Updated Inspection Plan (Inspection Reports 05000272/2019005 and 05000311/2019005)
ML19235A052
Person / Time
Site: Salem  PSEG icon.png
Issue date: 08/28/2019
From: Brice Bickett
Division Reactor Projects I
To: Carr E
Public Service Enterprise Group
References
IR 2019005
Download: ML19235A052 (7)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PA 19406-2713 August 28, 2019 Mr. Eric Carr President and Chief Nuclear Officer PSEG Nuclear LLC

- N09 P.O. Box 236 Hancocks Bridge, NJ 08038 SUBJECT: SALEM GENERATING STATION UNITS 1 AND 2 UPDATED INSPECTION PLAN (INSPECTION REPORTS 05000272/2019005 AND 05000311/2019005

)

Dear Mr. Carr:

The enclosed inspection plan lists the inspections scheduled through June 30 , 20 21 , for Salem Generating Station Units 1 and 2. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

Additionally, NRC Region I plans to conduct an inspection per Temporary Instruction 2515/194, Inspection of the Licensees' Implementation of Industry Initiative Associated with the Open Phase Condition Design Vulnerabilities in Electric Power Systems, and Inspection Procedure 71003, Post-Approval Site Inspection for License Renewal at your facility during the period

. You should be aware that the agency is pursuing potential changes to the ROP, including changes to engineering inspections (SECY-18-0113, "Recommendations for Modifying the Reactor Oversight Process Engineering Inspections").

Should these changes to the ROP be implemented, the engineering and other region-based inspections are subject to change in scope, as well as schedule, beginning in January 2020.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRC

's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room

).

E. C a rr 2 Please contact me at (610) 337-5312 with any questions you have regarding this letter.

Sincerely,

/RA/ Brice A. Bickett, Chief Project Branch 3 Division of Reactor Projects Docket Nos. 50-272 and 311 License Nos. DPR-70 and DPR-75 Enclosure:

Salem 1 and 2 Inspection Plan cc: Distribution via ListServ E. C a rr 3 SUBJECT: SALEM GENERATING STATION UNITS 1 AND 2 UPDATED INSPECTION PLAN (INSPECTION REPORTS 05000272/2019005 AND 05000311/2019005)

DATED AUGUST 28, 2019 DISTRIBUTION w/encl

DLew, RA (R1ORAMAIL Res)

RLorson, DRA (R1ORAMAIL Res)

DCollins, DRP (R1DRPMAIL Res)

BWelling, DRP (R1DRPMAIL Res)

JYerokun, DRS (R1DRSMAIL Res)

PKrohn, DRS (R1DRSMAIL Res

) MYoung, DRP BBickett, DRP PFinney, DRP SGhrayeb, DRP JHawkins, DRP, SRI MHardgrove, DRP, RI SCalabrese, DRP DDodson, RI, OEDO RidsNrrPMSalem Resource RidsNrrDorlLpl1 Resource ROPreports Resource DRS Branch Chiefs DTifft, RI, SLO DScrenci, RI, PAO NSheehan, RI, PAO RidsNrrDirslpab Resource ROPassessment Resource DOCUMENT NAME:

S:\ROP Assessment Meetings

\ROP-20 Second Quarter Process

\Branch 3\ROP20 Salem MC Letter.docx ADAMS ACCESSION NUMBER:

ML19235A052 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRP RI/DRP NAME BLin BBickett DATE 8/19/19 8/23/1 9 OFFICIAL RECORD CO PY Salem 07/01/2019 - 06/30/2021

Unit Start End Activity CAC Title Staff Count

3rd Quarter Integrated Inspection

1, 2 07/01/2019

11/12/2019

IP 71003 000687 Post-Approval Site Inspection for License Renewal

License Renewal - Phase 2 - Unit 2

2 07/14/2019

07/20/2019

IP 71003 000687 Post-Approval Site Inspection for License Renewal

EQ PROGRAM

1, 2 08/19/2019

08/23/2019

IP 71111.21N

000714 Design Bases Assurance Inspection (Programs)

1, 2 09/09/2019

09/13/2019

IP 71111.21N

000714 Design Bases Assurance Inspection (Programs)

SALEM REQUAL INSP WITH P/F RESULTS

1, 2 09/09/2019

09/13/2019

IP 71111.11B

000704 Licensed Operator Requalification Program and Licensed Operator Performance

HP Team Inspection 71124.01, 03, 05, 08, PIs 71151

1, 2 10/28/2019

11/01/2019

IP 71124.01

000725 Radiological Hazard Assessment and Exposure Controls

1, 2 10/28/2019

11/01/2019

IP 71124.03

000727 In-Plant Airborne Radioactivity Control and Mitigation

1, 2 10/28/2019

11/01/2019

IP 71124.05

000729 Radiation Monitoring Instrumentation

1, 2 10/28/2019

11/01/2019

IP 71124.08

000732 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and

Transportation

Triennial Heat Sink

1, 2 11/17/2019

11/23/2019

IP 71111.07T

000700 Heat Sink Performance

Design Basis Assurance Inspection

1, 2 01/13/2020

01/19/2020

IP 71111.21M

000713 Design Bases Assurance Inspection (Teams)

1, 2 01/27/2020

02/02/2020

IP 71111.21M

000713 Design Bases Assurance Inspection (Teams)

TI-194 Open Phase Condition Inspection-Salem

1, 2 01/20/2020

01/24/2020

TI 2515/194

000512 Inspection of the Licensee

s Implementation of Industry Initiative Associated With the

Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin

2012-01)

HP

1, 2 01/27/2020

01/31/2020

IP 71124.01

000725 Radiological Hazard Assessment and Exposure Controls

1, 2 01/27/2020

01/31/2020

IP 71124.02

000726 Occupational ALARA Planning and Controls

1, 2 01/27/2020

01/31/2020

IP 71124.03

000727 In-Plant Airborne Radioactivity Control and Mitigation

8/22/2019 11:36:56 AM

Page

of

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

IP 22 Inspection Activity Plan Report

Salem 07/01/2019 - 06/30/2021

Unit Start End Activity CAC Title Staff Count

HP

1, 2 01/27/2020

01/31/2020

IP 71124.04

000728 Occupational Dose Assessment

1, 2 01/27/2020

01/31/2020

IP 71124.05

000729 Radiation Monitoring Instrumentation

FORCE-ONFORCE PLANNING AND EXERCISE WEEKS

1, 2 02/24/2020

02/28/2020

IP 71130.03

000735 Contingency Response - Force-On-Force Testing

1, 2 03/16/2020

03/20/2020

IP 71130.03

000735 Contingency Response - Force-On-Force Testing

ISI - UNIT 2

2 04/27/2020

05/08/2020

IP 71111.08P

000702 Inservice Inspection Activities (PWR)

HP

1, 2 04/27/2020

05/01/2020

IP 71124.01

000725 Radiological Hazard Assessment and Exposure Controls

1, 2 04/27/2020

05/01/2020

IP 71124.02

000726 Occupational ALARA Planning and Controls

EP Exercise Inspection (at Hope Creek)

1, 2 05/18/2020

05/22/2020

IP 71114.01

000716 Exercise Evaluation

1, 2 05/18/2020

05/22/2020

IP 71114.04

000719 Emergency Action Level and Emergency Plan Changes

1, 2 05/18/2020

05/22/2020

IP 71151 001397 Performance Indicator Verification

SALEM INITIAL OL EXAM

1, 2 06/14/2020

06/20/2020

OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

1, 2 07/12/2020

08/01/2020

EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)

Access Control, Equip Perf, Training

1, 2 07/06/2020

07/10/2020

IP 71130.02

000734 Access Control

1, 2 07/06/2020

07/10/2020

IP 71130.04

000736 Equipment Performance, Testing, and Maintenance

1, 2 07/06/2020

07/10/2020

IP 71130.07

000739 Security Training

1, 2 07/06/2020

07/10/2020

IP 71151 001338 Performance Indicator Verification

REMP

1, 2 08/03/2020

08/07/2020

IP 71124.07

000731 Radiological Environmental Monitoring Program

MATERIAL CONTROL AND ACCOUNTABILITY

1, 2 09/14/2020

09/18/2020

IP 71130.11

000742 Material Control and Accounting (MC&A)

8/22/2019 11:36:56 AM

Page

of

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

IP 22 Inspection Activity Plan Report

Salem 07/01/2019 - 06/30/2021

Unit Start End Activity CAC Title Staff Count

RETS

1, 2 09/21/2020

09/25/2020

IP 71124.06

000730 Radioactive Gaseous and Liquid Effluent Treatment

ISI - UNIT 1

1 10/26/2020

11/06/2020

IP 71111.08P

000702 Inservice Inspection Activities (PWR)

HP

1, 2 10/26/2020

10/30/2020

IP 71124.01

000725 Radiological Hazard Assessment and Exposure Controls

1, 2 10/26/2020

10/30/2020

IP 71124.02

000726 Occupational ALARA Planning and Controls

TRIENNIAL FIRE PROTECTION

1, 2 01/25/2021

01/29/2021

IP 71111.05T

000696 Fire Protection

1, 2 02/08/2021

02/12/2021

IP 71111.05T

000696 Fire Protection

Access Auth, Fitness for Duty, Access Control, PI

1, 2 02/01/2021

02/05/2021

IP 71130.01

000733 Access Authorization

1, 2 02/01/2021

02/05/2021

IP 71130.02

000734 Access Control

1, 2 02/01/2021

02/05/2021

IP 71130.08

000740 Fitness For Duty Program

1, 2 02/01/2021

02/05/2021

IP 71151 001338 Performance Indicator Verification

HP

1, 2 02/08/2021

02/12/2021

IP 71124.01

000725 Radiological Hazard Assessment and Exposure Controls

1, 2 02/08/2021

02/12/2021

IP 71124.02

000726 Occupational ALARA Planning and Controls

1, 2 02/08/2021

02/12/2021

IP 71124.03

000727 In-Plant Airborne Radioactivity Control and Mitigation

1, 2 02/08/2021

02/12/2021

IP 71124.04

000728 Occupational Dose Assessment

1, 2 02/08/2021

02/12/2021

IP 71124.05

000729 Radiation Monitoring Instrumentation

Salem/Hope Creek EP Program Inspection

1, 2 03/22/2021

03/26/2021

IP 71114.02

000717 Alert and Notification System Testing

1, 2 03/22/2021

03/26/2021

IP 71114.03

000718 Emergency Response Organization Staffing and Augmentation System

1, 2 03/22/2021

03/26/2021

IP 71114.04

000719 Emergency Action Level and Emergency Plan Changes

1, 2 03/22/2021

03/26/2021

IP 71114.05

000720 Maintenance of Emergency Preparedness

1, 2 03/22/2021

03/26/2021

IP 71151 001397 Performance Indicator Verification

PI&R BIENNIAL

1, 2 04/26/2021

04/30/2021

IP 71152B 000747 Problem Identification and Resolution

8/22/2019 11:36:56 AM

Page

of

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

IP 22 Inspection Activity Plan Report

Salem 07/01/2019 - 06/30/2021

Unit Start End Activity CAC Title Staff Count

PI&R BIENNIAL

1, 2 05/10/2021

05/14/2021

IP 71152B 000747 Problem Identification and Resolution

2021 July Salem Initial Exam

1, 2 06/07/2021

06/11/2021

OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

Evaluations of Changes, Tests and Experiments

1, 2 06/13/2021

06/19/2021

IP 71111.17T

000709 Evaluations of Changes, Tests, and Experiments

HP

1, 2 06/28/2021

07/02/2021

IP 71124.01

000725 Radiological Hazard Assessment and Exposure Controls

1, 2 06/28/2021

07/02/2021

IP 71124.02

000726 Occupational ALARA Planning and Controls

1, 2 06/28/2021

07/02/2021

IP 71124.03

000727 In-Plant Airborne Radioactivity Control and Mitigation

1, 2 06/28/2021

07/02/2021

IP 71124.04

000728 Occupational Dose Assessment

1, 2 06/28/2021

07/02/2021

IP 71124.05

000729 Radiation Monitoring Instrumentation

8/22/2019 11:36:56 AM

Page

of

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

IP 22 Inspection Activity Plan Report