LCO Applicability 3.0 3.0 LIMITING CONDITION FOR OPERATION (LCO) APPLICABILITY LCO 3.0.1 LCOs shall be met during the MODES or other specified conditions in the Applicability, except as provided in LCO 3.0.2 and LCO 3.0.7.

LCO 3.0.2 Upon discovery of a failure to meet an LCO, the Required Actions of the associated Conditions shall be met, except as provided in LCO 3.0.5 and LCO 3.0.6.

If the LCO is met or is no longer applicable prior to expiration of the specified Completion Time(s), completion of the Required Action(s) is not required, unless otherwise stated.

LCO 3.0.3 When an LCO is not met and the associated ACTIONS are not met, an associated ACTION is not provided, or if directed by the associated ACTIONS, the unit shall be placed in a MODE or other specified condition in which the LCO is not applicable.

Action shall be initiated within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> to place the unit, as applicable, in:

a. MODE 2 within 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br />;
b. MODE 3 within 13 hours1.50463e-4 days <br />0.00361 hours <br />2.149471e-5 weeks <br />4.9465e-6 months <br />; and
c. MODE 4 within 37 hours4.282407e-4 days <br />0.0103 hours <br />6.117725e-5 weeks <br />1.40785e-5 months <br />.

Exceptions to this Specification are stated in the individual Specifications.

Where corrective measures are completed that permit operation in accordance with the LCO or ACTIONS, completion of the actions required by LCO 3.0.3 is not required.

LCO 3.0.3 is only applicable in MODES 1, 2, and 3.

LCO 3.0.4 When an LCO is not met, entry into a MODE or other specified condition in the Applicability shall only be made:

a. When the associated ACTIONS to be entered permit continued operation in the MODE or other specified condition in the Applicability for an unlimited period of time; (continued)

Columbia Generating Station 3.0 -1 Amendment No. 149,169,187

LCO Applicability 3.0 3.0 LCO APPLICABILITY LCO 3.0.4 (continued)

b. After performance of a risk assessment addressing inoperable systems and components, consideration of the results, determination of the acceptability of entering the MODE or other specified condition in the Applicability, and establishment of risk management actions, if appropriate; exceptions to this Specification are stated in the individual Specifications, or
c. When an allowance is stated in the individual value, parameter, or other Specification.

This Specification shall not prevent changes in MODES or other specified conditions in the Applicability that are required to comply with ACTIONS or that are part of a shutdown of the unit.

LCO 3.0.5 Equipment removed from service or declared inoperable to comply with ACTIONS may be returned to service under administrative control solely to perform testing required to

,demonstrate its OPERABILITY or the OPERABILITY of other equipment.

This is an exception to LCO 3.0.2 for the system returned to service under administrative control to perform the testing required to demonstrate OPERABILITY.

LCO 3.0.6 When a supported system LCO is not met solely due to a support system LCO not being met, the Conditions and Required Actions associated with this supported system are not required to be entered.

Only the support system LCO ACTIONS are required to be entered.

This is an exception to LCO 3.0.2 for the supported system.

In this event, additional evaluations and limitations may be required in accordance with Specification 5.5.11, "Safety Function Determination Program (SFDP)."

If a loss of safety function is determined to exist by this program, the appropriate Conditions and Required Actions of the LCO in which the loss of safety function exists are required to be entered.

When a support system's Required Action directs a supported system to be declared inoperable or directs entry into Conditions and Required Actions for a supported system, the applicable Conditions and Required Actions shall be entered in accordance with LCO 3.0.2.

(continued)

Columbia Generating Station 3.0- 2 Amendment No. 149,169,187

SR Applicability 3.0 3.0 SR APPLICABILITY SR 3.0.3 (continued)

When the Surveillance is performed within the delay period and the Surveillance is not met, the LCO must immediately be declared not met, and the applicable Condition(s) must be entered.

SR 3.0.4 Entry into a MODE or other specified condition in the Applicability of an LCO shall only be made when the LCO's Surveillances have been met within their specified Frequency, except as provided by SR 3.0.3.

When an LCO is not met due to Surveillances not having been met, entry into a MODE or other specified condition in the Applicability shall only be made in accordance with LCO 3.0.4.

This provision shall not prevent entry into MODES or other specified conditions in the Applicability that are required to comply with ACTIONS or that are part of a shutdown of the unit.

Columbia Generating Station 3.0- 5 Amendment No. 149d,169,18,187

PAM Instrumentation 3.3.3.1 3.3 INSTRUMENTATION 3.3.3.1 Post Accident Monitoring (PAM) Instrumentation LCO 3.3.3.1 APPLICABILITY:

The PAM instrumentation for each Function in Table 3.3.3.1-1 shall be OPERABLE.

MODES 1 and 2.

ACTIONS


NOTE-------------------------------------

Separate Condition entry is allowed for each Function.

I CONDITION REQUIRED ACTION COMPLETION TIME A. One or more Functions A.1 Restore required 30 days with one required channel to OPERABLE channel inoperable.

status.

B. Required Action and B.1 Initiate action in Immediately associated Completion accordance with Time of Condition A Specification 5.6.6.

not met.

C. One or more Functions C.1 Restore all but one 7 days with two or more required channel to required channels OPERABLE status.

inoperable.

(continued)

Columbia Generating Station 3.3.3. 1-1 Amendment No. 149.169,187

PAM Instrumentation 3.3.3.1 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME D. Required Action and D.1 Enter the Condition Immediately associated Completion referenced in Time of Condition C Table 3.3.3.1-1 for not met.

the channel.

E. As required by E.1 Be in MODE 3.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> Required Action D.1 and referenced in Table 3.3.3.1-1.

F. As required by F.1 Initiate action in Immediately Required Action D.1 accordance with and referenced in Specification 5.6.6.

Table 3.3.3.1-1.

Columbia Generating Station 3.3.3.1-2 Amendment No. +4-9 169

Remote Shutdown System 3.3.3.2 3.3 INSTRUMENTATION 3.3.3.2 Remote Shutdown System LCO 3.3.3.2 APPLICABILITY:

The Remote Shutdown System Functions shall be OPERABLE.

MODES 1 and 2.

ACTIONS


NOTE---------------------

Separate Condition entry is allowed for each Function.

I CONDITION REQUIRED ACTION COMPLETION TIME A. One or more required A.1 Restore required 30 days Functions inoperable.

Function to OPERABLE status.

B.. Required Action and B.1 Be in MODE 3.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> associated Completion Time not met.

Columbia Generating Station 3.3.3.2-1 Amendment No. 149,169,187

Remote Shutdown System 3.3.3.2 SURVEILLANCE REQUIREMENTS NOTE-------------------------------------

When a channel is placed in an inoperable status solely for performance of required Surveillances, entry into associated Conditions and Required Actions may be delayed for up to 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.

SURVEILLANCE FREQUENCY SR 3.3.3.2.1 Perform CHANNEL CHECK for each required 31 days instrumentation channel that is normally energized.

SR 3.3.3.2.2 Perform CHANNEL CALIBRATION for each 18 months required instrumentation channel, except the suppression pool water level instrumentation channel.

SR 3.3.3.2.3 Perform CHANNEL CALIBRATION for the 24 months suppression pool water level instrumentation channel.

SR 3.3.3.2.4 Verify each required control circuit and 24 months transfer switch is capable of performing the intended functions.

Columbia Generating Station 3.3.3. 2-2 Amendment No.

4-4-9 169

CREF System Instrumentation 3.3.7.1 ACTIONS I

CONDITION REQUIRED ACTION COMPLETION TIME E. As required by Required Action A.1 and referenced in Table 3.3.7.1-1.

E.1


NOTE----

Enter applicable Conditions and Required Actions of LCO 3.7.3, "Control Room Emergency Filtration (CREF)

System," when both remote air intakes are isolated.

I Isolate the associated remote air intake.

AND 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from discovery of loss of radiation monitoring capability in a remote air intake 7 days from discovery of inoperable channels associated with both remote air intakes AND E.2 Restore channel to OPERABLE status.

1 30 days F. Required Action and F.1 Declare both CREF Immediately associated Completion subsystems Time of Condition E inoperable.

not met.

Columbia Generating Station 3.3.7.1-3 Amendment No.

449.169,187

CREF System Instrumentation 3.3.7.1 SURVEILLANCE REQUIREMENTS I


NOTES------------------------------------

1. Refer to Table 3.3.7.1-1 to determine which SRs apply for each CREF System Function.
2. When a channel is placed in an inoperable status solely for performance of required Surveillances, entry into associated Conditions and Required Actions may be delayed for up to 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> provided the associated Function maintains CREF initiation or radiation monitoring capability, as applicable.

SURVEILLANCE FREQUENCY SR 3.3.7.1.1 Perform CHANNEL CHECK.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> SR 3.3.7.1.2 Perform CHANNEL FUNCTIONAL TEST.

92 days SR 3.3.7.1.3 Perform CHANNEL CALIBRATION.

18 months SR 3.3.7.1.4 Perform LOGIC SYSTEM FUNCTIONAL TEST.

24 months Columbia Generating Station 3.3.7.1 -4 Amendment No.

149,16 187

RCS Leakage Detection Instrumentation 3.4.7 3.4 REACTOR COOLANT SYSTEM (RCS) 3.4.7 RCS Leakage Detection Instrumentation LCO 3.4.7 The following RCS leakage detection instrumentation shall be OPERABLE:

a.

Drywell floor drain sump flow monitoring system; and

b.

One channel of either drywell atmospheric particulate or atmospheric gaseous monitoring system.

APPLICABILITY:

MODES 1, 2, and 3.

ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. Drywell floor drain A.1 Restore drywell floor 30 days sump flow monitoring drain sump flow system inoperable.

monitoring system to OPERABLE status.

B. Required drywell B.1 Analyze grab samples Once per atmospheric monitoring of drywell 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> system inoperable.

atmosphere.

AND 8.2 Restore required 30 days drywell atmospheric monitoring system to OPERABLE status.

(continued)

I Columbia Generating Station 3.4.7 -1 Amendment No. 149.169,187

RCS Leakage Detection Instrumentation 3.4.7 I

ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME C. Required Action and C.1 Be in MODE 3.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> associated Completion Time of Condition A or AND B not met.

C.2 Be in MODE 4.

36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> D. All required leakage D.1 Enter LCO 3.0.3.

Immediately detection systems inoperable.

Columbia Generating Station 3.4.7 -2 Amendment No. 449-165;187

RCS Specific Activity 3.4.8 3.4 REACTOR COOLANT SYSTEM (RCS) 3.4.8 RCS Specific Activity LCO 3.4.8 APPLICABILITY:

The specific activity of the reactor coolant shall be limited to DOSE EQUIVALENT I-131 specific activity

< 0.2 pCi/gm.

MODE 1.

MODES 2 and 3 with any main steam line not isolated.

ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. Reactor coolant


NOTE------------

specific activity LCO 3.0.4.c is applicable.

> 0.2 pCi/gm and

< 4.0 pCi/gm DOSE EQUIVALENT 1-131.

A.1 Determine DOSE Once per 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> EQUIVALENT 1-131.

AND A.2 Restore DOSE 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> EQUIVALENT 1-131 to within limits.

B. Required Action and B.1 Determine DOSE Once per 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> associated Completion EQUIVALENT I-131.

Time of Condition A not met.

AND OR B.2.1 Isolate all main 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> steam lines.

Reactor coolant specific activity OR

> 4.0 pCi/gm DOSE EQUIVALENT 1-131.

(continued)

I Columbia Generating Station 3.4.8-1 Amendment No.

149,169.187

RCS Specific Activity 3.4.8 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME B. (continued)

B.2.2.1 Be in MODE 3.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> AND B.2.2.2 Be in MODE 4.

36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.4.8.1


NOTE--------------------

Only required to be performed in MODE 1.

Verify reactor coolant DOSE 7 days EQUIVALENT 1-131 specific activity is

< 0.2 pCi/gm.

Columbia Generating Station 3.4.8-2 Amendment No.

4-4-9 169

RHR Shutdown Cooling System -

Hot Shutdown 3.4.9 3.4 REACTOR COOLANT SYSTEM (RCS) 3.4.9 Residual Heat Removal (RHR) Shutdown Cooling System -

Hot Shutdown LCO *3.4.9 Two RHR shutdown cooling subsystems shall be OPERABLE, and, with no recirculation pump in operation, at least one RHR shutdown cooling subsystem shall be in operation.

NOTES---------------------------

1.

Both RHR shutdown cooling subsystems and recirculation pumps may be removed from operation for up to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> per 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> period.

2.

One RHR shutdown cooling subsystem may be inoperable for up to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> for performance of Surveillances.

APPLICABILITY:

MODE 3 with reactor steam dome pressure less than 48 psig.

ACTIONS


NOTE-------------------------------------

Separate Condition entry is allowed for each RHR shutdown cooling subsystem.

I CONDITION REQUIRED ACTION COMPLETION TIME A. One or two RHR A.1 Initiate action to Immediately shutdown cooling restore RHR shutdown subsystems inoperable.

cooling subsystem to OPERABLE status.

AND (continued)

Columbia Generating Station 3.4.9-1 Amendment No. 149164

.169,187

RHR Shutdown Cooling System -

Hot Shutdown 3.4.9 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. (continued)

A.2 Verify an alternate 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> method of decay heat removal is available for each inoperable RHR shutdown cooling subsystem.

AND A.3 Be in MODE 4.

24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> B. No RHR shutdown B.1 Initiate action to Immediately cooling subsystem in restore one RHR operation.

shutdown cooling subsystem or one AND recirculation pump to operation.

No recirculation pump in operation.

AND B.2 Verify reactor 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from coolant circulation discovery of no by an alternate reactor coolant method.

circulation AND Once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> thereafter AND B.3 Monitor reactor Once per hour coolant temperature and pressure.

Columbia Generating Station 3.4.9-2 Amendment No.

4-44 169

ECCS - Operating 3.5.1 3.5 EMERGENCY CORE COOLING SYSTEMS (ECCS) AND REACTOR CORE ISOLATION COOLING (RCIC) SYSTEM 3.5.1 ECCS - Operating LCO 3.5.1 APPLICABILITY:

Each ECCS injection/spray subsystem and the Automatic Depressurization System (ADS) function of six safety/relief valves shall be OPERABLE.

MODE 1.

MODES 2 and 3, except ADS valves are not required to be OPERABLE with reactor steam dome pressure < 150 psig.

ACTIONS


NOTE-------------------------------------

LCO 3.0.4.b is not applicable to HPCS.

I CONDITION REQUIRED ACTION COMPLETION TIME A. One low pressure ECCS A.1 Restore low pressure 7 days injection/spray ECCS injection/spray subsystem inoperable.

subsystem to OPERABLE status.

B. High Pressure Core B.1 Verify by Immediately Spray (HPCS) System administrative means inoperable.

RCIC System is OPERABLE when RCIC System is required to be OPERABLE.

AND B.2 Restore HPCS System 14 days to OPERABLE status.

(continued)

Columbia Generating Station 3.5.1 -1 Amendment No. 149,169,187

ECCS - Operating 3.5.1 ACTIONS I

CONDITION REQUIRED ACTION COMPLETION TIME C. Two ECCS injection C.1 Restore one ECCS 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> subsystems inoperable.

injection/spray subsystem to OPERABLE OR status.

One ECCS injection and one ECCS spray subsystem inoperable.

D. Required Action and D.1 Be in MODE 3.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> associated Completion Time of Condition A, AND B. or C not met.

D.2 Be in MODE 4.

36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> E. One required ADS valve E.1 Restore ADS valve to 14 days inoperable.

OPERABLE status.

F. One required ADS valve F.1 Restore ADS valve to 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> inoperable.

OPERABLE status.

AND OR One low pressure ECCS F.2 Restore low pressure 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> injection/spray ECCS injection/spray subsystem inoperable.

subsystem to OPERABLE status.

(continued)

Columbia Generating Station

3. 5. 1-2 Amendment No.

4-4-9 169'

RCIC System 3.5.3 3.5 EMERGENCY CORE COOLING SYSTEMS (ECCS) AND REACTOR CORE ISOLATION COOLING (RCIC) SYSTEM 3.5.3 RCIC System LCO 3.5.3 APPLICABILITY:

The RCIC System shall be OPERABLE.

MODE 1, MODES 2 and 3 with reactor steam dome pressure > 150 psig.

ACTIONS


NOTE-------------------------------------

LCO 3.0.4.b is not applicable to RCIC.

I CONDITION REQUIRED ACTION COMPLETION TIME A. RCIC System A.1 Verify by Immediately inoperable.

administrative means High Pressure Core Spray System is OPERABLE.

AND A.2 Restore RCIC System 14 days to OPERABLE status.

B. Required Action and B.1 Be in MODE 3.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> associated Completion Time not met.

AND B.2 Reduce reactor steam 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> dome pressure to

< 150 psig.

Columbia Generating Station

3. 5.3 -1 Amendment No. 149d1'0,169,187

RCIC System 3.5.3 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.5.3.1 Verify the RCIC System piping is filled 31 days with water from the pump discharge valve to the injection valve.

SR 3.5.3.2 Verify each RCIC System manual, power 31 days operated, and automatic valve in the flow path, that is not locked, sealed, or otherwise secured in position, is *in the correct position.

SR 3.5.3.3 -----

NOTE--------------------

Not required to be performed until 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after reactor steam pressure and flow are adequate to perform the test.

Verify, with reactor pressure < 1035 psig 92 days and > 935 psig, the RCIC pump can develop a flow rate 2 600 gpm against a system head corresponding to reactor pressure.

SR 3.5.3.4


NOTE--------------------

Not required to be performed until 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after reactor steam pressure and flow are adequate to perform the test.

Verify, with reactor pressure < 165 psig, 24 months the RCIC pump can develop a flow rate

> 600 gpm against a system head corresponding to reactor pressure.

(continued)

Columbia Generating Station 3.5.3-2 Amendment No. 149.15O 169

Primary Containment Hydrogen Recombiners 3.6.3.1 I

3.6 CONTAINMENT SYSTEMS 3.6.3.1 Primary Containment Hydrogen Recombiners LCO 3.6.3.1 Two primary OPERABLE.

containment hydrogen recombiners shall be APPLICABILITY:

MODES 1 and 2.

ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. One primary A.1 Restore primary 30 days containment hydrogen containment hydrogen recombiner inoperable.

recombiner to OPERABLE status.

B. Two primary B.1 Verify by 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> containment hydrogen administrative means recombiners that the hydrogen and AND inoperable.

oxygen control function is Once per maintained.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> thereafter AND 8.2 Restore one primary 7 days containment hydrogen recombiner to OPERABLE status.

C. Required Action and C.1 Be in MODE 3.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> associated Completion Time not met.

I Columbia Generating Station 3.6.3. 1-1 Amendment No. 149.169,187

Primary Containment Hydrogen Recombiners 3.6.3.1 I

SURVEILLANCE REQUIREMENTS.

SURVEILLANCE FREQUENCY SR 3.6.3.1.1 Perform a system functional test for each 24 months primary containment hydrogen recombiner.

SR 3.6.3.1.2 Visually examine each primary containment 24 months hydrogen recombiner enclosure and verify there is n6 evidence of abnormal conditions.

SR 3.6.3.1.3 Perform a resistance to ground test for 24 months each heater phase.

Columbia Generating Station 3.6.3. 1-2 Amendment No.

149.169,187

Primary Containment Atmosphere Mixing System 3.6.3.2 3.6 CONTAINMENT SYSTEMS 3.6.3.2 Primary Containment Atmosphere Mixing System LCO 3.6.3.2 APPLICABILITY:

Two head area return fans shall be OPERABLE.

MODES 1 and 2.

ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. One head area return A.1 Restore head area 30 days fan inoperable.

return fan to OPERABLE status.

B. Two head area return B.1 Verify by 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> fans inoperable.

administrative means that the hydrogen and oxygen control function is maintained.

AND B.2 Restore one head area 7 days return fan to OPERABLE status.

C. Required Action and C.1 Be in MODE 3.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> associated Completion Time not met.

I Columbia Generating Station 3.6.3.2 -1 Amendment No. 149.169,187

Primary Containment Atmosphere Mixing System 3.6.3.2 SURVEILLANCE REQUIREMENTS_

SURVEILLANCE FREOUENCY SR 3.6.3.2.1 Operate each head area return fan for 92 days

> 15 minutes.

Columbia Generating Station 3.6.3.2-2 Amendment No. b4-4 169'

AC Sources - Operating 3.8.1 3.8 ELECTRICAL POWER SYSTEMS 3.8.1 AC Sources-Operating LCO 3.8.1 The following AC electrical power sources shall be OPERABLE:

a.

Two qualified circuits between the offsite transmission network and the onsite Class lE AC Electric Power Distribution System; and

b.

Three diesel generators (MGs).

APPLICABILITY:

MODES 1. 2, and 3.

NOTE---------------

Division 3 AC electrical power sources are not required to be OPERABLE when High Pressure Core Spray System is inoperable.

ACTIONS


NOTE------------------------

LCO 3.0.4.b is not applicable to DGs.

I CONDITION REQUIRED ACTION COMPLETION TIME A. One offsite circuit A.1 Perform SR 3.8.1.1 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> inoperable.

for OPERABLE offsite circuit.

AND Once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter AND (continued)

Columbia Generating Station 3.8.1-1 Amendment No. -149.169,187

AC Sources -Operating 3.8.1 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. (continued)

A.2 Declare required 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> from feature(s) with no discovery of no offslte power offsite power available inoperable to one division when the redundant concurrent with required feature(s) inoperability are inoperable.

of redundant required feature(s)

AND A.3 Restore offsite 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> circuit to OPERABLE status.

AND 6 days from discovery of failure to meet LCO B. One required DG B.1 Perform SR 3.8.1.1 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> inoperable.

for OPERABLE offsite circuit(s).

AND Once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter AND (continued)

Columbia Generating Station 3.8. 1-2 Amendment No. +4-4 169