ML101670523
| ML101670523 | |
| Person / Time | |
|---|---|
| Site: | Brunswick |
| Issue date: | 06/08/2010 |
| From: | Progress Energy Co |
| To: | NRC/NRR/DIRS/IRIB |
| Jeremy Bowen, 415-3471 | |
| Shared Package | |
| ML101670555 | List: |
| References | |
| Download: ML101670523 (18) | |
Text
Enclosure 3 Brunswick Nuclear Plant Presentation Meeting Summary of the 6/8/2010 Meeting with NRC/SNC/FPL/SCE&G Dated June 17, 2010
--~
2
--~
()
0>
--c C
Q)
~ a T"""
()
(J) a N
c 00
-
--o
.......
()
Q)
C
- J 2o J
~
a..
~
--
()
0:::
Z
- Opening Remarks
- NRC Fire Protection Screening Criteria
- Program Oversight
- NFPA 805 Transition
- Screening Criteria Summary
- Summary
~ 2 06/04/10 ~ Progress Energy
- OMA Feasibility Study conducted
- Conducted Drills and Validated Timeliness with each operating shift and implemented improvements
- Reviewed Training Material and created new Job Performance Measures (JPMs)
- Performed black-out testing of Emergency Lighting units to ensure adequate lighting
- Enhanced aiming and revised drawings to provide additional detail
- Performed comparison between Safe Shutdown Analysis and Alternate Safe Shutdown (ASSD)
Procedures
- Identified differences and made changes to ensure alignment
- Smoke model developed to address smoke movement
- Several Operator Manual Actions were eliminated
~ 3 06/04/10 ~ Progress Energy
Screening Criteria #1: Large number of OMAs
- Total III.G.2 OMAs Unit 1 = 30 and Unit 2 = 29
- 6 are common to both units
- Totallll.G.2 Fire Areas with Hot Shutdown (HSD)
OMAs for both Units: 9 Unit 1 III.G.2 Fire Areas OMAs Unit 2 III.G.2 Fire Areas OMAs CB-09: 1 CB-07: 3 DG-08 (Train "A" Shutdown): 7 DG-04: 7 DG-08 (Train "B" Shutdown): 3 DG-06: 3 DG-09: 7 DG-12: 7 DG-13: 3 DG-16E: 9 (3 are unit specific)
DG-16E: 9 (3 are unit specific)
~ 4 06104/10 ~ Progress EnergV
Screening Criteria #1: Large number of OMAs
- Confident our manual action are feasible and can be successfully implemented
- Small number of III.G.2 HSD OMAs per fire area
- Brunswick believes the risk of these OMAs is very small
~ 5 06/04/10 ~ Progress Energy
Screening Criteria #2: Single Fire affecting more than one Unit
- Criteria applies
- Brunswick is a dual unit plant
- OMA Feasibility Study addressed dual unit shutdown and ensured timeliness of actions
- Periodic Training, Evaluation and Drills conducted to ensure effectiveness
~ 6 06/04/10 ~ Progress Energy
L..
S L..
Q)
~
o 0...
.....
Q)
-
en I
e o
....e ....ro Q)
-o
-ro 0... enro N* :.:~
Oro CJ* eN
--- en .
oco ~~
"C =
-
CJ) ...::.:::~
- .~ e CJ) ~ ro ro ene
....o e*-
- JQ)
L..L..
Z CO'+=
- Brunswick III.G.2 OMAs are simple straightforward prescriptive actions
- No Coordination required with other operators
- Single discrete actions
+ If MOV does not open from Main Control Board ...
Then Open breaker and manually open valve
- Do not require diagnosis or complex decisions
- Manipulations are used in normal operation and for routine maintenance clearances
- One Time-Critical OMA to block open 6 Diesel Building doors - time validated
~ 8 06/04/10 ~ Progress Energy
Screening Criteria #6: Complex OMAs and insufficient time to complete OMAs
- Totallll.G.2 OMAs Unit 1 = 30 and Unit 2 = 29 (6 are common to both units)
- 6 QMAs block open 6 Diesel Building doors (common to both units)
- 11 OMAs monitor Condensate Storage Tank level
- Operator Initial and Continuing Training developed using the Systematic Approach to Training
- Periodic training, evaluation and drills conducted
- Over a 2 year Training Cycle
- Classroom
- Simulator/In-plant drills
. JPMs
~ 9 06/04/10 ~ Progress Energy
Screening Criteria #7: Mitigation requires cross-tying electrical or mechanical systems
- Criteria applies
- Brunswick can require cross-tying electrical systems for some fire areas
- Systems and components are operated in accordance with their design function
- Electrical cross-ties are part of original plant design
- The ability to cross-tie provides significant risk benefit
~ 10 06/04/10 ~ Progress Energy
Screening Criteria #8: Symptom-based procedures with complex OMAs
- ASSD procedures are event based
- Continuous Use Procedures
- Procedure Placekeeping required (circle and slash)
- None of the OMAs are considered complex
- Addressed in Screening Criteria #6
~ 11 06/04/10 ~ Progress Energy
- III.G.2 actions do not disable any equipment
Probability of success is very high
- Based upon NFPA 805 Transition results at Harris and Crystal River, OMAs may be deleted from procedures in future
- Many Fires do not damage the cables in the associated fire areas
~ 12 06/04/10 ~ Progress Energy
- Program Self Assessment with Industry Peers
- Independent Corporate Oversight
- NRC Inspections
~ 13 06/04/10 ~ Progress Energy
- Appendix R is current Licensing Basis
- OMAs reviewed per NRC Regulatory Issue SummarY 2006-10, "Regulatory Expectations with App.endix R Paragraph n1.G.2 Operator Manual Actions"
- Progress Energy submitted letter of intent to adopt NFPA 805
- Brunswick scheduled to submit the License Amendment Request by August 2011
- Implementation of NFPA 805 will improve the overall safety
~ 14 06/04/10 ~ Progress Energy
- 1. A large number of Operator Manual Actions (OMAs) used to YES NO mitigate cable separation issues
- 2. A single fire could affect more than one unit. YES YES
- 3. The use of thermoplastic cable . NO NO
- 4. Limited documentation of cable routing within the plant. NO NO
- 5. A Self-Induced Station Slack-Out (SISSO) strategy (isolating all YES NO on-site power to basically everything except the protected train to prevent spurious actuations) for fires in areas without adequate cable separation .
- 6. The OMAs are very complicated, not high confidence that YES NO operators would be able to implement them in fire conditions.
- 7. Mitigation of a fire requires the use of systems from multiple YES YES units (electrical or mechanical cross-unit ties) .
- 8. Symptom-based fire response procedures with complex OMAs. YES NO
~ 15 06/04/10 ~ Progress Energy
- Single fire could affect more than one unit
- Mitigation can require cross-tying electrical systems between units
- Do not have a large number of OMAs per Fire Area
- Not a SISBO strategy plant
- Simple, not complex
- OMAs do not require diagnosis or complex decisions
- Risk impact of OMAs is expected to be very small
- Periodic Training and Evaluation is conducted
- Brunswick is in compliance with current NRC requirements and are fully committed to transitioning to NFPA 805
~ 16 06/04/10 ~ Progress Energy
",. o en -~
~
c o oI *
.-
en (J.)
- J a