August 31, 2016
Mr. Kelvin Henderson Site Vice President Duke Energy Corporation Catawba Nuclear Station 4800 Concord Road York, SC 29745-9635
SUBJECT: MID-CYCLE ASSESSMENT LETTER FOR CATAWBA NUCLEAR STATION UNITS 1 AND 2 (NRC INSPECTION REPORT 05000413/2016005 AND 05000414/2016005)
Dear Mr. Henderson:
On August 9, 2016, the Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of Catawba Nuclear Station, Units 1 and 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2015 through June 30, 2016. This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility. The NRC determined that overall, Catawba Nuclear Station, Units 1 and 2 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Catawba Units 1 and 2 during the most recent quarter was within the Licensee Response Column of the NRC's Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility. The enclosed inspection plan lists the inspections scheduled through June 30, 2018. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the second half of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections which will be sent via separate, non-publicly available correspondence. In response to the accident at Fukushima, the Commission issued Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," and Order EA-12-051, "Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation." The NRC conducted audits of licensee efforts towards compliance with these Orders, and the information gathered will aid staff in development of the ultimate Safety Evaluation for the site. After the NRC staff receives the Final Compliance letter for the site, the Safety Evaluation will be issued. Then, the NRC staff will confirm through inspections the full implementation of the orders mentioned above by performing Temporary Instruction 191, "Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans."
In Staff Requirements Memorandum - SECY 16-0009, "Recommendations Resulting from the Integrated Prioritization and Re-Baselining of Agency Activities," the Commission approved the NRC staff recommendation to discontinue the formal mid-cycle assessment process beginning in calendar year 2017. This will be the final mid-cycle assessment letter. The staff will continue to conduct quarterly assessment meetings and communicate changes in the assessment of licensee performance in accordance with the guidance in Inspection Manual Chapter 0305, "Operating Reactor Assessment Program."
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact me at 404-997-4611 with any questions you have regarding this letter.
Sincerely,/RA/ Frank Ehrhardt, Chief Reactor Projects Branch 1 Division of Reactor Projects Docket Nos.: 50-413, 50-414 License Nos.: NPF-35, NPF-52
Enclosure:
Catawba Inspection/Activity Plan (09/01/2016 - 06/30/2018)
cc distribution via ListServ
_________________________ SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRP RII:DRP RII:DRP SIGNATURE MMT2 JGW1 FJE NAME M. Toth J. Worosilo F. Ehrhardt DATE 8/25/2016 8/25/2016 8/25/2016 8/ /2016 8/ /2016 8/ /2016 8/ /2016 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO Letter to Kelvin Henderson from Frank Ehrhardt dated August 31, 2016
SUBJECT: MID-CYLCE ASSESSMENT LETTER FOR CATAWBA NUCLEAR STATION UNITS 1 AND 2 (NRC INSPECTION REPORT 05000413/2016005 AND 05000414/2016005) DISTRIBUTION: D. Gamberoni, RII L. Gibson, RII OE Mail RIDSNRRDIRS PUBLIC A. Adams, NRR RidsNrrPMCatawba Resource ROP Assessment ROP Reports Institute of Nuclear Power Operations (INPO)
Page 1 of 208/31/201606:54:13Report 22UnitNumberPlanned DatesStart EndInspection ActivityTitleNo. of Staffon SiteCatawbaInspection / Activity Plan09/01/2016-06/30/2018RP-RP OCCUPATIONAL INSPECTION WEEK 131,2 IPRadiological Hazard Assessment and Exposure Controls71124.0109/12/201609/16/20161,2 IPOccupational ALARA Planning and Controls71124.0209/12/201609/16/20161,2 IPIn-Plant Airborne Radioactivity Control and Mitigation71124.0309/12/201609/16/20161,2 IPOccupational Dose Assessment71124.0409/12/201609/16/20161,2 IPRadiation Monitoring Instrumentation71124.0509/12/201609/16/20161,2 IPPerformance Indicator Verification7115109/12/201609/16/2016ISI-UNIT 2 IN-SERVICE INSPECTION1 2 IPInservice Inspection Activities - PWR7111108P09/19/201609/23/2016SGISI-UNIT 2 SG IN-SERVICE INSPECTION1 2 IPInservice Inspection Activities - PWR7111108P09/26/201609/30/2016RP-RP OCCUPATIONAL INSPECTION WEEK 221,2 IPRadiological Hazard Assessment and Exposure Controls71124.0109/26/201609/30/20161,2 IPOccupational ALARA Planning and Controls71124.0209/26/201609/30/20161,2 IPIn-Plant Airborne Radioactivity Control and Mitigation71124.0309/26/201609/30/20161,2 IPOccupational Dose Assessment71124.0409/26/201609/30/20161,2 IPRadiation Monitoring Instrumentation71124.0509/26/201609/30/20161,2 IPPerformance Indicator Verification7115109/26/201609/30/2016PI&R-PROBLEM IDENTIFICATION AND RESOLUTION71,2 IPProblem Identification and Resolution71152B10/24/201610/28/20161,2 IPProblem Identification and Resolution71152B11/07/201611/11/2016MODS-PLANT MODIFICATIONS INSPECTION31,2 IPEvaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T01/23/201701/27/20171,2 IPEvaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T02/06/201702/10/2017EP-EP PROGRAM INSPECTION41,2 IPAlert and Notification System Testing711140203/27/201703/31/20171,2 IPEmergency Preparedness Organization Staffing and Augmentation System711140303/27/201703/31/20171,2 IPEmergency Action Level and Emergency Plan Changes711140403/27/201703/31/20171,2 IPCorrection of Emergency Preparedness Weaknesses and Deficiencies711140503/27/201703/31/20171,2 IPPerformance Indicator Verification7115103/27/201703/31/2017ISI-UNIT 1 IN-SERVICE INSPECTION11 IPInservice Inspection Activities - PWR7111108P05/08/201705/12/2017This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.
Page 2 of 208/31/201606:54:13Report 22UnitNumberPlanned DatesStart EndInspection ActivityTitleNo. of Staffon SiteCatawbaInspection / Activity Plan09/01/2016-06/30/2018RP-RAD HAZARDS ANALYSIS AND TRANSPORTATION21,2 IPRadiological Hazard Assessment and Exposure Controls71124.0105/08/201705/12/20171,2 IPRadioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation71124.0805/08/201705/12/2017OL EXAM-INITIAL LICENSE EXAM PREP31 CATAWBA/JULY 2017 INITIAL EXAM AT POWER FACILITIESV2349505/29/201706/02/2017OL EXAM-INITIAL LICENSE EXAM31 CATAWBA/JULY 2017 INITIAL EXAM AT POWER FACILITIESV2349506/26/201707/07/2017RP-RP PUBLIC RAD SAFETY BASELINE21,2 IPRadioactive Gaseous and Liquid Effluent Treatment71124.0607/24/201707/28/20171,2 IPRadiological Environmental Monitoring Program71124.0707/24/201707/28/20171,2 IPPerformance Indicator Verification7115107/24/201707/28/2017TFPI-TRIENNIEL FIRE PROTECTION INSPECTION51,2 IPFire Protection [Triennial]7111105T07/24/201707/28/20171,2 IPFire Protection [Triennial]7111105T08/07/201708/11/2017ISI-UNIT 2 IN-SERVICE INSPECTION1 2 IPInservice Inspection Activities - PWR7111108P03/26/201803/30/2018SGISI-UNIT 2 SG IN-SERVICE INSPECTION1 2 IPInservice Inspection Activities - PWR7111108P04/02/201804/06/2018EP-EP EXERCISE61,2 IPExercise Evaluation711140106/04/201806/08/20181,2 IPEmergency Action Level and Emergency Plan Changes711140406/04/201806/08/20181,2 IPExercise Evaluation - Scenario Review711140806/04/201806/08/20181,2 IPPerformance Indicator Verification7115106/04/201806/08/2018CDBI-COMPONENT DESIGN BASES INSPECTION61,2 IPComponent Design Bases Inspection711112106/04/201806/08/20181,2 IPComponent Design Bases Inspection711112106/25/201806/29/2018This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.