March 4, 2015
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR PEACH BOTTOM ATOMIC POWER STATION (REPORT 05000277/2014001 AND 05000278/2014001)
Dear Mr. Hanson:
On February 12, 2015, the U. S. Nuclear Regulatory Commission (NRC) completed its end-of-cycle performance review of Peach Bottom Atomic Power Station (PBAPS). The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2014 through December 31, 2014. This letter informs you ssment of your facility during this period and its plans for future inspections at your facility. The NRC determined that overall, PBAPS Units 2 and 3 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at PBAPS Units 2 and 3 during the most recent quarter was within the Licensee inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility. The enclosed inspection plan lists the inspections scheduled through June 30, 2016. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. In addition to the baseline inspection program t Fuel Storage Installation at Operating The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security-related inspections, which will be sent via separate, non-publicly available correspondence. Additionally, an NRC audit of licensee efforts towards compliance with Order EA-12-049, -Design--12-051, "Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," is ongoing for various sites. The audit includes an onsite visit for the NRC staff to evaluate mitigating strategies as described in the licensee submittals, and to receive and review information relative to associated open items. This onsite audit will occur prior to the first unit at the site achieving compliance with the Orders and the audit will aid NRC staff in developing a final Safety Evaluation for the site. The audit at your site is being coordinated for the week of June 22, 2015. A site-specific audit plan for the visit will be provided in advance to allow sufficient time for preparations. From January 1 to December 31, 2014, the NRC issued one traditional escalated enforcement action associated with the violation found in the inspection report 07200029/14-008 (ML14307A797). Therefore, the NRC plans to conduct IP -up on Traditional Enforcement Actions Including Violations, Deviations, Confirmatory Action Letters, Confirmatory Orders, and Alternative Dispute Resolution Confirto follow-up on this violation. In accordance with Title 10 of the Code of Federal RegulationsPublic Document Room or from the Publicly Available Records component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact Fred Bower at (610) 337-5200 with any questions you have regarding this letter.
Sincerely,
/RA/ Fred L. Bower, III, Chief Division of Reactor Projects Projects Branch 4 Docket Nos. 50-277, 50-278 License Nos. DPR-44, DPR-56 Enclosure: Peach Bottom Atomic Power Station Inspection/Activity Plan cc w/encl: Distribution via ListServ
ML15062A180 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRP RI/DRP NAME SBarber/ GSB FBower/ FLB DATE 02/19/15 02/ 19 /15 Page 1 of 2 01/26/2015 09:41:20 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on Site Peach BottomInspection / Activity Plan 01/01/2015-06/30/20163/23EXAM-INITIAL OL EXAM 3 2 FY15 - PEACH BOTTOM INITIAL OPERATOR LICENSING EXAMU01911 02/23/2015 02/27/2015 2 FY15 - PEACH BOTTOM INITIAL OPERATOR LICENSING EXAMU01911 03/23/2015 04/03/20157111111B-REQUAL INSP W/ P/F RESULTS 2 2, 3 IP Licensed Operator Requalification Program7111111B 03/23/2015 03/27/2015 EP-EP PROGRAM INSPECTION 1 2, 3 IP A lert and Notification System Testing7111402 03/09/2015 03/13/2015 2, 3 IP Emergency Preparedness Organization Staffing and Augmentation System7111403 03/09/2015 03/13/2015 2, 3 IP Correction of Emergency Preparedness Weaknesses and Deficiencies7111405 03/09/2015 03/13/2015 TRI FI-TRIENNIAL FIRE PROTECTION INSPECTION 4 2, 3 IP Fire Protection [Triennial]7111105T 03/16/2015 03/20/2015 2, 3 IP Fire Protection [Triennial]7111105T 03/30/2015 04/03/201571152B-PI&R - BIENNIAL 5 2, 3 IP Problem Identification and Resolution71152B 04/06/2015 04/10/2015 2, 3 IP Problem Identification and Resolution71152B 04/20/2015 04/24/2015 ISFSI-ISFSI LOADING INSPECTION 1 2, 3 IP Operation Of An ISFSI 6085505/11/2015 05/15/2015 2, 3 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.105/11/2015 05/15/2015 RS7-71124.07 1 2, 3 IP Radiological Environmental Monitoring Program71124.07 06/22/2015 06/26/201571124.08-RADWASTE 1 2, 3 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation71124.08 07/20/2015 07/24/2015 RS45-71124.03, .04, .05 1 2, 3 IP Occupational Dose Assessment71124.04 07/20/2015 07/24/2015 2, 3 IP Radiation Monitoring Instrumentation71124.05 07/20/2015 07/24/20157111108G-U3 INSERVICE INSPECTION 1 3 IP Inservice Inspection Activities - BWR7111108G 09/14/2015 09/18/2015 RS123-71124.01, .02, .03 1 2, 3 IP Radiological Hazard Assessment and Exposure Controls71124.01 09/28/2015 10/02/2015 2, 3 IP Occupational ALARA Planning and Controls71124.02 09/28/2015 10/02/2015 2, 3 IP In-Plant Airborne Radioactivity Control and Mitigation71124.03 09/28/2015 10/02/2015 2, 3 IP71151-OR01 09/28/2015 10/02/2015 2, 3 IP71151-PR01 09/28/2015 10/02/2015 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.
Page 2 of 2 01/26/2015 09:41:20 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on Site Peach BottomInspection / Activity Plan 01/01/2015-06/30/20167111117T-PERMANENT PLANT MODIFICATIONS 3 2, 3 IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T 01/25/2016 01/29/2016 2, 3 IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T 02/08/2016 02/12/2016 EP-EP EXERCISE EVALUATION 4 2, 3 IP Exercise Evaluation7111401 04/25/2016 04/29/2016 RS1234-HP INSPECTION 1 2, 3 IP Radiological Hazard Assessment and Exposure Controls71124.01 03/07/201603/11/2016 2, 3 IP Occupational ALARA Planning and Controls71124.02 03/07/201603/11/2016 2, 3 IP In-Plant Airborne Radioactivity Control and Mitigation71124.03 03/07/201603/11/2016 2, 3 IP Occupational Dose Assessment71124.04 03/07/201603/11/20167111107T-TRIENNIAL HEAT SINK 1 2, 3 IP Heat Sink Performance7111107T 06/13/2016 06/17/2016 RS567-HP TEAM INSPECTION 3 2, 3 IP Radiation Monitoring Instrumentation71124.05 06/20/2016 06/24/2016 2, 3 IP Radioactive Gaseous and Liquid Effluent Treatment71124.06 06/20/2016 06/24/2016 2, 3 IP Radiological Environmental Monitoring Program71124.07 06/20/2016 06/24/2016 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.