Forwards Predecisional Enforcement Conference Summary Repts 50-295/96-11 & 50-304/96-11 on 961112.Response Not Required Until Licensee Notified of Proposed Enforcement Action
ML20135B678
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 11/27/1996
From: Grant G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Mueller J
COMMONWEALTH EDISON CO.
Shared Package
ML20135B679 List:
References
EA-96-355, NUDOCS 9612050095
Download: ML20135B678 (2)


Text

l r U November 27, 1996 i

l

' EA 96 355 Mr. J. i Site Vice President

'

Zion Generating Station Commonwealth Edison Company j 101 Shiloh Boulevard j Zion, IL 60099

!

SUBJECT: NRC PREDECISIONAL ENFORCEMENT CONFERENCE REPORT

]

Dear Mr. Mueller:

i This refers to a Predecisional Enforcement Conference conducted by Mr. A. B. Beach, i Regional Administrator, and other members of the Region ill and Headquarters staff on ,

November 12,1996. The subject of this conference was the apparent violations at Zion l Station identified in NRC Inspection Reports No. 50-295/96011: 50-304/96011 and i involving: (1) an ineffective 10 CFR 50.59 Safety Evaluation process: (2) inadequate

- modification closecut and post-modification testing: (3) failure to follow procedures and l inadequate procedures which contributed to lack of control of Technical Specification l

'

Interpretations: (4) inadequate identification and resolution of recurring equipment deficiencies; and (5) weak oversight of engineering activities. We have enclosed a report 4 summarizing the discussion.  :

i You will be notified by separate correspondence of our decision regarding the Enforcement l Action based on the information presented and discussed at the Predecisional Enforcement .

Conference. No response is required until you are notified of the proposed Enforcenient !

Action.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this letter and enclosed inspection report will be placed in the NRC Public Document Room. a

I l

d

~

9612050095 961127 gDR ADOCK 05000295 PDR h e (E-O(

f V J. H. Mu llar -2-We will gladly discuss any questions you have concerning this Predecisional Enforcement Conference.

Sincerely, Original signed by Geoffrey E. Grant Geoffrey E. Grant, Director Division of Reactor Safety Docket Nos. 50-295;50-304 Enclosure: Predecisional Enforcement Conference Report cc w/ encl: D. A. Sager, Vice President, Generation Support H. W. Keiser, Chief Nuclear Operating Officer l G. K. Schwartz, Station Manager i W. Stone, Regulatory Assurance Supervisor I. Johnson, Acting Nuclear Regulatory Services Manager Document Control Desk - Licensing Richard Hubbard Nathan Schloss, Economist, Office of the Attorney General Mayor, City of Zion State Liaison Officer, Wisconsin State Liaison Officer Chairman, Illinois Commerce Commission l T. J. flaiman, Senior Vice President Nuclear Operations Division Distribution:

Docket File w/ encl SRis, Zion, Braidwood, Enf. Coordinator, Rlll w/enct PUBLIC IE-01 w/enct Byron w/enct RAC1 w/enci (E-mail)

OC/LFDCB w/enci G. E. Grant, Rlil w/enci CAA1 w/enct (E-mail)

DRP w/enci LPM, NRR w/enci W. L. Axelson, Rlli w/ encl Rlll PRR w/ encl DRS w/ encl A. B. Beach, Rlll w/enci DOCUMENT NAME: G:\DRS\ZIO96011.ENF To receive a copy of this document, Indicate in the bos 'C' = Copy without attachment / enclosure *E" = Copy with attachment / enclosure

"N* es No copy OFFICE Rill p Rlli f_ Rlil , 5 Qlli , Alll NAME a M' B rso HClayton/GGrant JFalevits:nhgMRing@M UGuzmang MDapa C)k DATE 11/g/96 57 11h2/96 11/6 96 J(/ /96\ 11/fyM/

OFFICIAL RECORD COPY

-_