IR 05000390/2022010

From kanterella
Jump to navigation Jump to search
Design Basis Assurance Inspection (Teams) Inspection Report 05000390/2022010 and 05000391/2022010
ML22301A010
Person / Time
Site: Watts Bar  Tennessee Valley Authority icon.png
Issue date: 10/28/2022
From: James Baptist
Division of Reactor Safety II
To: Jim Barstow
Tennessee Valley Authority
References
IR 2022010
Download: ML22301A010 (16)


Text

SUBJECT:

WATTS BAR NUCLEAR PLANT - DESIGN BASIS ASSURANCE INSPECTION (TEAMS) INSPECTION REPORT 05000390/2022010 AND 05000391/2022010

Dear Jim Barstow:

On September 15, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Watts Bar Nuclear Plant and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, James Baptist, Chief Engineering Branch One Division of Reactor Safety Docket Nos. 05000390 and 05000391 License Nos. NPF-90 and NPF-96

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000390 and 05000391

License Numbers:

NPF-90 and NPF-96

Report Numbers:

05000390/2022010 and 05000391/2022010

Enterprise Identifier:

I-2022-010-0039

Licensee:

Tennessee Valley Authority

Facility:

Watts Bar Nuclear Plant

Location:

Spring City, TN 37381

Inspection Dates:

August 22, 2022 to September 16, 2022

Inspectors:

P. Braxton, Reactor Inspector

C. Franklin, Reactor Inspector

J. Lizardi-Barreto, Reactor Inspector

M. Schwieg, Senior Reactor Inspector

S. Gardner, contractor

M. Yeminy, contractor

Approved By:

James Baptist, Chief

Engineering Branch One

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (teams) inspection at Watts Bar Nuclear Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

===71111.21M - Design Bases Assurance (DBA) Inspection The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:

Design Review - Risk-Significant/Low Design Margin Components (IP Section 02.02) (5 Samples)

(1) Unit 1 - Emergency Diesel Generator 125VDC Control Power System and Governor Controls

Design bases documents, system descriptions, and training documents

Primary design calculations

Normal and Emergency Operating Procedures

Surveillance Test Procedures and Recent Results

Material Condition of Batteries, Rack, Charger and Governor

Vendor Manuals for Batteries, Charger, and Governor

Corrective Action History

Circuit Protection Scheme

(2)120V AC Vital Inverters

Operating Experience

Preventative Maintenance/Repair history

System Health Report

Corrective Action History

(3) Essential Raw Cooling Water Pumps

Design bases documents, system descriptions, and training documents

Primary design calculations

Normal and Emergency Operating Procedures

Inservice Test Procedures and Recent Results

Bases for Pump Test Acceptance Criteria

Calculation of Pump Capacity

Calculation of Pump NPSH

Material Condition of ERCW Pumps Vendor Manuals for Pump and Motor

Corrective Action History

(4) Component Cooling Water Heat exchangers

System P&ID

System Design Basis Documents

Normal operating procedures

System health reports

Design calculations

Condition reports issued since last DBAI

GL89-13 program and commitments

Completed surveillance tests

(5) Emergency Diesel Generator fuel transfer system

System P&ID

Vendor pump head capacity

Pump NPSH

Normal and abnormal operating procedures

Surveillance test

System health report

Preventive maintenance for inspection and lubrication

Condition reports issued since last DBAI

Design calculations Design Review - Large Early Release Frequency (LERFs) (IP Section 02.02)===

(1) FCV 63-73 RHR containment sump suction valve

System P&ID

System Design Basis Documents

Normal operating procedures

System health reports

Design calculations

Condition reports issued since last DBAI

Completed surveillance tests

Modification Review - Permanent Mods (IP Section 02.03) (5 Samples)

(1) WBN-20-1243-01, EDG Governor Actuators Replacement and Alarm Removal
(2) WBN-19-501, AFW Check Valve Modification for Water Hammer Resolution (3)

===66683, Revise Emergency Diesel Generator Overcurrent

(50) Relay Setpoints for EDG 1A-A, 1B-B, 2A-A, and 2B-B.

(4)100506-01, Throttle 1-THV-067-0643B-B and 1-THV-067-0646B-B and reduce design ERCW Flow to EBR Chillers A-A AND B-B

(5) WBN-19-491, Add T-Drain to 2-FCV-63-73, 2-FCV-72-44, & 2-FCV-72-45 Review of Operating Experience Issues (IP Section 02.06)===
(1) Information Notice 2010-23: Malfunctions of Emergency Diesel Generator Speed Switch Circuits
(2) Information Notice 2017-06: Battery and Battery Charger Short-Circuit Current Contribution to a Fault on the Direct Current Distribution System

INSPECTION RESULTS

Very Low Safety Significance Issue Resolution Process: Capability of Diesel Building Ventilation System to Withstand the Effects of a design basis Tornado 71111.21 M

This issue is a current licensing basis question and inspection effort is being discontinued in accordance with the Very Low Safety Significance Issue Resolution (VLSSIR) process. No further evaluation is required.

Description:

The DBAI inspectors identified an issue of concern in that the diesel building ventilation system does not appear to be designed to withstand the effects of a tornado depressurization event during two scenarios. First, a passing tornado may hit the side of the Diesel Generating Building (EDB) through which the blowers exhaust building air to ambient.

The pressure differential could potentially damage the ventilation system blowers and ductwork. Second, a tornado strike could occur without any warning and the operators would fail to start the blowers to open the inlet and exhaust dampers. The tornado pressure differential could damage the dampers. The result is a potential challenge to the diesel building ventilation system and subsequent unknown impact to the emergency diesel generators (EDGs) to maintain their safety functions due to rapidly increasing room temperatures.

The diesel building ventilation system consists of two large (each 50 percent capacity)ventilation fans, ducts, and dampers that are arranged to maintain minimum ventilation requirements during diesel operation. The maximum temperature expected in the Diesel Building is 120°F.

Calculation TIECS40, DIESEL GENERATOR BUILDING TORNADO DEPRESSURIZATION, Rev. 2, was performed to determine the pressures experienced in the EDG building in general and the ventilation system in particular. The calculation assumes that immediately following a tornado hit, the pressure differentials within the building and the ambient will be equalized immediately.

The inspectors reviewed the calculation and proposed that the licensee did not consider the pressure differential associated with a tornado approaching the EDG building. First, the inspectors assert that the calculation did not consider the impacts on the tornado direction. If the tornado hits the EDB from the north or south side, where the discharge of the two blowers is located, there would be an initial pressure differential between the fans outlet and their inlet openings. Second, the calculation input assumed the tornado translational speed was 60 mph. The inspectors could not review a calculation that evaluated lower tornado translational speeds (i.e. 60 mph to 5 mph). The inspectors believe that, with lower speeds, the pressure differentials within the building would not equalize immediately with ambient.

The licensee stated that the requirement to analyze a tornado with a translational velocity of less than 60 mph is outside of the WBN design basis and licensing basis. To support this claim, the licensee provided the following quote from the plants SER: All seismic Category I structures exposed to tornado forces and needed for the safe shutdown of the plant were originally designed to resist a design-basis tornado consisting of the following parameters: a 300-mph tangential wind velocity; a 60-mph translational wind velocity; a total pressure drop of 3 psi at the rate of 1 psi per second; and a postulated spectrum of tornado missiles that was appropriate. The inspectors postulate that this maximum translational speed bounds certain design concerns related to the structure but not necessarily systems that support the EDGs.

Finally, the calculation assumed that upon notification of a tornado warning, the operators will immediately (prior to the tornado whose translational speed is 60 mph hitting the building)turn two switches located in the EDG building to the tornado bypass position which will start the blowers and open the inlet and outlet dampers. The inspectors were concerned that not all tornado hits are preceded by tornado warnings. The inspectors reviewed data by the NOAA and NWS capturing the probability of detection (POD) of a tornado and the lead time to being hit by the tornado. Over a five-year period (2016 to 2020), the average POD was 60% with the average response time of 8.8 minutes. In other words, there could be a 40%

probability of a tornado strike without any detection. The inspectors' concern is that, if the operator failed to start the blowers, the tornado induced differential pressure across the dampers in the closed position could damage the dampers and result in a partial or complete loss of ventilation to the diesel generating room.

The inspectors believe the maximum pressure differential would be in the range of 1.0 to 3.0 psi (27.7 inches of water to 83.1 inches of water) between the fans outlet and their inlet openings depending on the size of the tornado. This caused the inspectors to question the capability of the blowers/dampers/ductwork to withstand higher pressure differential. The licensee stated that the blowers are rated to 5 inches of water or 0.2 psi. Even though the blowers appear to be robust, the licensee did not provide any additional data that may suggest capability to withstand higher pressure differentials. The vendor data for the installed air intake dampers did not contain pressure limits for the dampers. Based on generic manufacturers data for similar dampers, the inspectors believe that this type of dampers can withstand a maximum dP range of 14.8 in of water or 0.53 psi. The licensee was unable to provide any data on the maximum design dP of the ductwork.

The inspectors postulate that the blowers/dampers/ductwork would potentially not withstand a pressure differential of 1.0 to 3.0 psi. The ductwork could collapse, and the blowers/dampers would fail. However, these failures could be recoverable in an emergency. The inspectors did not evaluate the potential impact of the loss of the diesel building ventilation system, though the inspectors estimated that without recovery actions, with the loss of both ventilation blowers, at maximum ambient conditions, the emergency diesel generators could exceed their design ambient temperature within an hour or two.

Licensing Basis: The NRC staff reviewed the licensing basis documents, regulatory requirements, and regulatory correspondence related to the diesel building tornado protection criterion. The main documents reviewed are detailed below.

USFAR 2.3.1.3 Severe Weather - For the additional Diesel Generator Building and structures initiated after July 1979, the design basis tornado parameters are as follows:

1. 290 mph = Rotational Speed 2. 70 mph = Translational Speed

3. 360 mph

= Maximum Wind Speed 4. 3 psi = Pressure Drop 5. 2 psi/sec = Rate of Pressure Drop (3 psi/1.5 sec is assumed)

UFSAR 9.4.5.2.1.3, Item 4 states: During tornadoes, the essential components of the system remain functional because they are located in a Seismic Category I structure that is designed to resist damage by tornado missiles. For tornado depressurization mitigation, intake, and exhaust dampers are opened to assist in pressure equalization.

UFSAR Table 9.4-4: for components 2-FCO-30-444-A for Train 2A-A, 2-FCO-30-446-B for Train 2B-B, Tornado induced differential pressure across damper in closed position could damage damper and result in partial or complete loss of ventilation to DG room. Note that the damper may be closed in case of a tornado that was not preceded with a tornado warning. Also note that this may be a common cause failure that may affect all Emergency Diesel Generators.

UFSAR 9.5.8.2, System Descriptions, states: the major components of the diesel generator combustion air and exhaust systems are housed within the Diesel Generator Building which provides protection from missiles, snow, and ice. That portion of the exhaust subsystems exposed above the roof level is short and below the parapet level to reduce the vulnerability to tornado missiles.

10 CFR 50, Appendix A, I. Overall Requirements, Criterion 2Design bases for protection against natural phenomena: Structures, systems, and components important to safety shall be designed to withstand the effects of natural phenomena such as earthquakes, tornadoes, hurricanes, floods, tsunami, and seiches without loss of capability to perform their safety functions. The design bases for these structures, systems, and components shall reflect:

(1) Appropriate consideration of the most severe of the natural phenomena that have been historically reported for the site and surrounding area, with sufficient margin for the limited accuracy, quantity, and period of time in which the historical data have been accumulated,
(2) appropriate combinations of the effects of normal and accident conditions with the effects of the natural phenomena and
(3) the importance of the safety functions to be performed.

10 CFR 50, Appendix B, Criterion III, Design Control: Measures shall be established to assure that applicable regulatory requirements and the design basis, as defined in 10 CFR 50.2 and as specified in the license application, for those structures, systems, and components to which this appendix applies are correctly translated into specifications, drawings, procedures, and instructions.

Regulatory Issue Summary (RIS) 2006-23: Notifies licensees of its regulatory position regarding loading effects caused by natural phenomena to safety related systems and components housed inside a structure partially exposed to the outside environment, specifically ventilating and air-conditioning (VAC) systems housed in the EDG room.

WBN is not committed to NUREG 1.76, though the WBNs SER specifies the same tornado parameters and values as Rev. 0 of NUREG 1.76.

Ultimately, the inspectors' conclusion differed from that of the licensee as to whether the current licensing basis analysis of a design basis tornado could inflict conditions which are more limiting than those assumed in the licensees calculation.

Significance: A risk evaluation was performed by a regional senior reactor analyst (SRA)using SAPHIRE Version 8.2.6 and NRC Watts Bar model version 8.67 dated 6/23/2021. The conditional analysis assumed failure of the diesel building ventilation fans for tornado initiating events with wind speeds

(1) greater than 200 mph,
(2) 166 - 200 mph, and
(3) 136-165 mph)with a one-year exposure time. The SRA also credited operator actions to open the EDG building dampers upon receipt of a tornado warning. This was done by adjusting the EDG Failure to run probability to 0.5. This is conservative because it is recognized the room heat up would likely take approximately 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> to exceed design limits and equipment failures would also occur sometime after this temperature limit is reached. The dominant sequences were a tornado initiator accompanied by a loss of offsite power with failures of the emergency diesel generators and the turbine driven Auxiliary feedwater pump with operators failing to recover offsite power or and emergency diesel generator. The analysis determined that if a performance deficiency was assumed to have existed, it would result in an increase in core damage frequency of <1E-06/year and an estimated increase in large early release frequency of <1E-07/year, representing very low safety significance (Green).

Technical Assistance Request: No technical assistance was requested Corrective Action Reference: CR

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On September 15, 2022, the inspectors presented the Design Basis Assurance Inspection results to Tony Williams, site VP and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

EDQ00099920080014

Diesel Generator Loading Analysis

Rev. 39

EPM-JFL-120285

ERCW System Flow Requirements

Rev. 34

EPMRCT121490

ERCW Maximum Rejected Heat Load Requirement

Rev. 24

GEN-EEB-MS-TI28-

0001

Generic Accuracy Calculation for Non-Safety Related

Instrumentation

Rev. 0

SQN-CPS-007

Diesel Generator Battery Capacity

Rev. 0

TIECS40

Diesel Generator Building Tornado Depressurization

Calculations

WBEEBMSTI110062

25VDC Diesel Generator Control Power System

Evaluation

Rev. 32

1309040

Nonconforming Gasket on MSIV

06/20/2017

1345251

OE Review: NRC IN 17-6 Battery & Battery Charger

Short-Circuit

10/05/2017

1510550

2-FCV-63-72 Water Found Inside Limit Switch

Compartment

August 7,

2019

27123

T-08 WW 0819, WO 119839479 to perform VLF Testing

on the ERCW Pump Motor D-A cables was required

07/03/2019

1717990

ERCW G-B VLF Testing W/O 119402902 Work Delays

in WW 0823

09/20/2021

1791169

VLF Trend Results for ERCW Motor H-B Power Cables

08/16/2022

Corrective Action

Documents

773953

WBN Review of SQN PERs 763751 and 768294, Water

Intrusion into MOV Actuator Housings

September

15, 2017

1798208

22 WBN DBAI - Unvaulted SIs

August 24,

22

1802303

22 WBN DBAI DFOTP Skid Mounted Check Valves

09/14/2022

Corrective Action

Documents

Resulting from

Inspection

1802605

EDG HVAC Exhaust Blowers and Ductwork Rating

09/15/2022

0-45W727

6900V Diesel Generators Single Line

Rev. 2

0-45W760-82-1B

Units 1/2: Wiring Diagrams 6900V Standby Diesel

Generator 2A-A Schematic Diagrams

09/22/2015

0-45W760-82-2

Standby Diesel Generator System Schematic Diagrams

Rev. 1

0-45W760-82-3B

Units 1/2: Wiring Diagram Standby Diesel Generator

System Schematic Diagram DG 2A-A

10/08/2015

71111.21M

Drawings

0-45W760-82-6

Standby Diesel Generator System Schematic Diagrams

Rev. 2

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

0-47E235-77

Environmental Data Environment Harsh EL 685.0

Rev. 3

0-47W479-3

Mechanical Drains & Embedded Piping (Equipment

Drains)

Rev. 10

0-47W610-82-3

Units 1/2: Electrical Control Diagram DSL STG Air

System DG 2A-A

04/30/2015

0-47W611-82-4B

Electrical Logic Diagram DSL Gen System DG 2A-A

05/19/2015

0-47W840-1

Flow Diagram Fuel Oil Atomizing Air and Steam

1-47W845-1

Mechanical Flow Diagram, Essential Raw Cooling Water

System

Rev. 32

115E615

Motor Op Gate Valve Mod 18000GM84FEH01B 18-300

ASME C

L. 1, GPO ASSY

Rev. 0

1167E38

Motor Op Gate Valve Mod 12000GM82FBH01B 12-150

ASME C

L. 1, GPO ASSY

Rev. 0

17W910-1

Mechanical Heating and Ventilation

17W910-2

Mechanical Heating and Ventilation

2-47W576-100

Mechanical Motor Operated Valve Orientation and T-

Drain Requirements

Rev. 1

2-47W576-101

Mechanical Motor Operated Valve Orientation and T-

Drain Requirements

Rev. 1

5V159V00027

P&ID HVAC Miscellaneous Buildings Essential Cooling

Water Intake Structure & Electrical Equipment Room-

CWIS

0-45W760-82-3

Standby Diesel Generator System Schematic Diagrams

Rev. 1

WBN-19-491

Add T-Drain to 2-FCV-63-73, 2-FCV-72-44, & 2-FCV-72-

Rev. 0

WBN-19-501

AFW Check Valve Modification for Water Hammer

Resolution

Rev. 4

WBN-19-501-01

AFW Check Valve Modification for Water Hammer

Resolution - Unit 1 Train A

Rev. 3

WBN-19-501-02

AFW Check Valve Modification for Water Hammer

Resolution - Unit 1 Train B

Rev. 3

WBN-19-501-03

AFW Check Valve Modification for Water Hammer

Resolution - Unit 2 Train A

Rev. 3

Engineering

Changes

WBN-19-501-04

AFW Check Valve Modification for Water Hammer

Rev. 2

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Resolution - Unit 2 Train B

B26930924359

Justification for Use of Dow Corning RTV 738 Sealant on

Conduit Fittings and Junction Boxes for Flooding Due to

MELB

Rev. 1

CEB850214913

Summary of Piping Analysis Problem No. N3-63-08A

Rev. 11

CEB850214913

Summary of Piping Analysis Problem No. N3-63-08A

Rev. 8

WBN-VTD-W120-

2958

WESTINGHOUSE MOTOR OPERATED GATE

VALVES, MANUALLY

OPERATED GATE VALVES, SWING CHECK VALVES

[PUB. # 5710-99-H003]

Rev. 16

Engineering

Evaluations

WBN-VTD-W120-

5030

WESTINGHOUSE WATTS BAR UNIT 2 INSTRUCTION

BOOK FOR MOTOR OPERATED GATE VALVES,

MANUALLY OPERATED GATE VALVES AND SWING

CHECK VALVES

Rev. 3

CFR 50.55(e)

REVISED FINAL

REPORT

WATTS BAR AND BELLEFONTE NUCLEAR PLANTS

UNITS I AND 2 QUALIFICATIONN OF RR/DUR SUMP

VALVE ROOM NCRs WI NEB 8207 AND ELM MIB 8204

fBRD-50-390/82-42, WBID-50-391/82-39 &LR-50-

438/82-349 BLRD-50-439/82-31 10 CFR 50.55(e)

August 22,

1983

100506-01

Throttle 1-THV-067-0643B-B and 1-THV-067-0646B-B

and reduce design ERCW Flow to EBR Chillers A-A

AND B-B

3-OT-ECA0000

Operator Training, Emergency Contingency Actions

Rev. 17

B26850422023

Watts Bar Nuclear Plant - RHR SUMP Manways -

Deletion of Inspection Requirements from the FSAR

April 22,

1985

Datasheet Code US:

5-14-205

Kaowool Blanket SDS: 201

July 2018

N3-82-4002

Letter, Power Systems, Exhaust Temperature Data

10/12/1982

NETP-116.1

Inservice Testing Program Evaluations and Reference

Values

Rev. 1

NRC Inspection

Reports 50-390/83-46

and 50-391/83-35

Inspection on September 22 -October 22, 1933

November

2, 1983

Miscellaneous

SDD-N3-82-4002

Standby Diesel Generator System QA Record

Rev. 29

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

SDD-N3-82-4002

Standby Diesel Generator System

System 236 Health

Report

20VAC Vital Power, 125VDC Vital Power, 120VAC

Instrument Power, 120VAC Preferred Power, and

25VDC Emergency Diesel Generator Batteries

03/31/2022

WB-DC-30-27

AC & DC Control Power Systems

Rev. 35

WBN-SFCP-003

STRIDE Station Blackout Test and Slave Relay Testing

Rev. 0

WBN-VTD-A998-0040

Amtek Solidstate Controls Instruction and Operating

Manual Dual 20Amp Battery Chargers in Single

Rev. 1

WBN-VTD-B260-0020

Sulzer Pumps Installation, General Operation &

Maintenance Manual for TVA WBN ERCW Pumps

Sulzer Model 30cc 2 Stage Vertical

Rev. 2

WBN-VTD-C173-0070

C&D Technologies Standby Battery Vented Cell

Instructions

Rev. 8

WBN-VTD-FR03-

0010

Formsprag Installation Instructions General Purpose

Overrunning Clutches FSO 300 THRU 700, FSO 750

Thru 1027, FS 750 Thru 1027.

Rev. 7

WBN-VTD-SI06-0020

Instruction Book for Siemens Energy And Automation

Systems Essential Raw Cooling Water Pump Motors

Rev. 13

WBNEQ-MOV-001

Equipment Qualification Package Binder

Rev. 39

0-AOI-13

Loss of Essential Raw Cooling Water

Rev. 9

0-S I-67-901-A

O-SI-67-901-A Essential Raw Cooling Water Train A

Pumps Performance Test

Rev. 66

0-SI-215-1

Diesel Generator Battery Inspection

Rev. 25

0-SI-215-41-A

DG Battery Service Test and Charger Test

Rev. 21

0-SI-215-51-A

DG Battery Modified Performance Test and Charger

Test

Rev. 18

0-SI-215-65-A

Diesel Generator Battery Charging Test

Rev. 7

0-SI-67-918-A

0-SI-67-918-A Essential Raw Cooling Water Pump C-A

and Pump D-A Comprehensive Pump Test

Rev. 21

0-SI-82-11-A

Monthly DG Start and Load Test

Rev. 58

0-SI-82-11-A

Monthly DG Start and Load Test

Rev. 58

0-SOI-30.07

Shutdown Boardrooms HVAC Elevations 757 & 772

Procedures

0-TI-50.002

Diesel Generator 1A Fuel Oil Day Tank Pump Quarterly

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Performance Test

0-TI-50.003

Diesel Generator 1B Fuel Oil Day Tank Transfer Pump

Quarterly Performance Test

0-TI-50.004

, Diesel Generator 2A Fuel Oil Day Tank Transfer Pump

quarterly Performance Test

E-1

Loss of Reactor or Secondary Coolant

Rev. 18

EAP-82-2

Emergency Diesel Generator Local Control Emergency

Abnormal Operation

Rev. 0

ECA-0.0

Loss of All AC Power

Rev. 25

MMTP-141

Routine Inspection and Maintenance of Limitorque Motor

Actuators

Rev. 5

NEDP-2

Design Calculation Process Control

Rev. 26

NPG-SPP-09.1.21

Inservice Testing Program Evaluations and Reference

Values

Rev. 0

O-SI-67-917-A

O-SI-67-917-A Essential Raw Cooling Water Pump A-A

and Pump B-A Comprehensive Pump Test

Rev. 20

TI-100.002

Inservice Testing of Valves

Rev. 17

Self-

Assessments

Health Report

Scorecard

Safety Injection System 63

April 2022

118815050

Replace Nonforming Gasket on MSIV Zone Switches

09/25/2018

119205912

Troubleshoot/Repair Inverter 1-IV, Inverter Failed

11/20/2017

119317659

Year Capacitor, Circuit Board and Fan Assembly

Replacements for 120V Vital Inverters

01/27/2018

21659800

PMT EDG 1A Governor

2/05/2022

21852727

MMG to Install New Centrifugal Governor IAW WBN-20-

243-04

04/26/2021

21878127

Surveillance Task Sheet for Work Order Number

21878127

June 22,

22

2196540

O-SI-67-901-A Essential Raw Cooling Water Train A

Pumps Performance Test

01/22/2022

2403812

O-SI-67-901-A Essential Raw Cooling Water Train A

Pumps Performance Test

05/07/2022

2457198

Work Orders

2463381

O-SI-67-917-A Essential Raw Cooling Water Pump A-A

2/03/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

and Pump B-A Comprehensive Pump Test

2499568

2528922

0-SI-67-918-A Essential Raw Cooling Water Pump C-A

and Pump D-A Comprehensive Pump Test

2/05/2021

2561669

O-SI-67-901-A Essential Raw Cooling Water Train A

Pumps Performance Test

08/18/2022

2561676