DCL-03-096, Day Response to Request for Information on Generic Letter 2003-01, Control Room Habitability

From kanterella
(Redirected from DCL-03-096)
Jump to navigation Jump to search
Day Response to Request for Information on Generic Letter 2003-01, Control Room Habitability
ML032310415
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 08/08/2003
From: Oatley D
Pacific Gas & Electric Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
DCL-03-096, GL-03-001, OL-DPR-80, OL-DPR-82
Download: ML032310415 (10)


Text

El Pacifc Gas and

.65 Electric Company David H. Oatley Diablo Canyon Power Plant Vice President and P0. Box 56 General Manager Avila Beach, CA 93424 August 8, 2003 Fax: 805.545.4234 PG&E Letter DCL-03-096 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 60-Day Response to Request for Information on Generic Letter 2003-01, "Control Room Habitability"

Dear Commissioners and Staff:

This letter is a response to the Nuclear Regulatory Commission's (NRC) request for information pursuant to Generic Letter (GL) 2003-01, "Control Room Habitability," dated June 12, 2003. This 60-day response letter is submitted because Pacific Gas and Electric (PG&E) does not believe that all the information requested can be provided by the requested completion date of 180 days from the date of GL 2003-01. Specifically, GL 2003-01 requests that licensees confirm the most limiting inleakage into the control room envelope by testing. Due to the time required to place a contract with a qualified tracer gas test contractor, and contractor availability, PG&E does not expect that testing will be completed prior to the requested 180-day completion date.

Since late 1999, PG&E has proactively participated in a joint-effort with the Strategic Teaming and Resource Sharing (STARS) alliance to confirm control room habitability of its facility. STARS consists of six plants operated by TXU Generation Company LP, AmerenUE, Wolf Creek Nuclear Operating Corporation, Pacific Gas and Electric Company, STP Nuclear Operating Company and Arizona Public Service Company. The STARS effort included a series of peer assessments performed during the year 2000 to demonstrate that control room habitability was maintained in accordance with regulatory requirements and the facility's design and licensing bases. The assessments concluded that each facility's control room(s) was designed and maintained such that the likelihood of unfiltered inleakage was low. In the absence of confirmatory testing, the assessments concluded that regulatory requirements and the design and licensing bases were met at each facility. In addition, the assessments concluded that confirmatory testing was necessary. The results of these assessments and the STARS plan to perform inleakage testing was A member of the STARS (Strategic Teaming and Resource Sharing) Alliance CalLaway

  • Comanche Peak
  • Diablo Canyon
  • Palo Verde
  • Wolf Creek

Document Control Desk PG&E Letter DCL-03-096 August 8, 2003 Page 2 reported to the NRC on March 5, 2001, "Submittal of the Strategic Teaming and Resource Sharing (STARS) Engineering Report on Control Room In-leakage (ULNRC-04402)."

STARS developed the "component test" referred to in NRC Regulatory Guide (RG) 1.197, "Demonstrating Control Room Envelope Integrity at Nuclear Power Reactor, May 2003." This test was determined to be a more suitable method for determining control room inleakage for the robust design, low-leakage control rooms characteristic of the STARS facilities. STARS provided information to the NRC in a letter on August 31, 2001, "Submittal of Strategic Teaming and Resource Sharing (STARS) Additional Information on Control Room Habitability (STARS-01002)," regarding the suitability of component testing at their facilities.

During the last few years, STARS has actively participated in various industry and public forums with the NRC to address issues surrounding control room habitability.

A central issue of those forums was what constitutes an acceptable test for control room inleakage. A number of licensees had tested their control rooms using a version of American Society for Testing and Materials (ASTM) consensus standard E741, "Standard Test Method for Determining Air Change in a Single Zone by Means of a Tracer Gas Dilution." STARS performed comparison testing between the ASTM E741 method and the component test method for two facilities' control rooms to validate the acceptability of the component test method. The testing demonstrated that the results of the two test methods correlated. In addition, the testing confirmed the previous assessment findings that the control rooms had a robust design and were maintained such that inleakage could be expected to be low. The tests determined that there was no control room unfiltered inleakage at each facility. The results of these tests were reported to the NRC in a letter on June 7, 2002, "Strategic Teaming and Resource Sharing (STARS) "Demonstration of the Component Test Method for Determining Control Room In-leakage" (STARS-02008)." The June 7, 2002, letter stated that STARS plants planned to use the component test method for any future baseline testing of their control rooms.

NRC RG 1.197 provides conditions for component testing to be acceptable for determining control room envelope integrity. RG 1.197 states that:

(1) an integrated test (i.e., the ASTM E741 method) should be conducted in concert with the component test, (2) the results of the two methods should correlate; and (3) the components tested should account for no less than 95 percent of the control room envelope inleakage as determined by the integrated test.

A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway

  • Comanche Peak
  • Diablo Canyon
  • Palo Verde
  • Wolf Creek

Document Control Desk PG&E Letter DCL-03-096 August 8, 2003 Page 3 RG 1.197 states these conditions are necessary when subsequent control room envelope integrity tests are intended to be component tests. Although PG&E believes that the component method has been adequately demonstrated as an acceptable stand-alone test, to be responsive to the requirements of GL 2003-01 and RG 1.197, PG&E intends to conduct correlation testing of its control room design using the two methods.

PG&E will schedule testing to occur as early as feasible and provide a detailed status of the testing schedule in the 180-day response to GL 2003-01. The 180-day response to GL 2003-01 will provide as much requested information as feasible in the absence of inleakage confirmation testing results. After testing is completed, a summary of the test results to confirm the most limiting inleakage and any impact of those results that cause previous submitted information to be modified will be submitted within 90 days of test completion. contains the 60-day response by PG&E to the requested information of GL 2003-01.

If you have any questions or require additional information, please contact Stan Ketelsen at (805) 545-4720.

Sincerely, David H. Oatley Vice President and General Manager - Diablo Canyon jer/3664 Enclosure cc:

Edgar Bailey, DHS Thomas P. Gwynn David L. Prouix Diablo Distribution cc/enc:

Girija S. Shukla A member of the STARS (Strategic Teaming and Resource Sharing) AlLiance CalLaway

  • Comanche Peak
  • Diablo Canyon
  • Palo Verde

Requested Information

1.

Confirm that your facility's CRE meets its applicable habitability regulatory requirements (e.g., GDC 1, 3, 4, 5, and 19) and that the CRE and CREHSs are designed, constructed, configured, operated, and maintained in accordance with the facility's design and licensing basis.

PG&E Response:

PG&E has not performed a tracer gas test to confirm that the most limiting unfiltered inleakage into the control room envelope is no more than the value assumed in its design basis radiological analyses for control room habitability.

See response to item 1 (a) below for more detail.

As stated in the Diablo Canyon Power Plant (DCPP) Final Safety Analysis Report Update (FSARU) Chapter 3, 'Design of Structures, Components, Equipment, and Systems," the DCPP units were designed to comply with the Atomic Energy Commission (AEC) (now the Nuclear Regulatory Commission, or NRC) General Design Criteria (GDC) for Nuclear Power Plant Construction Permits, published in July 1967. The DCPP construction permits were issued in April 1968 and December 1970 for Units 1 and 2, respectively. FSARU Appendix 3.1A lists the GDCs published as Appendix A to 10 CFR 50 in February 1971 and provides a discussion of conformance with the 1971 GDC (e.g., DCPP Units 1 and 2 conform to the intent of the 1971 GDCs 1, 3,4, 5, and 19).

PG&E, assisted by peers from the Strategic Teaming and Resource Sharing (STARS) alliance, performed a control room habitability assessment from February 8 through 11, 2000. In the absence of confirming testing for control room inleakage, the assessment confirmed that the control room habitability systems were designed, constructed, configured, operated, and maintained consistent with the control room habitability design and licensing bases. Some issues regarding control room design were identified during the assessment. These issues did not prevent meeting the GDCs. These issues were summarized in a report to the NRC on March 5, 2001, "Submittal of the Strategic Teaming and Resource Sharing (STARS) Engineering Report on Control Room In-leakage (ULNRC-04402)." The two issues identified for DCPP and their status are as 1

PG&E Letter DCL-03-096 follows (reference Appendix S of the March 2, 2001, STARS Engineering Report on Control Room In-Leakage):

Item Issue Status 2

The cable spreading room below the Design changes have been control room was essentially at the implemented to modify operation same pressure as the control room of the battery room ventilation when the HVAC system was operating system which was causing high in emergency mode.

pressure in the cable spreading room. Action is complete except for minor flow balancing to optimize system performance.

9 Any leakage past the normal exhaust Implementation of design dampers would be pulled into filter changes are in progress to unit and become potential additional provide isolation capability for filtered in-leakage not accounted for in damper inspection and the accident analysis. Any leakage maintenance. Following damper past the double isolation sets of inspection, and repairs if needed, normal supply and smoke exhaust component testing of the dampers is potential unfiltered in-dampers will be performed in the leakage. These potential sources of same time frame as tracer gas in-leakage require component testing.

testing to correlate the two tests.

The schedule for performing tracer gas and component testing will be provided in the 180-day response to GL 2003-01.

PG&E plans to review the assessment conclusions from 2000 to confirm they remain valid and to conduct any additional assessments (e.g. reactor control capability in the event of smoke) as required to confirm that regulatory requirements and the control room habitability design and licensing bases continue to be met. The results of any additional assessments will be reported in PG&E's 1 80-day response to GL 2003-01.

PG&E has established administrative controls that ensure continued compliance with the control room habitability design and licensing bases. A summary of these controls is provided below.

1. Surveillance Test Procedure (STP) M-6A, 'Routine Surveillance Testing of Control Room Ventilation System," tests the system's ability to function correctly including checking fan starts, damper lineups and preheater operation.

2

Enclosure I PG&E Letter DCL-03-096

2. STP M-53, 'Control Room Ventilation System - DOP and Halide Penetration Test," tests for filter bypass leakage, and includes the control room pressurization test.
3. STP M-70A, "Inspection of Fire Barrier and HELB Penetration Seals,"

inspects the adequacy of control room fire barrier and high energy line break (HELB) penetrations, and is used as a post maintenance test for new and existing penetrations of this type following installation, repairs or maintenance.

4. STP M-70C, "Inspection/Maintenance of Doors," inspects the adequacy of control room doors that provide one or more of the following functions; (1) fire door, (2) flood protection door, (3) HELB door, or (4) heating, ventilation or air conditioning (HVAC) door.
5. Administrative Procedure CF3.1D9, "Design Change Package Development,"

provides comprehensive review requirements for design modifications affecting the control room boundary.

6. Administrative Procedure AD7.DC8, "Work Control," provides controls for breaching the control room envelope, including envelope penetrations and control room doors.
7. Equipment Control Guideline 80.1, 'Doors Required for HELB, HVAC, or Flood Protection," provides controls for control room doors including completion times for nonfunctional and degraded control room doors. Also, compensatory measures are specified for cases in which a control room door must be held open for an extended period (such as for maintenance).

PG&E plans to continue to work in alliance with STARS to ensure that the control room habitability program is maintained in the long-term.

1(a) That the most limiting unfiltered inleakage into your CRE (and the filtered inleakage if applicable) is no more than the value assumed in your design basis radiological analyses for CRE habitability. Describe how and when you performed the analyses, tests, and measurements for this confirnation.

PG&E Response:

The large break loss-of-coolant accident (LOCA) and the fuel handling accident inside containment are currently the limiting control room dose analyses of record.

The calculated exposures to control room personnel for the large break LOCA are 30 rem thyroid and 0.12 rem whole body and the exposures for the containment fuel handling accident are 11.56 rem thyroid and 0.007 rem whole body.

3 PG&E Letter DCL-03-096 The accident analysis for the large break LOCA is discussed in FSARU Section 15.4.1. The radiological consequences are discussed in FSARU Section 15.5.17.3 and are tabulated in FSARU Table 15.5-63. A 10 standard cubic feet per minute (scfm) inleakage rate per NUREG-0800, Standard Review Plan, Section 6.4, was assumed in the analysis to account for the possible pathway through the single doors from the equipment condensing unit areas to the heating, ventilation, and air conditioning equipment room. Estimated post-accident exposures to control room personnel during egress-ingress are 4.7 rem thyroid and 0.0066 rem whole body (Reference FSARU Table 15.5-63). The egress-ingress exposures are not part of the assumed 10 scfm unfiltered inleakage contribution from NUREG-0800 and are incurred during transit outside of the control room envelope. Direct radiation exposures account for an additional 0.076 rem whole body. The remainder of the exposures (25.31 rem thyroid and 0.0398 rem whole body) are attributable to airborne fission products in the control room envelope.

The accident analysis for the fuel handling accident inside containment was submitted in License Amendment Request (LAR) 01-04 (PG&E Letter DCL 01-104 dated October 17, 2001) and approved by License Amendments No. 155 (Unit 1) and No. 155 (Unit 2) dated October 21, 2002. This analysis assumed that containment was open to the environment at the time of the accident and credited operation of the control room ventilation system after the initial release. An unfiltered inleakage rate of 10 cfm was assumed for the analysis. In the context of control room habitability, it should be noted that the fuel handling accident is a very short duration event (the event duration is 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />) and is insensitive to inleakage assumptions.

PG&E has not performed a test to confirm the accident analysis inleakage assumption. Assessments performed in 2000 determined that PG&E and each of the other STARS facilities' control room envelopes had minimal vulnerability to unfiltered inleakage. Integrated testing and component testing, as described in NRC Regulatory Guide 1.197, was performed at Comanche Peak and Palo Verde.

These test results validated the assessment findings for these facilities.

An integrated test and component test for control room inleakage are being planned for DCPP. This is to justify use of component tests for subsequent testing. Due to the time required to place a contract with a qualified tracer gas test contractor, and contractor availability, PG&E does not expect that testing will be completed prior to the requested 1 80-day completion date. PG&E will schedule testing to occur as early as feasible and provide a detailed status of the testing plan in the 180-day response to GL 2003-01.

DCPP will perform component testing in the same time frame as integrated testing for its common control room to allow the two test methods to be correlated. The 4

PG&E Letter DCL-03-096 results from the two test methods will meet the conditions specified in NRC Regulatory Guide (RG) 1.197.

1(b) That the most limiting unfiltered inleakage into your CRE is incorporated into your hazardous chemical assessment. This inleakage may differ from the value assumed in your design basis radiological analyses. Also confirm that the reactor control capability is maintained from either the control room or the alternate shutdown panel in the event of smoke.

PG&E Response:

During the 2000 assessments, PG&E determined that there were no offsite storage or transportation of chemicals that presented a hazard to control room habitability. In addition, there were no onsite chemicals that posed a credible hazard to control room habitability. Engineered controls for the control room are not required to ensure habitability against a hazardous chemical threat. Therefore, the amount of unfiltered inleakage is not incorporated into PG&E's hazardous chemical assessment. PG&E has re-reviewed the results of the hazardous chemical assessment performed in 2000 and has determined there has been no change. There are no offsite or onsite chemicals that would pose a credible hazard to control room habitability.

The 2000 assessments did not evaluate the reactor control capability in the event of smoke since this issue was not fully developed at that time. PG&E plans to evaluate reactor control capability in the event of smoke, consistent with Regulatory Position 2.6 of NRC RG 1.196, uControl Room Habitability at Light-Water Nuclear Power Reactors," dated May 2003, and report the results in the 1 80-day response to GL 2003-01.

1(c) That your Technical Specifications verify the integrity of your CRE and the assumed inleakage rates of potentially contaminated air. If you currently have a AP surveillance requirement to demonstrate CRE integrity, provide the basis for your conclusion that it remains adequate to demonstrate CRE integrity in light of the ASTM E741 testing results. If you conclude that your AP surveillance requirement is no longer adequate, provide a schedule for:

1) revising the surveillance requirement in your technical specification to reference an acceptable surveillance methodology (e.g., ASTM E-741), and
2) making any necessary modifications to your CRE so that compliance with your new surveillance requirement can be demonstrated.

5 PG&E Letter DCL-03-096 If your facility does not currently have a technical specification surveillance requirement for your CRE, explain how and on what frequency you confirm your CRE integrity.

PG&E Response:

PG&E's Technical Specifications (TS) require that a surveillance be performed on a 24-month staggered test basis to verify that one control room ventilation system (CRVS) train can maintain a positive pressure of grater than or equal to 0.125 inches water gauge, relative to the outside atmosphere during the pressurization mode of operation. The TS Bases state that this surveillance requirement verifies the integrity of the control room enclosure, and the assumed inleakage rates of potentially contaminated air.

PG&E believes that the positive pressure surveillance verifies the operability of the CRVS train and provides an indication of control room boundary integrity, although not confirmation. In light of the ASTM E741 testing results reported in GL 2003-01, inleakage testing appears to be the best method to confirm assumed inleakage rates of potentially contaminated air.

PG&E plans to submit a TS change to incorporate a Control Room Integrity Program that will include periodic verification of control room inleakage. This change is expected to be consistent with Industry/TSTF Standard Technical Specification Change Traveler, TSTF-448. PG&E is aware that the NRC is currently reviewing TSTF-448 and has not approved it yet. PG&E will submit a schedule for submittal of a TS change in its 180-day response to GL 2003-01.

PG&E does not believe any plant modifications are required, other than those already in progress, to incorporate a Control Room Integrity Program into TSs as described above.

It should be noted that PG&E has submitted LAR 03-05 (PG&E Letter DCL-03-034, dated April 2, 2003) which includes a change to TS 3.7.10, uControl Room Ventilation System (CRVS)," to add a new required action for two CRVS trains being inoperable due to an inoperable control room boundary. The proposed action has a completion time of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. The current TS requires entry into TS 3.0.3 for this condition. The proposed action, which is consistent with NUREG-1431, Revision 2, "Standard Technical Specifications Westinghouse Plants," dated April 2001 is intended to allow sufficient time to diagnose, plan, possibly repair, and test most problems that would occur with the control room boundary, without requiring entry into TS 3.0.3.

6 PG&E Letter DCL-03-096

2.

If you currently use compensatory measures to demonstrate CRE habitability, describe the compensatory measures at your facility and the corrective actions needed to retire these compensatory measures.

PG&E Response:

PG&E does not use compensatory measures to demonstrate control room envelope habitability.

PG&E performed a self-assessment of control room habitability in 2000 and concluded that regulatory requirements and the design and licensing bases were being met. PG&E plans to perform additional assessments and confirmatory inleakage testing. PG&E plans to submit a TS change to incorporate a Control Room Integrity Program that will include periodic verification of control room inleakage. These additional measures will provide assurance to demonstrate control room envelope habitability.

3.

If you believe that your facility is not required to meet either the GDC, the draft GDC, or the "Principle Design Criteria" regarding control room habitability, in addition to responding to items 1 and 2 above, provide the documentation (e.g., Preliminary Safety Analysis Report, Final Safety Analysis Report sections, or correspondence, etc.) of the basis for this conclusion and identify your actual requirements.

PG&E Response:

As stated in the response to Request for Information Item #1, the DCPP units were designed to comply with the AEC GDCs for Nuclear Power Plant Construction Permits published in July 1967. DCPP FSARU Appendix 3.1A provides a discussion of conformance with the 1971 GDCs (Appendix A to 10 CFR 50).

7