ML101670523

From kanterella
Revision as of 18:46, 6 December 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
NRC Fire Protection Screening Criteria, Brunswick Nuclear Plant
ML101670523
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 06/08/2010
From:
Progress Energy Co
To:
NRC/NRR/DIRS/IRIB
Jeremy Bowen, 415-3471
Shared Package
ML101670555 List:
References
Download: ML101670523 (18)


Text

Enclosure 3 Brunswick Nuclear Plant Presentation Meeting Summary of the 6/8/2010 Meeting with NRC/SNC/FPL/SCE&G Dated June 17, 2010

--~

2

--~

()

0>

--c C

Q)

~ a T"""

()

(J) a N

c 00

-

--o

.......

()

Q)

C

J 2o J

~

a..

~

--

LL

()

0:::

Z

  • Opening Remarks
  • NRC Fire Protection Screening Criteria
  • Program Oversight
  • Screening Criteria Summary
  • Summary

~ 2 06/04/10 ~ Progress Energy

  • OMA Feasibility Study conducted
  • Conducted Drills and Validated Timeliness with each operating shift and implemented improvements
  • Enhanced aiming and revised drawings to provide additional detail

Procedures

  • Identified differences and made changes to ensure alignment
  • Smoke model developed to address smoke movement

~ 3 06/04/10 ~ Progress Energy

Screening Criteria #1: Large number of OMAs

  • Total III.G.2 OMAs Unit 1 = 30 and Unit 2 = 29
  • 6 are common to both units
  • Totallll.G.2 Fire Areas with Hot Shutdown (HSD)

OMAs for both Units: 9 Unit 1 III.G.2 Fire Areas OMAs Unit 2 III.G.2 Fire Areas OMAs CB-09: 1 CB-07: 3 DG-08 (Train "A" Shutdown): 7 DG-04: 7 DG-08 (Train "B" Shutdown): 3 DG-06: 3 DG-09: 7 DG-12: 7 DG-13: 3 DG-16E: 9 (3 are unit specific)

DG-16E: 9 (3 are unit specific)

~ 4 06104/10 ~ Progress EnergV

Screening Criteria #1: Large number of OMAs

  • Confident our manual action are feasible and can be successfully implemented
  • Small number of III.G.2 HSD OMAs per fire area
  • Brunswick believes the risk of these OMAs is very small

~ 5 06/04/10 ~ Progress Energy

Screening Criteria #2: Single Fire affecting more than one Unit

  • Criteria applies
  • Brunswick is a dual unit plant
  • OMA Feasibility Study addressed dual unit shutdown and ensured timeliness of actions
  • Periodic Training, Evaluation and Drills conducted to ensure effectiveness

~ 6 06/04/10 ~ Progress Energy

L..

S L..

Q)

~

o 0...

.....

Q)

-

en I

e o

....e ....ro Q)

-o

-ro 0... enro N*  :.:~

Oro CJ* eN

--- en .

oco ~~

"C =

-

CJ) ...::.:::~

- .~ e CJ) ~ ro ro ene

....o e*-

JQ)

L..L..

Z CO'+=

  • Screening Criteria #6: Complex OMAs and insufficient time to complete OMAs
  • Brunswick III.G.2 OMAs are simple straightforward prescriptive actions
  • No Coordination required with other operators
  • Single discrete actions

+ If MOV does not open from Main Control Board ...

Then Open breaker and manually open valve

  • Do not require diagnosis or complex decisions
  • Manipulations are used in normal operation and for routine maintenance clearances
  • One Time-Critical OMA to block open 6 Diesel Building doors - time validated

~ 8 06/04/10 ~ Progress Energy

Screening Criteria #6: Complex OMAs and insufficient time to complete OMAs

  • Totallll.G.2 OMAs Unit 1 = 30 and Unit 2 = 29 (6 are common to both units)
  • 6 QMAs block open 6 Diesel Building doors (common to both units)
  • 11 OMAs monitor Condensate Storage Tank level
  • 18 OMAs manually operate valves (4 MOVs per unit)
  • Operator Initial and Continuing Training developed using the Systematic Approach to Training
  • Periodic training, evaluation and drills conducted
  • Over a 2 year Training Cycle
  • Classroom
  • Simulator/In-plant drills

. JPMs

~ 9 06/04/10 ~ Progress Energy

Screening Criteria #7: Mitigation requires cross-tying electrical or mechanical systems

  • Criteria applies
  • Brunswick can require cross-tying electrical systems for some fire areas
  • Systems and components are operated in accordance with their design function
  • Electrical cross-ties are part of original plant design
  • The ability to cross-tie provides significant risk benefit

~ 10 06/04/10 ~ Progress Energy

Screening Criteria #8: Symptom-based procedures with complex OMAs

  • ASSD procedures are event based
  • Continuous Use Procedures
  • Procedure Placekeeping required (circle and slash)
  • None of the OMAs are considered complex
  • Addressed in Screening Criteria #6

~ 11 06/04/10 ~ Progress Energy

  • III.G.2 actions do not disable any equipment
  • OMAs Human Reliability Analysis (HRA)

Probability of success is very high

  • Based upon NFPA 805 Transition results at Harris and Crystal River, OMAs may be deleted from procedures in future
  • Many Fires do not damage the cables in the associated fire areas

~ 12 06/04/10 ~ Progress Energy

  • Program Self Assessment with Industry Peers
  • Independent Corporate Oversight
  • NRC Inspections

~ 13 06/04/10 ~ Progress Energy

  • Appendix R is current Licensing Basis
  • OMAs reviewed per NRC Regulatory Issue SummarY 2006-10, "Regulatory Expectations with App.endix R Paragraph n1.G.2 Operator Manual Actions"
  • Progress Energy submitted letter of intent to adopt NFPA 805
  • Brunswick scheduled to submit the License Amendment Request by August 2011
  • One of NFPA 805 transition goals is to reduce dependence on OMAs
  • Implementation of NFPA 805 will improve the overall safety

~ 14 06/04/10 ~ Progress Energy

1. A large number of Operator Manual Actions (OMAs) used to YES NO mitigate cable separation issues
2. A single fire could affect more than one unit. YES YES
3. The use of thermoplastic cable . NO NO
4. Limited documentation of cable routing within the plant. NO NO
5. A Self-Induced Station Slack-Out (SISSO) strategy (isolating all YES NO on-site power to basically everything except the protected train to prevent spurious actuations) for fires in areas without adequate cable separation .
6. The OMAs are very complicated, not high confidence that YES NO operators would be able to implement them in fire conditions.
7. Mitigation of a fire requires the use of systems from multiple YES YES units (electrical or mechanical cross-unit ties) .
8. Symptom-based fire response procedures with complex OMAs. YES NO

~ 15 06/04/10 ~ Progress Energy

  • Single fire could affect more than one unit
  • Mitigation can require cross-tying electrical systems between units
  • Do not have a large number of OMAs per Fire Area
  • Not a SISBO strategy plant
  • Simple, not complex
  • OMAs do not require diagnosis or complex decisions
  • Risk impact of OMAs is expected to be very small
  • Periodic Training and Evaluation is conducted
  • Brunswick is in compliance with current NRC requirements and are fully committed to transitioning to NFPA 805

~ 16 06/04/10 ~ Progress Energy

",. o en -~

~

c o oI *

.-

en (J.)

J a