(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Letter Sequence Other |
|---|
|
|
MONTHYEARML22353A6422023-01-0505 January 2023 Terrapower - Audit Plan - Regulatory Management of Natrium Nuclear Island and Energy Island Design Interfaces Project stage: Other ML23257A2592023-09-28028 September 2023 Terrapower, LLC - Final Safety Evaluation for Topical Report NATD-LIC-Report-0001, Regulatory Management of Natrium Nuclear Island and Energy Island Design Interfaces, Revision 0 (CAC: 000431 / EPID: L-2022-TOP-0045) Project stage: Approval PMNS20240072, Status of the NRC Staffs Review of EPRI Technical Report 3002025288 Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components (Risk-Informed Cmpbc)2024-01-31031 January 2024 Status of the NRC Staffs Review of EPRI Technical Report 3002025288 Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components (Risk-Informed Cmpbc) Project stage: Approval ML24044A0002024-02-12012 February 2024 EPRI Technical Report 3002025288 Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components - NRC Public Meeting, February 12, 2024 Project stage: Meeting PMNS20240272, U. S. Nuclear Regulatory Commission (NRC) Public Meeting with the Nuclear Energy Institute (NEI) to Discuss the Review of NEI-99-01, Rev. 7, Development of Emergency Action Levels for Non-Passive Reactors2024-03-12012 March 2024 U. S. Nuclear Regulatory Commission (NRC) Public Meeting with the Nuclear Energy Institute (NEI) to Discuss the Review of NEI-99-01, Rev. 7, Development of Emergency Action Levels for Non-Passive Reactors Project stage: Request ML24054A0062024-03-29029 March 2024 Summary of Meeting to Discussion the Status of the NRC Staffs Review of Technical Report 3002025288 Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components Project stage: Meeting PMNS20240466, U. S. Nuclear Regulatory Commission (NRC) Public Meeting with the Nuclear Energy Institute (NEI) to Discuss the Review of NEI-99-01, Rev. 7, Development of Emergency Action Levels for Non-Passive Reactors2024-04-0404 April 2024 U. S. Nuclear Regulatory Commission (NRC) Public Meeting with the Nuclear Energy Institute (NEI) to Discuss the Review of NEI-99-01, Rev. 7, Development of Emergency Action Levels for Non-Passive Reactors Project stage: Request ML24100A0682024-04-0909 April 2024 Submittal of NRC Draft Slides for 04/20/2024 Meeting on Sufficiency Gaps Identified in EPRI Report 3002025288 on Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components (L-2023-TOP-0031) ML24117A2962024-04-23023 April 2024 E-Mail - EPRI Forwards Slides for Public Meeting on 4/30/2024 EPRI Report 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components Project stage: Meeting PMNS20240525, Sufficiency Gaps Identified in EPRI Report 3002025288 on Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components2024-04-26026 April 2024 Sufficiency Gaps Identified in EPRI Report 3002025288 on Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components Project stage: Other ML24100A0702024-04-30030 April 2024 Draft Slides for 04/30/2024 Meeting on Sufficiency Gaps Identified in EPRI Report 3002025288 on Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components ML24117A2562024-04-30030 April 2024 24-04-30 - Acceptance Review Status EPRI PRI TR 3002025288 Ri Cmpbc - NRC Slides Project stage: Acceptance Review ML24117A2592024-04-30030 April 2024 EPRI Technical Report 3002025288 Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components - NRC Public Meeting - April 30, 2024 Project stage: Meeting ML24117A2792024-06-10010 June 2024 Meeting Summary to Discuss Sufficiency Gaps Identified in EPRI Report 3002025288 on Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components Project stage: Meeting ML23352A0622024-07-11011 July 2024 NRC Form 898, Topical Report Completeness Determination, for EPRI Technical Report 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components (RI-CMPBC) (EPRI L-2023-TOP-0045) Project stage: Other ML23352A0582024-07-11011 July 2024 E-Mail - Acceptance of Electric Power Research Institute Technical Report 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components Project stage: Acceptance Review ML24166A0912024-07-16016 July 2024 NEI 99-01 R7 Meeting Summary March 15 and April 16, 2024 Project stage: Meeting ML24219A0222024-08-0101 August 2024 Change in Estimated Review Schedule for Electric Power Research Institute Report 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components Project stage: Other ML24211A0732024-08-0808 August 2024 Change in Estimated Review Schedule for Electric Power Research Institute Report 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components Project stage: Other ML24241A1662024-08-30030 August 2024 E-mail - Electric Power Research Institute Regulatory Audit in Support of Review of Technical Report 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components, Revision 0 Project stage: Approval ML24241A1732024-08-30030 August 2024 Electric Power Research Institute Regulatory Audit in Support of Review of Technical Report 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components, Revision 0 (EPID L?2023?TOP?0045) Project stage: Approval ML24352A4812025-01-13013 January 2025 Final Request for Additional Information - EPRI Report 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components Project stage: RAI ML24352A4712025-01-13013 January 2025 E-Mail - Final Request for Additional Information - EPRI Report 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components Project stage: RAI ML25063A2492025-03-0404 March 2025 Non Proprietary - EPRI 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components, RAI Responses - Draft for Public Meeting Only PMNS20250244, Public Meeting Between NRC and EPRI to Discuss the Status of Request for Additional Information Associated with the NRC Staffs Review of Report 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Componen2025-03-0505 March 2025 Public Meeting Between NRC and EPRI to Discuss the Status of Request for Additional Information Associated with the NRC Staffs Review of Report 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components Project stage: RAI ML25054A0012025-03-0606 March 2025 March 6, 2025, Public Meeting on Between NRC and EPRI on EPRI TR 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components, Requests for Additional Information Project stage: RAI ML25060A0012025-03-0606 March 2025 EPRI Slides for March 6, 2025, Public Meeting on EPRI Report 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components Project stage: Meeting ML25091A0932025-04-0101 April 2025 EPRI Report 3002025288 Requests for Additional Information Project stage: RAI PMNS20250361, Technical Discussion EPRIs Draft Responses to NRC Staff Issued Request for Additional Information for EPRI Report 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components2025-04-0202 April 2025 Technical Discussion EPRIs Draft Responses to NRC Staff Issued Request for Additional Information for EPRI Report 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components Project stage: Draft RAI ML25078A2682025-04-29029 April 2025 Summary of Technical Discussion on EPRIs Draft Responses to NRC Staff Issued Request for Additional Information for EPRI Report 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components Project stage: Draft RAI ML25163A0502025-06-11011 June 2025 EPRIs Thoughts and Response to the Limitations and Conditions in the Safety Evaluation for EPRI Report 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components Project stage: Other PMNS20250719, Discussion Between NRC and EPRI on the Proposed Limitations/Conditions in the NRC Staffs Safety Evaluation for Proprietary Review for EPRI Report 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Compon2025-06-11011 June 2025 Discussion Between NRC and EPRI on the Proposed Limitations/Conditions in the NRC Staffs Safety Evaluation for Proprietary Review for EPRI Report 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components Project stage: Approval 2024-07-11
[Table View] |
Text
To:
fferrante@epri.com CC:
Subject:
RidsNrrOd Resource <RidsNrrOd.Resource@nrc.gov>; RidsNrrDnrl Resource
<RidsNrrDnrl@nrc.gov>; RidsNrrDnrlNphp Resource <RidsNrrDnrlNphp.Resource@nrc.gov>;
RidsNrrDra Resource <RidsNrrDra.Resource@nrc.gov>; RidsNrrDraApla Resource
<RidsNrrDraApla.Resource@nrc.gov>; RidsNrrDorl Resource <RidsNrrDorl.Resource@nrc.gov>;
RidsNrrDorlLlpb Resource <RidsNrrDorlLlpb.Resource@nrc.gov>; RidsNrrLADHarrison Resource
<RidsNrrLADHarrison.Resource@nrc.gov>; RidsACRS_MailCTR Resource
<RidsACRS_MailCTR.Resource@nrc.gov>; Lois James <Lois.James@nrc.gov>; Gerond George
<Gerond.George@nrc.gov>; Jeff Circle <Jeff.Circle@nrc.gov>; Bob Pascarelli
<Robert.Pascarelli@nrc.gov>; Stephen Cumblidge <Stephen.Cumblidge@nrc.gov>; Matthew Mitchell Matthew.Mitchell@nrc.gov; fferrante@epri.com; PORegan@epri.com Change in Estimated Review Schedule for Electric Power Research Institute Report 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components (EPID: L-2022-TOP-0045)
By letter dated August 17, 2023 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML23234A266), as supplemented on November 30, 2023 (ADAMS Accession No. ML23334A210), and June 14, 2024 (ADAMS Accession No. ML24180A016),
Electric Power Research Institute (EPRI) submitted EPRI Technical Report (TR) 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components, dated June 2023, to the U.S. Nuclear Regulatory Commission (NRC) for review and approval.
EPRI TR 3002025288 presents an enhanced methodology for categorizing pressure boundary components in support of Title 10 of the Code of Federal Regulations (10 CFR) 50.69 applications.
By letter dated July 11, 2024 (ADAMS Accession No. ML23352A054), the NRC staff accepted EPRI TR 3002025288 for review.
The purpose of this email is to inform you that the NRC is revising the review schedule for EPRI TR 3002025288.
The NRC staff now expects to issue the draft safety evaluation (SE) by August 29, 2025.
The NRC staffs decision to revise the estimated completion date of the draft SE to an earlier date was influenced by the multiple rounds of interactions with your staff and the significant effort previously expended by NRC staff during the acceptance review phase of the TR review.
However, this schedule estimate could change due to several factors, such as an untimely response to requests for additional information or an unanticipated addition of scope to the review. Therefore, to maintain this efficient schedule, we encourage you and your staff to respond to all audit questions and formal requests for information in a timely manner.
If there are emergent complexities or challenges in our review that would result in a change to the revised issuance date for the draft SE, the reasons for the change, and a revised estimate will be communicated during routine interactions with the assigned project manager.
The change in revised issuance date for the draft SE was discussed with and approved by the Director for the Division of Operating Reactor Licensing.
ML24211A073
- via email NRR-106 OFFICE NRR/DORL/LLPB/PM NRR/DORL/LLPB/LA NRR/DNRL/NPHP/BC NRR/DRA/APLA/BC NAME LJames DHarrison MMitchell BPascarelli DATE 7/31/24 7/31/24 7/31/24 7/31/24 OFFICE DORL/LLPB/BC DORL/LLPB/PM NAME GGeorge LJames DATE 8/1/24