Dominion Energy Services, Inc.
5000 Dominion Boulevard, Glen Allen, VA 23060 A, Dominion DominionEnergy.com iJ a,, Energy April 14, 2020 Attn: Document Control Desk Serial No.: 20-083 United States Nuclear Regulatory Commission NRA/khb Washington, DC 20555-0001 Docket Nos.: 50-336/423 50-395 License Nos.: DPR-65 NPF-49 NPF-12 DOMINION ENERGY NUCLEAR CONNECTICUT, INC. (DENC)
DOMINION ENERGY SOUTH CAROLINA, INC.
MILLSTONE POWER STATION UNITS 2 AND 3 VIRGIL C. SUMMER NUCLEAR STATION (VCSNS) UNIT 1 NRC REGULATORY ISSUE
SUMMARY
2020-01 PREPARATION AND SCHEDULING OF OPERATOR LICENSING EXAMINATIONS In response to NRC Regulatory Issue Summary 2020-01 , enclosed is the requested information on proposed site-specific operator licensing examination schedules and the estimated number of applicants planning to take those examinations and/or the NRC's generic fundamentals examinations (GFEs).
No new commitments are intended by this letter. If you have any questions concerning this information, please contact Mr. Craig Sly at (804) 273-2784.
Sincerely, Mark D. Sartain Vice President - Nuclear Engineering and Fleet Support Dominion Energy Services, Inc. for Dominion Energy Nuclear Connecticut, Inc. and Dominion Energy South Carolina, Inc.
Enclosures:
- 1. NRC Form 536 for Millstone
- 2. NRC Form 536 for V. C. Summer Commitments made by this letter: None
SN 20-083 Scheduling of Operator Licensing Examinations Page 2 of 2 cc: U.S. Nuclear Regulatory Commission Region I ATTN: Operations Branch 2100 Renaissance Boulevard Suite 100 King of Prussia, Pennsylvania 19406-2713 U. S. Nuclear Regulatory Commission Region II ATTN: Operations Branch Marquis One Tower 245 Peachtree Center Avenue, NE Suite 1200 Atlanta, Georgia 30303-1257 Mr. Richard Guzman NRC Senior Project Manager U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 C-2 11555 Rockville Pike Rockville, MD 20852-2738 Mr. Ted Carter NRC Senior Project Manager U.S. Nuclear Regulatory Commission Two White Flint North 11545 Rockville Pike Mail Stop T-8 F5 Rockville, MD 20852-2738 Mr. Shawn A. Williams U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 B1-A 11555 Rockville Pike Rockville, MD 20852-2738 NRC Senior Resident Inspector Millstone Power Station NRC Senior Resident Inspector V. C. Summer Nuclear Station
Serial No 20-083 Enclosure 1 NRC Form 536 for Millstone Power Station Millstone Power Station Dominion Energy Nuclear Connecticut, Inc.
NRC FORM 538 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY 0MB: NO. 3150-0131 EXPIRES: 11/30/2020
{11-2017)
,>~~
'l'
. OPERATOR LICENSING Es11mama booferl per rnsponse 1D comply wilh !hiS V<lklllla/Y lnfQl'lllaljof) cc~ ,equest 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. Thi$
information oollection is used 1D plan budgets and resources for opera!Pr examinations. Send commenlll regl!lding burden eslimale to !he ln!ormat!on SeNiiles Brancl! (T-2 F43), U.S. Nuclear EXAMINATION DATA Reguiaull}' Commission. Washing1Dn. DC20555-0001, or by 8-mal to lnfocollecls.Resouree@nrc.gov, and to the Dll$1< Officer. Office of lnlormation and Regulau,iy Aoo, NEOB-10202. (3150-0131), Office of Management and Budge!, Washingron. DC 20503. If a means used lo impose an infonnation
- "" colleciioo doe$ not display a curranff)I vafid 0MB ootilrol number, the NRC may not eooduct or sponsor, and a ptlfllO!l is not required 1D raspond to, me ml!llllion COiiection.
FACILITY NRCREGION
!MILLSTONE POWER STATION - UNIT 2 1 A. PROPOSED EXAMINATION PREPARATION SCHEDULE 11 I PROPOSED NUMBER CY 22 CY 23 CY 24 CY 25 ESTIMATED NUMBER OF LICENSEE-PREPARED 1 0 l 0 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0 0 0 0 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS CY 22 CY 23 CY 24 CY 25 PROPOSED NUMBER NUMBER OF REACTOR OPERATORS 8 0 8 0
. NUMBER OF SENIOR REACTOR OPERATORS- INSTANT 4 0 4 0 NUMBER OF SENIOR REACTOR OPERATORS-UPGRADE 4 0 4 0 NUMBER OF SENIOR REACTOR OPERATORS - LIMITED 0 0 0 0 PROPOSED DATES PRIMARY DATE 9/12/22 9/16/24 ALTERNATE DATE 9/19/22 9/23/24 NRC FORM 536 (11*2017)
NRCFORM536 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY 0MB: NO. 3150-0131 EXPIRES: 11/30/2020 (11-2017}
+'"
~"'""<. Estimaleo burden per respoosG to complywilh this voiuntaly fnfomla1!on collediol'I request I hour. This OPERATOR LICENSING informalion colleciion is used to plan budgeiS and resourees for operator examlnatiQns. Send commenlS regarding burden estimam to Iha lnfonnalioll Services Branch (T-2 F43J. U.S. NU<:lear EXAMINATION DATA Regulatory Commlssio!l, Wal!hingti,n, DC20555-0001, or by e-mail Ill lnfocollec!R.Resooree@nro.9ov.
,,;.-1'.r; +d"~ and to 1he Desi< Officer, Office of lnformalion and Regulatory Affairs, NEOS.10202, (3150--0131). Office
't- ..... ,fll or Maoagement and Bu(l;let Washington, DC 20503. If a means used to impose an i11ID!lll8lion colledi<:>fl does not display a - l l y '1811d 0MB control number, the NRC mr,;1 not conduct or sponsor, and a pe!SOO IS not required to raspo!ld lo, Ille information co!lediof!.
FACILITY NRCRE.GION
!MILLSTONE PO~R STATION - UNIT 3 A. PROPOSED EXAMINATION PREPARATION SCHEDULE 11 1
I PROPOSED NUMBER CY 22 CY 23 CY 24 CY 25 ESTIMATED NUMBER OF LICENSEE-PREPARED 0 1 0 l EXAMINATlONS ESTIMATED NUMBER OF NRG-PREPARED 0 0 0 0 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS CY 22 CY 23 CY 24 CY 25 PROPOSED NUMBER NUMBER OF REACTOR OPERATORS 0 8 0 8 NUMBER OF SENIOR REACTOR OPERATORS - INSTANT 0 4 0 4 NUMBER OF SENIOR REACTOR OPERATORS-UPGRADE 0 4 0 4 NUMBER OF SENIOR REACTOR OPERATORS- LIMITED 0 0 0 0 PROPOSED DATES PRIMARY DATE 9/11/23 9/15/25 ALTERNATE DATE 9/18/23 9/22/25 NRC FORM 536 (11-2017)
Serial No 20-083 Enclosure 2 NRC Form 536 for V. C. Summer Nuclear Station Virgil C. Summer Nuclear Station Unit 1 Dominion Energy South Carolina, Inc.
NRC FORM536 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY 0MB: NO. 3150-0131 EXPIRES: 11/30/2020 (11-2017)
~C....J;>ff.FfEOq<.,>:
Estimated burden per response to comply with this voluntary information collection request: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This
~ %. OPERATOR LICENSING infonnation collection is used to plan budgets and resources for operator examinations. Send comments regarding burden estimate to the Information Services Branch (T-2 F43), U.S. Nuclear EXAMINATION DATA Regulatory Commission, Washington, DC20555-0001, or by e-mail to lnfocoUects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0131), Office
"°'1"q****¥ of Management and Budget Washington, DC 20503. If a means used to impose an information colleclion does not display a curren!ly valid 0MB control number, the NRG may not conduct or sponsor, and a person is not required to respond to. the information collection.
FACILITY NRCREGION lv.c. Summer I!Region II I
A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2022 CY 2023 CY 2024 cy202s ESTIMATED NUMBER OF LICENSEE-PREPARED NIA 1 NIA 1 EXAMINATIONS ESTIMATED NUMBER OF NRG-PREPARED NIA NIA NIA NIA EXAMINATIONS
- 8. INITIAL OPERATOR LICENSE EXAMINATIONS CY2022 CY2023 CY2024 CY2025 PROPOSED NUMBER NUMBER OF REACTOR OPERATORS NIA 6 NIA 6 NUMBER OF SENIOR REACTOR OPERATORS INSTANT NIA NIA NIA NIA NUMBER OF SENIOR REACTOR OPERATORS-UPGRADE NIA 6 NIA 6 NUMBER OF SENIOR REACTOR OPERATORS- LIMITED NIA NIA NIA NIA PROPOSED DATES PRIMARY DATE NIA 08/0712023 NIA 0412812025 ALTERNATE DATE NIA 09/04/2023 NIA 0512612025 NRC FORM 536 (11-2017)