MONTHYEARHNP-11-001, Request for License Amendment, Measurement Uncertainty Recapture Power Uprate2011-04-28028 April 2011 Request for License Amendment, Measurement Uncertainty Recapture Power Uprate Project stage: Request ML11165A1862011-06-10010 June 2011 NRR E-mail Capture - FW: Acceptance Review for Harris 1 Measurment Uncertainity Recapture (MUR) TAC ME6169 Project stage: Acceptance Review ML11206A4962011-06-29029 June 2011 NRR E-mail Capture - Draft RAI Questions to Support Harris MUR Review (ME6169) Project stage: Draft RAI ML11181A0162011-07-0101 July 2011 Acceptance for Review of Measurement Uncertainty Recapture Power Uprate License Amendment Request Project stage: Acceptance Review ML11208C5092011-07-27027 July 2011 NRR E-mail Capture - Request for Additional Information Shearon Harris Unit 1, License Amendment Request Measurement Uncertainty Recapture Power Uprate Project stage: RAI ML1122001162011-07-29029 July 2011 NRR E-mail Capture - Shearon Harris Unit 1 - Measurement Uncertainty Recapture - MUR RAI (Cont/Vent) ME6169 Project stage: RAI ML11213A0002011-07-29029 July 2011 NRR E-mail Capture - Measurement Uncertainty Recapture Power Uprate - MUR RAI (HP-HPB)(ME6169) Project stage: RAI HNP-11-073, Response to Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate License Amendment Request2011-08-0303 August 2011 Response to Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate License Amendment Request Project stage: Response to RAI ML11213A1792011-08-0505 August 2011 Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate Project stage: RAI ML11214A0792011-08-0505 August 2011 Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate Project stage: RAI ML11214A1742011-08-0505 August 2011 Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate Project stage: RAI ML11222A1492011-08-0808 August 2011 NRR E-mail Capture - Measurement Uncertainty Recapture Power Uprate - MUR RAI (Mat)(ME6169) Project stage: RAI ML11222A1482011-08-0808 August 2011 NRR E-mail Capture - Measurement Uncertainty Recapture Power Uprate - MUR RAI (EMCB)(ME6169) Project stage: RAI HNP-11-076, Response to Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate License Amendment Request2011-08-15015 August 2011 Response to Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate License Amendment Request Project stage: Response to RAI HNP-11-034, Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule2011-08-16016 August 2011 Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule Project stage: Request HNP-11-079, Response to Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate License Amendment2011-08-31031 August 2011 Response to Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate License Amendment Project stage: Response to RAI ML11256A0262011-09-0606 September 2011 Response to Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate License Amendment Request Project stage: Response to RAI HNP-11-082, Response to Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate License Amendment Request2011-09-0707 September 2011 Response to Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate License Amendment Request Project stage: Response to RAI ML11271A1652011-09-28028 September 2011 NRR E-mail Capture - Additional MUR RAI (EEB)(ME6169) Project stage: RAI ML11272A0652011-09-28028 September 2011 NRR E-mail Capture - Additional MUR RAI (Emcb Part 2)(ME6169) Project stage: RAI ML11276A1872011-09-30030 September 2011 NRR E-mail Capture - MUR RAI (Cvib)( ME6169) Project stage: RAI ML1127300822011-09-30030 September 2011 Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate Project stage: RAI ML11276A1022011-10-14014 October 2011 Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate Project stage: RAI ML11276A1052011-10-14014 October 2011 Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate Project stage: RAI ML11278A1702011-10-14014 October 2011 Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate Project stage: RAI ML11276A1072011-10-18018 October 2011 Request for Additional Information Regarding Measurement Uncertainty Recapture Project stage: RAI HNP-11-094, Response to Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate (RAI 8)2011-10-20020 October 2011 Response to Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate (RAI 8) Project stage: Response to RAI HNP-11-095, Request for License Amendment Measurement Uncertainty Recapture Power Uprate Response to Request for Additional Information (RAI 9)2011-10-21021 October 2011 Request for License Amendment Measurement Uncertainty Recapture Power Uprate Response to Request for Additional Information (RAI 9) Project stage: Response to RAI HNP-11-096, Request for License Amendment Measurement Uncertainty Recapture Power Uprate Response to Request for Additional Information (RAI 10)2011-10-28028 October 2011 Request for License Amendment Measurement Uncertainty Recapture Power Uprate Response to Request for Additional Information (RAI 10) Project stage: Response to RAI HNP-11-107, Supplement to Request for License Amendment Measurement Uncertainty Recapture Power Update2011-11-28028 November 2011 Supplement to Request for License Amendment Measurement Uncertainty Recapture Power Update Project stage: Supplement ML11340A0812011-12-0909 December 2011 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance HNP-11-097, Request for License Amendment - Measurement Uncertainty Recapture Power Uprate Supplemental Information2011-12-20020 December 2011 Request for License Amendment - Measurement Uncertainty Recapture Power Uprate Supplemental Information Project stage: Supplement ML11356A1592012-02-0808 February 2012 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML11356A1542012-02-0808 February 2012 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance HNP-12-002, Request for License Amendment Measurement Uncertainty Recapture Power Uprate Supplemental Information2012-02-0909 February 2012 Request for License Amendment Measurement Uncertainty Recapture Power Uprate Supplemental Information Project stage: Supplement HNP-12-044, Response to Request for Additional Information on License Amendment Request - Measurement Uncertainty Recapture Power Uprate2012-03-26026 March 2012 Response to Request for Additional Information on License Amendment Request - Measurement Uncertainty Recapture Power Uprate Project stage: Response to RAI HNP-12-065, CFR 50.46 Annual Report of Changes to LOCA Analyses2012-05-30030 May 2012 CFR 50.46 Annual Report of Changes to LOCA Analyses Project stage: Request ML11356A0962012-05-30030 May 2012 Issuance of License Amendment Regarding Measurement Uncertainty Recapture Power Uprate Project stage: Approval HNP-12-069, Request for License Amendment Measurement Uncertainty Recapture Power Uprate Comments Re Amendment 1392012-06-0505 June 2012 Request for License Amendment Measurement Uncertainty Recapture Power Uprate Comments Re Amendment 139 Project stage: Request ML12157A2812012-06-11011 June 2012 Correction to Issuance of Amendment No. 139 Measurement Uncertainty Recapture Power Uprate Project stage: Approval 2011-08-15
[Table View] |
Text
~
Progress ne y May 30, 2012 Serial: HNP-12-065 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Shearon Harris Nuclear Power Plant, Unit 1 Docket No. 50-400 I Renewed Facility Operating License No. NPF-63 David H. Corlett Supervisor, Licensing/Regulatory Programs Harris Nuclear Plant Progress Energy Carolinas, Inc.
10 CFR 50.46
Subject:
10 CFR 50.46 Annual Report of Changes to LOCA Analyses Ladies and Gentlemen:
In accordance with 10 CFR 50.46(a)(3)(ii), Carolina Power & Light Company, doing business as Progress Energy Carolinas, Inc., hereby submits the annual report of changes to and errors discovered in the Loss of Coolant Accident (LOCA) analyses for the Shearon Harris Nuclear Power Plant, Unit 1 (HNP) for the period May 23,2011, through May 22,2012.
The previous HNP 10 CFR 50.46 annual report to the NRC, dated May 23,2011 (Serial: HNP-11-046), documented a Small Break LOCA Peak Cladding Temperature (PCT) of 1594°F and a Large Break LOCA PCT of2081 OF. For this reporting period, there have been no errors or changes in the LOCA analyses and the results stand as previously reported. The 10 CFR 50.46 annual report is enclosed.
This document contains no regulatory commitments. Please refer any questions regarding this submittal to me at (919) 362-3137.
Sincerely,
Enclosure:
10 CFR 50.46 Annual Report of Changes to LOCA Analyses cc:
Mr. 1. D. Austin, NRC Sr. Resident Inspector, HNP Ms. A. T. Billoch Colon, NRC Project Manager, HNP Mr. V. M. McCree, NRC Regional Administrator, Region II P.O. Box 165 New Hill, NC 27562 T> 919.362.3137
HNP-12-065 Enclosure Shearon Harris Nuclear Power Plant, Unit 1 Docket No. 50-400 / Renewed Facility Operating License No. NPF-63 10 CFR 50.46 Annual Report of Changes to LOCA Analyses
U.S. Nuclear Regulatory Commission Page 1 of 1 HNP-12-065 Enclosure Shearon Harris Nuclear Power Plant, Unit 1 10 CFR 50.46 Annual Report of Changes to LOCA Analyses Reporting Period May 23, 2011, through May 22, 2012 Small Break Loss of Coolant Accident (SBLOCA) Analysis Peak Cladding Temperature Evaluation Model: XN-NF-82-49(P)(A), Revision 1 Supplement 1, Exxon Nuclear Company Evaluation Model Revised EXEM PWR Small Break Model, Siemens Power Corporation, December 1994.
SBLOCA Peak Cladding Temperature (PCT) reported May 23, 2011 1594 °F Changes during reporting period None Errors during reporting period None Total PCT change during reporting period PCT = 0 °F End of Reporting Period SBLOCA PCT 1594 °F Large Break Loss of Coolant Accident (LBLOCA) Analysis Peak Cladding Temperature Evaluation Model: EMF-2087(P)(A), SEM/PWR-98: ECCS Evaluation Model for PWR LBLOCA Applications, Siemens Power Corporation, June 1999.
LBLOCA Peak Cladding Temperature reported May 23, 2011 2081 °F Changes during reporting period None Errors during reporting period None Total PCT change during reporting period PCT = 0 °F End of Reporting Period LBLOCA PCT 2081 °F