Updated Inspection Plan Inspection Report 05000334/2019005 and 05000412/2019005
ML19232A338
Person / Time
Site: Beaver Valley
Issue date: 08/28/2019
From: Matt Young
NRC/RGN-I/DRP/PB6
To: Penfield R
FirstEnergy Nuclear Operating Co
References
IR 2019005
Download: ML19232A338 (7)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BLVD.

KING OF PRUSSIA, PA 19406-2713 August 28, 2019 Mr. Rod Penfield Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077 SUBJECT: BEAVER VALLEY POWER STATION, UNIT NOS. 1 AND 2 UPDATED INSPECTION PLAN INSPECTION REPORT 05000334/2 019 00 5 AND 05000412/2019 00 5

Dear Mr. Penfield:

The enclosed inspection plan lists the inspections scheduled through June 30 , 20 21 , for Beaver Valley Power Station, Units 1 and 2. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan.

The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

Additionally, NRC Region I plans to conduct an inspection per Temporary Instruction 2515/194

, "Inspection of the Licensees'

Implementation of Industry Initiative Associated with the Open Phase Condition Design Vulnerabilities in Electric Power Systems ," at your facility during the period. You should be aware that the agency is pursuing potential changes to the ROP, including changes to engineering inspections (SECY-18-0113, "Recommendations for Modifying the Reactor Oversight Process Engineering Inspections"), and other changes to the baseline inspection program described in SECY-19-0067, "Recommendations for Enhancing the Reactor Oversight Process." Should these changes to the ROP be implemented, the engineering and other region-based inspections are subject to change in scope, as well as schedule, beginning in January 2020.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRC

's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room

). Please contact me at 610-337-5205 with any questions you have regarding this letter.

Sincerely,

/RA/ Matthew R. Young, Chief Reactor Projects Branch 6 Division of Reactor Projects Docket Nos.

50-334 and 50-412 License Nos.

DPR-66 and NPF-73 Enclosure:

Beaver Valley Inspection Plan cc: Distribution via ListServ SUBJECT: BEAVER VALLEY POWER STATION, UNIT NOS. 1 AND 2 UPDATED INSPECTION PLAN INSPECTION REPORT 05000334/2019 00 5 AND 05000412/2019 00 5 DATED AUGUST 28, 2019 DISTRIBUTION w/encl (via e-mail) DLew, RA (R1ORAMAIL)

RLorson, DRA (R1ORAMAIL)

DCollins, DRP (R1DRPMAIL)

Deputy Director, DRP (R1DRPMAIL)

JYerokun, DRS (R1DRSMAIL)

PKrohn, DRS (R1DRSMAIL)

MFerdas, DRP MYoung, DRP RVadella, DRP JKrafty, DRP SHorvitz, DRP AGould, AA DDodson, RI, OEDO RidsNrrPMBeaverValley Resource RidsNrrDorlLpl1 Resource ROPreports Resource DRS Branch Chiefs DTifft, RI, SLO DScrenci, RI, PAO NSheehan, RI, PAO RidsNrrDirslpabResource ROPassessment Resource DOCUMENT NAME:

S:\ROP Assessment Meetings

\ROP-20 Second Quarter Process

\Branch 6\2019 Beaver Valley MC Letter.docx ADAMS ACCESSION NUMBER:

ML19232A338 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRP RI/DRP NAME RVadella MYoung DATE 8/15/19 8/16/19 OFFICIAL RECORD CO PY Beaver Valley

07/01/2019 - 06/30/2021

Unit Start End Activity CAC Title Staff Count

RAD SAFETY REMP

1, 2 07/08/2019

07/12/2019

IP 71124.07

000731 Radiological Environmental Monitoring Program

1, 2 07/08/2019

07/12/2019

IP 71151 000746 Performance Indicator Verification

Triennial Heat Sink

1, 2 07/14/2019

07/20/2019

IP 71111.07T

000700 Heat Sink Performance

BV-ACCESS CONTROL, EQUIP PERF, TRAINING

1, 2 07/22/2019

07/26/2019

IP 71130.02

000734 Access Control

1, 2 07/22/2019

07/26/2019

IP 71130.04

000736 Equipment Performance, Testing, and Maintenance

1, 2 07/22/2019

07/26/2019

IP 71130.07

000739 Security Training

1, 2 07/22/2019

07/26/2019

IP 71151 001338 Performance Indicator Verification

RAD SAFETY 01,02,03,04

1, 2 07/29/2019

08/02/2019

IP 71124.01

000725 Radiological Hazard Assessment and Exposure Controls

1, 2 07/29/2019

08/02/2019

IP 71124.02

000726 Occupational ALARA Planning and Controls

1, 2 07/29/2019

08/02/2019

IP 71124.03

000727 In-Plant Airborne Radioactivity Control and Mitigation

1, 2 07/29/2019

08/02/2019

IP 71124.04

000728 Occupational Dose Assessment

50.59 Process

1, 2 08/04/2019

08/17/2019

IP 71111.17T

000709 Evaluations of Changes, Tests, and Experiments

BEAVER VALLEY 2 INITIAL OL EXAM

2 09/01/2019

09/07/2019

OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

10/06/2019

10/19/2019

EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)

INSERVICE INSPECTION - UNIT 1

1 10/20/2019

11/02/2019

IP 71111.08P

000702 Inservice Inspection Activities (PWR)

RAD SAFETY OUT

1, 2 10/21/2019

10/25/2019

IP 71124.01

000725 Radiological Hazard Assessment and Exposure Controls

1, 2 10/21/2019

10/25/2019

IP 71124.02

000726 Occupational ALARA Planning and Controls

1, 2 10/21/2019

10/25/2019

IP 71124.03

000727 In-Plant Airborne Radioactivity Control and Mitigation

1, 2 10/21/2019

10/25/2019

IP 71124.04

000728 Occupational Dose Assessment

1, 2 10/21/2019

10/25/2019

IP 71151 000746 Performance Indicator Verification

8/20/2019 8:19:13 AM

Page

of

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

IP 22 Inspection Activity Plan Report

Beaver Valley

07/01/2019 - 06/30/2021

Unit Start End Activity CAC Title Staff Count

TI-194 Open Phase Condition Inspection - BV

1, 2 01/27/2020

01/31/2020

TI 2515/194

000512 Inspection of the Licensee

s Implementation of Industry Initiative Associated With the

Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin

2012-01)

Rad Safety Inspection

1, 2 01/27/2020

01/31/2020

IP 71124.01

000725 Radiological Hazard Assessment and Exposure Controls

1, 2 01/27/2020

01/31/2020

IP 71124.02

000726 Occupational ALARA Planning and Controls

1, 2 01/27/2020

01/31/2020

IP 71124.03

000727 In-Plant Airborne Radioactivity Control and Mitigation

1, 2 01/27/2020

01/31/2020

IP 71124.04

000728 Occupational Dose Assessment

BV1 Requal Inspection with P/F Results

1 04/12/2020

04/18/2020

IP 71111.11A

000703 Licensed Operator Requalification Program and Licensed Operator Performance

04/12/2020

04/18/2020

IP 71111.11B

000704 Licensed Operator Requalification Program and Licensed Operator Performance

Rad Safety Refuel

1, 2 04/13/2020

04/17/2020

IP 71124.01

000725 Radiological Hazard Assessment and Exposure Controls

1, 2 04/13/2020

04/17/2020

IP 71124.02

000726 Occupational ALARA Planning and Controls

1, 2 04/13/2020

04/17/2020

IP 71124.03

000727 In-Plant Airborne Radioactivity Control and Mitigation

1, 2 04/13/2020

04/17/2020

IP 71124.04

000728 Occupational Dose Assessment

ISI - UNIT 2

2 04/20/2020

05/01/2020

IP 71111.08P

000702 Inservice Inspection Activities (PWR)

BEAVER VALLEY EP EXERCISE INSPECTION

1, 2 06/08/2020

06/12/2020

IP 71114.01

000716 Exercise Evaluation

1, 2 06/08/2020

06/12/2020

IP 71114.04

000719 Emergency Action Level and Emergency Plan Changes

1, 2 06/08/2020

06/12/2020

IP 71151 001397 Performance Indicator Verification

Rad Safety RETS

1, 2 06/22/2020

06/26/2020

IP 71124.06

000730 Radioactive Gaseous and Liquid Effluent Treatment

1, 2 06/22/2020

06/26/2020

IP 71151 000746 Performance Indicator Verification

Rad Safety Instruments

1, 2 08/17/2020

08/21/2020

IP 71124.05

000729 Radiation Monitoring Instrumentation

8/20/2019 8:19:13 AM

Page

of

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

IP 22 Inspection Activity Plan Report

Beaver Valley

07/01/2019 - 06/30/2021

Unit Start End Activity CAC Title Staff Count

Access Control, Equip Perf, Training

1, 2 09/07/2020

09/11/2020

IP 71130.02

000734 Access Control

1, 2 09/07/2020

09/11/2020

IP 71130.04

000736 Equipment Performance, Testing, and Maintenance

1, 2 09/07/2020

09/11/2020

IP 71130.07

000739 Security Training

1, 2 09/07/2020

09/11/2020

IP 71151 001338 Performance Indicator Verification

DESIGN BASIS ASSURANCE INSPECTION

1, 2 09/14/2020

09/18/2020

IP 71111.21M

000713 Design Bases Assurance Inspection (Teams)

1, 2 09/28/2020

10/02/2020

IP 71111.21M

000713 Design Bases Assurance Inspection (Teams)

Rad safety Inspection

1, 2 11/16/2020

11/20/2020

IP 71124.01

000725 Radiological Hazard Assessment and Exposure Controls

1, 2 11/16/2020

11/20/2020

IP 71124.02

000726 Occupational ALARA Planning and Controls

1, 2 11/16/2020

11/20/2020

IP 71124.03

000727 In-Plant Airborne Radioactivity Control and Mitigation

1, 2 11/16/2020

11/20/2020

IP 71124.04

000728 Occupational Dose Assessment

1, 2 11/16/2020

11/20/2020

IP 71151 000746 Performance Indicator Verification

Radwaste

1, 2 11/16/2020

11/20/2020

IP 71124.08

000732 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and

Transportation

Rad Safety Inspection

1, 2 01/11/2021

01/15/2021

IP 71124.01

000725 Radiological Hazard Assessment and Exposure Controls

1, 2 01/11/2021

01/15/2021

IP 71124.02

000726 Occupational ALARA Planning and Controls

1, 2 01/11/2021

01/15/2021

IP 71124.03

000727 In-Plant Airborne Radioactivity Control and Mitigation

1, 2 01/11/2021

01/15/2021

IP 71124.04

000728 Occupational Dose Assessment

FY21 Beaver Valley 1 Initial Examination

1 01/31/2021

02/06/2021

OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

02/28/2021

03/13/2021

EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)

PI&R BIENNIAL

1, 2 02/08/2021

02/12/2021

IP 71152B 000747 Problem Identification and Resolution

1, 2 02/22/2021

02/26/2021

IP 71152B 000747 Problem Identification and Resolution

8/20/2019 8:19:13 AM

Page

of

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

IP 22 Inspection Activity Plan Report

Beaver Valley

07/01/2019 - 06/30/2021

Unit Start End Activity CAC Title Staff Count

Beaver Valley EP Program Inspection

1, 2 04/05/2021

04/09/2021

IP 71114.02

000717 Alert and Notification System Testing

1, 2 04/05/2021

04/09/2021

IP 71114.03

000718 Emergency Response Organization Staffing and Augmentation System

1, 2 04/05/2021

04/09/2021

IP 71114.04

000719 Emergency Action Level and Emergency Plan Changes

1, 2 04/05/2021

04/09/2021

IP 71114.05

000720 Maintenance of Emergency Preparedness

1, 2 04/05/2021

04/09/2021

IP 71151 001397 Performance Indicator Verification

Rad Safety Inspection

1, 2 04/19/2021

04/23/2021

IP 71124.01

000725 Radiological Hazard Assessment and Exposure Controls

1, 2 04/19/2021

04/23/2021

IP 71124.02

000726 Occupational ALARA Planning and Controls

1, 2 04/19/2021

04/23/2021

IP 71124.03

000727 In-Plant Airborne Radioactivity Control and Mitigation

1, 2 04/19/2021

04/23/2021

IP 71124.04

000728 Occupational Dose Assessment

8/20/2019 8:19:13 AM

Page

of

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

IP 22 Inspection Activity Plan Report