ML19064B075

From kanterella
Revision as of 11:03, 2 February 2020 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Enclosure 2 - NRC Presentations on Lessons-Learned from Reviews of TSTF-505 or TS Initiative 4b
ML19064B075
Person / Time
Issue date: 01/30/2019
From: Jonathan Evans, Hartle B
NRC/NRR/DRA
To:
References
Download: ML19064B075 (22)


Text

Risk-Informed Technical Specification Initiative 4b: Risk-Informed Completion Times Brandon Hartle, Reliability and Risk Analyst Jonathan Evans, Reliability and Risk Analyst PRA Licensing Branch A, Division of Risk Assessment, NRR NEI Lessons-Learned Workshop, January 30 - 31, 2019

Executive Summary

  • 3 plant-specific 4b LARs in house; 3 SEs issued

- Revision resolves issues, except Loss of Function Conditions

Initiative 4b Overview

  • Risk-Informed process to extend TS CTs based on plant configuration
  • Risk evaluation using current configuration to calculate a specific CT called Risk-informed Completion Time (RICT)
  • Frontstop = existing TS CT
  • Backstop = 30 day maximum
  • Applies to planned and emergent conditions 3

Initiative 4b Overview

- Introduced term PRA Functional as an alternative to Operable and allowed a RICT for all PRA Functional configurations

- This replaces design basis analysis requirements with PRA success criteria in the TSs

- Restricted definition of PRA Functional as capable of meeting design basis analysis requirements or appropriate disposition or programmatic restriction will be provided

- A RICT can only apply to (restorative) TS Required Actions that are not Mode changes or unit shutdown 4

Attributes of a RICT Program

  • Integrates Plant Risk

- Manage multiple SSC outages

- Manage broader scope of SSCs (TS and non-TS)

  • Flexible Configuration Management

- Decisions include real-time risk insights

- Focus on repair, not necessarily shutdown

- Emergent problems

  • Ongoing/continuous risk awareness 5

Description of TSTF-505 Rev. 1

  • Defined Conditions, Required Actions, and CTs within scope
  • Added new Conditions, Required Actions, and CTs to replace TS 3.0.3 and mode change conditions
  • Added a new program in TS Chapter 5, "Administrative Controls," entitled the "Risk-Informed Completion Time Program."
  • Provided additional clarity for RICT entry using PRA Functional to extend CT for loss of function (LOF) mode change conditions (e.g., 3.0.3 conditions) 6

Early Challenges for TSTF-505 Rev. 1

  • Vogtle pilot 4b review on-going in 2016
  • 5 other TSTF-505 reviews submitted before pilot completed
  • Discrepancies between NEI 06-09 and TSTF-505 Rev. 1 were discovered during these integrated reviews
  • Implementation of the TSTF in these LARs would have resulted in indeterminate and potentially substantive reduction in safety margin 7

Issues With TSTF-505 Rev. 1

  • Included changes to the Technical Specifications beyond scope of NRC SE on NEI 06-09

- Included PRA Functional to extend CT for configurations with loss of capability to achieve design basis success criteria

- Added new TS 3.0.3 Conditions and Required Actions to replace default TS 3.0.3 entry and included PRA Functional to extend CTs in the new TS

- Included (in model TSTF-505 SE) justification for adequate defense-in-depth and safety margin which relied on assuming NRCs restricted definition of PRA Functional, without additional disposition or programmatic restrictions for TS 3.0.3 and mode change CTs 8

TSTF-505 Rev. 1 Suspension

  • NRC staff suspended approval of TSTF -505, Rev.1, explaining concerns identified during review of plant-specific LARs:

- Definition of PRA Functional

  • SE on NEI 06-09 limited use of PRA Functionality by requiring remaining performance capability to meet design basis analysis requirements (e.g., maintain functional capability to perform at level of one operation train)

- TS Conditions Involving Mode Changes or Unit Shutdowns

  • SE on NEI 06-09 a RICT can only apply to (restorative) TS Required Actions that are not Mode changes or unit shutdown 9

TSTF-505 Rev. 1 Condition B does not meet design basis analysis requirements, therefore, would not meet intent of SE for NEI 06-09 1

0

TSTF-505 Rev. 2 1

1

TSTF-505 Rev. 2 Changes

  • Removed Loss of Function Conditions

- Staff concerned with maintaining adequate defense in depth and safety margins

- The conditions in Table 1 require additional justification that those are not Loss of Function

  • Newly Developed PRA Method Administrative Control Constraint
  • Conditions not modeled in the PRA are in scope

- Can be plant specific, PRA model dependent

- Table 1 in Model application requires additional justification 1

2

TSTF-505 Rev. 2 Changes

  • Common Cause Failures (CCF)

- Included in the TS Admin Section to address emergent failures

- CCF PRA Modeling to be handled on a plant specific basis

  • All hazards require technically adequate dispositions

- External hazards need to be systematically considered

- Addressing only the impact on baseline risk is insufficient

- Impact on configuration specific change in risk should be addressed 1

3

Initiative 4b Loss of Function Considerations

  • 4b allows the use of PRA Functional and calculation of RICT when all trains are Inoperable

- But available equipment can provide design basis success parameters upon demand OR

- Define and justify adequate defense in depth and safety margins when available equipment can only provide PRA success parameters

  • Change in Backstop for CT upon Inoperability of all trains from 30 days to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />

- Consistent with approved and used TSTF-426 which allows a maximum of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> when all trains are Inoperable 1

4

Initiative 4b Loss of Function Considerations

  • Using design basis success criteria for PRA Functional for loss of all trains alleviates need for justifying PRA success criteria, i.e.,

- Use only SSCs relied on in the original TS specified safety function

- Ensure design basis success criteria for parameters are met for all design basis initiators

  • May deviate by requesting TS changes for Inoperability of all trains using PRA Functional with supporting information

- This review may be complex and resource intensive

- Suggest only using on a limited basis 1

5

TSTF-505 and 4b LAR Content 4b, Risk-Informed Completion Times

  • Greater reliance NFPA-805, Risk-Informed on PRA Required Fire Protection scope, level of detail,
  • More flexibility for technical 50.69 SSC Categorization licensee robustness, and plant representation 5b, Risk-Informed
  • More complex staff Surveillance Frequencies review Risk-Informed Inservice Inspection 1

6

TSTF-505 and 4b LAR Content

  • Scope, level of detail, and technical adequacy of PRA are to be commensurate with application

- Requires confidence in plant specific PRA models

  • Up-to-date full-scope PRA peer reviews

- Supporting Requirements assessed to Capability Category II for all PRA hazards

  • Facts and Observations (F&Os) resolved or dispositioned prior to LAR submittal
  • Deviations from NRC accepted guidance and pilot applications add to review time and resources 1 7

4b Application Review Best Practices

- Familiarizes staff with licensees strategy and goals

- Allows for clarifications to reduce acceptance review pitfalls

  • Reviewing recent submittals

- Helps licensee anticipate and address common RAIs

- Minimizes deviations from acceptable approaches/templates

  • F&O Closure Observations
  • Audits

- Assists with NRC review of complex 4b applications

- Clarifies information in the LAR to reduce RAIs 1

8

Conclusions

  • NRC SE for TSTF-505 Rev. 2 issued November 21, 2018

- Revision resolves issues, except for loss of function conditions

- 3 Initiative 4b LARS in house; 3 SEs issued

- 3 LARs in house for TSTF-505 Rev. 2

- Complex reviews that rely on the technical adequacy of the PRA

- High quality submittals needed to support efficient review by the NRC

  • Progress/Path forward

- With issuance of the SE for TSTF-505 Rev. 2, we expect a large number of submittals in 2019

- Reviewing previous submittals and using best practices will facilitate efficient NRC review 1

9

List of Acronyms

  • CC - Capability Category
  • CCF - Common Cause Failure
  • CDF - Core Damage Frequency
  • CT - Completion Time
  • F&O - Facts and Observations
  • LAR - License Amendment Request
  • NRC - Nuclear Regulatory Commission
  • RAI - Request for Additional Information
  • RICT - Risk Informed Completion Time
  • SE - Safety Evaluation
  • SR - Supporting Requirement
  • SSC - Systems, Structures, and Components
  • TS - Technical Specification

References

  • TSTF-505, Revision 1, Provide Risk-Informed Extended Completion Times

- RITSTF Initiative 4b, June 14, 2011, and Model Application dated January 31, 2012 (ADAMS Accession No. ML120330410).

  • Draft Revised Model Safety Evaluation of TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, May 1, 2018 (ADAMS Accession No. ML17290A005).
  • Letter from Timothy J. McGinty, U.S. Nuclear Regulatory Commission, to Technical Specifications Task Force, Issues With Technical Specifications Task Force Traveler TSTF-505, Revision 1, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4B, dated November 15, 2016 (ADAMS Accession No. ML16281A021).
  • Final Safety Evaluation For Nuclear Energy Institute (NEI) Topical Report (TR) NEI 06 09, Risk-Informed Technical Specifications Initiative 4b, Risk-Managed Technical Specifications (RMTS) Guidelines, May 17, 2007 (ADAMS Accession No. ML071200238). 2 1

References

  • Topical Report NEI 06-09, Revision 0-A, Risk-Informed Technical Specifications Initiative 4B, Risk-Managed Technical Specifications (RMTS) Guidelines, October 2012 (ADAMS Package Accession No. ML122860402).

2 2