IR 05000458/2013005

From kanterella
Revision as of 11:55, 6 February 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
IR 05000458-13-005; 09/29/2013 - 12/31/2013; River Bend Station; Integrated Resident and Regional Report; Radioactive Gaseous and Liquid Effluent Treatment; Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, & Transportation
ML14044A033
Person / Time
Site: River Bend Entergy icon.png
Issue date: 02/13/2014
From: Allen D B
NRC/RGN-IV/DRP/RPB-C
To: Olson E W
Entergy Operations
References
IR-13-005
Download: ML14044A033 (65)


Text

EA-13-031

February 13, 2014 EA-14-031

Mr. Eric Site Vice President Entergy Operations, Inc.

River Bend Station 5485 U.S. Highway 61 St. Francisville, LA 70775

SUBJECT: RIVER BEND STATION - NRC INTEGRATED INSPECTION REPORT 05000458/2013005 AND EXERCISE OF ENFORCEMENT DISCRETION

Dear Mr. Olson:

On December 31, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your River Bend Station, Unit 1. On January 16, 2014, the NRC inspectors discussed the results of this inspection with Mr. R. Gadbois, General Manager, Plant Operations and other members of your staff. Inspectors documented the results of this inspection in the enclosed inspection report. NRC inspectors documented one finding of very low safety significance (Green) in this report. This finding involved a violation of NRC requirements. Additionally, NRC inspectors documented one Severity Level IV violation with no associated finding. The NRC is treating these violations as non-cited violations consistent with Section 2.3.2.a of the Enforcement Policy. A violation of technical specification 3.6.1.10 was identified. Because the violation was identified during the discretion period described in Enforcement Guidance Memorandum 11-003, the NRC is exercising enforcement discretion in accordance with Section 3.5, "Violations Involving Special Circumstances," of the NRC Enforcement Policy and, therefore, will not issue enforcement action for this violation, subject to a timely license amendment request being submitted.

If you contest the violations or significance of these non-cited violations, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC resident inspector at the River Bend Station. If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the Regional Administrator, Region IV; and the NRC resident inspector at the River Bend Station.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,/RA/ Donald B. Allen, Branch Chief Project Branch C Division of Reactor Projects Docket No.: 50-458 License No.: NPF-47

Enclosure:

Inspection Report 05000458/2013005

w/Attachments:

1) Supplemental Information 2) Request for Information for the TI 2515-182 Phase 2 Inspection 3) Request for Information for the Occupational/Public Radiation Safety Inspection Electronic Distribution to River Bend Station

SUMMARY

IR 05000458/2013005; 09/29/2013 - 12/31/2013; River Bend Station; Integrated Resident and Regional Report; Radioactive Gaseous and Liquid Effluent Treatment; Radioactive Solid Waste

Processing and Radioactive Material Handling, Storage, & Transportation

The inspection activities described in this report were performed between September 29, 2013, and December 31, 2013, by the resident inspectors at the River Bend Station, nine inspectors from the NRC's Region IV office, and an inspector from the NRC's Office of Nuclear Security and Incident Response. One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. Additionally, NRC inspectors documented one Severity Level IV violation with no associated finding in this report. The significance of inspection findings is indicated by their color (Green, White, Yellow, or Red), which is determined using Inspection Manual Chapter 0609, "Significance Determination Process." Their cross-cutting aspects are determined using Inspection Manual Chapter 0310,

"Components Within the Cross-Cutting Areas." Violations of NRC requirements are dispositioned in accordance with the NRC's Enforcement Policy. The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process."

Cornerstone: Public Radiation Safety

Green.

Inspectors reviewed a self-revealing non-cited violation of 10 CFR 20.1501(a) because the licensee failed to perform radiation surveys to evaluate radiological conditions associated with a 5 gallons per minute water leak to ensure compliance with 10 CFR 20.1406(c). The leak continued for approximately five months before a radiological survey was completed that identified the leak source to be the circulating water blowdown system which contained liquid radioactive waste. This issue was entered into the corrective action program as Condition Report CR-RBS-2013-02400. The failure to perform a timely radiological survey was a performance deficiency. The finding was more than minor because if left uncorrected it could have led to a more significant concern. If not for the outage, the unidentified releases would have continued depositing radioactivity onsite and into the environment. Using NRC Manual Chapter 0609, Appendix D, "Public Radiation Safety Significance Determination Process," issued February 12, 2008, the finding was determined to be of very low safety significance because it was not a failure to implement an effluent program and public dose was not greater than Appendix I criteria or 10 CFR 20.1301(e). The finding had a cross-cutting aspect associated with the problem identification and resolution component because the licensee did not thoroughly evaluate the source of the leak in a timely manner P.1(c) (Section 2RS6).

  • SL-IV. The inspectors identified two examples of a Severity Level IV non-cited violation of 10 CFR 50.71(e) for failure to update the Updated Safety Analysis Report. Specifically, the licensee failed to adequately describe the Low-Level Radwaste Storage Facility and the Independent Spent Fuel Storage Installation in the Updated Safety Analysis Report in accordance with Regulatory Guide 1.70, Revision 3. The licensee entered the issue into their corrective action program as Condition Report CR-RBS-2013-07265. The failure to update the Updated Safety Analysis Report to reflect changes made to the facility was a violation of regulatory requirements of 10 CFR 50.71(e), "Maintenance of Records, Making of Reports." This issue was evaluated using traditional enforcement because it had the potential to impact the NRC's ability to perform its regulatory function. The issue was characterized as a Severity Level IV violation in accordance with Section 6.1.d.3 of the NRC Enforcement Policy, issued January 28, 2013, because the erroneous information in the Updated Safety Analysis Report was not used to make an unacceptable change to the facility or procedures. Since this issue was dispositioned using traditional enforcement, there is no cross-cutting aspect (Section 2RS8).

PLANT STATUS

The River Bend Station began the inspection period at 100 percent reactor power. It departed from full power as follows:

  • On October 27, operators reduced power to 71 percent to perform a rod sequence exchange, turbine valve testing, a partially withdrawn rod operability test, and to remove reactor feedwater pump 1B from service to correct a steam leak from the inboard pump seal and to correct lube oil leaks on the pump's gear increaser. The licensee returned the plant to full power on October 31.
  • On December 2, operators reduced power to 85 percent to remove reactor feedwater pump 1B from service to repair a steam leak from the pump's inboard shell casing. The licensee returned the plant to full power on December 2.

The plant remained at 100 percent reactor power for the remainder of the inspection period.

REPORT DETAILS

REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity

1R01 Adverse Weather Protection

Readiness for Seasonal Extreme Weather Conditions

a. Inspection Scope

On October 4, the inspectors completed an inspection of the station's readiness for seasonal extreme weather conditions. The inspectors reviewed the licensee's adverse weather procedures for hurricane season and evaluated the licensee's implementation of these procedures. The inspectors verified that prior to the landfall of Hurricane Karen, the licensee had corrected weather-related equipment deficiencies identified during the station's walkdown of plant property.

The inspectors selected four risk-significant systems that were required to be protected from high precipitation and high winds:

  • Safety-related switchgear
  • Transformer yard
  • Fire water system The inspectors reviewed the licensee's procedures and design information to ensure the systems would remain functional when challenged by adverse weather. The inspectors verified that operator actions described in the licensee's procedures were adequate to maintain readiness of these systems. The inspectors walked down portions of these systems to verify the physical condition of each individual system's protection features.

These activities constituted one sample of readiness for seasonal adverse weather, as defined in Inspection Procedure 71111.01.

b. Findings

No findings were identified.

1R04 Equipment Alignment

.1 Partial Walkdown

a. Inspection Scope

The inspectors performed partial system walkdowns of the following risk-significant systems:

  • October 22, Division 1 batteries and charger, backup charger
  • October 24, Division 1 control building chilled water system
  • October 29, Makeup water system following system (pump and valve) maintenance The inspectors reviewed the licensee's procedures and system design information to determine the correct lineup for the systems. They visually verified that critical portions of the systems or divisions were correctly aligned for the existing plant configuration.

These activities constituted four partial system walkdown samples, as defined in Inspection Procedure 71111.04.

b. Findings

No findings were identified.

.2 Complete Walkdown

a. Inspection Scope

On October 24, the inspectors performed a complete system walkdown inspection of the reactor core isolation cooling system. The inspectors reviewed the licensee's procedures and system design information to determine the correct system lineup for the existing plant configuration. The inspectors also reviewed outstanding work orders, open condition reports, in-process design changes, temporary modifications, and other open items tracked by the licensee's operations and engineering departments. The inspectors then visually verified that the system was correctly aligned for the existing plant configuration.

These activities constituted one complete system walkdown sample, as defined in Inspection Procedure 71111.04.

b. Findings

No findings were identified.

1R05 Fire Protection

Quarterly Inspection

a. Inspection Scope

The inspectors evaluated the licensee's fire protection program for operational status and material condition. The inspectors focused their inspection on four plant areas important to safety:

  • September 29, control building, 136-foot elevation
  • September 30, reactor building, 141-foot, 162-foot, and 186-foot elevations
  • October 1, control building, 116-foot and 95-foot elevations
  • October 16, diesel generator building, 98-foot elevation For each area, the inspectors evaluated the fire plan against defined hazards and defense-in-depth features in the licensee's fire protection program. The inspectors evaluated control of transient combustibles and ignition sources, fire detection and suppression systems, manual firefighting equipment and capability, passive fire protection features, and compensatory measures for degraded conditions.

These activities constituted four quarterly inspection samples, as defined in Inspection Procedure 71111.05.

b. Findings

No findings were identified.

1R06 Flood Protection Measures

a. Inspection Scope

On October 31, the inspectors completed an inspection of the station's ability to mitigate flooding due to internal causes. After reviewing the licensee's flooding analysis, the inspectors chose two plant areas containing risk-significant structures, systems, and components that were susceptible to flooding:

  • Diesel generator building, 98-foot elevation

The inspectors reviewed plant design features and licensee procedures for coping with internal flooding. The inspectors walked down the selected areas to inspect the design features, including the material condition of seals, drains, and flood barriers. The inspectors evaluated whether operator actions credited for flood mitigation could be successfully accomplished. In addition, on November 21, the inspectors completed an inspection of underground bunkers susceptible to flooding. The inspectors selected two underground electrical manholes that contained risk-significant cables whose failure could disable risk-significant equipment:

  • Electrical manhole EMH-600
  • Electrical manhole EMH-602 The inspectors observed the material condition of the cables and splices contained in the electrical manholes and looked for evidence of cable degradation due to water intrusion. The inspectors verified that the cables and vaults met design requirements.

These activities constitute completion of two flood protection measures samples and one bunker/manhole sample, as defined in Inspection Procedure 71111.06.

b. Findings

No findings were identified.

1R11 Licensed Operator Requalification Program and Licensed Operator Performance

.1 Review of Licensed Operator Requalification

a. Inspection Scope

On November 6, the inspectors observed a portion of two annual requalification tests for licensed operators for an operating crew. The inspectors assessed the performance of the operators and the evaluators' critique of their performance. The inspectors also assessed the modeling and performance of the simulator during the requalification activities. These activities constitute completion of two quarterly licensed operator requalification program samples, as defined in Inspection Procedure 71111.11.

b. Findings

No findings were identified.

.2 Review of Licensed Operator Performance

a. Inspection Scope

On September 29, the inspectors observed the performance of on-shift licensed operators in the plant's main control room. At the time of the observations, the plant was in a period of heightened activity due to potential contamination of the normal service water system from tritium in the reactor plant component cooling water system.

In addition, the inspectors assessed the operators' adherence to plant procedures, including the conduct of operations procedure and other operations department policies. These activities constitute completion of one quarterly licensed operator performance sample, as defined in Inspection Procedure 71111.11.

b. Findings

No findings were identified.

.3 Annual Review of Requalification Examination Results (Unit 1)

The licensed operator requalification program involves two training cycles that are conducted over a 2-year period. In the first cycle, the annual cycle, the operators are administered an operating test consisting of job performance measures and simulator scenarios. In the second part of the training cycle, the biennial cycle, operators are administered an operating test and a comprehensive written examination. For this annual inspection requirement, the River Bend Station was in the first part of the training cycle.

a. Inspection Scope

The inspector reviewed the results of the operating tests for the station to satisfy the annual inspection requirements.

On December 10, 2013, the licensee informed the lead inspector of the results:

  • 6 of 6 crews passed the simulator portion of the operating test
  • 43 of 43 licensed operators passed the simulator portion of the operating test
  • 43 of 43 licensed operators passed the job performance measure portion of the examination Because there were no overall failures in any of these areas, there were no required remediations performed.

The inspector completed one inspection sample of the annual licensed operator requalification program, as defined in Inspection Procedure 71111.11.

b. Findings

No findings were identified.

1R12 Maintenance Effectiveness

a. Inspection Scope

The inspectors reviewed two instances of degraded performance or condition of safety-related structures, systems, and components:

  • December 5, 2013, main steam system The inspectors reviewed the extent of condition of possible common cause structures, systems, and components failures and evaluated the adequacy of the licensee's corrective actions. The inspectors reviewed the licensee's work practices to evaluate whether these may have played a role in the degradation of the structures, systems, and components. The inspectors assessed the licensee's characterization of the degradation in accordance with 10 CFR 50.65 (the Maintenance Rule), and verified that the licensee was appropriately tracking degraded performance and conditions in accordance with the Maintenance Rule. These activities constituted completion of two maintenance effectiveness samples, as defined in Inspection Procedure 71111.12.

b. Findings

No findings were identified.

1R13 Maintenance Risk Assessments and Emergent Work Control

a. Inspection Scope

The inspectors reviewed four risk assessments performed by the licensee prior to changes in plant configuration and the risk management actions taken by the licensee in response to elevated risk:

  • October 14, Fancy Point breaker maintenance
  • October 22, Fancy Point switchyard battery capacitance test and switchyard backup diesel maintenance
  • October 31, Fancy Point switchyard, switchgear cross connect out of service
  • December 10, feedwater flow controller time delay relay replacement The inspectors verified that these risk assessments were performed timely and in accordance with the requirements of 10 CFR 50.65 (the Maintenance Rule) and plant procedures. The inspectors reviewed the accuracy and completeness of the licensee's risk assessments and verified that the licensee implemented appropriate risk management actions based on the results of the assessments.

Additionally, on November 5, the inspectors observed portions of the reactor core isolation cooling turbine insulation repair emergent work activities that had the potential to affect the functional capability of mitigating systems.

The inspectors verified that the licensee appropriately developed and followed a work plan for these activities. The inspectors verified that the licensee took precautions to minimize the impact of the work activities on unaffected structures, systems, and components.

These activities constitute completion of five maintenance risk assessments and emergent work control inspection samples, as defined in Inspection Procedure 71111.13.

b. Findings

No findings were identified.

1R15 Operability Determinations and Functionality Assessments

a. Inspection Scope

The inspectors reviewed three operability determinations and functionality assessments that the licensee performed for degraded or nonconforming structures, systems, and components:

The inspectors reviewed the timeliness and technical adequacy of the licensee's evaluations. Where the licensee determined the degraded structures, systems, and components to be operable or functional, the inspectors verified that the licensee's compensatory measures were appropriate to provide reasonable assurance of operability or functionality. The inspectors verified that the licensee had considered the effect of other degraded conditions on the operability or functionality of the degraded structures, systems, and components.

These activities constitute completion of three operability and functionality review samples, as defined in Inspection Procedure 71111.15.

b. Findings

No findings were identified.

1R19 Post-Maintenance Testing

a. Inspection Scope

The inspectors reviewed six post-maintenance testing activities that affected risk-significant structures, systems, and components:

  • November 7, WO-00359884, "C85-FLT1B Replace Filter with New Filter"
  • November 13, WO-52517719, "Calibrate HVK-FTX5C per Loop Calibration Report"
  • November 21, WO-00366214, "Perform Troubleshooting of Diesel Trip"
  • November 29, WO-00368107, "ENS-SWG1B-ACB27-1A Would Not Open From Panel H13-P877" The inspectors reviewed licensing- and design-basis documents for the structures, systems, and components and the maintenance and post-maintenance test procedures.

The inspectors observed the performance of the post-maintenance tests to verify that the licensee performed the tests in accordance with approved procedures, satisfied the established acceptance criteria, and restored the operability of the affected structures, systems, and components.

These activities constitute completion of six post-maintenance testing inspection samples, as defined in Inspection Procedure 71111.19.

b. Findings

No findings were identified.

1R22 Surveillance Testing

a. Inspection Scope

The inspectors observed eight risk-significant surveillance tests and reviewed test results to verify that these tests adequately demonstrated that the structures, systems, and components were capable of performing their safety functions: In-service test:

  • December 23, STP-309-6301, Revision 17, "Division 1 EDG Fuel Oil Transfer Pump and Valve Operability Test" Containment isolation valve surveillance test:
  • November 5, STP-000-0001, Revision 72, "Daily Operating Logs" Other surveillance tests:
  • October 12, STP-052-0102, Revision 008, "Partially Withdrawn Control Rod Insertion Operability Check"
  • October 24, STP-410-3601, Revision 7, "Performance Monitoring Program for Control Building Chiller HVK-CHL1A (Division 1)"
  • November 4, STP-402-3601, Revision 7, "Performance Monitoring Program for the Control Room Air Handling Unit HVC*ACU1A (Division 1)"
  • December 30, COP-0001, Revision 23, "Sampling via Various Balance of Plant Systems" The inspectors verified that these tests met technical specification requirements, that the licensee performed the tests in accordance with their procedures, and that the results of the test satisfied appropriate acceptance criteria. The inspectors verified that the licensee restored the operability of the affected structures, systems, and components following testing.

These activities constitute completion of eight surveillance testing inspection samples, as defined in Inspection Procedure 71111.22.

b. Findings

No findings were identified.

Cornerstone:

Emergency Preparedness 1EP4 Emergency Action Level and Emergency Plan Changes (IP 71114.04)

a. Inspection Scope

The NSIR headquarters staff performed an in-office review of the latest revisions of various Emergency Plan Implementing Procedures (EPIPs) and the Emergency Plan located under ADAMS accession numbers ML12354A521 and ML13014A041 as listed in the Attachment.

The licensee determined that in accordance with 10 CFR 50.54(q), the changes made in the revisions resulted in no reduction in the effectiveness of the Plan, and that the revised Plan continued to meet the requirements of 10 CFR 50.47(b) and Appendix E to 10 CFR Part 50. The NRC review was not documented in a safety evaluation report and did not constitute approval of licensee-generated changes; therefore, this revision is subject to future inspection. The specific documents reviewed during this inspection are listed in the Attachment.

These activities constitute completion of three samples as defined in Inspection Procedure 71114.04-05.

b. Findings

No findings were identified.

RADIATION SAFETY

Cornerstones: Public Radiation Safety and Occupational Radiation Safety

2RS5 Radiation Monitoring Instrumentation

a. Inspection Scope

The inspectors verified the accuracy and operability of the radiation monitoring equipment used by the licensee (1) to monitor areas, materials, and workers to ensure a radiologically safe work environment, and (2) to detect and quantify radioactive process streams and effluent releases. The inspectors interviewed licensee personnel, walked down various portions of the plant, and reviewed licensee performance in the following areas:

  • Selected plant configurations and alignments of process, postaccident, and effluent monitors with descriptions in the Updated Safety Analysis Report and the offsite dose calculation manual
  • Selected instrumentation, including effluent monitoring instruments, portable survey instruments, area radiation monitors, continuous air monitors, personnel contamination monitors, portal monitors, and small article monitors to examine their configurations and source checks
  • Calibration and testing of process and effluent monitors, laboratory instrumentation, whole body counters, postaccident monitoring instrumentation, portal monitors, personnel contamination monitors, small article monitors, portable survey instruments, area radiation monitors, electronic dosimetry, air samplers, and continuous air monitors
  • Audits, self-assessments, and corrective action documents related to radiation monitoring instrumentation since the last inspection These activities constitute completion of one sample of radiation monitoring instrumentation as defined in Inspection Procedure 71124.05-05.

b. Findings

No findings were identified.

2RS6 Radioactive Gaseous and Liquid Effluent Treatment

a. Inspection Scope

The inspectors verified that the licensee maintained gaseous and liquid effluent processing systems and properly mitigated, monitored, and evaluated radiological discharges with respect to public exposure. The inspectors verified that abnormal radioactive gaseous or liquid discharges and conditions, when effluent radiation monitors are out-of-service, were controlled in accordance with the applicable regulatory requirements and licensee procedures. The inspectors verified that the licensee's quality control program ensured radioactive effluent sampling and analysis adequately quantified and evaluated discharges of radioactive materials. The inspectors verified the adequacy of public dose projections resulting from radioactive effluent discharges. The inspectors interviewed licensee personnel and reviewed or observed the following items:

  • Radiological effluent release reports since the previous inspection and reports related to the effluent program issued since the previous inspection
  • Effluent program implementing procedures, including sampling, monitor setpoint determinations, and dose calculations
  • Equipment configuration and flow paths of selected gaseous and liquid discharge system components, filtered ventilation system material condition, and significant changes to their effluent release points, if any, and associated 10 CFR 50.59 reviews
  • Selected portions of the routine processing and discharge of radioactive gaseous and liquid effluents (including sample collection and analysis)
  • Controls used to ensure representative sampling and appropriate compensatory sampling
  • Results of the inter-laboratory comparison program
  • Surveillance test results of technical specification-required ventilation effluent discharge systems since the previous inspection
  • Significant changes in reported dose values
  • A selection of radioactive liquid and gaseous waste discharge permits
  • Latest land use census
  • Records of abnormal gaseous or liquid tank discharges
  • Groundwater monitoring results
  • Changes to the licensee's written program for identifying and controlling contaminated spills/leaks to groundwater
  • Identified leakage or spill events and entries made into 10 CFR 50.75(g) records, if any, and associated evaluations of the extent of the contamination and the radiological source term
  • Offsite notifications, and reports of events associated with spills, leaks, and groundwater monitoring results
  • Audits, self-assessments, reports, and corrective action documents related to radioactive gaseous and liquid effluent treatment since the last inspection These activities constitute completion of one sample of radioactive gaseous and liquid effluent treatment as defined in Inspection Procedure 71124.06.

b. Findings

Introduction.

Inspectors reviewed a Green self-revealing non-cited violation of 10 CFR 20.1501(a) because the licensee failed to perform radiation surveys to evaluate radiological conditions associated with a 5 gallons per minute water leak to ensure compliance with 10 CFR 20.1406(c). The leak continued for approximately five months before a radiological survey was completed to identify the water's source.

Description.

On October 2, 2012, plant personnel found water seeping from the ground and accumulating in a ditch near the site's sewage treatment pond at a leak rate of approximately 5 gallons per minute. The leak was assumed to be waste water from the sewage treatment plant. Based on a pH and chlorine sample, the licensee further assumed that the leak was clean domestic water being delivered to the waste water treatment plant. A radiological analysis was not completed at this time. A work order was created to find and isolate the leak, but it was a low priority work item based on the assumed source of the water. Refueling Outage 17 began in February 2013. As part of the outage, the circulating water blowdown (CWBD) line was removed from service. Around this time, plant personnel noticed that the water leak had stopped. An investigation revealed that no maintenance was performed to stop the leak. Further investigation determined that check valve 1PBS-V3014 was stuck open. This allowed CWBD system water to flow backward into the 4-inch effluent line which flowed towards the waste water treatment plant. This backflow water was also leaking through an air relief valve into a plant ditch. The liquid radwaste (LRW) system routinely discharges flow into the CWBD line upstream of the waste water treatment plant tie-in. As a result, during periods of LRW batch releases, radioactive effluents were being released into the environment via this unmonitored release path. A radiological analysis was performed on March 17, 2013, which confirmed that Co-60 had been improperly released onsite and into the environment. No accumulated water was available to determine how much tritium had also been released. There were 18 LRW batch releases discharged during this time period; approximately 25,650 gallons of diluted radioactive (waste) water leaked through the air relief valve. In the fourth quarter of 2012, in the Annual Radiological Effluent Release Report, the licensee reported that LRW discharges from its normal release pathway were 7.44 curies tritium with an average diluted concentration of 5.47E-6 microcuries/milliliter [5470 picoCuries/liter]. The licensee documented the leak in Condition Report CR-RBS-2012-06329 and the identification of the source of the leak in CR-RBS-2013-02480. The licensee also isolated the CWBD line when it was identified as the potential source of the leak.

Analysis.

The failure to perform a timely radiological survey was a performance deficiency. The finding was more than minor because if left uncorrected it could have led to a more significant concern. If not for the outage, the unidentified releases would have continued depositing radioactivity onsite and into the environment. Using NRC Manual Chapter 0609, Appendix D, "Public Radiation Safety Significance Determination Process," issued February 12, 2008, the finding was determined to be of very low safety significance because it was not a failure to implement an effluent program and public dose was not greater than Appendix I criteria or 10 CFR 20.1301(e). The finding had a cross-cutting aspect associated with the problem identification and resolution component because the licensee did not thoroughly evaluate the source of the leak in a timely manner P.1(c).

Enforcement.

Title 10 CFR 20.1501(a) states that "Each licensee shall make or cause to be made, surveys of areas, including the subsurface, that may be necessary for the licensee to comply with the regulations in this part." Title 10 CFR 20.1406(c) states, in part, that "Licensees shall, to the extent practical, conduct operations to minimize the introduction of residual radioactivity into the site, including the subsurface, in accordance with the existing radiation protection requirements." Contrary to the above, from October 2012 to March 2013, the licensee failed to perform radiation surveys or analyses and evaluate radiological conditions of a 5 gallons per minute leak to ensure compliance with 10 CFR 20.1406(c). Since this violation was of very low safety significance and was documented in the licensee's corrective action program as Condition Report CR-RBS-2013-02480, it is being treated as a non-cited violation, consistent with Section 2.3.2.a of the Enforcement Policy: NCV 05000458/2013005-01, Failure to Perform a Survey on Water Leak.

2RS7 Radiological Environmental Monitoring Program

a. Inspection Scope

The inspectors verified that the licensee's radiological environmental monitoring program quantified the impact of radioactive effluent releases to the environment and sufficiently validated the integrity of the radioactive gaseous and liquid effluent release program. The inspectors verified that the radiological environmental monitoring program was implemented consistent with the licensee's technical specifications and offsite dose calculation manual, and that the radioactive effluent release program met the design objective in Appendix I to 10 CFR Part 50. The inspectors verified that the licensee's radiological environmental monitoring program monitored non-effluent exposure pathways, was based on sound principles and assumptions, and validated that doses to members of the public were within regulatory dose limits. The inspectors reviewed or observed the following items:

  • Selected air sampling and dosimeter monitoring stations
  • Collection and preparation of environmental samples
  • Operability, calibration, and maintenance of meteorological instruments
  • Selected events documented in the annual environmental monitoring report which involved a missed sample, inoperable sampler, lost dosimeter, or anomalous measurement
  • Selected structures, systems, and components that may contain licensed material and has a credible mechanism for licensed material to reach ground water
  • Significant changes made by the licensee to the offsite dose calculation manual as the result of changes to the land census or sampler station modifications since the last inspection
  • Calibration and maintenance records for selected air samplers, composite water samplers, and environmental sample radiation measurement instrumentation
  • Inter-laboratory comparison program results
  • Audits, self-assessments, reports, and corrective action documents related to the radiological environmental monitoring program since the last inspection These activities constitute completion of one sample of radiological environmental monitoring program as defined in Inspection Procedure 71124.07.

b. Findings

No findings were identified.

2RS8 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation

a. Inspection Scope

The inspectors verified the effectiveness of the licensee's programs for processing, handling, storage, and transportation of radioactive material. The inspectors interviewed licensee personnel and reviewed the following items:

  • The solid radioactive waste system description, process control program, and the scope of the licensee's audit program
  • Control of radioactive waste storage areas including container labeling/marking and monitoring containers for deformation or signs of waste decomposition
  • Changes to the liquid and solid waste processing system configuration including a review of waste processing equipment that is not operational or abandoned in place
  • Radio-chemical sample analysis results for radioactive waste streams and use of scaling factors and calculations to account for difficult-to-measure radionuclides
  • Processes for waste classification including use of scaling factors and 10 CFR Part 61 analysis
  • Shipment packaging, surveying, labeling, marking, placarding, vehicle checking, driver instructing, and preparation of the disposal manifest
  • Audits, self-assessments, reports, and corrective action reports related to radioactive solid waste processing and radioactive material handling, storage, and transportation since the last inspection These activities constitute completion of one sample of radioactive solid waste processing and radioactive material handling, storage, and transportation as defined in Inspection Procedure 71124.08.

b. Findings

Introduction.

The inspectors identified two examples of a Severity Level IV non-cited violation of 10 CFR 50.71(e), "Maintenance of Records, Making of Reports," for failure to update the Updated Safety Analysis Report. Specifically, the licensee failed to adequately describe two radioactive waste storage facilities (the Low-Level Radwaste Storage Facility (LLRWSF) and the dry spent fuel storage system or independent spent fuel storage installation (ISFSI)) in its Updated Safety Analysis Report in accordance with Regulatory Guide 1.70 (RG 1.70).

Description.

While inspecting the licensee's solid radwaste management activities and storage facilities, the inspectors identified that the LLRWSF and ISFSI were not adequately described in Chapters 11 and 12 of the Updated Safety Analysis Report.

The licensee built these facilities in the owner controlled area for interim storage of low-level radioactive waste (Class A, B, or C) and long-term storage of high-level radioactive waste (i.e., spent fuel and greater than Class-C), respectively. The licensee is committed to RG 1.70, Revision 3, "Standard, Format, and Content of Safety Analysis Reports for Nuclear Power Plants," which describes the information and detail to be included in each section of the Updated Safety Analysis Report. Regulatory Guide 1.70, Chapter 11, Section 4, "Solid Waste Management System," specifies the design objectives and design criteria for the solid radioactive waste handling and treatment system in terms of the types of wastes, the maximum and expected volumes to be handled, and the isotopic and curie content. This section (11.4), also stipulates for dry solid waste to tabulate the maximum and expected waste inputs in terms of type, sources of waste, volume, and isotopic and curie content. Section 11.4 also discusses the methods of handling and packaging large waste materials and equipment that have been activated during reactor operation. Regulatory Guide 1.70, Chapter 12, Section 2.1, "Contained Sources," provides the basis for the radiation protection design that should be described in the manner needed as input to the shield design calculations. Those sources that are contained in equipment like the radioactive waste management systems should be described. The source location in the plant should be specified so that all important sources of radioactivity can be located on plant layout drawings. Also, the safety analysis report should provide a listing of isotope, quantity, form, and use of all sources that exceed 100 millicuries (mCi). The following two examples illustrate how the licensee failed to update the Updated Safety Analysis Report, Chapter 11, "Radioactive Waste Management," and Chapter 12, "Radiation Protection," with the most recent information in accordance with RG 1.70.

1. In 1997, the licensee built the LLRWSF outside the protected area for interim storage of dry, solid, low-level radioactive waste. The licensee estimated that 538 mCi are currently stored in the LLRWSF, and the facility was designed to store approximately 33 curies. During this inspection, NRC inspectors toured the facility and identified

that the LLRWSF was not adequately described in Chapters 11 and 12 of the Updated Safety Analysis Report. Specifically, the description of the LLRWSF does not include the maximum isotopic and curie contents of the waste in Chapter 11.

There was also no description of isotopes, quantity, form, or use in Chapter 12 for the LLRWSF which currently exceeds 100 mCi of activity. 2. In 2000, the licensee received a Certificate of Compliance for spent fuel storage casks. In 2005, the first spent fuel storage casks were loaded and delivered to the ISFSI. Currently, the licensee has 1,292 spent fuel bundles stored in casks on the ISFSI. During this inspection, NRC inspectors identified that the ISFSI was not adequately described in Chapters 11 and 12 of the Updated Safety Analysis Report.

Specifically, there was no description of the facility, types of waste, the maximum and expected volumes to be handled, the isotopic and curie content, or the method of handling and packaging large waste materials and equipment that had been activated during reactor operation in Chapter 11. There was no description of isotopes, quantity, form, or use of all sources exceeding 100 mCi in Chapter 12.

Analysis.

The failure to update the Updated Safety Analysis Report to reflect changes made to the facility was a violation of 10 CFR 50.71(e). This issue was evaluated using traditional enforcement because it had the potential to impact the NRC's ability to perform its regulatory function. The issue was characterized as a Severity Level IV violation in accordance with Section 6.1.d.3 of the Enforcement Policy, issued January 28, 2013, because the erroneous information in the Updated Safety Analysis Report was not used to make an unacceptable change to the facility or procedures.

Since this issue was dispositioned using traditional enforcement, there is no cross-cutting aspect assigned.

Enforcement.

Title 10 CFR 50.71, "Maintenance of Records," requires, in part, that licensees periodically update their Updated Safety Analysis Report with submittals that include the effects of all changes made in the facility or procedures as described in the Updated Safety Analysis Report. Contrary to the above, from 1997 through the present, the licensee failed to include in a periodic update of the Updated Safety Analysis Report, changes made to the facility. Specifically, since its construction in 1997, the licensee stored an unknown amount of radioactivity in the LLRWSF, but failed to adequately describe the facility source, volume, and curie content in Chapters 11 and 12 of the Updated Safety Analysis Report. Additionally, in 2005, the licensee started using the ISFSI inside the protected area that was not described in Chapters 11 or 12 of the Updated Safety Analysis Report. In both examples, the licensee made changes to the facility as described in the Updated Safety Analysis Report, performed safety analyses and evaluations in support of these changes; however, failed to update the Updated Safety Analysis Report with the specific, detailed information required by these changes.

This violation has been entered into the licensee's corrective action program as Condition Report CR-RBS-2013-07265. This Severity Level IV violation is being treated as a non-cited violation, consistent with Section 2.3.2.a of the Enforcement Policy:

NCV 05000458/2013005-02, Failure to Periodically Update the Updated Safety Analysis Report.

OTHER ACTIVITIES

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, Emergency Preparedness, Public Radiation Safety, Occupational Radiation Safety, and Security

4OA1 Performance Indicator Verification

.1 Reactor Coolant System Specific Activity (BI01)

a. Inspection Scope

The inspectors reviewed the licensee's reactor coolant system chemistry sample analyses for the period of October 2012 through September 2013 to verify the accuracy and completeness of the reported data. The inspectors observed a chemistry technician obtain and analyze a reactor coolant system sample on December 30. The inspectors used definitions and guidance contained in Nuclear Energy Institute Document 99-02, "Regulatory Assessment Performance Indicator Guideline," Revision 7, to determine the accuracy of the reported data.

These activities constituted verification of the reactor coolant system specific activity performance indicator, as defined in Inspection Procedure 71151.

b. Findings

No findings were identified.

.2 Reactor Coolant System Total Leakage (BI02)

a. Inspection Scope

The inspectors reviewed the licensee's records of reactor coolant system total leakage for the period of October 2012 through September 2013 to verify the accuracy and completeness of the reported data. The inspectors observed the performance of the reactor coolant system leakage surveillance procedure on November 5. The inspectors used definitions and guidance contained in Nuclear Energy Institute Document 99-02, "Regulatory Assessment Performance Indicator Guideline," Revision 7, to determine the accuracy of the reported data.

These activities constituted verification of the reactor coolant system leakage performance indicator, as defined in Inspection Procedure 71151.

b. Findings

No findings were identified.

4OA2 Problem Identification and Resolution

.1 Routine Review

a. Inspection Scope

Throughout the inspection period, the inspectors performed daily reviews of items entered into the licensee's corrective action program and periodically attended the licensee's condition report screening meetings. The inspectors verified that licensee personnel were identifying problems at an appropriate threshold and entering these problems into the corrective action program for resolution. The inspectors verified that the licensee developed and implemented corrective actions commensurate with the significance of the problems identified. The inspectors also reviewed the licensee's problem identification and resolution activities during the performance of the other inspection activities documented in this report.

c. Findings

No findings were identified.

.2 Semiannual Trend Review

a. Inspection Scope

The inspectors reviewed the licensee's corrective action program, performance indicators, system health reports, and other documentation to identify trends that might indicate the existence of a more significant safety issue. The inspectors verified that the licensee was taking corrective actions to address identified adverse trends. The inspectors focused the trend review on maintenance effectiveness and equipment operability. These activities constitute completion of one semiannual trend review sample, as defined in Inspection Procedure 71152.

b. Findings

No findings were identified.

.3 Annual Follow-up of Selected Issues

a. Inspection Scope

The inspectors selected two issues for an in-depth follow-up:

  • On November 5, Fitness-for-Duty Quality Assurance Review Findings The inspectors assessed the licensee's problem identification threshold, cause analyses, extent of condition reviews, and compensatory actions. The inspectors verified that the licensee appropriately prioritized the planned corrective actions and that these actions were adequate to correct the condition.
  • On November 14, Cumulative Operator Workarounds The inspectors assessed the licensee's problem identification threshold, cause analyses, extent of condition reviews, and compensatory actions for issues associated with operator workarounds. The inspectors then assessed the impact of the cumulative effect of the workarounds. The inspectors verified that the licensee appropriately prioritized the planned corrective actions, that these actions were adequate to correct the conditions, and that the overall impact of all of the conditions did not adversely impact the plant. These activities constitute completion of two annual follow-up samples, which included one operator work-around sample, as defined in Inspection Procedure 71152.

b. Findings

No findings were identified.

4OA3 Follow-up of Events and Notices of Enforcement Discretion

(Closed) Licensee Event Report 05000458/2013-001-00: Operations Prohibited by Technical Specifications for Operations with a Potential to Drain the Reactor Vessel (EA 14-031) On March 2, 2013, with the plant in a refueling outage, the licensee performed maintenance to replace the pump seals and the flow control valve packing in the "A" loop of the reactor recirculation system. The maintenance constituted an operation with a potential to drain the reactor vessel (OPDRV). Technical Specification 3.6.1.10 requires an operable primary containment during an OPDRV. The licensee did not take the actions to establish an operable primary containment during the maintenance window for the reactor recirculation system. Instead the licensee met the alternative requirements as described in NRC Enforcement Guidance Memorandum (EGM) 11-003, "Dispositioning Boiling Water Reactor License Noncompliance with Technical Specification Containment Requirements during Operations with a Potential for Draining the Reactor Vessel," Revision 1. The alternative requirements that the licensee complied with include the following: 1) The inspectors verified that the licensee declared, in the control room logs, that the plant was in an OPDRV activity. In addition, the licensee took actions to ensure water inventory was maintained and that a defense-in-depth criteria, was in place prior to entering the OPDRV activity. 2) During the OPDRV activities, the reactor vessel water level was maintained at or above 23 feet over the top of the reactor pressure vessel flange. 3) The OPDRV was not conducted in Mode 4 and the licensee did not move recently irradiated fuel during the OPDRV.

4) The licensee evaluated that during the OPDRV activity, the time to drain down the water inventory from 23 feet over the top of the reactor pressure vessel flange, to the reactor pressure vessel flange was greater than 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. This was based on the calculated maximum leak rate of OPDRV activities.

5) The capability to isolate the potential leakage path during OPDRV activities before the inventory reached the reactor pressure vessel flange was maintained. 6) During OPDRV activities, more than one safety-related pump was available that was aligned to a makeup water source with the capability to inject water at greater than the maximum potential leakage rate from the reactor pressure vessel, for a minimum time period of 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. 7) The inspectors verified that the licensee maintained two independent means of monitoring the reactor pressure vessel water level in an effort to identify the onset of a loss of inventory event during the OPDRV activity. These monitoring methods were in accordance with the requirements stipulated in EGM 11-003 Technical Specification 3.6.1.10 is applicable during movement of recently irradiated fuel assemblies in the primary containment and/or during an OPDRV. This technical specification requires that primary containment shall be maintained operable during the applicable conditions. If containment operability is not maintained, then immediate actions should be taken to suspend either of the applicable conditions (fuel movement/OPDRVs).

Contrary to the above, between 2:48 p.m. CST on March 2, 2013, and 8:30 a.m. CST on March 7, 2013, the licensee did not maintain primary containment in an operable status while conducting an OPDRV. This is a violation of NRC requirements. Because the violation was identified during the discretion period described in EGM 11-003, the NRC is exercising enforcement discretion in accordance with Section 3.5, "Violations Involving Special Circumstances," of the NRC Enforcement Policy and, therefore, will not issue enforcement action for this violation. The inspectors reviewed this licensee event report and the actions taken by the licensee. No problems were noted. This licensee event report is closed.

4OA5 Other Activities

(Closed)Temporary Instruction 2515/182 - Review of the Industry Initiative to Control Degradation of Underground Piping and Tanks

a. Inspection Scope

Leakage from buried and underground pipes has resulted in groundwater contamination incidents with associated heightened NRC and public interest. The industry issued a guidance document, NEI 09-14, "Guideline for the Management of Buried Piping Integrity," (ADAMS Accession No. ML1030901420) to describe the goals and required actions (commitments made by the licensee) resulting from this underground piping and tank initiative. On December 31, 2010, NEI issued Revision 1 to NEI 09-14, "Guidance for the Management of Underground Piping and Tank Integrity," (ADAMS Accession No. ML110700122) with an expanded scope of components which included underground piping that was not in direct contact with the soil and underground tanks. On November 17, 2011, the NRC issued Temporary Instruction 2515/182, "Review of the Industry Initiative to Control Degradation of Underground Piping and Tanks," to gather information related to the industry's implementation of this initiative.

b. Observations The licensee's buried and underground piping and tanks program was inspected in accordance with paragraph 03.02.a of the Temporary Instruction and it was confirmed that activities which correspond to completion dates specified in the program, which have passed since the Phase 1 inspection was conducted, have been completed.

Additionally, the licensee's buried and underground piping and tanks program was inspected in accordance with paragraph 03.02.b of the Temporary Instruction and responses to specific questions were submitted to the NRC headquarters staff. Based upon the scope of the review described above, Phase 2 of TI-2515/182 was completed.

c. Findings

No findings were identified.

4OA6 Meetings, Including Exit Exit Meeting Summary On November 22, 2013, the inspectors presented the radiation safety inspection results to Mr. E. Olson, Site Vice President, and other members of the licensee staff.

The licensee acknowledged the issues presented. The licensee confirmed that any proprietary information reviewed by the inspectors had been returned or destroyed.

On December 19, 2013, the lead inspector obtained the final annual examination results and exited with Mr. D. Bergstrom, Senior Training Instructor. The inspector did not review any proprietary information during this inspection.

On January 16, 2014, the inspectors presented the integrated inspection results to Mr. R. Gadbois, General Manager, Plant Operations, and other members of the licensee staff. The licensee acknowledged the issues presented. The licensee confirmed that any proprietary information reviewed by the inspectors had been returned or destroyed.

A1-

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

D. Bergstrom, Senior Training Instructor
J. Blair, Engineer, Reactor Engineering
T. Brooks, Supervisor - HP (Radwaste Operations)
D. Burnett, Manager, Emergency Preparedness
G. Bush, Manager, Material, Procurement, and Contracts
M. Chase, Manager, Training
J. Clark, Manager, Licensing
C. Coleman, Manager, Engineering Programs & Components
F. Corley, Manager, Design Engineering
R. Creel, Superintendent, Plant Security
T. Evans, Director, Nuclear Safety Assurance
M. Feltner, Manager, Production
M. Ferrentelli, Manager, Maintenance
A. Fredieu, Manager, Outage
R. Gadbois, General Manager, Plant Operations
T. Gates, Assistant Operations Manager - Shift
K. Hallaran, Manager, Chemistry
K. Huffstatler, Senior Licensing Specialist
V. Huffstatler, Senior HP/Chemistry Specialist, Chemistry
G. Krause, Assistant Operations Manager - Training
P. Lucky, Manager, Corrective Actions and Assessments
J. Maher, Manager, System Engineering
W. Mashburn, Director, Engineering
M. Mella, Engineer, Reactor Engineering
E. Neal, Acting Manager, Radiation Protection
E. Olson, Site Vice President
W. Renz, Director, Emergency Planning
J. Reynolds, Assistant Operations Manager - Support
T. Santy, Manager, Security
T. Shenk, Manager, Operations
J. Soileau, HP/Chemistry Specialist, Radiation Protection
W. Spell, Environmental Specialist
J. Vukovics, Supervisor, Reactor Engineering
J. Wieging, Manager, Planning and Scheduling, Outages
L. Woods, Manager, Quality Assurance

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened and Closed

05000458/2013005-01 NCV Failure to Perform a Survey on Water Leak (Section 2RS6)
05000458/2013005-02 NCV Failure to Periodically Update the Updated Safety Analysis Report (Section 2RS8)

Closed

05000458/LER-2013-001-00 LER Operations Prohibited by Technical Specifications for Operations with a Potential to Drain the Reactor Vessel

(Section 4OA3)

TI 2515/182 TI Review of Industry Initiative to Control Degradation of Underground Piping and Tanks (Section 4OA5)

LIST OF DOCUMENTS REVIEWED

Section 1R01: Adverse Weather Protection

Procedures

Number Title Revision
SOP-0037 Fire Protection Water System Operating Procedure (SYS 251) 33
SOP-0045 13.8 KV System 24
SOP-0046 4.16 KV System 50
SOP-0115 Service Water Cooling (SYS #130)
25

Section 1R04: Equipment Alignment

Condition Reports

(CRs)

CR-RBS-2013-06729
CR-RBS-2013-06730
CR-RBS-2013-06731
CR-RBS-2013-06732
CR-RBS-2013-06733
CR-RBS-2013-06934

Miscellaneous Documents

Number Title Date
NMAC Terry Turbine Industry Feedback Information Repository April 11, 2005

Miscellaneous Documents

Number Title Date
TR-1007461 Terry Turbine Maintenance Guide, AFW Application Final Report (Replaces
TR-105874 and TR-016909-
R1) November 2002 Procedures Number Title Revision
SOP-0035 Reactor Core Isolation Cooling System (SYS #209) 045
SOP-0099 Makeup Water System (SYS #659) 027
STP-209-6310 RCIC Quarterly Pump and Valve Operability Test 037
River Bend Station Training Document Number Title Revision R-STM-0209 Reactor Core Isolation Cooling (RCIC) System 10
Specification Number Title Revision 228.410 Furnishing and Installation of Thermal Insulation Outside the Drywell 2

Section 1R05: Fire Protection

Procedures

Number Title Revision
CB-098-122 Water Chiller Equipment 1A Room Firer Area C-13W 3
DG-098-054 Diesel Generator A Room Fire Area
DG-6/Z-1 4
DG-098-055 Diesel Generator A Control Room Fire Area
DG-6/Z-1 4
EN-TQ-125 Fire Brigade Drills 1
FPP-0020 Guidelines for Preparation of Pre-Fire Strategies and Pre-Fire Plans 10

Section 1R06: Flood Protection Measures

Calculations

Number Title Revision G13.18.12.3*013 Miscellaneous Internal Flooding Calculations 000
G13.18.12.3*014 External Flooding of Tunnel G from the Unit 2 Excavation Area 000 G13.18.12.3*015 Internal Flooding Screening Analysis 000
PN-316 MELC - Maximum Leak Rate for a Moderate Energy Line Crack (MELC) During RHR Shutdown Cooling 000
PN-317 MELC - Max Flood Elevations for Moderate Energy Line Cracks in Cat 1 Structures 001

Condition Reports

(CRs)

CR-OE-NOE-2005-00376
CR-OE-NOE-2007-00076
CR-RBS-2011-02904
CR-RBS-2011-03272
CR-RBS-2011-03356
CR-RBS-2013-07117
Engineering Document Number Title Revision
EC-15549 Revise Flood Calc
PN-317 and Criterion 220.940 for Standby Gas Treatment Cubicles, Annulus, and
CB 70 000

Operating Experience

Smart Sample Number Title Date OpESS
FY 2007-02 Flooding Vulnerabilities Due to Inadequate Design and Conduit / Hydrostatic Seal Barrier Concerns December 20, 2006 Procedure Number Title Revision
EOP-0001 Emergency Operating Procedure - RPV Control 026

Work Orders

(WOs)

WO 52338186 WO 52508085

Section 1R11: Licensed Operator Requalification Program and Licensed Operator Performance

Miscellaneous

Document Number Title Date
Operating Test Results December 13, 2013

Procedures

Number Title Revision
AOP-0001 Reactor Scram 028
AOP-0002 Main Turbine and Generator Trip 026
AOP-0003 Automatic Isolations 033
EOP-0001 RPV Control 026
EOP-0002 Primary Containment Control 015
RSMS-OPS-0825 *Loss of RPS B/Relief Valve Fails Open/Steam Leak in the Drywell with Failure of the Drywell 02
RSMS-OPS-0837 *C33-R605 Fails Upscale, Feedwater Pump Trip/FCV Runback Fails, Turbine Trip, ATWS

(electric) 02

Section 1R12: Maintenance Effectiveness

Miscellaneous

Document Number Title Date
RBS Maintenance Rule Reliability and Availability Sheet October 15, 2013

Section 1R13: Maintenance Risk Assessments and Emergent Work Control

Condition Reports

(CRs)

CR-RBS-2013-03660
CR-RBS-2013-06513
CR-RBS-2013-06724
Engineering Document Number Title Revision
EC-44741 Document EOOS Risk Assessment of
NJS-SWG4A(B) Cross-Tie with
NNS-SWG6B Out of Service for
CR-RBS-2013-03660 (MCR-RB-4831) 000

Procedure

Number Title Revision
OSP-0048 Switchyard, Transformer Yard, and Sensitive Equipment Controls 23

Section 1R15: Operability Determinations and Functionality Assessments

Condition Reports

(CRs)

CR-RBS-2013-02968
CR-RBS-2013-04732
CR-RBS-2013-04780
CR-RBS-2013-05132
CR-RBS-2013-05211
CR-RBS-2013-05484
CR-RBS-2013-05558
CR-RBS-2013-05572
CR-RBS-2013-05772
CR-RBS-2013-05802
CR-RBS-2013-05803
CR-RBS-2013-05805
CR-RBS-2013-05806
CR-RBS-2013-05807
CR-RBS-2013-05816
CR-RBS-2013-05926
CR-RBS-2013-06331
CR-RBS-2013-06332

Miscellaneous Documents

Number Title Date
ANS-59.51; ANSI N195-1976 American National Standard Fuel Oil Systems for Standby Diesel-Generators April 12, 1976 Lab Number V5012252 DFO Storage Tank, Label States:
No. 20204, Time:
1545, Sample Point:
All Levels August 30, 2013

Procedures

Number Title Revision
STP-309-6301 Div I EDG Fuel Oil Transfer Pump and Valve Operability Test 017
STP-309-6302 Div II EDG Fuel Oil Transfer Pump and Valve Operability Test 021
STP-309-6315 Div III EDG Fuel Oil Transfer Pump and Valve Operability Test 013

Work Orders

(WOs)

WO 00234891
WO 00338263
WO 51023678
WO 52221569
WO 52222758
WO 52331761
WO 52331762
WO 52331770
WO 52335514
WO 52347923
WO 52353126
WO 52363812
WO 52453899
WO 52459999
WO 52477715
WO 52481349
WO 52482406
WO 52483846
WO 52485243
WO 52487628
WO 52487629
WO 52487860
WO 52503040 WO 52506680

Section 1R19: Post-Maintenance Testing

Condition Reports

(CRs)

CR-RBS-1995-00749
CR-RBS-2013-06056
CR-RBS-2013-06562
CR-RBS-2013-06789
CR-RBS-2013-06832
CR-RBS-2013-06992
CR-RBS-2013-07105
CR-RBS-2013-07201
Drawing Number Title Revision
ESK-05ENS07 Elementary Diagram 4.16KV SWGR. STBY. Bus 1B Gen
ACB 17
Loop Calibration Reports Number Title Revision LCR 1.ILHVK.011 Control Building Chilled Water - Chilled Water Inlet Flow to
HVK-CHL1C
HVK-FTX5c 3 LCR 1.ILEGA.001 Generator Emergency Air Compr Diesel Starting Air - Local Pressure Indicators 2

Miscellaneous Documents

Number Title Revision Set Pint Data Sheet Number 12210-
1MSS-PS135 Pressure Switch Signals Alarm for Low Hydraulic Supply Pressure to Bypass Valve 0
EPRI NMAC Manual - Basler SR8A Voltage Regulators for Emergency Diesel Generators 0

Procedure

Number Title Revision
EN-WM-107 Post Maintenance Testing 4
Vendor Technical Documents Number Title Revision
VTD-R369-0156 Rosemount Operations Manual for Trip/Calibration System Model 710 DU [PUB. #4471-1] 0
VTD-R369-0157 Rosemount Service Manual for Trip/Calibration System Model 710 DU [PUB. #4471-2] 0

Work Orders

(WOs)

WO 00067482
WO 00328593 WO 52516509

Section 1R22: Surveillance Testing

Calculations

Number Title Revision G13.18.2.1*018 Control Building Air Handling Units Chilled Water Flow Requirements and Associated Required Chiller Capacity 1 G13.18.2.1*059 Control Building Heat Load Evaluation During LOCA w/Offsite Power Available and Normal Operating Conditions 3 G13.18.2.1*078 Evaluation of Control Building Chillers (HVK-CHL1A, B, and D Performance Test Data 00

Condition Reports

(CRs)

CR-RBS-2013-04945
CR-RBS-2013-05848
CR-RBS-2013-06143
CR-RBS-2013-06479
CR-RBS-2013-06544
CR-RBS-2013-06562
Engineering Documents Number Title Revision
EC-45911 Provide Temporary Side Stream Filtration and Dehydration for Bypass
EC-EHC System Sump Tank C85-D002 Contents and Maintain EHC System Operation During Installation, Ops, and Removal 0
MR 95-0514 Minor Modification - Improve Main Turbine and Bypass EHC Filtration 0

Miscellaneous Documents

Number Title Revision 3222.350-000-002A HYD Power Unit Operation and Maintenance Instruction Manual B
GE 22A4956 Steam Bypass and Pressure Regulator System 0

Procedures

Number Title Revision
CMP-1026 MCC Circuit Breakers, Starters and Thermal Overloads 19
COP-0001 Sampling Via Various Balance of Plant Systems 23

Procedures

Number Title Revision
COP-0032 Startup and Operation of the Reactor Sample Panel G33-Z020 10
COP-0044 Configuration Control of Sampling Valves 2
COP-0619 Gamma Isotopic Analysis Sample Preparation 6
STP-303-1601 120 and 480VAC Breaker Overload Functional Test 30
STP-309-0203 Division III Diesel Generator Operability Test 320
STP-402-3604 Performance Monitoring Program for the Control Room Air Handling Unit HVC*ACU1A (Div I) 007
STP-410-3604 Performance Testing for Control Building Chiller
HVK-CHL1D 303
STP-509-0101 Main Turbine Bypass System Valve Cycle Test 12
River Bend Station System Design Criteria Number Title Revision
Control Building HVAC - System Number 402 Control Building Chilled Water - System Number
410 3

Work Orders

(WOs)

WO 00087667
WO 00234777
WO 00255863
WO 00364294
WO 52491674 WO 52514958

Section 1EP4: Emergency Action Level and Emergency Plan Changes

Number Title Revision
Emergency Plan 38 and 39
EIP-2-001 Classification of Emergencies 24

Section 2RS5: Radiation Monitoring Instrumentation Procedures Number Title Revision

EN-RP-301 Radiation Protection Instrument Control 6
EN-RP-302 Operation of Radiation Protection Instrumentation 2
EN-RP-303 Source Checking of Radiation Protection Instrumentation 2

Procedures

Number Title Revision
EN-RP-306 Calibration and Operation of the Eberline
PM-7 2
EN-RP-307 Operation and Calibration of the Eberline Personnel Contamination Monitors 1
EN-RP-308 Operation and Calibration of Gamma Scintillation Tool Monitors 5
RHP-0106 Calibration of the Canberra Fastscan and Accuscan II Whole Body Counters 3
RPP-0036
Calibration of DRMS Area Monitors and Determination of Alert and High Alarm Setpoints 7
STP-511-4201 Main Steam Line Radiation High High Calibration and Logic System Functional Test 19
Audits and Self-Assessments Number Title Date
QA 14-15-2009 Calibration Laboratory Audit Report December 5, 2009
Radiation Protection Instrumentation Calibrations Identification-Model No. Instrument Type Calibration Date Fastcan II
Whole Body Counter February 26, 2013 Accuscan II Whole Body Counter February 28, 2013 A006
89-0527 Tool Monitor Tool Monitor February 23, 2012 September 6, 201289-0527 Tool Monitor March 28, 2013
PCM-1B #572 Personnel Contamination Monitor May 1, 2013
PCM-2 #614 Personnel Contamination Monitor February 6, 2012 421
PM-7 January 29, 2013 436
PM-7 June 28, 2013
Process Effluent and Area Monitor Functional Test and Calibrations Effluent Monitor Calibrations Channel No. Monitor Description Procedure Calibration Date RE125 Plant vent exhaust noble gas
STP-511-4214 May 13, 2013 RE219 RE3A RE5A RCIC Room Area Monitor Main Steam Line Monitor Fuel Building Vent Exhaust
MCP-4201
STP-511-4201
STP-511-4205 July 17, 2012 January 24, 2013 June 27, 2013 RE125 Plant Vent Stack Flow Rate
STP-511-4231 May 13, 2013
RE107 RE5B Liquid Radwaste Effluent Monitor Fuel building Ventilation
STP-511-4280
STP-511-4205 September 14,2011 July 26, 2012 RE16A Primary Containment Area Monitor
STP-511-4249 May 21, 2013

Condition Reports

(CRs)

CR-HQN-2013-00899
CR-HQN-2013-00203
CR-HQN-2011-01062
CR-HQN-2013-00931
CR-RBS-2011-08977
CR-RBS-2013-04845
CR-RBS-2011-06829
CR-RBS-2012-04105
CR-RBS-2012-05478
CR-RBS-2011-02642
CR-RBS-2010-02457 CR-RBS-2011-03377

Section 2RS6: Radioactive Gaseous and Liquid Effluent Treatment Procedures Number Title Revision

COP-0046 Sampling Gaseous Effluents via the Wide Range Gas Monitors 15
RSP-0008 Offsite Dose Calculation Manual
14
ADM-0054 Radioactive Liquid Effluent Batch Discharge 6A
CSP-0110 Radioactive Liquid Effluent Batch Discharge 19
EN-CY-102 Laboratory Analytical Quality Control 4
EN-CY-108 Monitoring of Nonradioactive Systems 5
EN-CY-109 Sampling and Analyses of Groundwater Monitoring Wells 3
EN-CY-111 Radiological Groundwater Monitoring Program 4
ESP-8-023 Sampling of Airborne Radioiodine and Particulates for Radiological Environmental Monitoring 14
RHP-0032 Dose Rate Calculation from Gaseous Effluents 10
RPP-0027 Gaseous Effluents Monitor Setpoint Determination 3A
RPP-0102 Dose Calculations from Gaseous Effluents 301
STP-257-8601 Division I Standby Gas Treatment System Laboratory Carbon Filter Analysis 14
STP-402-3601 Inservice Testing of Division 1 Control Room Fresh Air System 303
STP-406-3601 Inservice Testing of Division I Fuel Building Ventilation System 301
STP-406-8602 Division I Fuel Building Ventilation System Laboratory Carbon Filter Analysis 11

Condition Reports

(CRs)

CR-RBS-2011-06810
CR-RBS-2011-07332
CR-RBS-2011-07424
CR-RBS-2011-07531
CR-RBS-2011-07943
CR-RBS-2011-07946
CR-RBS-2011-08583
CR-RBS-2011-08685
CR-RBS-2011-08821
CR-RBS-2011-08879
CR-RBS-2011-08899
CR-RBS-2011-08993
CR-RBS-2012-00368
CR-RBS-2012-00485
CR-RBS-2012-00503
CR-RBS-2012-00609
CR-RBS-2012-00611
CR-RBS-2012-00673
CR-RBS-2012-00676
CR-RBS-2012-00725
CR-RBS-2012-01152
CR-RBS-2012-01244
CR-RBS-2012-01273
CR-RBS-2012-01774
CR-RBS-2012-01845
CR-RBS-2012-03726
CR-RBS-2012-04388
CR-RBS-2012-05159
CR-RBS-2012-05466
CR-RBS-2012-05520
CR-RBS-2012-05827
CR-RBS-2012-05969
CR-RBS-2012-06008
CR-RBS-2012-06056
CR-RBS-2012-06474
CR-RBS-2012-06591
CR-RBS-2012-07285
CR-RBS-2012-08821
CR-RBS-2013-00216
CR-RBS-2013-00615
CR-RBS-2013-00958
CR-RBS-2013-01243
CR-RBS-2013-01513
CR-RBS-2013-01581
CR-RBS-2013-01877
CR-RBS-2013-02058
CR-RBS-2013-02062
CR-RBS-2013-02094
CR-RBS-2013-02194
CR-RBS-2013-02388
CR-RBS-2013-02480
CR-RBS-2013-02487
CR-RBS-2013-02641
CR-RBS-2013-02793
CR-RBS-2013-02833
CR-RBS-2013-03170
CR-RBS-2013-03720
CR-RBS-2013-03822
CR-RBS-2013-04119
CR-RBS-2013-04350
CR-RBS-2013-04530
CR-RBS-2013-05020
CR-RBS-2013-05325
CR-RBS-2013-05619
CR-RBS-2013-05649
CR-RBS-2013-05667
CR-RBS-2013-05822
CR-RBS-2013-06354
CR-RBS-2013-06471
CR-RBS-2013-06476
CR-RBS-2013-06486
CR-RBS-2013-06501
CR-RBS-2013-06746
CR-RBS-2013-06755
CR-HQN-2012-00368
Audits/Self-Assessments Number Title Date
QA-2/6-2011-RBS-01 Combined Chemistry, Effluents and Environmental Monitoring Programs Quality Assurance Audit Report August 22 - October 6, 2011
QS-2011-RBS-025 QA Follow-up Surveillance of the QAFs from the 2011 Combined Chemistry, Effluents and Environmental Monitoring Programs Quality Assurance Audit Report,
QA-2/6-2011-RBS-01
December 5-7, 2011
QS-2012-RBS-015 Second QA Follow-up Surveillance of the two QAFs from the 2011 Combined Chemistry, Effluents and Environmental Monitoring Programs Quality Assurance Audit Report,
QA-2/6-2011-RBS-01 May 1 - 3, 2012
QS-2013-RBS-005 Quality Assurance second Follow-up Surveillance of "A" level
CR-RBS-2011-08993, "Tritium Identified in Groundwater Monitoring Well." February 12 - 14, 2013
QS-2012-RBS-007 Quality Assurance Follow-up Surveillance of "A" level
CR-RBS-2011-08993, "Tritium Identified in Groundwater Monitoring Well." March 12 - 15, 2012

Miscellaneous Documents

Number Title Date
2011 Annual Effluent Report April 30, 2012
2012 Annual Effluent Report May 1, 2013
Permit
2012082 Radioactive Liquid Effluent Discharge December 6, 2012Permit
2013001 Radioactive Liquid Effluent Discharge January 24, 2013

Miscellaneous Documents

Number Title Date Permit
2013026 Radioactive Liquid Effluent Discharge July 7, 2013 Permit
2013068 Radioactive Liquid Effluent Discharge September 12, 2013

Section 2RS7: Radiological Environmental Monitoring Program Procedures

Number Title Revision
EN-CY-109 Sampling and Analysis of Groundwater Monitoring Wells 3
EN-CY-111 Radiological Groundwater Monitoring Program 4
EN-EV-100 Environmental Expectations 4
EN-RP-210 Area Monitoring Program 0
ESP-8-021 Sampling Of Water For Radiological Environmental Monitoring 14
ESP-8-050 Conduct of the Radiological Environmental Monitoring Program (REMP) 15
RSP-0008 Offsite Dose Calculation Manual 14
Audits, Self-Assessments, and Surveillances Number Title Date
LO-RLO-2012-0164 Focused Self-Assessment: Pre NRC Inspection July 25,2013
NUPIC 22937 NUPIC Audit: Teledyne Brown Engineering Environmental Services:
SR 2011-009 February 21, 2011 S-CRB-25046 QA Audit Report: Q/A-2/6-2011-RBS-1 October 14, 2011 S-CRB-25079 QA Surveillance Report:
QS-2012-RBS-015 May 3, 2012
S-CRB-25173 QA Audit Report: Q/A-2/6-2013-RBS-1 October 10, 2013

Condition Reports

(CRs)

CR-RBS-2011-07322
CR-RBS-2011-08993
CR-RBS-2012-05448
CR-RBS-2012-06008
CR-RBS-2013-01514
CR-RBS-2013-01915
CR-RBS-2013-03073
CR-RBS-2013-03428
CR-RBS-2013-05470
CR-RBS-2013-05667
CR-RBS-2013-06623
CR-RBS-2013-06653
CR-RBS-2013-07205
CR-RBS-2013-07299
CR-HQN-2013-00574
CR-HQN-2013-00861
CR-HQN-2013-00932
Calibration and Maintenance Records Number Title Date S/N 0042 RAS Pump Calibration Data Sheet October 17, 2013 S/N 0234 RAS Pump Calibration Data Sheet June 12, 2013
S/N 0236 RAS Pump Calibration Data Sheet October 21, 2013
S/N 0237 RAS Pump Calibration Data Sheet June 12, 2013
WO-52479086 Meteorological Monitoring - Air Temperature Difference Elev. 30/150 foot (Primary) Calibration Test August 29, 2013
WO-52479652 Meteorological Monitoring - Wind Speed Elev. 30 foot (Primary) Calibration Test August 29, 2013
WO-52479654 Meteorological Monitoring - Wind Speed Elev. 150 foot (Primary) Calibration Test August 29, 2013
WO-52479656 Meteorological Monitoring - Wind Direction Elev. 30 foot (Primary) Calibration Test August 29, 2013
WO-52481335 Meteorological Monitoring - Wind Direction Elev. 150 foot (Primary) Calibration Test August 29, 2013

Miscellaneous Documents

Number Title Date
Groundwater Monitoring Plan: River Bend, Rev. 4 August 29, 2013
2011 Annual Radiological Environmental Operating Report April 30, 2012
2012 Annual Radiological Environmental Operating Report May 1, 2013
2013 River Bend Area Monitoring Program Report October 30, 2013

Section 2RS8: Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation Procedures Number Title Revision

RWS-0304 Radioactive Waste Control 15
RW-108 Radioactive Shipment Accident Response 1
RW-106 Integrated Transportation Security Plan 2
RW-105 Process Control Program 3
RW-104 Scaling Factors 9

Procedures

Number Title Revision
RW-103 Radwaste Tracking 4
RW-102 Radwaste Shipping 10
RW-101 Radwaste Management 3
RP-121 Rad Material Control 7
RP-121-01 Receipt of Rad Material 1
RWS-0336 Operation of Dewatering System 11
ER-RB-2001-0407-000 Fire Protection Requirements for Storage of Combustible materials at the Offsite Low Level Radwaste Storage Facility 0
RSP-0221 Controls for Storage, Monitoring, and Decontamination Areas Outside the Protected Area 5

Condition Reports

(CRs)

CR-RBS -2011-7419
CR-RBS -2011-7466
CR-RBS-2012-0075
CR-RBS-2012-0256
CR-RBS- 2012-0434
CR-RBS-2012-4566
CR-RBS-2012-6443
CR-RBS-2013-1195
CR-RBS- 2013-1801
CR-RBS-2013-2480
CR-RBS-2013-2703
CR-RBS-2013-2915
CR-RBS -2013-2919
CR-RBS-2013-3505
CR-RBS-2013-4657
CR-RBS-2013-5070
CR-RBS-2013-5604
CR-RBS-2013-5739
CR-RBS-2013-5939
CR-RBS-2013-6025
CR-RBS-2013-6299
CR-RBS-2013-6524
CR-RBS-2013-6525
CR-RBS-2013-6540
CR-HQN-2012-0840
CR-HQN-2012-1224
CR-HQN-2013-0573
CR-HQN-LO-2012-0085
Shipments
RBS-2013-032
RBS-2012-046
RBS-2012-032
RBS-2012-004
RBS-2012-081
RBS-2013-084
RBS-2013-070
RBS-2013-071
RBS-2013-072
RBS-2013-073
RBS-2013-074
RBS-2013-086
RBS-2013-088 RBS-2013-089

Section 4OA1: Performance Indicator Verification Procedure Number Title Revision

EN-LI-114 Performance Indicator Process 6

Section 4OA2: Problem Identification and Resolution

Condition Reports

CR-RBS-2013-04749
CR-RBS-2013-04773
CR-RBS-2013-06228
CR-RBS-2013-07104

Miscellaneous

Document Number Title Date Audit #QA-01-2013-HQN-1 Scope Element - II.
Drug and Alcohol Testing (FFD-02) (10CFR26.31) 0

Procedures

Number Title Revision
EN-FAP-OP-006 Operator Aggregate Impact Index Performance Indicator 0
EN-MP-120 Material Receipt 6

Section 4OA3: Follow-up of Events and Notices of Enforcement Discretion

Condition Report (CR)

CR-RBS-2013-00225

Procedures

Number Title Revision
EN-OU-108 Shutdown Safety Management Program (SSMP) 6
OSP-0033 Operations with Potential to Drain the Reactor Vessel/Cavity 11

Section 4OA5: Other Activities

Condition Reports

(CRs)

CR-RBS-2011-08993
CR-RBS-2012-01978
CR-RBS-2012-02124
CR-RBS-2012-02354
CR-RBS-2012-07163
CR-RBS-2012-07363
CR-RBS-2012-07706
CR-RBS-2013-00122
CR-RBS-2013-00613
CR-RBS-2013-00653
CR-RBS-2013-00655
CR-RBS-2013-06354

Miscellaneous Documents

Number Title Date
Assorted Piping Ultrasonic / Guided Wave Inspection Report 12/18/12

Miscellaneous Documents

Number Title Date
ISI-VE-13-001 Thickness Examination Report,
CSH-016-054-001 10/11/13
EN-EP-S-002-MULTI attachment 7.2 Pipe/Tank Coating Visual Inspection Checklist,
CNS-750-497 01/18/13
EN-EP-S-002MULTI attachment 7.2 Pipe/Tank Coating Visual Inspection Checklist,
CSH-016-054-001A 12/03/12
EN-EP-S-002MULTI attachment 7.2 Pipe/Tank Coating Visual Inspection Checklist,
CNS-006-251 12/17/12
EN-EP-S-002MULTI attachment 7.2 Pipe/Tank Coating Visual Inspection Checklist,
CSH-012-001 01/18/13
EN-EP-S-002MULTI attachment 7.2 Pipe/Tank Coating Visual Inspection Checklist,
IAS-001-165 01/18/13
EN-EP-S-002MULTI attachment 7.2 Pipe/Tank Coating Visual Inspection Checklist,
LWS-004-586 09/11/13
EN-EP-S-002MULTI attachment 7.2 Pipe/Tank Coating Visual Inspection Checklist,
CWS-020-035-4 &
PBS 01/18/13
ISI-VT-12-091 Visual Exam of Equipment and Components,
CSH-016-054-001A 12/03/12
ISI-VT-12-094 Visual Exam of Equipment and Components,
LWS-004-586-001 01/09/13
ISI-VT-12-093 Visual Exam of Equipment and Components,
CNS-750-497-004 01/09/13
ISI-VT-13-001 Visual Exam of Equipment and Components,
IAS-001-165-001 01/09/13
ISI-VT-12-096 Visual Exam of Equipment and Components,
CNS-012-001-001A 01/09/13

Miscellaneous Documents

Number Title Date
ISI-VT-12-095 Visual Exam of Equipment and Components,
CNS-006-251-001 01/09/13
20" Circulating Water Blowdown Line 4" Effluent Line External Visual and Ultrasonic Thickness Inspection Report 09/10/13
Report: In-Service Inspections: Turbine Building Drain System Piping (el 67'), Condensate Pump Can. Annulus Undated
SEP-UIP-RBS River Bend Station Underground Components Inspection Plan Undated
Project Summary Report: Radiological Material Leak Prevention to Groundwater of Above and Under Ground Structures, Systems, and Components 09/30/10
ECH-EP-10-00001 Radiological SSC Groundwater Initiative Risk Evaluation Criteria 06/15/10
Buried Piping and Tanks Program Health Report Q2-2013
Cathodic Protection System health Report Q2-2013
LO-RLO-2012-00023 Underground Piping and Tanks Inspection and Monitoring Program Self Assessment 05/31/12
RBS BPT Program and Inspection Review Undated
WO 52443734 Work Order:
PCS-Test-STA1 Eng Review PM Results Annually for Cathodic Protection 12/12/12
WO 52296891
PCS-Rect 9 - Inspect 06/12/13
WO 52296890
PCS-Rect 3B - Inspect, Measure, Record Rectifier Data 02/04/13
RBS 241.261 Cathodic Protection Design Criteria 02/21/79

Procedures

Number Title Revision / Date
CEP-NDE-0505 Ultrasonic Thickness Examination Rev 4 / 07/29/09
UT.ASME.3 Ultrasonic Thickness Measurement Rev 8 / 10/31/11
EN-EP-S-002-MULTI Underground Piping and Tanks General Visual Inspection Rev 2 / 04/15/13
CEP-UPT-0100 Underground Piping and Tanks Inspection and Monitoring Rev 2 / 02/18/13
EN-DC-343 Underground Piping and Tanks Inspection Monitoring Program Rev 8 / 04/30/13
SOP-0051 Cathodic Protection Rev 301 / 03/17/10OSP-0031 Log Report - Outside Area Rev 062 / 08/21/13
EN-DC-105` Configuration Management Rev 3 / 11/09/10
EN-DC-115 Engineering Change Process Rev 15 / 06/17/13
TI 2515-182 PHASE 2 INSPECTION DOCUMENT REQUEST
A2-1 Attachment 2 September 26, 2013
We have discussed the schedule for these inspection activities and understand that you will be our regulatory contact for this inspection.
If there are any questions about this inspection or the material requested, please contact Peter Jayroe at 817-200-1174, e-mail Peter.Jayroe@nrc.gov.
This e-mail does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.).
Existing information collection requirements were approved by the Office of Management and Budget, Control Number 3150 0011.
The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.
TI 2515-182 PHASE 2 INSPECTION DOCUMENT REQUEST
A2-2 Inspection Dates:
October 2013 Inspection Procedures:
TI 2515-182, "Review of Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks"
Inspector:
Peter Jayroe (817) 200-1174, Peter.Jayroe@nrc.gov A. Information Requested for the In-Office Preparation Week The following information should be sent to the Region IV office in hard copy or electronic format (ims.certrec.com preferred), in care of Peter Jayroe to facilitate the preparation for the onsite inspection week.
Please provide requested documentation electronically if possible.
If requested documents are large and only hard copy formats are available, please inform the inspector(s), and provide subject documentation during the first day of the onsite inspection. If you have any questions regarding this information request, please call the inspector as soon as possible.
1. Organization list of site individuals responsible for the site's underground piping and tanks program.
2. Copy of Site Underground Piping and Tanks program.
3. Please review the attached "Questions" list and provide the response and/or document requests. The questions are to be provided in advance of the inspection to support preparation for onsite week.
4. Schedule for the completion of the following
NEI 09-14 Rev.1 attributes:
Buried Piping * Procedures and Oversight * Risk Ranking * Inspection Plan * Plan Implementation * Asset Management Plan Underground Piping and Tanks * Procedures and Oversight * Prioritization * Condition Assessment Plan * Plan Implementation * Asset Management Plan The inspector may select specific items from the information requested for the preparation week and request follow-up documents during the on-site inspection week.
B. Information To Be Provided On-Site To The Inspector Following The Entrance Meeting
TI 2515-182 PHASE 2 INSPECTION DOCUMENT REQUEST
A2-3 1. Location maps of buried & underground piping and tanks identified by the inspector from the information requested for the preparation week.
2. Copy of EPRI document "Recommendations for an Effective Program to Control the Degradation of Buried Pipe".
3. Self or third party assessments of the Underground Piping and Tanks Program (if any have been performed).
4. For any of the
NEI 09-14 Rev.1 attributes identified below which have been completed prior to the NRC's onsite inspection, provide written records that demonstrate that the program attribute is complete.
Buried Piping * Procedures and Oversight * Risk Ranking * Inspection Plan * Plan Implementation * Asset Management Plan Underground Piping and Tanks * Procedures and Oversight * Prioritization * Condition Assessment Plan * Plan Implementation * Asset Management Plan
TI 2515-182 PHASE 2 INSPECTION DOCUMENT REQUEST
A2-4
Questions Response Initiative Consistency Has the licensee taken any deviations to either of the initiatives?
Yes / No If so, what deviations have been taken and what is (are) the basis for these deviations? Provide documentation of deviations and any associated corrective action reports. Does the licensee have an onsite buried piping program manager (owner) and, potentially, a staff? Yes / No How many buried piping program owners have there been since January 1, 2010?
Provide documentation identifying individuals responsible for the site buried piping program since January 1, 2010.
How many other site programs are assigned to the buried piping program owner?
List all site programs that are under the direct responsibility of the site's buried piping program owner.
Does the licensee have requirements to capture program performance, such as system health reports and performance indicators?
Yes / No Provide copies of most recent systems health reports if applicable Are these requirements periodic or event driven? Periodic / Event Driven / None
TI 2515-182 PHASE 2 INSPECTION DOCUMENT REQUEST
Are there examples where these requirements have been successfully used to upgrade piping systems or to avert piping or tank leaks? Yes / No Provide documentation related to examples if applicable Does the licensee have a program or procedure to confirm the as-built location of buried and underground piping and tanks at the plant?
Yes / No Has the licensee used this program? Yes / No
Was the program effective in identifying the location of buried pipe?
Yes / No For a sample of buried pipe and underground piping and tanks (sample size at least 1 high and 1 low risk/priority pipe or tank), did the risk ranking and/or prioritization process utilized by the licensee produce results in accordance with the initiative guidelines, i.e., which emphasize the importance of components which have a high likelihood and Yes / No
Sample size examined _____
Prep: Provide copy of site's risk ranking documents including documents pertaining to the actual risk rankings and methodology
TI 2515-182 PHASE 2 INSPECTION DOCUMENT REQUEST

consequence of failure and deemphasize the importance of components which have a low likelihood and consequence of failure? used.

Prep: Provide documents/drawings and/or list which identifies the risk ranking for each pipe segment or tank in each system within the scope of these programs.
Onsite: Provide the documents which record/describe how the risk methodology was applied to determine the risk of pipe segments or tanks as selected by the inspector during the preparation week.
As part of its risk ranking process did the licensee estimate/determine the total length of buried/ underground piping included in the initiatives? Yes / No As part of its risk ranking process did the licensee estimate/determine the total length of high risk buried/underground Yes / No
TI 2515-182 PHASE 2 INSPECTION DOCUMENT REQUEST

piping included in the initiatives?

Preventive Actions / System Maintenance
For buried steel, copper, or aluminum piping or tanks which are not cathodically protected, has the licensee developed a technical basis for concluding that structural (e.g. ASME Code minimum wall, if applicable) and leaktight integrity of buried piping can be maintained? Yes / No / Not Applicable (no buried steel, copper, or aluminum piping which is not cathodically protected)
Is the technical basis provided as justification by the licensee consistent with the initiative (including its reference documents) or industry standards (e.g. Yes / No
Provide documented technical basis including
TI 2515-182 PHASE 2 INSPECTION DOCUMENT REQUEST
NACE SP0169) referencing documents.
For uncoated steel piping, has the licensee developed a technical basis for concluding that structural (e.g. ASME
Code minimum wall, if applicable) and leaktight integrity of buried piping can be maintained? Yes / No / Not Applicable (no uncoated buried steel pipe)
Is the technical basis provided as justification by the licensee consistent with the initiative (including its reference documents) or industry standards (e.g.
NACE SP0169)? Yes / No Provide documented technical basis including referencing documents.
For licensees with cathodic protection systems, does the licensee have procedures for the maintenance, monitoring and surveys of this equipment?
Yes / No / Not Applicable (no cathodic protection systems)
Are the licensee procedures consistent with the initiative (including its reference documents) or industry standards (e.g. NACE SP0169)? Yes / No
Provide copy of procedures if applicable.
TI 2515-182 PHASE 2 INSPECTION DOCUMENT REQUEST
Is the cathodic protection system, including the evaluation of test data, being operated and maintained by personnel knowledgeable of, or trained in, such activities? Yes / No Provide documentation of training or qualification records of personnel. Is there a program to ensure chase and vault areas which contain piping or tanks subject to the underground piping and tanks initiative are monitored for, or protected against, accumulation of leakage from these pipes or tanks? Yes / No / N/A (No piping in chases or vaults)
Provide copy of program. Inspection Activities / Corrective Actions
Has the licensee prepared an inspection plan for its buried piping and underground piping and tanks?
Yes / No
Does the plan specify dates and locations where inspections are planned? Yes / No Provide copy of inspection plan and associated implementation procedures.
TI 2515-182 PHASE 2 INSPECTION DOCUMENT REQUEST
Have inspections, for which the planned dates have passed, occurred as scheduled or have a substantial number of inspections been deferred? Occurred as scheduled / Deferred Has the licensee experienced leaks and/or significant degradation in safety related piping or piping carrying licensed material since January 1, 2009?
Leaks Yes / No
Degradation Yes / No
If leakage or significant degradation did occur, did the licensee determine the cause of the leakage or degradation?
Yes / No Based on a review of a sample of root cause analyses for leaks from buried piping or underground piping and tanks which are safety related or contain licensed material, did the licensee's corrective action taken as a result of the incident include addressing the cause of the degradation? Yes / No / N/A (no leaks)
Provide root cause analyses of identified leaks if applicable.
TI 2515-182 PHASE 2 INSPECTION DOCUMENT REQUEST
Did the corrective action include an evaluation of extent of condition of the piping or tanks and possible expansion of scope of inspections?

(Preference should be given to high risk piping and "significant" leaks where more information is likely to be available). Yes / No / N/A (no leaks)

Provide corrective action documents concerning leaks if applicable.
Based on a review of a sample of NDE activities which were either directly observed or for which records were reviewed, were the inspections conducted using a predetermined set of licensee/contractor procedures?
Yes / No
Provide list of scheduled NDE activities scheduled during onsite week and list of NDE

activities that have already been conducted.

Were these procedures sufficiently described and recorded such that the inspection could be reproduced at a later date?
Yes / No Provide copies of NDE procedures for the various NDE activities that have occurred or are scheduled to occur.
Were the procedures appropriate to detect the targeted degradation Yes / No
TI 2515-182 PHASE 2 INSPECTION DOCUMENT REQUEST

mechanism?

For quantitative inspections, were the procedures used adequate to collect quantitative information?
Yes / No Did the licensee disposition direct or indirect NDE results in accordance with their procedural requirements?
Yes / No Provide sample of direct and/or indirect NDE results and the subsequent evaluations of these NDE results.
Based on a sample of piping segments, is there evidence that licensees are substantially meeting the pressure testing requirements of ASME Section XI
IWA-5244?
Yes / No Provide the completed records for the last two required Section XI periodic pressure/flow test on safety-related buried pipe segments Attachment 3
The following items are requested for the Occupational/Public Radiation Safety Inspection at River Bend Station
November 18-22, 2013 Integrated Report 2013-005
The items listed below are needed to support the Occupational Radiation Safety inspection to be conducted by Louis Carson, Casey Alldredge, John O'Donnell, and Pete Hernandez during the week of November 18, 2013.
The primary focus for Louis Carson will be on both Occupational & Public Radiation Safety using Inspection Procedures (IPs) 71124.05 - 08.
NOTE: Inspection areas are listed in the attachments below.
Please provide the requested information on or before November 8, 2013.
Please submit this information using the same lettering system as below.
For example, all contacts and phone numbers for Inspection Procedure 71124.05 should be in a file/folder titled "1- A," applicable organization charts in file/folder "1- B," etc. If information is placed on ims.certrec.com, please ensure the inspection exit date entered is at least 30 days later than the onsite inspection dates, so the inspectors will have access to the information while writing the report. In addition to the corrective action document lists provided for each inspection procedure listed below, please provide updated lists of corrective action documents at the entrance meeting.
The dates for these lists should range from the end dates of the original lists to the day of the entrance meeting. If more than one inspection procedure is to be conducted and the information requests appear to be redundant, there is no need to provide duplicate copies.
Enter a note explaining in which file the information can be found. If you have any questions or comments, please contact Louis Carson at (817)200.1221 or Louis.Carson @nrc.gov.
PAPERWORK REDUCTION ACT STATEMENT This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, control number 3150-0011.
5.
Radiation Monitoring Instrumentation (71124.05) Date of Last Inspection: May 26, 2010
A. List of contacts and telephone numbers for the following areas: 1. Effluent monitor calibration
2. Radiation protection instrument calibration
3. Installed instrument calibrations
4. Count room and Laboratory instrument calibrations B. Applicable organization charts C. Copies of audits, self-assessments, vendor or NUPIC audits for contractor support and LERs, written since date of last inspection, related to:
1. Area radiation monitors, continuous air monitors, criticality monitors, portable survey instruments, electronic dosimeters, teledosimetry, personnel contamination monitors, or whole body counters
2. Installed radiation monitors D. Procedure index for: 1. Calibration, use and operation of continuous air monitors, criticality monitors, portable survey instruments, temporary area radiation monitors, electronic dosimeters, teledosimetry, personnel contamination monitors, and whole body counters. 2. Calibration of installed radiation monitors E. Please provide specific procedures related to the following areas noted below.
Additional Specific Procedures will be requested by number after the inspector reviews the procedure indexes.
1. Calibration of portable radiation detection instruments (for portable ion chambers) 2. Whole body counter calibration 3. Laboratory instrumentation quality control F. A summary list of corrective action documents (including corporate and subtiered systems) written since date of last inspection, related to the following programs: 1. Area radiation monitors, continuous air monitors, criticality monitors, portable survey instruments, electronic dosimeters, teledosimetry, personnel contamination monitors, whole body counters,
2. Installed radiation monitors,
3. Effluent radiation monitors
4. Count room radiation instruments NOTE: The lists should indicate the significance level of each issue and the search criteria used. G. Offsite dose calculation manual, technical requirements manual, or licensee controlled specifications which lists the effluent monitors and calibration requirements. H. Current calibration data for the whole body counters.
I. Primary to secondary source calibration correlation for effluent monitors. J.
A list of the point of discharge effluent monitors with the two most recent calibration dates and the work order numbers associated with the calibrations.
6. Radioactive Gaseous and Liquid Effluent Treatment (71124.06)
Date of Last Inspection: September 16, 2011
A. List of contacts and telephone numbers for the following areas: 1. Radiological effluent control
2. Engineered safety feature air cleaning systems B. Applicable organization charts C. Audits, self assessments, vendor or NUPIC audits of contractor support, and LERs written since date of last inspection, related to: 1.
Radioactive effluents
2.
Engineered Safety Feature Air cleaning systems D. Procedure indexes for the following areas 1.
Radioactive effluents
2.
Engineered Safety Feature Air cleaning systems E. Please provide specific procedures related to the following areas noted below.
Additional Specific Procedures will be requested by number after the inspector reviews the procedure indexes.
1. Sampling of radioactive effluents
2. Sample analysis
3. Generating radioactive effluent release permits
4. Laboratory instrumentation quality control
5. In-place testing of HEPA filters and charcoal adsorbers 6. New or applicable procedures for effluent programs (e.g., including ground water monitoring programs) F. List of corrective action documents (including corporate and subtiered systems) written since date of last inspection, associated with:
1.
Radioactive effluents 2.
Effluent radiation monitors 3.
Engineered Safety Feature Air cleaning systems NOTE: The lists should indicate the significance level of each issue and the search criteria used. G. 2011 and 2012 Annual Radioactive Effluent Release Report
H. Current Copy of the Offsite Dose Calculation Manual I. Copy of the 2011 and 2012 interlaboratory comparison results for laboratory quality control performance of effluent sample analysis J. Effluent sampling schedule for the week of the inspection
K. New entries into 10
CFR 50.75(g) files since date of last inspection
L. Operations Dept (or other responsible dept) log records for effluent monitors removed from service or out of service M. Listing or log of liquid and gaseous release permits since date of last inspection N.
For technical specification-required air cleaning systems, the most recent surveillance test results of in-place filter testing (of HEPA filters and charcoal adsorbers) and laboratory testing (of charcoal efficiency)
7. Radiological Environmental Monitoring Program (71124.07)
Date of Last Inspection: September 16, 2011
A. List of contacts and telephone numbers for the following areas: 1. Radiological environmental monitoring
2. Meteorological monitoring B. Applicable organization charts C. Audits, self assessments, vendor or NUPIC audits of contractor support, and LERs written since date of last inspection, related to: 1. Radiological environmental monitoring program (including contractor environmental laboratory audits, if used to perform environmental program functions) 2. Environmental TLD processing facility 3. Meteorological monitoring program D. Procedure index for the following areas: 1. Radiological environmental monitoring program
2. Meteorological monitoring program E. Please provide specific procedures related to the following areas noted below.
Additional Specific Procedures will be requested by number after the inspector reviews the procedure indexes.
1. Environmental Program Description
2. Sampling, collection and preparation of environmental samples
3. Sample analysis (if applicable)
4. Laboratory instrumentation quality control 5. Procedures associated with the Offsite Dose Calculation Manual
6. Appropriate QA Audit and program procedures, and/or sections of the station's QA manual (which pertain to the REMP) F. A summary list of corrective action documents (including corporate and subtiered systems) written since date of last inspection, related to the following programs: 1. Radiological environmental monitoring 2. Meteorological monitoring
NOTE: The lists should indicate the significance level of each issue and the search criteria used. G. Wind Rose data and evaluations used for establishing environmental sampling locations H. Copies of the 2 most recent calibration packages for the meteorological tower instruments
I. Copy of the 2011 and 2012 Annual Radiological Environmental Operating Report and Land Use Census, and current revision of the Offsite Dose Calculation Manual J. Copy of the environmental laboratory's interlaboratory comparison program results for 2011 and 2012, if not included in the annual radiological environmental operating report K. Data from the environmental laboratory documenting the analytical detection sensitivities for the various environmental sample media (i.e., air, water, soil, vegetation, and milk) L. Quality Assurance audits (e.g., NUPIC) for contracted services
M. Current NEI Groundwater Initiative Plan and status
8. Radioactive Solid Waste Processing, and Radioactive Material Handling, Storage, and Transportation (71124.08)
Date of Last Inspection: September 16, 2011
A. List of contacts and telephone numbers for the following areas: 1. Solid Radioactive waste processing
2. Transportation of radioactive material/waste B. Applicable organization charts (and list of personnel involved in solid radwaste processing, transferring, and transportation of radioactive waste/materials) C. Copies of audits, department self-assessments, and LERs written since date of last inspection related to:
1. Solid radioactive waste management
2. Radioactive material/waste transportation program D. Procedure index for the following areas: 1. Solid radioactive waste management 2. Radioactive material/waste transportation
E. Please provide specific procedures related to the following areas noted below.
Additional Specific Procedures will be requested by number after the inspector reviews the procedure indexes.
1. Process control program 2. Solid and liquid radioactive waste processing
3. Radioactive material/waste shipping
4. Methodology used for waste concentration averaging, if applicable
5. Waste stream sampling and analysis F. A summary list of corrective action documents (including corporate and subtiered systems) written since date of last inspection related to: 1. Solid radioactive waste 2. Transportation of radioactive material/waste
NOTE: The lists should indicate the significance level of each issue and the search criteria used. G. Copies of training lesson plans for 49CFR172 subpart H, for radwaste processing, packaging, and shipping.
H. A summary of radioactive material and radioactive waste shipments made from date of last inspection to present I. Waste stream sample analyses results and resulting scaling factors for 2011 and 2012 J. Waste classification reports if performed by vendors (such as for irradiated hardware) Although it is not necessary to compile the following information, the inspector will also review: K. Training, and qualifications records of personnel responsible for the conduct of radioactive waste processing, package preparation, and shipping