IR 05000280/2020010
| ML20310A112 | |
| Person / Time | |
|---|---|
| Site: | Surry |
| Issue date: | 11/05/2020 |
| From: | James Baptist NRC/RGN-II |
| To: | Stoddard D Virginia Electric & Power Co (VEPCO) |
| References | |
| IR 2020010 | |
| Download: ML20310A112 (11) | |
Text
November 5, 2020
SUBJECT:
SURRY POWER STATION - DESIGN BASIS ASSURANCE INSPECTION (TEAMS) INSPECTION REPORT 05000280/2020010 AND 05000281/2020010
Dear Mr. Stoddard:
On October 2, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Surry Power Station and discussed the results of this inspection with Mr. Doug Lawrence, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
James B. Baptist, Chief Engineering Br 1 Div of Reactor Safety
Docket Nos. 05000280 and 05000281 License Nos. DPR-32 and DPR-37
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000280 and 05000281
License Numbers:
Report Numbers:
05000280/2020010 and 05000281/2020010
Enterprise Identifier: I-2020-010-0045
Licensee:
Virginia Electric and Power Company
Facility:
Surry Power Station
Location:
Surry, VA
Inspection Dates:
September 14, 2020 to October 02, 2020
Inspectors:
P. Braxton, Reactor Inspector
W. Deschaine, Senior Resident Inspector
A. Lerch, Reactor Inspector
R. Patterson, Senior Reactor Inspector
B. Pinson, Reactor Inspector
M. Riley, Senior Reactor Inspector
T. Su, Reactor Inspector
M. Yeminy, Contractor
Approved By:
James B. Baptist, Chief
Engineering Br 1
Div of Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (teams) inspection at Surry Power Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.
REACTOR SAFETY
===71111.21M - Design Bases Assurance Inspection (Teams)
The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:
Design Review - Risk-Significant/Low Design Margin Components (IP Section 02.02) (4 Samples)
- (1) Unit 1 Motor Driven Auxiliary Feedwater Pump 1-FW-P-3A
- Calculation for system flow rates, vortex limits, and net positive suction head for each pump
- Calculation for emergency condensate storage tank size, including high and low water levels
- Suction flow rates, including combined pump suction capabilities and transfer of flow rate to another source when tank level is low
- Material condition and configuration (e.g. visual inspection during a walkdown)
- Operating procedures
- Maintenance effectiveness
- Component health reports, corrective maintenance records, and corrective action history
- Operator actions
- Surveillance and calibration testing and recent test results
- Modifications performed
- (2) Unit 2 Auxiliary Building Backflow Preventers
- Calculations for expected internal flood heights in turbine and auxiliary buildings
- Updated Final Safety Analysis Report (UFSAR), including applicable design and licensing basis requirements
- Material condition and configuration (e.g. visual inspection during a walkdown)
- Time critical operator actions associated with internal flooding scenario
- Maintenance effectiveness
- Corrective action and corrective maintenance history
- Preventive maintenance history
- Component modification history
- (3) Unit 2 4160V 2H Emergency Bus
- Operating Environment
- Compliance with UFSAR, Technical Specifications (TS), and TS Bases
- Conformance with manufacturer instructions for installation, maintenance, and operation
- Material condition and configuration (e.g. visual inspection during a walkdown)
- Verification that system health reports accurately reflect current system conditions
- Design requirements (rating, loading, short circuit analysis, etc.)
- Protective relays and coordination
- Adequacy of corrective action activities
- (4) Emergency Diesel Generator #3 Output Breaker 25J3
- Operating Environment
- Compliance with UFSAR, TS and TS Bases
- Conformance with manufacturer instructions for installation, maintenance, and operation
- Material condition and configuration (e.g. visual inspection during a walkdown)
- Identification and follow-up of issues identified in system health reports
- Verification of system design requirements (Rating, loading, etc.)
- Adequacy of corrective action activities
Design Review - Large Early Release Frequency (LERFs) (IP Section 02.02)===
- (1) Unit 2 Main Steam Safety Valve (MSSV) 2-MS-SV-201A
- UFSAR, TS, and other design and licensing basis requirements
- MSSV capacity and system steam flow (normal and accident)
- MSSV seismic qualification
- Corrective actions
- In-service test requirements and required maintenance
- Susceptibility to tornado missiles
- Component condition and walkdown
- System health reports
Modification Review - Permanent Mods (IP Section 02.03) (6 Samples)
- (1) SU-18-00116, Stem and Disc Arm Replacement for 1-SI-MOV-1863A
- (2) SU-19-01068, Replacement of 01-FW-LT-1495-IXMITR
- (3) SU-19-00113, 1-RC-P-1A Abeyance Seal Upgrade
- (5) SU-19-01001, Replacement of Service Water Transmitter, 01-SW-FT-106A
- (6) SU-PTE-000, Fuel Oil Day Tank ASCO SOV Series 8210
Review of Operating Experience Issues (IP Section 02.06) (3 Samples)
- (1) NRC Information Notice 09-11, Configuration Control Errors
- (2) NRC Information Notice 15-01, Degraded Ability to Mitigate Flooding Events
- (3) NRC Information Notice 16-08, Inadequate Work Practices Resulting in Faulted Circuit Breaker Connections
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On October 2, 2020, the inspectors presented the design basis assurance inspection (teams) inspection results to Mr. Doug Lawrence, Site Vice President, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
71111.21M Calculations
ME-0747
MOV Differential Pressure Calculation for the LHSI Supply
Isolation Valves to the Charging Pump
Revision 0
ME-3330
JOG Calculation of Required Thrust Settings for MOV 1-SI-
MOV-1863A
Revision 4
14937.44-C-11
Main Steam Relief Valve Capacity Limits at 110%
Revision 1
DCP-00-20
Miscellaneous NSSS Protection and Control System
Setpoints
09/13/2001
EE-0339
Relay Setting Calculations for the Protection of Safety Bus
2H at Surry Power Station
Revision 0
EE-0879
SPS 4160V and 480 V Short-Circuit Analysis
Revision 0
ME-0277
North Anna 1&2 / Surry 1&2 Secondary-Side Design
Thermal Performance and Heat Balances
Revision 2
ME-0637
PEPSE Heat Balance Model for Surry Power Station Core
Uprate and Turbine Retrofit Projects
Revision 0
SM-796
Surry SGTR Analysis for Core Uprate Condition
Revision 0
SU-CALC-EEP-
EE-0336
Protective Relay Setting
Revision 0
SU-CALC-EEP-
EE-0336
Protective Relay Settings
Revision 0
Corrective Action
Documents
CRs 570285,
1098552,
1109856,
1148513, 360054,
518985
Various Corrective Action Reports
Various
Corrective Action
Documents
Resulting from
Inspection
CR 1155555
JOG Classification Documented in a Superseded
Engineering Technical Evaluation (ETE)
09/16/2020
CR 1155602
Error in Calculation SU-CALC-ICC-EE-0111
09/17/2020
CR 1156028
Calculation Error in PQE
09/22/2020
CR 1156261
PQE Review for 3152N Rosemount Transmitter
09/24/2020
CR 1156667
Non-Safety Classification of Backflow Preventers
09/29/2020
CR 1156851
Periodic Testing of Circuit Breaker 25J3 Undervoltage Relay
10/01/2020
Drawings
11448-FE-1A2
Electrical Power Distribution - One Line Integrated
Revision 44
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Schematic
SU-DWG-000-
11448-FM-068A
AFW System Flow Diagrams
Revision 65
SU-DWG-000-
11448-FM-089A
Safety Injection Flow Diagram
Revision 54
SU-DWG-000-
11448-FM-089B
Safety Injection Flow Diagram
Revision 35
Engineering
Changes81-050
EDG Transfer Bus Mod 2 Second Delay
10/09/81
DCP 00-049
EDG Output Breaker Circuit Modification and Relay Setpoint
Change/Surry/Unit 1 & 2
07/12/01
SU-19-00113
1-RC-P-1A Abeyance Seal Upgrade
08/29/2019
SU-19-01001
Replacement of Service Water Flow Transmitters
Revision 1
SU-19-01068
Replacement of 01-FW-LT-1495-IXMITR
Revision 0
SU-PTE-000
Fuel Oil Day Tank ASCO SOV Series 8210
Version 01
Engineering
Evaluations
CT-EQUAL-000-
PQE-08.27-P01
3154N Pressure Transmitters
Revision 2
D2013003
IEEE Qualification Report of Rosemount 3154N Pressure
Transmitters
Revision B
EE-0116
Allowable Custom Values for North Anna Improved
Technical Specifications (ITS) Tables 3.3.1-1 and 3.3.2-1
and Setting Limits for Surry Technical Specifications (CTS),
Sections 2.3 and 3.7
Revision 17
EE-0432
CSA Calculation for Surry Power Station, Steam Generator
Narrow Range Level, Units 1 & 2
Revision 5
ET-NAF-07-0092
Evaluation of Main Steam Exhaust Piping Vulnerability to
Tornado Generated Missiles at North Anna and Surrv
Revision 0
ETE-CEE-2016-
0006
Performance Specification for Rosemount 3153N and
3154N Series Transmitters
Revision 0
ETE-SU-2015-
0069
Design Basis for Backflow Preventers in Charging Pump
Cubicles, MER 3, MER 4, and MER 5
Revision 0
ETE-SU-2020-
0037
Main Steam Safety Valves and Pressurizer Safety Valves
repaired/refurbished without SCM Vendor Surveillance
Revision 0
PA3035300
Evaluate IN 16-08
08/21/16
SU-EQUAL-000-
3154N Pressure Transmitters EQ Evaluation
Revision 2
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
PQE-08.27-P01
Miscellaneous
Surry EQML
09/17/2020
CT-EQUAL-000-
GQE-08.27-G01
3154N Series Transmitters Rosemount Report
Revision 0
D2013003
IEEE Qualification Report for Rosemount 3154N Pressure
Transmitters
Revision B
ET-CEM-99-0009
Spectral Peaks and Zero Period Accelerations (ZPA) - OBE
and DBE Surry Power Station - Units 1 and 2
Revision 0
ME-0009
Design Specification for Reactor Coolant Pump N-9000 Seal
Assembly
Revision 001
OEE000707
OPEX002248: IN 2009-11 Configuration Control Errors
04/05/2010
PI-AA-100-1007-
Attachmentt 9
NRC Information Notice 2016-08
08/10/16
PIR 1040648
IN 16-08, Inadequate Work Practices Resulting in Faulted
Circuit Breaker Connections
06/30/16
SDBD-SPS-EG
System Design Basis Document for Emergency Diesel
Generator System, Surry Power Station
Revision 24
SDBD-SPS-FW
System Design Basis Document for Feedwater System
Surry Power Station
Revision 18
SU-EQUAL-000-
38-EZD
Surry Environmental Zone Description Units 1 & 2
Revision 29
Procedures
0-AP-13.00
Turbine Building or MER 3 Flooding
Revision 33
0-AP-13.01
Uncontrollable Turbine Building Flooding
Revision 10
0-AP-13.02
Loss of ESGR Cooling
Revision 11
0-DRP-049
Time Critical Operator Actions
Revision 19
0-OSP-TCA-001
Time Critical Operator Action Validation
Revision 22
1-AP-9.02
Loss of RCP Seal Cooling
Revision 14
1-AP-9.02
Loss of RCP Seal Cooling
Revision 14
2-DRP-006
Protective Relay Setpoints
Revision 28
2-MPT-0427-02
Main Steam Safety Setpoint Verification
Revision 12
CFR 50.59 and 10 CFR 72.48 - Changes, Tests, and
Experiments
Revision 13
DNES-AA-MEL-
4001
Determining the Safety Classification of Structures,
Systems, and Components
Revision 3
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
ER-AA-IST-103
ASME IST Program - Inservice Testing of Pressure Relief
Devices
Revision 3
ER-AA-IST-PRD-
103
ASME IST Program - Inservice Testing of Pressure Relief
Devices Implementation
Revision 1
Operating Experience Program
Revision 2
Work Orders
203877019,
38103441574,
38103791010,
204185642,
204185670,
204209440,
204209678,
204210949,
38102151703,
204036719,
203920040,
38103690022,
381021411743,
38102166449,
38103724130,
203871047