ES-301 Control Room Systems and Facility Walk-Throuah Test Outline Facility: FENOC BVPS Unit 2 Date of Examination: 5/29/01 Exam Level (circle one): RO / SRO([) / SRO(U)
Operating Test No.: 2LOT3 B.1 Control Room Systems System / JPM Title Type Code*
Safety Function
- 1.
Emergency Borate the Reactor Coolant System [Faulted]
S, M, A 3
- 2.
Block SI Following a Loss of Heat Sink [Faulted]
S, M, A 4
- 3.
Respond to Radiation Monitor Alarm - Leak Collection S, D, A 9
Tank [Faulted]
- 4.
Initiate a Natural Circulation Cooldown per ES-0.2 S, M, A 2
[Faulted]
- 5.
Calculate and Restore Containment Air Partial Pressure S, N 5
- 6.
Energize 4KV Emergency Bus 2AE From Offsite Power S, D 6
- 7.
Respond To Failed Power Range Channel N-44 S, D 7
B.2 Facility Walk-Through
- 8.
Isolate AFW During Alternate Safe Shutdown D, R 8
[Abnormal Task]
- 9.
Startup A Rod Drive MG Set D
1
- 10. Shutdown Uninterruptible Power Supply [UPS*VITBS2-3]
D 6
- Type Codes: (D)irect from bank, (M)odified from bank, (N)ew, (A)lternate path, (C)ontrol Room, (S)imulator, (L)ow-Power, (R)CA 2LOT3 Rev. 3 Form ES-301-2
RTL#A5.640U 1/2-ADM-1303.F02 Page I of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-511 JPM REVISION: 3a JPM TITLE: Emergency Borate the Reactor Coolant System (Faulted)
K/A
REFERENCE:
006A1.11 3.1/3.4 TASK ID:
0071-039-01-013 JPM APPLICATION:
[-
REQUALIFICATION
[
INITIAL EXAM
[F] TRAINING
] FAULTED JPM
-- ADMINISTRATIVE JPM EVALUATION METHOD:
LOCATION:
TYPE:
ADMINISTERED BY:
[E Perform Plant Site Annual Requal Exam BVT F[1 Simulate E
Simulator Z
Initial Exam Z
NRC E] Classroom E-OJT/TPE
-] Other:
E] Training E] Other:
S~EVALUATION RESULTS Performer Name:
Performer SSN:
Time
'-1Yes Allotted 15 minutes Actual minutes Critical:
Z No Time:
Time:
UNSAT (Comments required for UNSAT evaluation)
Comments:
OBSERVERS Name/SSN:
Name/SSN:
Name/SSN:
Name/SSN:
EVALUATOR Evaluator (Print):
Date:
Evaluator Signature:
I
RTL#A5.640U 1/2-ADM-1303.F02 Page 2 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-511 "JPM REVISION: 3a JPM TITLE: Emergency Borate the Reactor Coolant System (Faulted)
EVALUATOR DIRECTION SHEET TASK STANDARD:
RECOMMENDED STARTING LOCATION:
DIRECTIONS:
INITIAL CONDITIONS:
INITIATING CUE:
REFERENCES:
TOOLS:
Emergency boration is established to the Reactor Coolant System at a flow greater than 30 gpm.
Control Room You are to simulate (perform) the task of initiating emergency boration of the RCS.
The plant was at 100% power when an inadvertent dilution occurred.
The CVCS system is in operation with all components in their normal operating alignment.
Your Supervisor directs you initiate emergency boration of the RCS in accordance with the operating procedure at a flow rate greater than 30 gpm.
20M-7.4.Q Issue 4, Rev. 6 None.
20M-7.4.Q Issue 4, Rev. 6 I
HANDOUT:
RTL#A5.640U OPERATIONS JOB PERFORMANCE MEASURE 1/2-ADM-1303.F02 Page 3 of 8 Revision 0 Read:
CANDIDATE DIRECTION SHEET THIS SHEET TO BE GIVEN TO CANDIDATE Emergency borate the Reactor Coolant System.
INITIAL CONDITIONS:
The plant was at 100% power when an inadvertent dilution occ The CVCS system is in operation with all components in their r operating alignment.
INITIATING CUE:
Your Supervisor directs you initiate emergency boration of the accordance with the operating procedure at a flow rate greater gpm.
El At this time, ask the evaluator any questions you have on this JPM.
El When satisfied that you understand the assigned task, announce "I am now beginning the J j-Simulate performance or perform as directed the required task.
Point to any indicator or component you verify or check and announce your observations.
After determining the Task has been met announce " I have completed the JPM".
Then hand this sheet to the evaluator.
urred.
iormal RCS in than 30 PM1.
M1 TASK:
RTL#A5.640U 1/2-ADM-1303.F02 Page 4 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-511 JPM TITLE:
Borate the Reactor Coolant S JPM REVISION: 3a E
B t
STEP STANDARD
("C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)=* S/U 2~~'~
\\~.
'~~ ~
START TIVIE: ________
Setup: Initialize IC-176.
- 1. Candidate obtains procedure, 2GM-
- 1.
Candidate locates 20M-7.4.Q, Emergency Boration.
7.4.Q, Emergency Boration.
COMMENTS:
- 2. Open [2CHS*MOV350], Emergency 2.1 Candidate locates [2CHS*MOV350].
Boration Isolation Valve.
2.2 Candidate takes [2CHS*MOV350] Control Switch to OPEN.
SIMULATED CUE: Green light is lit.
EVALUATOR NOTE: If asked, state that all other attempts to open the valve fail.
COMMENTS:
RTL#A5.640U 1/2-ADM-1303..F02 Page 5 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-511
"-A JPM REVISION: 3a JPM TITLE: Emergency Borate the Reactor Coolant System STEP STANDARD
("C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)=>
S/U 3.C Open [2CHS*SOV206] Alternate 3.1 Candidate identifies abnormal conditions and refers to Part B of Emergency Boration Valve, procedure.
NOTE: FAULTED PATH 3.2 Candidate locates control switch for [2CHS*SOV206].
3.3.C Candidate turns switch to the OPEN position.
3.4 Candidate verifies red light lit.
SIMULATED CUE: [2CHS*SOV206] red light is lit.
COMMENTS:
4.C Place Makeup Mode Selector Switch 4.C Candidate turns Makeup Mode Selector Switch to the BORATE to BORATE.
position.
COMMENTS:
5.C Set Boric Acid To Blender Flow 5.1 Candidate locates Boric Acid To Blender Flow Totalizer.
Totalizer to a makeup volume of at least 1000 gallons.
5.2C Candidate sets Boric Acid To Blender Flow Totalizer to 1000 gallons or greater.
COMMENTS:
I
RTL#A5.640U 1/2-ADM-1303.F02 Page 6 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-511 JPM TITLE: Emergency Borate the Reactor Coolant System "I JPM REVISION: 3a STEP STANDARD
( "C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)zz SIU 6.C Place the Boric Acid Makeup 6.1 Candidate locates the Boric Acid Makeup Blender Control Blender Control Switch to the Switch.
START position.
6.2.C Candidate places control switch to the START position.
6.3 Candidate verifies red light lit.
SIMULATED CUE: If asked, red light is lit.
COMMENTS:
EVALUATOR NOTE: If asked, [2CHS*P22A] is the in-service boric acid pump.
- 7.
Check the inservice boric acid transfer
- 7.
Candidate identifies the inservice boric acid pump and explains pump starts.
that the control switch would be verified in AUTOMATIC and the pump should start.
SIMULATED CUE: Pump red light is lit.
COMMENTS:
I
RTL#A5.640U 1/2-ADM-1303.F02 Page 7 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-51 1 JPM TITLE: Emergency Borate the Reactor Coolant System 1PM REVISION: 3a STEP STANDARD
( "C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)=*
S/U 8.C Place [2CHS*FCV113A], Boric Acid 8.1 Candidate locates [2CHS*FCV1 13A] control station.
to Blender Control Station in MAN and full OPEN.
8.2C Candidate places control station in MAN and full OPEN.
8.3 Candidate verifies that the demand indicator moves to the open direction.
SIMULATED CUE: [2CHS*FCV113A] demand indicator is at 0, full OPEN.
COMMENTS:
9.C Place [2CHS*FCV1l3B], Boric Acid 9.1 Candidate locates [2CHS*FCV1 13B].
Blender Disch To Chg Pumps control switch to CLOSE.
9.2.C Candidate places control switch to CLOSE.
9.3 Candidate verifies valve closed indication.
SIMULATED CUE: [2CHS*FCV1 13B] green light is lit.
COMMENTS:
I
RTL#A5.640U 1/2-ADM-1303.F02 Page 8 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE "JP NU BR CI1 JPM NUMBER: 2CR-511 JPM TITLE: Emergency Borate the Reactor Coolant System SJPM REVISION: 3a STEP STANDARD
( "C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)=>
S/U
- 10. Check [2CHS-FR1 13], Boric Acid to 10.1 Candidate locates [2CHS-FR113] (VB-A).
Blender Flow Recorder red pen indicates full scale (> 40 gpm boric acid 10.2 Candidate verifies flow is > 40 GPM.
flow).
SIMULATED CUE: [2CHS-FRl 13] indicates > 40 gpm boric acid flow.
COMMENTS:
- 11. Verify [2CHS*FI122] Charging Line Flow indicates > 40 gpm flow.
11.1 Candidate locates [2CHS*FI122].
11.2 Candidate verifies flow is > 40 gpm.
SIMULATED CUE: [2CHS*FI122] indicates 100 gpm flow.
COMMENTS:
STOP TIME: _
RTL#A5.640U 1/2-ADM-1303.F02 Page 1 of 9 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-H 1N JPM TITLE: Block SI Following a Loss of Heat Sink (Faulted)
IJPM REVISION: 0 K/A
REFERENCE:
E05 EAI.1 4.1/4.0 TASK ID:
0533-006-05-013 JPM APPLICATION:
REQUALIFICATION Z
INITIAL EXAM F] TRAINING Z
FAULTED JPM F] ADMINISTRATIVE JPM EVALUATION METHOD:
LOCATION:
TYPE:
ADMINISTERED BY:
Z Perform E] Plant Site
--] Annual Requal Exam BVT F
Simulate Z
Simulator Z
Initial Exam Z
NRC F-- Classroom
-- OJT/TPE F-] Other:
Training E-] Other:
I EVALUATION RESULTS Performer Name:
Performer SSN:
STime F--1 Yes Allotted 20 minutes
]Actual minutes Critical:
Z No Time:
Time:
El UNSAT (Comments required for UNSAT evaluation)
Comments:
OBSERVERS Name/SSN:
]Name/SSN:
Name/SSN:
Name/SSN:
EVALUATOR Evaluator (Print):
Date:
Evaluator Signature:
I
RTL#A5.640U 1/2-ADM-1303.F02 Page 2 of 9 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE "JPM NUMBER: 2CR-uN JPM TITLE: Block SI Following a Loss of Heat Sink (Faulted)
I JPM REVISION: 0 EVALUATOR DIRECTION SHEET TASK STANDARD:
RECOMMENDED STARTING LOCATION:
DIRECTIONS:
INITIAL CONDITIONS:
INITIATING CUE:
REFERENCES:
TOOLS:
Safety injection is blocked as indicated by annunciators A12-1B and A12-1A.
Control Room You are to simulate (perform) the task of blocking safety injection.
The plant was tripped from 100% power when a loss of all feedwater occurred. The crew entered E-0 and transitioned to FR-H. 1, which is currently in progress and completed through Step 4.
Your Supervisor directs you continue with FR-H. 1 at Step 5 and block safety injection.
FR-H.1 Issue 1B, Rev. 6 None.
FR-H.1 Issue 1B, Rev. 6 HANDOUT:
l I
RTL#A5.640U 1/2-ADM-1303.F02 Page 3 of 9 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE CANDIDATE DIRECTION SHEET THIS SHEET TO BE GIVEN TO CANDIDATE Read:
You are to simulate (perform) the task of blocking safety injection.
INITIAL CONDITIONS:
INITIATING CUE:
The plant was tripped from 100% power when a loss of all feedwater occurred. The crew entered E-0 and transitioned to FR-H. 1, which is currently in progress, and completed through Step 4.
Your Supervisor directs you continue with FR-H. 1 at Step 5 and block safety injection.
D7 At this time, ask the evaluator any questions you have on this JPM.
When satisfied that you understand the assigned task, announce "I am now beginning the JPM".
m Simulate performance or perform as directed the required task.
Point to any indicator or component you verify or check and announce your observations.
After determining the Task has been met announce " I have completed the JPM".
Then hand this sheet to the evaluator.
TASK:
RTL#A5.640U 1/2-ADM-1303.F02 Page 4 of 9 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-HIN "JPM REVISION: 0 JPM TITLE: Block SI Following a Loss of Heat Sink Accident STEP STANDARD
("C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)==
SlU START TIME:
Setup: Initialize IC-175. Place RDT on [2FWS-P24]
SG Startup Feed Pump control switch.
- 1. Candidate obtains procedure FR-H. 1.
- 1.
Candidate locates procedure FR-H. 1.
EVALUATOR CUE: Provide Candidate a copy of procedure FR-H. 1.
COMMENTS:
- 2.
Check if SI is in service.
2.1 Candidate locates [2SIS*FI945 (946)] and verifies no LHSI flow indicated.
2.2 Candidate locates [2SIS*FI940 (943)] and verifies no HIHSI flow indicated.
COMMENTS:
- 3. Set steam dumps in AUTO mode.
3.1 Candidate locates [2MSS*PK464] and adjusts above existing steam header pressure.
3.2 Candidate verifies [2MSS*PK464] in AUTO.
3.3 Candidate verifies steam dump control mode selector switch in STM PRESS position.
COMMENTS:
l I
RTL#A5.640U 1/2-ADM-1303..F02 Page 5 of 9 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-HIN
"- JPM REVISION: 0 JPM TITLE: Block SI Following a Loss of Heat Sink Accident STEP STANDARD
("C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)==
S/U EVALUATOR NOTE: RCP's may be stopped in any order.
4.C STOP all RCP's.
4.1 Candidate locates control switch for [2RCS*P21A].
4.2.C Candidate turns [2RCS*P21A] control switch to the STOP position.
4.3 Candidate locates control switch for [2RCS*P21B].
4.4.C Candidate turns [2RCS*P2lB] control switch to the STOP position.
4.5 Candidate locates control switch for [2RCS*P21C].
4.6.C Candidate turns [2RCS*P21C] control switch to the STOP position.
COMMENTS:
5.C Place all PRZR heaters in Pull-To-5.1 Candidate locates PRZR heater control switches.
Lock.
5.2.C Candidate places all PRZR heater control switches in Pull-To Lock position.
COMMENTS:
I
RTL#A5.640U 1/2-ADM-1303.F02 Page 6 of 9 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-HIN JPM TITLE: Block SI Following a Loss of Heat Sink Accident JPM REVISION: 0 STEP STANDARD
( "C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)=>
S/U
- 6.
Verify [2BDG*AOV100Al, B1, CI]
6.1 Candidate locates [2BDG*AOV100A1, B1, C1] indications and CLOSED.
verifies all valves CLOSED.
COMMENTS:
- 7.
Verify [2SSR*AOV 117A, B, C]
7.1 Candidate locates [2SSR*AOV1 17A, B, C] indications and CLOSED.
verifies all valves CLOSED.
COMMENTS:
- 8. Try to establish Main FW Flow to at 8.1 Candidate locates [2CNM-P21A, B, C] indications and verifies at least one SIG. Check any condensate least one pump RUNNING.
pump RUNNING.
COMMENTS:
- 9.
Try to establish Main FW Flow: Check 9.1 Candidate locates [2FWS*HYV157A, B, C] indications and FW isolation valves OPEN.
verifies all valves are OPEN.
COMMENTS:
I I
RTL#A5.640U 1/2-ADM-1303.F02 Page 7 of 9 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE 1PM NIUMBER: 2CR-HN I JPM TITLE: Block SI Following a Loss of Heat Sink Accident I 1PMREVISON:
STEP STANDARD
("C" Denotes CRITICAL STEP )
(Indicate "S" FOR SAT or "U" FOR UNSAT)=
S/U
- 10.
Try to establish Main FW Flow by 10.1 Candidate locates [2FWS-P24] control switch and notes that the starting the SG Startup Feed Pump.
pump is unavailable due to an equipment clearance.
EVALUATOR NOTE: Candidate may attempt to start a Main FW Pump; however, neither will start requiring a transition to Step 9.
COMMENTS:
- 11. Depressurize RCS to < 1950 psig.
11.1 Candidate locates [2CHS-FI150] and verifies letdown flow NOT Check letdown flow indicated, indicated.
S~COMMENTS:
NOTE: FAULTED PATH 12.C Use one PORV to depressurize the 12.1 Candidate locates [2RCS*MOV535, 536, 537] indications and RCS.
verifies at least one valve is OPEN.
12.2.C Candidate locates [2RCS*PCV455C, 456, 455D] control switches and OPENS one PORV.
COMMENTS:
I
RTL#A5.640U 1/2-ADM-1303.F02 Page 8 of 9 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-H IN JPM TITLE: Block SI Following a Loss of Heat Sink Accident "JPM REVISION: 0 STEP STANDARD
( "C" Denotes CRITICAL STEP )
(Indicate "S" FOR SAT or "U" FOR UNSAT)=>
S/U
- 13.
Adjust charging flow to maintain 13.1 Candidate locates [2CHS*FCV122] control station and adjusts to PRZR level, maintain PRZR level.
COMMENTS:
14.C Stop depressurization when RCS 14.1.C Candidate monitors RCS pressure and CLOSES PORV when reaches 1950 psig.
RCS pressure decreases to 1950 psig.
COMMENTS:
15.C Block SI Signals. BLOCK Low 15.1.C Candidate locates Low Steamline Pressure SI switches and Steamline Pressure SI.
places BOTH switches momentarily in the BLOCK position.
15.2 Candidate verifies annunciator A12-1B LIT.
COMMENTS:
I
RTL#A5.640U 1/2-ADM-1303.F02 Page 9 of 9 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-HIN JPM TITLE: Block SI Following a Loss of Heat Sink Accident JPM REVISION: 0 STEP STANDARD
( "C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)=*
S/U 16.C Block SI Signals. BLOCK Low 16.1.C Candidate locates Low PRZR Pressure SI switches and places PRZR Pressure SI.
BOTH switches momentarily in the BLOCK position.
16.2 Candidate verifies annunciator A12-1A LIT.
EVALUATOR NOTE: If Candidate continues with procedure, secure JPM at this point.
COMMENTS:
STOP TIME:
-r-
RTL#A5.640U 1/2-ADM-1303.F02 Page 1 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-622 JPM TITLE: Respond to a Radiation Monitor Alarm - Leak Collection JPM REVISION: 1 a Tank (Faulted)
K/A
REFERENCE:
073 A4.02 3.7/3.7 TASK ID:
0431-028-01-013 JPM APPLICATION:
REQUALIFICATION Z
INITIAL EXAM
] TRAINING Z
FAULTED JPM
[] ADMINISTRATIVE JPM EVALUATION METHOD:
LOCATION:
TYPE:
ADMINISTERED BY:
Z Perform D
Plant Site Annual Requal Exam
-- BVT F--
Simulate Z
Simulator Z
Initial Exam Z
NRC F-1 Classroom OJT/TPE E] Other:
Training
_--] Other:
EVALUATION RESULTS Performer Name:
Performer S SN:
Time F Yes
[Allotted 20 minutes IActual minutes Critical:
Z* No Time:
Time:
SA M S UNSAT (Comments required for UNSAT evaluation)
Comments:
OBSERVERS Name/SSN:
Name/SSN:
Name/SSN:
Name/SSN:
EVALUATOR Evaluator (Print):
Date:
Evaluator Signature:
RTL#A5.640U 1/2-ADM-1303.F02 Page 2 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-622 JPM TITLE: Respond to a Radiation Monitor Alarm - Leak Collection JPM REVISION: la Tank (Faulted)
I EVALUATOR DIRECTION SHEET TASK STANDARD:
RECOMMENDED STARTING LOCATION:
DIRECTIONS:
INITIAL CONDITIONS:
INITIATING CUE:
REFERENCES:
TOOLS:
Radiation monitor automatic actions have been verified.
Control Room Respond to a radiation monitor high alarm.
The plant is currently at 100% power. Annunciator A4-5C has just been received.
Your Supervisor directs you to respond to the alarm using the appropriate alarm response procedures.
20M-43.4.AAC Issue 4, Rev. 0 20M-43.4.AEB Issue 1, Rev. 4 None 20M-43.4. AAC & AEB HANDOUT:
RTL#A5.640U 1/2-ADM-1303.F02 Page 3 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE CANDIDATE DIRECTION SHEET THIS SHEET TO BE GIVEN TO CANDIDATE Read:
Respond to a radiation monitor high alarm.
INITIAL CONDITIONS:
INITIATING CUE:
The plant is currently at 100% power. Annunciator A4-5C has just been received.
Your Supervisor directs you to respond to the alarm using the appropriate alarm response procedures.
L At this time, ask the evaluator any questions you have on this JPM.
E When satisfied that you understand the assigned task, announce "I am now beginning the JPM".
Z Simulate performance or perform as directed the required task.
Point to any indicator or component you verify or check and announce your observations.
After determining the Task has been met announce " I have completed the JPM".
Then hand this sheet to the evaluator.
TASK:
RTL#A5.640U 1/2-ADM-1303.F02 Page 4 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE I JPM NUMBER: 2CR-622 JPM TITLE: Respond to a Radiation Monitor Alarm (Leak Collection JPM REVISION: la Vent)
STEP STANDARD
("C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)=>
S/U STEP STANDARD
("C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)z>
S/U START TIME:
Setup: Initialize IC-176.
EVALUATOR NOTE: JPM steps I - 6 are optional, N/A if Candidate omits them.
- 1.
Candidate obtains procedure 2GM-1.1 Candidate locates procedure for annunciator A4-5C.
43.4.AAC, Radiation Monitoring Level High.
EVALUATOR CUE: Provide Candidate a copy of 20M-43.4.AAC.
COMMENTS:
- 2.
Verify or depress the grid six 2.1 Candidate locates the grid six pushbutton and depresses it, OR pushbutton and determine which verifies that the grid is already displayed.
radiation monitor is in alarm at the RM-11 console.
COMMENTS:
RTL#A5.640U 1/2-ADM-1303.F02 Page 5 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-622 JPM TITLE: Respond to a Radiation Monitor Alarm (Leak Collection I WM REVISION: Ila Vent)
STEP STANDARD
( "C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)*
S/U
- 4.
Depress the STATUS pushbutton.
4.1 Candidate locates and depresses the STATUS pushbutton.
COMMENTS:
- 5.
Silence the alarm console.
5.1.
Candidate depresses the SYSTEM ACK pushbutton to silence the alarm.
EVALUATOR CUE: The audible alarm may be defeated and not sound, otherwise cue that the alarm has silenced.
COMMENTS:
- 6.
Check if radiation level is at or 6.1 Candidate compares reading against background or notifies NSS.
approaching 1000 times background.
EVALUATOR CUE: The NSS is aware of the alarm level.
COMMENTS:
RTL#A5.640U 1/2-ADM-1303.F02 Page 6 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-622 JPM TITLE: Respond to a Radiation Monitor Alarm (Leak Collection JPM REVISION: la Vent)
STEP STANDARD
( "C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)='
S/U 7.C Candidate determines that [2RMR-7.1.C Candidate determines 2RMR-RQI301 is in alarm.
RQI3011 Leak Collection Ventilation Radiation Monitor is in alarm and 7.2 Candidate locates 20M-43.4.AEB.
then refers to local alarm response procedure for the corrective actions.
EVALUATOR CUE: Provide Candidate a copy of 20M-43.4.AEB.
EVALUATOR NOTE: Candidate may verbalize monitor in alarm or may just use the correct procedure. Either action satisfies the critical step.
COMMENTS:
- 8.
At the RM-1 1 console, verify the 8.1 Candidate verifies that the red box moves to the right.
indicating box turns red and moves to the right of CHANNEL IN HIGH SIMULATED CUE: The alarm box to the right of ALARM.
CHANNEL IN HIGH ALARM is red.
COMMENTS:
- 9.
Depress the CHANNEL ITEMS 9.1 Candidate depresses the CHANNEL ITEMS pushbutton.
pushbutton and verify that the actual level is higher than the high alarm 9.2 Compares actual level to high alarm setpoint.
setpoint.
SIMULATED CUE: The monitor radiation level is 1.00E-01 4CI/ml and high alarm setpoint is 3.6E-05.
COMMENTS:
RTL#A5.640U 1/2-ADM-1303.F02 Page 7 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE SJPM NUMBER: 2CR-622 WPM TITLE: Respond to a Radiation Monitor Alarm (Leak Collection JPM REVISION: la Vent)
STEP STANDARD
( "C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)*
S/U
- 10. Notify the ANSS/NSS and obtain 10.1 Candidate notifies NSS of the HIGH radiation monitor alarm and directions.
asks for direction.
EVALUATOR CUE: The NSS is aware of the alarm NOTE: FAULTEDPATH and has notified RADCON. H ste d
.f.
COMMENTS:
- 11. Verify that 2HVS*MOD201A & B are 11.1 Candidate locates 2HVS*MOD201A & B and 2HVS*MOD202A closed, and that 2HVS*MOD202A & B
& B on BSP.
are open.
11.2 Verifies that 2HVS*MOD201A & B are closed and that 2HVS*MOD202A & B are open.
11.3 Verifies that the damper green or red lights are lit.
SIMULATED CUE: Dampers 2HVS*MOD201A & B are open, RED lights are lit. Dampers 2HVS*MOD202A
& B are shut, GREEN lights are lit.
EVALUATOR CUE: If asked for guidance, act as Supervisor and direct Candidate to place the dampers in their required position.
COMMENTS:
RTL#A5.640U I/2-ADM-1303.F02 Page 8 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE IJPM NUMBER: 2CR-622 JPM TITLE: Respond to a Radiation Monitor Alarm (Leak Collection 1PM REVISION: la Vent)
STEP STANDARD
("C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)z:>
S/U 12.C Position dampers by placing the common control switch to "FILT" position for both Train 'A' and Train
'B'.
12.1 Candidate locates Train 'A' and Train 'B' control switches on the Building Service Panel.
12.2.C Places the control switches to the "FILT" position.
12.3 Candidate verifies that the damper green and red lights are lit.
SIMULATED CUE: Dampers 2HVS*MOD201A & B GREEN lights are lit. 2HVS*MOD202A & B RED lights are lit.
COMMENTS:
STOP TIME:
RTL#A5.640U 1/2-ADM-1303.F02 Page 1 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-076 JPM TITLE: Initiate a Natural Circulation Cooldown per ES-0.2 JPM REVISION: 4a (Faulted)
K/A
REFERENCE:
002 A4.02 4.3/4.5 TASK ID:
0061-009-01-013 E09 EA1.1 3.5/3.5 0061-011-01-013 JPM APPLICATION:
[-
REQUALIFICATION
] INITIAL EXAM
[-
TRAINING Z
FAULTED JPM E] ADMINISTRATIVE JPM EVALUATION METHOD:
LOCATION:
TYPE:
ADMINISTERED BY:
Z Perform F--
Plant Site F-] Annual Requal Exam
[-] BVT Simulate Z
Simulator Z
Initial Exam Z
NRC
[-
Classroom E] OJT/TPE F-- Other:
R-Training E][] Other:
EVALUATION RESULTS Performer Name:
Performer SSN:
Time R Yes Allotted 20 minutes Actual minutes Critical:
Z No Time:
Time:
E1SAT JPM[ RESULTS:E SA 1 R U UNSAT (Comments required for UNSAT evaluation)
Comments:
OBSERVERS Name/SSN:
Name/SSN:
Name/S SN:
Name/S SN:
EVALUATOR Evaluator (Print):
Date:
Evaluator Signature:
RTL#A5.640U 1/2-ADM-1303.F02 Page 2 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE I JPM NUMBER: 2CR-076 JPM TITLE: Initiate a Natural Circulation Cooldown per ES-0.2 JPM REVISION: 4a (Faulted)
EVALUATOR DIRECTION SHEET TASK STANDARD:
RECOMMENDED STARTING LOCATION:
DIRECTIONS:
INITIAL CONDITIONS:
INITIATING CUE:
REFERENCES:
TOOLS:
HANDOUT:
Natural circulation cooldown established at a rate of< 25°F/hr.
Control Room Establish a cooldown per EOP ES-0.2.
The plant has been tripped manually due to a component cooling water problem that required stopping all reactor coolant pumps. The plant is now in a natural circulation cooldown mode. The operators have completed EOP's E-0, ES-0. 1 and ES-0.2 through Step 5. The plant is stable with condenser steam dumps in automatic in the steam pressure mode and the bypass feedwater regulating valves in automatic maintaining S/G levels.
Your supervisor directs you to initiate a cooldown at a rate of less than 25°F/hour in accordance with EOP ES-0.2, Step 6.
EOP ES-0.2 EOP Attachment A-4.1 None EOP ES-0.2 EOP Attachment A-4.1
RTL#A5.640U 1/2-ADM-1303.F02 Page 3 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE CANDIDATE DIRECTION SHEET THIS SHEET TO BE GIVEN TO CANDIDATE Read:
TASK:
Establish a cooldown per EOP ES-0.2.
INITIAL CONDITIONS:
INITIATING CUE:
E1 U--
The plant has been tripped manually due to a component cooling water problem that required stopping all reactor coolant pumps. The plant is now in a natural circulation cooldown mode. The operators have completed EOP's E-0, ES-0. 1 and ES-0.2 through Step 5. The plant is stable with condenser steam dumps in automatic in the steam pressure mode and the bypass feedwater regulating valves in automatic maintaining S/G levels.
Your Supervisor directs you to initiate a cooldown at a rate of less than 257F/hour in accordance with EOP ES-0.2, Step 6.
At this time, ask the evaluator any questions you have on this JPM.
When satisfied that you understand the assigned task, announce "I am now beginning the JPM".
i-Simulate performance or perform as directed the required task.
Point to any indicator or component you verify or check and announce your observations.
r, After determining the Task has been met announce " I have completed the JPM".
Then hand this sheet to the evaluator.
RTL#A5.640U 1/2-ADM-1303.F02 Page 4 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-076 JPM TITLE: Initiate a Cooldown per ES-0.2 JPM REVISION: 4a STEP STANDARD
( "C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)=>
S/U STEP STANDARD
( "C" Denotes CRITICAL STEP (Indicate "S" FOR SAT or "U" FOR UNSAT)=
S/IU START TIMIE:___
Setup: Initialize IC-172 and run file JPM2CR-076.cae.
EVALUATOR CUE: Inform the Candidate that the Evaluator will act as the Reactor Operator.
NOTE: It may be necessary to reduce letdown, manually operate FCV-122 or use a PORV to control pressure.
Also, AFW starts are inhibited, so no actuation will occur if S/G levels are low.
I.
Obtain procedure ES-0.2.
2.1 Candidate locates EOP ES-0.2.
EVALUATOR CUE: Provide Candidate a copy of EOP ES-0.2.
COMMENTS:
RTL#A5.640U 1/2-ADM-1303.F02 Page 5 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-076 JPM TITLE: Initiate a Cooldown per ES-0.2 JPM REVISION: 4a STEP STANDARD
("C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)7*
S/U EVALUATOR CUE: I will trend the RCS cold leg temperatures and RCS pressure. You are responsible for monitoring the cooldown rate. I can give you data as you request it.
- 2.
Trend RCS temperature and pressure at 2.1 Candidate acknowledges report to trend RCS cold leg 10 minute intervals, temperatures and RCS pressure.
2.2 Candidate refers to Attachment A-4.1 and ensures the following cooldown rate does not exceed 25°F/hr.
COMMENTS:
- 3. Maintain S/G level between 30% and 3.1 Locates appropriate S/G narrow range level indication.
50%.
3.2 Checks S/G narrow range level indication.
EVALUATOR CUE: As each S/G level is checked, inform the Candidate that it is at 35% and slowly trending to 33%.
EVALUATOR NOTE: S/G levels may have to be adjusted. Inform the Candidate that the Evaluator will be responsible for S/G level control.
COMMENTS:
RTL#A5.640U 1/2-ADM-1303.F02 Page 6 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-076 JPM TITLE: Initiate a Cooldown per ES-0.2 JPM REVISION: 4a I
STEP STANDARDS/
("C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)>
S/U
- 4.
Dump steam to condenser.
4.1 Candidate checks MSIV's open.
EVALUATOR CUE: All MSIV's are open.
4.2 Candidate checks Annunciator A12-4C "Condenser Unavailable (C-9)" - NOT LIT.
EVALUATOR CUE: Annunciator A12-4C is NOT LIT.
COMMENTS:
RTL#A5.640U 1/2-ADM-1303.F02 Page 7 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-076 1PM TITLE: Initiate a Cooldown per ES-O.2 JPM REVISION: 4a J
STEP STANDARD
( "C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)>
SIU 5.C Set steam header pressure setpoint to 5.1 Candidate sets STEAM HEADER pressure setpoint on initiate dumping steam.
[2MSS*PK4641 MAIN STM MANIFOLD pressure control above existing steam header pressure.
EVALUATOR NOTE: If EVALUATOR CUE: All condenser steam dump Candidate elects to go directly to valve green (closed) lights are lit.
manual and raise steam dump rate, request Simulator Instructor to lock 5.2.C Candidates places 2MSS*PK464 in manual.
out the condenser steam dumps.
5.3 Candidate verifies demand on 2MSS*PK464 is 0%.
5.4 Candidate places/verifies the "Steam Dump Control Mode" selector switch in the STM PRESS MODE.
5.5.C Candidate depresses raise pushbutton to open the steam dump valves.
EVALUATOR NOTE: All condenser steam dumps nre. failed crln'q.d 5.6.C Candidate notes failure of condenser steam dumps and informs Supervisor.
EVALUATOR CUE: As Supervisor, acknowledge condenser steam dump failure and direct Candidate to use 2SVS*HCV104 to dump steam.
5.7.C Candidate refers to RNO and manually dumps steam using
[2SVS*HCV104I Residual Heat Release Valve.
COMMENTS:
NOTE: FAULTED PATH
RTL#A5.640U 1/2-ADM-1303.F02 Page 8 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-076 JPM TITLE: Initiate a Cooldown per ES-0.2 JPM REVISION: 4a STEP STANDARD
( "1C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)=>
S/U 6.C Establish desired cooldown rate.
6.1 Candidate monitors cooldown rate.
6.2.C Candidate adjusts cooldown rate as necessary to establish a cooldown rate less than 25°F/hr.
EVALUATOR NOTE: A final stable cooldown rate is the critical element. A short term rise or drop in the cooldown rate is allowed.
COMMENTS:
STOP TIME:
RTL#A5.640U 1/2-ADM-1303.F02 Page 1 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE "JPM NUMBER: 2CR-080a JPM TITLE: Calculate and Restore CNMT Air Partial Pressure JPM REVISION: 0 K/A
REFERENCE:
103A1.01 3.7/4.1 TASK ID:
0121-004-01-013 0121-005-01-013 JPM APPLICATION:
REQUALIFICATION Z
INITIAL EXAM
-- TRAINING FAULTED JPM F--
ADMINISTRATIVE JPM EVALUATION METHOD:
LOCATION:
TYPE:
ADMINISTERED BY:
Z Perform
[-] Plant Site E] Annual Requal Exam BVT
--] Simulate Z
Simulator Z
Initial Exam Z
NRC D] Classroom
-- OJT/TPE F-] Other:
E] Training
_---] Other:
EVALUATION RESULTS Performer Name:
Performer SSN:
Time F---
Yes Allotted 20 minutes Actual minutes Critical:
Z* No Time:
Time:
12]SAT JPM RESULTS:
SA PLI UNSAT (Comments required for UNSAT evaluation)
Comments:
OBSERVERS Name/SSN:
Name/SSN:
Name/S SN:
Name/S SN:
EVALUATOR Evaluator (Print):
Date:
Evaluator Signature:
I
RTL#A5.640U 1/2-ADM-1303.F02 Page 2 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE
- JPM NUMBER: 2CR-080a IJPM REVISION: 0 JPM TITLE: Calculate and Restore CNMT Air Partial Pressure EVALUATOR DIRECTION SHEET TASK STANDARD:
RECOMMENDED STARTING LOCATION:
DIRECTIONS:
INITIAL CONDITIONS:
INITIATING CUE:
REFERENCES:
TOOLS:
HANDOUT:
CNMT air partial pressure calculated, compared to Technical Specification and restored to within limits.
Control Room You are to simulate (perform) the task of calculating CNMT air partial pressure.
The plant is in Mode 1 and CNMT total air pressure has just been reduced based on an MAO calculation of 10.0 psia. The computer points required for the calculation are out-of-service and the Ohio river water temperature is 70. 10F.
Your Supervisor directs you to calculate CNMT air partial pressure in accordance with 20M-54.3.L5, Surveillance Verification Log and adjust as necessary to satisfy Technical Specification limits.
20M-54.3.L5, Rev. 29 20M-54.2.S1 Issue 4, Rev. 4 Technical Specifications 3.6.1.4 and Figure 3.6-1 Steam Tables Calculator 20M-54.3.L5, Rev. 29 20M-54.2.S1 Issue 4, Rev. 4 Technical Specifications LCO 3.6.1.4 and Figure 3.6-1 Steam Tables I
RTL#A5.640U 1/2-ADM-1303.F02 Page 3 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE CANDIDATE DIRECTION SHEET THIS SHEET TO BE GIVEN TO CANDIDATE El TASK:
Read:
INITIAL CONDITIONS:
INITIATING CUE:
n-You are to simulate (perform) the task of calculating CNMT air partial pressure.
The plant is in Mode 1 and CNMT total air pressure has just been reduced based on an MAO calculation of 10.0 psia. The computer points required for the calculation are out-of-service and the Ohio river water temperature is 70. I°F.
Your Supervisor directs you to calculate CNMT air partial pressure in accordance with 20M-54.3.L5, Surveillance Verification Log and adjust as necessary to satisfy Technical Specification limits.
At this time, ask the evaluator any questions you have on this JPM.
F1 When satisfied that you understand the assigned task, announce "I am now beginning the JPM".
D Simulate performance or perform as directed the required task.
F1 Point to any indicator or component you verify or check and announce your observations.
After determining the Task has been met announce "I have completed the JPM".
El Then hand this sheet to the evaluator.
RTL#A5.640U l/2-ADM-1303.F02 Page 4 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-080a JPM TITLE: Calculate and Restore CNMT Air Partial Pressure I IPMTWFVI,1TON" C STEP STANDARD (t"C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)*
S/U 0START TIME:
Setup: Initialize IC-176.
- 1. Obtain procedure 20M-54.3.L5.
- 1.
Candidate locates 20M-54.3.L5.
EVALUATOR CUE: Provide Candidate a copy of 20M-54.3.L5, Steam Tables and calculator.
COMMENTS:
- 2.
Calculate CNMT average dewpoint 2.1 Candidate locates [2LMS-MI1OO-2, 3, 4, 5].
temperature.
SIMULATED CUE: [2LMS-MlI00-2, 3, 4, 5] read 52.80 F.
2.2 Candidate records readings and calculates average dewpoint temperature.
EVALUATOR NOTE: Average dewpoint temperature equals 52.8 0F.
COMMENTS:
I
RTL#A5.640U 1/2-ADM-1303.F02 Page 5 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-080a JPM TITLE: Calculate and Restore CNMT Air Partial Pressure JPM REVISION: 0 STEP STANDARD
("C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)>
S/U
- 3. Calculate average CNMT total air 3.1 Candidate locates [2CVS-PI101AI, B1].
pressure.
3.2 Candidate records readings and calculates average CNMT total air pressure.
SIMULATED CUE: [2CVS-PI101A1, B1] both read 10.1 psia.
EVALUATOR NOTE: Average CNMT total air pressure equals 10.1 psia.
COMMENTS:
- 4.
Determine saturation pressure.
- 4.
Candidate determines saturation pressure corresponding to average dewpoint temperature from Steam Tables.
EVALUATOR NOTE: Saturation pressure for 52.8°F equals 0.19 psia.
COMMENTS:
- 5. Calculate air partial pressure.
5.1 Candidate subtracts saturation pressure from average CNMT total air pressure to determine calculated air partial pressure.
EVALUATOR NOTE: Calculated air partial pressure equals 9.9 psia.
COMMENTS:
RTL#A5.640U 1"
OPERATIONS JOB PERFORMANCE MEASURE 1/2-ADM-1303.F02 Page 6 of 8 Revision 0 JPM NUMBER: 2CR-080a JPM TITLE: Calculate and Restore CNMT Air Partial Pressure JPM REVISION: 0 STEP STANDARD
( "C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT):
SIU
- 6.
Obtain Ohio river water temperature.
6.1 Candidate records Ohio river water temperature given in the initial conditions.
COMMENTS:
- 7.
Detemine MAO from T.S. Figure
- 7.
Candidate refers to T.S. Figure 3.6-1 and determines MAO based 3.6-1.
on temperature of 70. 1°F.
EVALUATOR NOTE: MAO equals 9.85 psia.
COMMENTS:
8.C Verify calculated air partial pressure 8.1C Candidate determines that air partial pressure is NOT within is within T.S. limits.
T.S. limits (greater than MAO).
8.2 Candidate verifies that [2CVS-PIl01A1, B 1] is greater than MAO.
EVALUATOR NOTE: This step is optional based on previously recorded readings.
8.3 Candidate reports air partial pressure is above T.S. limit.
EVALUATOR CUE: As Supervisor, direct Candidate to take required action to restore CNMT pressure to within T.S. limits.
COMMENTS:
RTL#A5.640U I/2-ADM-1303.F02 Page 7 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-080a JPM TITLE: Calculate and Restore CNMT Air Partial Pressure JPM REVISION: 0 STEP STANDARD
( "C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)*
S/U
- 9. Obtain procedure 20M-12.4.E.
9.1 Candidate locates procedure 20M-12.4.E EVALUATOR NOTE: After locating procedure, provide Candidate a copy of 20M-12.4.E and 20M-54.2.S1.
Inform that procedure Initial Conditions are met.
COMMENTS:
- 10. Log reading of 2CVS-FQI101.
10.1 Candidate logs reading of[2CVS-FQIlO11 on 20M-54.2.S1.
COMMENTS:
EVALUATOR CUE: An Operator is stationed locally at the pump.
ll.C Start [2CVS-P21A (21B)] (t3B-A).
IlI.C Candidate starts [2CVS-P21A (21B)] Cnmt Vacuum Pump (BB-A).
COMMENTS:
RTL#A5.640U 1/2-ADM-1303.F02 Page 8 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-080a JPM TITLE: Calculate and Restore CNMT Air Partial Pressure JPM REVISION: 0 STEP STANDARD
("C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)*'
S/U
- 12. Verify local pump parameters.
- 12.
Candidate verifies acceptable pump operating parameters.
EVALUATOR CUE: Report as local Operator that Cnmt vacuum pump noise, vibration, leakage are not excessive and seal water pressure is 30 psig.
COMMENTS:
13.C Verify air is being discharged through 2CVS-FQI101 (BB-A).
13.C Candidate verifies that air is being discharged through [2CVS FQI1011 Cnmt Vacuum Total Flow (BB-A).
EVALUATOR NOTE: If Candidate continues with procedure, conclude JPM at this point.
COMMENTS:
STOP TIME:
RTL#A5.640U 1/2-ADM-1303.F02 Page 1 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-007 JPM TITLE: Energize 4KV Emergency Bus 2AE From Offsite Power JPM REVISION: 8a K/A
REFERENCE:
055EA1.07 4.3/4.5 TASK ID:
0532-001-05-013 JPM APPLICATION:
REQUALIFICATION Z
INITIAL EXAM TRAINING F-]
FAULTED JPM
--] ADMINISTRATIVE JPM EVALUATION METHOD:
LOCATION:
TYPE:
ADMINISTERED BY:
Z Perform F
Plant Site Annual Requal Exam
[:] BVT F
Simulate Z
Simulator Z
Initial Exam Z
NRC Classroom
-- OJT/TPE E] Other:
Training
_---] Other:
EVALUATION RESULTS Performer Name:
Performer SSN:
Time F--Yes
[Allotted 15 minutes
[Actual minutes Critical:
Z* No Time:
Time:
SA 1 R S I
UNSAT (Comments required for UNSAT evaluation)
Comments:
OBSERVERS Name/S SN:
Name/S SN:
Name/S SN:
Name/S SN:
EVALUATOR Evaluator (Print):
Date:
Evaluator Signature:
RTL#A5.640U 1/2-ADM-1303.F02 Page 2 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE j JPM NUMBER: 2CR-007 IJPM REVISION: 8a JPM TITLE: Energize 4KV Emergency Bus 2AE From Offsite Power EVALUATOR DIRECTION SHEET TASK STANDARD:
RECOMMENDED STARTING LOCATION:
DIRECTIONS:
INITIAL CONDITIONS:
INITIATING CUE:
REFERENCES:
TOOLS:
4KV Bus 2AE is energized from offsite power.
Control Room Energize 4KV Emergency Bus 2AE from offsite power.
Following a reactor trip from 100% power, plant conditions warrant the performance of ECA-0.0, "Loss Of All AC Power." Both diesel generators did not start. OCB 94 is open and cannot be closed (yellow caution tagged). All non-emergency and emergency bus pump loads are in Pull-To-Lock.
Your Supervisor directs you to restore power to 4KV Bus 2A from offsite power and energize 4KV Emergency Bus 2AE using EOP Attachment A-1.4.
EOP Attachment A-1.4 Issue 1B, Rev. 2 None EOP Attachment A-1.4 I
HANDOUT:
RTL#A5.640U 1/2-ADM-1303.F02 Page 3 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE CANDIDATE DIRECTION SHEET THIS SHEET TO BE GIVEN TO CANDIDATE Read:
Energize 4KV Emergency Bus 2AE from offsite power.
INITIAL CONDITIONS:
INITIATING CUE:
Following a reactor trip from 100% power, plant conditions warrant the performance of ECA-0.0, "Loss Of All AC Power." Both diesel generators did not start. OCB 94 is open and cannot be closed (yellow caution tagged). All non-emergency and emergency bus pump loads are in Pull-To-Lock.
Your Supervisor directs you to restore power to 4KV Bus 2A from offsite power and energize 4KV Emergency Bus 2AE using EOP Attachment A-1.4.
At this time, ask the evaluator any questions you have on this JPM.
When satisfied that you understand the assigned task, announce "I am now beginning the JPM".
D Simulate performance or perform as directed the required task.
Point to any indicator or component you verify or check and announce your observations.
r-After determining the Task has been met announce " I have completed the JPM".
Then hand this sheet to the evaluator.
TASK:
RTL#A5.640U 1/2-ADM-1303.F02 Page 4 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NTJMBER: 2CR-007 JPM TITLE: Energize 4KV Emergency Bus 2AE From Offsite Power JPM REVISION: 8a STEP STANDARD
( "C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)=
S/U STEP STANDARD
("C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)=
S/U
,$s<.~
ESTART TIME Setup: Initialize IC-171 and perform the following:
Trip OCB 94 and YCT. Depress 'Reset' on reheat controller, close 2CHS*AOV200A, B, & C and 2CHS*LCV460A & B. Depress steam line isolation pushbuttons. Place pump control switches listed in Attachment A-1.4, Steps 6 and 9 in PTL.
- 1.
Obtain procedure.
1.1 Candidate locates EOP Attachment A-1.4.
EVALUATOR CUE: Provide candidate a copy of EOP Attachment A-1.4.
COMMENTS:
- 2.
Establish communications with System 2.1 Candidate contacts System Operator.
Operator.
EVALUATOR CUE: Inform Candidate that offsite power is available and to continue with procedure.
EVALUATOR NOTE: Candidate may opt to only perform steps applicable to the "A" bus.
EVALUATOR CUE: If asked, inform Candidate that 4KV buses 2A, 2B, 2C & 2D indicate zero volts.
COMMENTS:
RTL#A5.640U 1/2-ADM-1303.F02 Page 5 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE k
1PM NUMBER: 2CR-007 JPM TITLE: Energize 4KV Emergency Bus 2AE From Offsite Power JPM REVISION: 8a STEP STANDARD
( "C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)*
S/U 3.C Open the 4KV breakers [ACB 42A, 3.1C Candidate takes 4KV breakers [ACB 42A, 142A, 242B, 342B]
142A, 242B, 342B] (BB-C).
control switches to Open.
COMMENTS:
- 4.
Verify Closed SSST 2A 138KV Motor-4.1 Candidate observes indicating lights for Switch 89-2A.
Operated Disconnect Switch 89-2A.
(BB-C).
SIMULATED CUE: Red light on Switch 89-2A is LIT, green light is DARK.
COMMENTS:
- 5.
Verify Closed OCB 85. (BB-C) 5.1 Candidate observes indicating lights for OCB 85.
SIMULATED CUE: OCB 85 red light LIT, green light DARK. OCB 94 is not available (yellow caution tagged).
COMMENTS:
RTL#A5.640U 1/2-ADM-1303.F02 Page 6 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-007 JPM TITLE: Energize 4KV Emergency Bus 2AE From Offsite Power JPM REVISION: 8a STEP STANDARD
( "C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)*
S/U
- 6.
Place all control room controlled non-6.1 Candidate places control switches for the non-emergency pumps operating 4160V pumps, powered from in PULL-TO-LOCK.
non-emergency busses, in Pull-To Lock.
EVALUATOR CUE: Inform Candidate that pumps are already in Pull-To-Lock. (Part of the Initial Conditions).
COMMENTS:
EVALUATOR NOTE: If asked about applicability of station cross-tie, inform Candidate that information is available using plant indications to determine cross-tie status.
7.C Close [ACB 42A] to energize 4KV 7.1.C Candidate places [ACB 42A] control switch in the close bus 2A.
position.
SIMULATED CUE: ACB42A, red light LIT, green light DARK. It is not desired to energize the 2B, 2C and 2D buses at this time.
EVALUATOR CUE: Both emergency buses 2AE and 2DF are de-energized due to diesel generator failures.
EVALUATOR CUE: A service water pump should be kept available to provide diesel generator cooling.
COMMENTS:
RTL#A5.640U 1/2-ADM-1303.F02 Page 6 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-007 JPM TITLE: Energize 4KV Emergency Bus 2AE From Offsite Power JPM REVISION: 8a STEP STANDARD
( "C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)>
S/U
- 6.
Place all control room controlled non-6.1 Candidate places control switches for the non-operating pumps in operating 4160V pumps, powered from PULL-TO-LOCK.
non-emergency busses, in Pull-To Lock.
EVALUATOR CUE: Inform Candidate that pumps are already in Pull-To-Lock. (Part of the Initial Conditions).
COMMENTS:
EVALUATOR NOTE: If asked about applicability of station cross-tie, inform Candidate that information is available using plant indications to determine cross-tie status.
7.C Close [ACB 42A] to energize 4KV 7.1.C Candidate places [ACB 42A] control switch in the close bus 2A.
position.
SIMULATED CUE: ACB42A, red light LIT, green light DARK. It is not desired to energize the 2B, 2C and 2D buses at this time.
EVALUATOR CUE: Both emergency buses 2AE and 2DF are de-energized due to diesel generator failures.
EVALUATOR CUE: A service water pump should be kept available to provide diesel generator cooling.
COMMENTS:
RTL#A5.640U 1/2-ADM-1303.F02 Page 8 of 8 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-007 JPM TITLE: Energize 4KV Emergency Bus 2AE From Offsite Power JPM REVISION: 8a I
STEP STANDARD
( "C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)*I S/U 10.C Close 4KV emergency bus feeder breaker 2E7.
I0.I.C Candidate places 4KV emergency bus feeder breaker 2E7 control switch in the Close position.
10.2 Candidate performs this step within 30 seconds of completing previous step.
SIMULATED CUE: BKR 2AI0, red light LIT, green light is DARK.
EVALUATOR CUE: Another Operator will energize the 480V 2N bus.
COMMENTS:
STOP TIME:
RTL#A5.640U I/2-ADM-1303.F02 Page 1 of6 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-053 JPM TITLE: Respond to a Failed Power Range Channel N-44 JPM REVISION: 3a K/A
REFERENCE:
051A2.01 3.5/3.9 TASK ID:
0535-010-04-013 015A2.02 3.1/3.5 0021-004-01-013 JPM APPLICATION:
F]
REQUALIFICATION
[
INITIAL EXAM E] TRAINING
--]
FAULTED JPM ADMINISTRATIVE JPM EVALUATION METHOD:
LOCATION:
TYPE:
ADMINISTERED BY:
Z Perform E] Plant Site E] Annual Requal Exam E] BVT
-- Simulate Z
Simulator Z
Initial Exam Z
NRC F-- Classroom
-] OJT/TPE
-] Other:
F-1 Training
[--] Other:
EVALUATION RESULTS Performer Name:
Performer SSN:
Time F
Yes Allotted 15 minutes Actual minutes Critical:
Z No Time:
Time:
VlSAT JPM RESULTS:
E A
P:1 UNSAT (Comments required for UNSAT evaluation)
Comments.
OBSERVERS Name/SSN:
Name/SSN:
Name/SSN:
Name/SSN:
EVALUATOR Evaluator (Print):
Date:
Evaluator Signature:
RTL#A5.640U 1/2-ADM-1303.F02 Page 2 of 6 Revision 0 OPERATIONS JOB PERFORMANCE MtASURE JPM NUMBER: 2CR-053 JPM TITLE: Respond to a Failed Power Range Channel N-44 IJPM REVISION: 3a EVALUATOR DIRECTION SHEET TASK STANDARD:
RECOMMENDED STARTING LOCATION:
DIRECTIONS:
INITIAL CONDITIONS:
INITIATING CUE:
REFERENCES:
TOOLS:
The failed nuclear instrumentation and power range channel is bypassed per procedure.
Control Room You are to respond to a failed power range channel.
The plant is operating at 46% power following the failure of a power range channel. The actions required to stabilize the plant following the failure have been taken. Reactor power, turbine power and Tavg are all stable at their current values. Tavg is within one degree of Tref, and the control rods are in manual. The bypass feedwater regulating valves]
are in manual. All other systems are operating normally.
Your supervisor directs you to bypass the failed power range channel using the appropriate procedure.
20M-53C.4.2.2.IC Issue IA, Rev. 6 None HANDOUT:
~~1 I
RTL#A5.640U 1/2-ADM-1303.F02 Page 3 of 6 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE CANDIDATE DIRECTION SHEET THIS SHEET TO BE GIVEN TO CANDIDATE Read:
Respond to a failed power range channel.
INITIAL CONDITIONS:
INITIATING CUE:
The plant is operating at 46% power following the failure of a power range channel. The actions required to stabilize the plant following the failure have been taken. Reactor power, turbine power and Tavg are all stable at their current values. Tavg is within one degree of Tref, and the control rods are in manual. The bypass feedwater regulating valves are in manual. All other systems are operating normally.
Your supervisor directs you to bypass the failed power range channel using the appropriate.
5 At this time, ask the evaluator any questions you have on this JPM.
When satisfied that you understand the assigned task, announce "I am now beginning the JPM".
r-Simulate performance or perform as directed the required task.
Point to any indicator or component you verify or check and announce your observations.
Dj After determining the Task has been met announce " I have completed the JPM".
El Then hand this sheet to the evaluator.
C TASK:
n
RTL#A5.640U 1/2-ADM-1303.F02 Page 4 of 6 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-053 JPM TITLE: Respond to a Failed Power Range Channel N44 JPM REVISION: 3a STEP STANDARD
( "C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)=>
Su STEP STANDARD
("C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)=*
S/U
- !t v*.*:*@
START TIME:
Setup: InitializelC-167 and set Control Bank 'D' group step counters at 160 steps.
- 1. Obtain procedure.
1.1 Candidate locates AOP-2.2.IC.
EVALUATOR CUE: Provide Candidate a copy of AOP-2.2. IC.
COMMENTS:
- 2. Check if malfunction of one power 2.1 Candidate verifies N-44 has failed (high).
range channel has occurred.
2.2 Candidate determines no other power range channel has failed.
SIMULATED CUE: Inform Candidate of power range channel indications:
N 46%
N42 - 46%
N 46%
N 120% (offscale high)
COMMENTS:
RTL#A5.640U I/2-ADM-1303.F02 Page 5 of 6 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-053 JPM TITLE: Respond to a Failed Power Range Channel N44 STEP STANDARD
( "C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)=
S/U 3.C Within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> remove control 3.1.C Candidate removes control power fuses from N-44 Drawer "A".
power fuses from drawer "A" of channel N-44.
EVALUATOR NOTE: Candidate may verify control rods in manual and bypass feed reg. valves in manual.
SIMULATED CUE: Fuses removed.
COMMENTS:
4.C Place "Rod Stop Bypass Switch" in 4.1.C Candidate places "Rod Stop Bypass Switch" in N-44 position.
N-44 position. (NIS Rack) 4.2 Candidate verifies Overpower Rod Stop Bypass Status Light is lit.
SIMULATED CUE: Overpower Rod Stop Bypass Status Light is lit.
COMMENTS:
- 5. Check reactor power greater than 50%.
5.1 Candidate locates functioning NIS channels and verifies power is less than 50%.
SIMULATED CUE: Channels N-41, N-42, and N-43 all indicate 46%.
COMMENTS:
RTL#A5.640U 1/2-ADM-1303.F02 Page 6 of 6 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2CR-053 JPM TITLE: Respond to a Failed Power Range Channel N44 J PM REVISION: 3a STEP STANDARD
( "C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)>
S/U 6.C Place "Comparator Channel Defeat 6.C Candidate places "Comparator Channel Defeat Switch" in N-44 Switch" in N-44 position. (NIS position.
Rack)
SIMULATED CUE: Comparator Channel Defeat Switch is in N-44 position.
COMMENTS:
- 7.
Ensure vertical board recorders are
- 7.
Candidate checks NIS vertical board recorders to ensure N-44 is selected to monitor only operable not selected.
detectors.
COMMENTS:
- 8.
Refer to T.S. 4.2,1.1.b.
- 8.
Candidate reports N-44 bypassed and states that axial flux needs to be monitored per T.S. 4.2.1. l.b.
EVALUATOR CUE: As Supervisor, inform Candidate that another operator will be asked to monitor axial flux and refer to Technical Specifications.
COMMENTS:
STOP TIME:
RTL#A5.640U 1/2-ADM-1303.F02 Page 1 of 5 Revision 0 OPERATIONS JOB PERFORMANCE MtASURE I
JPM NUMBER: 2PL-076 JPM TITLE: Isolate AFW During Alternate Safe Shutdown [Abnormal JPM REVISION: Ob Task]
K/A
REFERENCE:
061A2.05 3.1/3.4 TASK ID:
0241-030-01-013 JPM APPLICATION:
[E REQUALIFICATION
[;
INITIAL EXAM
["
TRAINING
-] FAULTED JPM ADMINISTRATIVE JPM EVALUATION METHOD:
LOCATION:
TYPE:
ADMNINISTERED BY:
F--
Perform
[
Plant Site Annual Requal Exam F-BVT E
Simulate E] Simulator
[
Initial Exam I
NRC E] Classroom
[] OJT/TPE
-] Other:
E] Training E]-1 Other:
EVALUATION RESULTS Performer Name:
PefrerSN Time F--
Yes
[Allotted 15 minutes
[Actual minutes Critical:
[E No Time:
Time:
E A
1 S UNSAT (Comments required for UNSAT evaluation)
Comments:
OBSERVERS Name/SSN:
Name/SSN:
Name/S SN:
Name/S SN:
EVALUATOR Evaluator (Print):
Date:
Evaluator Signature:
RTL#A5.640U 1/2-ADM-1303.F02 Page 2 of 5 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE "I JPM NUMBER: 2PL-076 JPM TITLE: Isolate AFW During Alternate Safe Shutdown [Abnormal JPM REVISION: Ob Task]
Ij EVALUATOR DIRECTION SHEET TASK STANDARD:
RECOMMENDED STARTING LOCATION:
DIRECTIONS:
INITIAL CONDITIONS:
INITIATING CUE:
REFERENCES:
TOOLS:
AFW flow is isolated to the 'C' steam generator.
In Plant You are to simulate (perform) the task of isolating AFW flow to the 'C' steam generator.
A deep seated fire has occurred in the cable spreading area just below the Control Room. The NSS has evacuated the Control Room and activated the Alternate Shutdown Panel (ASP). Procedure 20M 56C.4.D, Part 2 for Nuclear Operator #1 has been completed through Step 10. For the 'C' steam generator AFW throttle valves:
2FWE*HCV1 OOA has been de-energized and is still open, and 2FWE*HCV10OB has been de-energized and is closed.
The NSS directs you to perform 20M-56C.4.D, Part 2 Step 11 to close 2FWE*HCV100A and report back when you have completed this step.
20M-56C.4.D, Rev. 11 Simulated allen wrench and pump handle.
20M-56C.4.D, Rev. 11 HANDOUT:
I "T
I
RTL#A5.640U 1/2-ADM-1303.F02 Page 3 of 5 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE CANDIDATE DIRECTION SHEET THIS SHEET TO BE GIVEN TO CANDIDATE Read:
Isolate AFW flow to the 'C' steam generator.
INITIAL CONDITIONS:
<./
INITIATING CUE:
A deep seated fire has occurred in the cable spreading area just below the Control Room. The NSS has evacuated the Control Room and activated the Alternate Shutdown Panel (ASP). Procedure 20M 56C.4.D, Part 2 for Nuclear Operator #1 has been completed through Step 10. For the 'C' steam generator AFW throttle valves:
2FWE*HCV100A has been de-energized and is still open, and 2FWE*HCV100B has been de-energized and is closed.
The NSS directs you to perform 20M-56C.4.D, Part 2 Step 11 to close 2FWE*HCV100A and report back when you have completed this step.
At this time, ask the evaluator any questions you have on this JPM.
When satisfied that you understand the assigned task, announce "I am now beginning the JPM".
Simulate performance or perform as directed the required task.
El Point to any indicator or component you verify or check and announce your observations.
After determining the Task has been met announce " I have completed the JPM".
El Then hand this sheet to the evaluator.
TASK:
-1
RTL#A5.640U 1/2-ADM-1303.F02 Page 4 of 5 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2PL-076 JPM TITLE: Isolate AFW During Alternate Safe Shutdown JPM REVISION: Ob STEP STANDARD
"("C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)>
S/U START TIME: _________
EVALUATOR CUE: Provide Candidate a copy of procedure 20M-56C.4.D.
- 1. Candidate locates local placard.
- 1.
Candidate locates local placard in South Safeguards 741'.
COMMENTS:
2.C Remove valve cover for 2.C Candidate removes cover from [2FWE*HCV100A].
[2FWE*HCVOOA].
COMMENTS:
- 3.
Check hydraulic plunger.
- 3.
Candidate checks hydraulic plunger FULL OUT.
SIMULATED CUE: The plunger is full out, about 6 inches.
COMMENTS:
4.C Switch three position valve to close.
4.C Candidate switches the three position valve to CLOSE.
SSIMULATED CUE: Pointer UP, handle DOWN.
COMMENTS:
RTL#A5.640U 1/2-ADM-1303.F02 Page 5 of 5 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2PL-076 JPM TITLE: Isolate AFW During Alternate Safe Shutdown JPM REVISION: Ob STEP STANDARD
("C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)>
S/U 5.C Insert handle onto hydraulic pump.
5.C Candidate inserts handle onto hydraulic pump.
COMMENTS:
6.C Pump handle until valve is closed.
- 6. 1.C Candidate pumps handle.
6.2.C Candidate verifies valve stem moving CLOSED as handle is pumped.
SIMULATED CUE: Valve stem is moving closed.
COMMENTS:
7.C Switch three position valve to neutral.
7.C Candidate switches the three position valve to NEUTRAL.
COMMENTS:
- 8. Replace valve cover for
- 8.
Candidate replaces cover for [2FWE*HCV100A].
[2FWE*HCV1OOA].
COMMENTS:
- 9.
Report completion to the NSS.
- 8.
Candidate reports task completion to the NSS.
COMMENTS:
STOP TIME:
RTL#A5.640U 1/2-ADM-1303.F02 Page 1 of 6 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE SJPM NUMBER: 2PL-003 JPM TITLE: Startup A Rod Drive MG Set JPM REVISION:2 K/A
REFERENCE:
001A4.08 3.7/3.4 TASKID:
0011-005-01-010 JPM APPLICATION:
REQUALIFICATION Z
INITIAL EXAM F1-TRAINING FAULTED JPM
[-
ADMINISTRATIVE JPM EVALUATION METHOD:
LOCATION:
TYPE:
ADMINISTERED BY:
-- Perform l
Plant Site E] Annual Requal Exam E] BVT Z
Simulate
[:] Simulator Z
Initial Exam Z
NRC F--
Classroom
-] OJT/TPE E] Other:
El Training
--'E] Other:
EVALUATION RESULTS Performer Name:
Performer SSN:
Time F1-' Yes IAllotted 15 minutes IActual minutes Critical:
Z No Time:
Time:
SA El UNSAT (Comments required for UNSAT evaluation)
Comments:
OBSERVERS Name/SSN:
Name/SSN:
Name/S SN:
Name/S SN:
EVALUATOR Evaluator (Print):
Date:
Evaluator Signature:
RTL#A5.640U 1/2-ADM-1303.F02 Page 2 of 6 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2PL-003 JPM TITLE: Startup A Rod Drive MG Set IJPM REVISION: 2a EVALUATOR DIRECTION SHEET TASK STANDARD:
RECOMMENDED STARTING LOCATION:
DIRECTIONS:
INITIAL CONDITIONS:
INITIATING CUE:
REFERENCES:
TOOLS:
Startup a Rod Drive MG Set.
In Plant You are to simulate (perform) the task to Startup a Rod Drive MG Set.
The plant is in Mode 3 preparing for reactor startup. The Full Length Rod Control System is being placed in service. Control Rod Drive Set MG21 is operating and the reactor trip breakers are open.
Your Supervisor directs you to startup Rod Drive Set MG22 and close the generator output breaker per procedure 20M-1.4.B beginning at Step IV.I. Steps IV.A through IV.H were completed on a previous shift. You are also directed to have the reactor trip breakers closed from the Control Room.
20M-1.4.B, Rev. 3 None 20M-1.4.B, Rev. 3 HANDOUT:
III I
RTL#A5.640U 1/2-ADM-1303.F02 Page 3of 6 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE CANDIDATE DIRECTION SHEET THIS SHEET TO BE GIVEN TO CANDIDATE Read:
Startup a Rod Drive MG Set INITIAL CONDITIONS:
INITIATING CUE:
The plant is in Mode 3 preparing for reactor startup. The Full Length Rod Control System is being placed in service. Rod Drive Set MG21 is operating and the reactor trip breakers are open.
Your Supervisor directs you to startup Rod Drive Set MG22 and close the generator output breaker per procedure 20M-1.4.B beginning at Step IV.I. Steps IV.A through IV.H were completed on a previous shift. You are also directed to have the reactor trip breakers closed from the Control Room.
El At this time, ask the evaluator any questions you have on this JPM.
El When satisfied that you understand the assigned task, announce "I am now beginning the JPM".
E Simulate performance or perform as directed the required task.
Point to any indicator or component you verify or check and announce your observations.
After determining the Task has been met announce " I have completed the JPM".
Then hand this sheet to the evaluator.
El TASK:
RTL#A5.640U 1/2-ADM-1303.F02 Page 4 of 6 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE I JPM NUMBER: 2PL-003 JPM TITLE: Startup A Rod Drive MG Set JPM REVISION: 2a STEP STANDARD
"("C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)=:'
S/U START TIME:
EVALUATOR CUE: Provide candidate a copy of procedure 20M-1.4.B.
1C Start #2 Rod Drive MG Set by
.1..C Candidate indicates location of MG Set #2 Motor Circuit closing it's associated motor circuit Breaker Control Switch and simulates taking it to the CLOSE breaker.
position.
1.2 Candidate indicates that the MG set can be heard accelerating.
EVALUATOR CUE: The red close light is LIT.
COMMENTS:
2.C Depress generator field flash 2.1.C Candidate locates field flash pushbutton.
pushbutton until MG22 voltmeter indicates approximately 234 VAC.
2.2.C Simulates depressing it until the voltage stops rising (approximately 234 VAC).
EVALUATOR CUE: Voltage increased to 234 VAC.
COMMENTS:
3.C Rotate generator MG22 voltage 3.1 Candidate locates MG22 generator voltage adjust adjust potentiometer clockwise until potentiometer.
voltage indicates 260 VAC.
3.2.C Simulates rotating it clockwise until voltage indicators shows 260 VAC.
EVALUATOR CUE: Voltage increases to 260 VAC.
COMMENTS:
RTL#A5.640U I/2-ADM-1303.F02 Page 5 of 6 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2PL-003 JPM TITLE: Startup A Rod Drive MG Set JPM REVISION: 2a STEP STANDARD
"("C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)
S/U EVALUATOR CUE: Procedure 20M-1.4.Q, "Administrative Guidelines For Closing Reactor Trip/Bypass Breakers" has been completed.
- 4. Close the reactor trip breakers.
4.1 Candidate requests Control Room Reactor Operator to CLOSE the reactor trip breakers.
EVALUATOR CUE: Reactor trip breakers are closed.
COMMENTS:
5.C Rotate the MG22 generator circuit 5.1.C Candidate simulates turning MG22 generator circuit breaker to breaker to the close position.
CLOSE.
EVALUATOR CUE: The red close light is LIT.
COMMENTS:
- 6.
Determine voltage difference between 6.1 Candidate locates MG21 set voltage indicator.
the two generators is less than 5.0 volts.
6.2 Observe difference between it and MG22 set.
EVALUATOR CUE: Voltage on MG21 set is 260 VAC.
COMMENTS:
RTL#A5.640U 1/2-ADM-1303.F02 Page 6 of 6 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE
- 8. Return MG22 synchronize switch to the "OFF" position.
8.1 Candidate simulates placing MG22 synchronize switch in the "OFF" position.
COMMENTS:
STOP TIME:
JPM NUMBER: 2PL-003 JPM TITLE: Startup A Rod Drive MG Set WPM REVISION: 2a STEP STANDARD
( "C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)='
S/U 7.C Place MG22 synchronize switch to 7.1 Candidate locates MG22 synchronize switch.
the "ON" position.
7.2.C Simulates placing it in the "ON" position.
EVALUATOR CUE: MG22 generator output breaker red light is LIT and the generators are synchronized.
COMMENTS:
RTL#A5.640U 1/2-ADM-1303.F02 Page 1 of 5 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE "1PM NUMEBER: 2PL-021I JPM TITLE: Shutdown Uninterruptible Power Supply [UPS*VITBS2-3] j K/A
REFERENCE:
057AA1.01 3.7/3.7 TASK ID:
0361-005-06-013 JPM APPLICATION:
E]
REQUALIFICATION Z
INITIAL EXAM E] TRAINING
[]
FAULTED JPM
[-
ADMINISTRATIVE JPM EVALUATION METHOD:
LOCATION:
TYPE:
ADMINISTERED BY:
F-- Perform Z
Plant Site Annual Requal Exam BVT Z
Simulate 1-Simulator Z
Initial Exam
[
NRC F-1 Classroom
-] OJT/TPE
[
Other:
-] Training
[---] Other:
EVALUATION RESULTS Performer Name:
Performer SSN:
Time R-- Yes
[Allotted 15 minutes
]Actual minutes Critical:
Z No Time:
Time:
E A
1 SI' UNSAT (Comments required for UNSAT evaluation)
Comments:
OBSERVERS Name/S SN:
Name/SSN:
Name/SSN:I Name/SSN:
EVALUATOR Evaluator (Print):
Date:
Evaluator Signature:
RTL#A5.640U 1/2-ADM-1303.F02 Page 2 of 5 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2PL-021 JPM TITLE: Shutdown Uninterruptible Power Supply [UPS*VITBS2-3] I JPM REVISION: 4a I
EVALUATOR DIRECTION SHEET TASK STANDARD:
RECOMMENDED STARTING LOCATION:
DIRECTIONS:
INITIAL CONDITIONS:
INITIATING CUE:
REFERENCES:
TOOLS:
Uninterruptable Power Supply [UPS*VITBS2-3] is removed from service with the static switch isolated.
In Plant You are to simulate (perform) the task to Shutdown Uninterruptable Power Supply [UPS*VITBS2-3].
- Mode 1, 30% power.
"* Annunciator AI-IC "VITAL BUS 2-3 OPERATION/TROUBLE" has alarmed.
The corrective actions of 20M-38.4.AAA have been completed and it is necessary to transfer Vital Bus 2-3 to its alternate power source and shutdown the Inverter/Rectifier portion of UPS 2-3.
Your Supervisor directs you to remove Uninterruptable Power Supply
[UPS*VITBS2-3] from service and isolate the static switch. All initial conditions of 20M-38.4.J are satisfied.
20M-38.4.J, Rev. 3 None.
20M-38.4.J, Rev. 3 HANDOUT:
RTL#A5.640U 1/2-ADM-1303.F02 Page 3 of 5 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE CANDIDATE DIRECTION SHEET THIS SHEET TO BE GIVEN TO CANDIDATE Read:
Shutdown Uninterruptable Power Supply [UPS*VITBS2-3].
INITIAL CONDITIONS:
INITIATING CUE:
EJ El Mode 1, 30% power.
"* Annunciator Al-IC "VITAL BUS 2-3 OPERATION/TROUBLE" has alarmed.
" The corrective actions of 2OM-38.4.AAA have been completed and it is necessary to transfer Vital Bus 2-3 to its alternate power source and shutdown the Inverter/Rectifier portion of UPS 2-3.
Your Supervisor directs you to remove Uninterruptable Power Supply
[UPS*VITBS2-3] from service and isolate the static switch. All initial conditions of2OM-38.4.J are satisfied.
At this time, ask the evaluator any questions you have on this JPM.
When satisfied that you understand the assigned task, announce "I am now beginning the JPM".
Simulate performance or perform as directed the required task.
Point to any indicator or component you verify or check and announce your observations.
r, After determining the Task has been met announce " I have completed the JPM".
Then hand this sheet to the evaluator.
TASK:
RTL#A5.640U 1/2-ADM-1303.F02 Page 4 of 5 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM R EV : 4 2PL-021 PM TITLE: Shutdown Uninterruptible Power Supply [IPS*VITBS2-3] I STEP STANDARD
("C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)=>
S/U
~~ 2 ~~~
~~
START TIME:_________
EVALUATOR CUE: Provide Candidate a copy of 9.OM-3R 4 T
- 2. Verify Sync Loss indicating light is 2.1 Candidate locates Sync Loss indicating light and verifies that it is
'OFF'.
'OFF'.
EVALUATOR CUE: The Sync Loss indicating light ik OFF COMMENTS:
- 3. Notify NSS/ANSS to log TS 3.8.2.1 3.1 Candidate notifies ANSS/NSS to log Tech. Spec. 3.8.2.1 Action Action Statement entry.
Statement 'c' entry in the NOMS Daily Journal.
SEVALUATOR CUE: The NSS will make the entry.
COMMENTS:
4.C Transfer loads to the Static Switch.
4.1.C Candidate locates and depresses lower Static Switch DS1 18 pushbutton to transfer the static switch.
4.2 Candidate verifies static switch in the alternate position by observing Static Switch DS 118 red indicating light 'ON'.
EVALUATOR CUE: Static switch red indicating light is ON and the amber light is OFF.
COMMENTS:
RTL#A5.640U I/2-ADM-1303.F02 Page 5 of 5 Revision 0 OPERATIONS JOB PERFORMANCE MEASURE JPM NUMBER: 2PL-021 JPM TITLE: Shutdown Uninterruptible Power Supply [UPS*VITBS2-3] I JPM REVISION: 4a STEP STANDARD
( "C" Denotes CRITICAL STEP)
(Indicate "S" FOR SAT or "U" FOR UNSAT)>
S/U 5.C Place Manual Bypass Switch to the 5.1.C Candidate locates and places the Manual Bypass Switch S5 to BYPASS position.
the 'BYPASS' position.
I EVALUATOR CUE: Switch is in BYPASS.
COMMENTS:
6.C Isolate the Inverter/Rectifier.
6.1.C Candidate locates and OPENS [UPS*VITBS2-31 breaker CB 13 1, DC Input Breaker.
6.2.C Candidate locates and OPENS [UPS*VITBS2-3] breaker CB 132, AC Input Breaker.
6.3.C Candidate locates and OPENS [UPS*VITBS2-3] breaker CB 133, Static Switch AC Output Breaker.
EVALUATOR CUE: If asked, all amber lights on the mimic panel de-energize. The static switch is to be isolated per the initiating cue.
COMMENTS:
7.C Secure the Static Switch.
7.1.C Candidate locates and OPENS [UPS*VITBS2-3] Breaker CB 2, Static Switch Bypass Input.
EVALUATOR CUE: Another Operator will place the spare battery charger in service.
COMMENTS:
STOP TIME: