Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision
ML23263B129
Person / Time
Site: Browns Ferry, Watts Bar, Sequoyah  Tennessee Valley Authority icon.png
Issue date: 09/20/2023
From: Hulvey K
Tennessee Valley Authority
To:
Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation, Document Control Desk
References
CNL-23-061
Download: ML23263B129 (1)


Text

10 CFR 50.54(q) 10 CFR 72.44(f) 1101 Market Street, Chattanooga, Tennessee 37402 CNL-23-061 September 20, 2023 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Renewed Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, 50-296, and 72-052 Sequoyah Nuclear Plant, Units 1 and 2 Renewed Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327, 50-328, and 72-034 Watts Bar Nuclear Plant, Units 1 and 2 Facility Operating License Nos. NPF-90 and NPF-96 NRC Docket Nos. 50-390, 50-391, and 72-1048

Subject:

Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision In accordance with the requirements of Title 10 of the Code of Federal Regulations (10 CFR) 50.54(q) and 10 CFR 72.44(f), Tennessee Valley Authority (TVA) is submitting a description of changes to the TVA Radiological Emergency Plan (REP). The affected documents are the Central Emergency Control Center (CECC) Emergency Plan Implementing Procedure (EPIP) listed below.

Document Revision Title Effective Date CECC EPIP-12 37 Operational Readiness Check of the 8/31/2023 CECC and the Field Coordination Centers for SQN, BFN, & WBN and Joint Information Centers (JIC)

U.S. Nuclear Regulatory Commission CNL-23-061 Page 2 September 20, 2023 Description of Changes and Summary Analysis CECC EPIP-12 TVA revised this EPIP as follows.

Updated Attachment 3, CECC Quarterly Inventory and Operability Checks, to add communications checks between the Environs Radio Maestro VIP Console in the CECC and the radios in the field team vans at Browns Ferry Nuclear Plant (BFN), Sequoyah Nuclear Plant (SQN), and Watts Bar Nuclear Plant (WBN).

Relocated Attachment 7, BFN Joint Information Center Quarterly Inventory, in its entirety to the site-specific procedure, BFN EPIP-12, Emergency Equipment and Supplies, Attachment 17, BFN Joint Information Center (JIC).

Updated Attachment 9, SQN/WBN Additional Equipment Quarterly Inventory and Operability Check CECC Computer Room, to replace the Signal Mountain radio repeater with the Falling Water radio repeater.

The above changes were evaluated in accordance with 10 CFR 50.54(q)(3). TVA determined that the changes did not reduce the effectiveness of the TVA REP. The TVA REP, as revised, continues to meet the requirements in Appendix E to 10 CFR 50 and the planning standards of 10 CFR 50.47(b).

There are no new regulatory commitments in this letter. Please address any questions regarding this submittal to Stuart L. Rymer, Senior Manager, Fleet Licensing, at slrymer@tva.gov.

Respectfully, Kimberly D. Hulvey Director, Nuclear Regulatory Affairs cc:

NRC Regional Administrator - Region II NRC Senior Resident Inspector - Browns Ferry Nuclear Plant NRC Senior Resident Inspector - Sequoyah Nuclear Plant NRC Senior Resident Inspector - Watts Bar Nuclear Plant NRC Project Manager - Browns Ferry Nuclear Plant NRC Project Manager - Sequoyah Nuclear Plant NRC Project Manager - Watts Bar Nuclear Plant NRC Director - Division of Spent Fuel Management, NMSS Digitally signed by Edmondson, Carla Date: 2023.09.20 13:59:17 -04'00'