Screening (will quantify all Fire Compartments)
6 Fire PRA Status
Sub-Task 5.6 - Fire-Induced Risk Model
Sub-Task 5.7 - Quantitative Screening
Sub-Task 5.8 - Scoping Fire Modeling
Sub-Task 5.9 - Detailed Circuit Failure Analysis (combined w/
5.10)
Sub-Task 5.10 - Circuit Failure Mode Likelihood Analysis
Sub-Task 5.11 - Detailed Fire Modeling
Sub-Task 5.12 - Post-Fire Human Reliability Analysis
Sub-Task 5.13 - Seismic-Fire Interactions Assessment
Sub-Task 5.14 - Fire Risk Quantification
Sub-Task 5.15 - Uncertainty and Sensitivity Analysis
Sub-Task 5.16 - Fire PRA Documentation
7 Duke 3-Site Transition Schedule ONS MNS CNS 2005 2006 2007 2008 2009 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd ONS NRC Audit MNS NRC Audit CNS NRC Audit (June)
MNS - Reconstitution ONS Unit 0/2 Reconst ONS Unit 3 Reconstitution (July 05 - Sept 06)
ONS Transition to NFPA-805 (March 05 - March 07)
ONS Fire PRA CNS Transition to NFPA-805 CNS Fire PRA CNS - Reconstitution MNS Transition to NFPA-805 MNS Fire PRA
8 Oconee NFPA-805 Transition Schedule
9 NFPA-805 Transition Project Organization George Mc Aninch Project Sponsor Bob Johansen MNS Technical Lead Dennis Henneke NGO PRA Lead Steve Graham Cable Testing Lead Julius Bryant MNS PM Dorothea Mebane MNS FPE Cable Test PM David Goforth CNS Technical Lead James Oldham Fire 3-Site Lead Matt Hogan CNS FPE Jim Jones CNS PM Paul Boulden ONS Technical Lead Expert Panel OPS SRO System Engineer Electrical Engineer Dorothea Mebane MNS FPE Dennis Henneke NGO PRA Lead Steve Alexander ONS PM Harold Lefkowitz ONS FPE Expert Panel OPS SRO System Engineer Electrical Engineer Harold Lefkowitz ONS FPE Dennis Henneke NGO PRA Lead Expert Panel OPS SRO System Engineer Electrical Engineer Matt Hogan CNS FPE Dennis Henneke NGO PRA Lead Cable Test Contractors as necessary NFPA-805 Contractors as necessary Harry Barrett Transition Technical Lead Brandi Weaver NGO PRA Electrical Reene Gambrell RGC Lead RGC Lead TBD PRA Contractors as necessary RGC Lead TBD
10 Near Term Tasks (Next Six Months)
Multiple Spurious Operations Expert Panel
Armored Cable Fire Testing (1st Qtr 2006)
Chapter 3 Non-Fire Area Specific Transition
Transient Analysis
Manual Action Feasibility
CAFTA Logic Pilot