IR 05000280/2008001
| ML080630294 | |
| Person / Time | |
|---|---|
| Site: | Surry |
| Issue date: | 03/03/2008 |
| From: | Eugene Guthrie NRC/RGN-II/DRP/RPB5 |
| To: | Christian D Virginia Electric & Power Co (VEPCO) |
| References | |
| IR-08-001 | |
| Download: ML080630294 (7) | |
Text
rch 3, 2008
SUBJECT:
ANNUAL ASSESSMENT LETTER - SURRY POWER STATION (NRC INSPECTION REPORT 05000280/2008001 AND 05000281/2008001)
Dear Mr. Christian:
On February 6, 2008, the NRC staff completed its performance review of the Surry Power
Station. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from January 1 through December 31, 2007. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only--Security Related Information" will include the security cornerstone review and resultant inspection plan.
Overall, Surry Power Station Units 1 and 2 operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter, as well as for the first three quarters of the assessment cycle, was within the Licensee Response column of the NRC
=s Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility. We also plan on conducting several non-ROP inspections which include: TI 2515/166, "Pressurized Water Reactor Containment Sump Blockage;" TI 2515/171, "Verification of Site Specific Implementation of B.5.b Phase 2 & 3 Mitigating Strategies;" and TI 2515/172, "Reactor Coolant System Dissimilar Metal Butt Welds."
The enclosed inspection plan details the inspections, less those related to physical protection scheduled through June 30, 2009. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature.
The inspections in the last nine months of the inspection plan are tentative and may be revised at the mid-cycle review.
VEPCO 2In accordance with 10 CFR 2.390 of the NRC
=s A Rules of Practice,@ a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (404) 562-4662 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/ Eugene Guthrie, Chief Reactor Projects Branch 5
Division of Reactor Projects Docket Nos.: 50-280, 50-281 License Nos.: DPR-32, DPR-37
Enclosure: Surry Inspection/Activity Plan (03/01/08 - 06/30/09)
cc w/encl.: (See page 3)
_________________________ OFFICE RII:DRP RII:DRP RII:DRP RII:DRP SIGNATURE /RA/ /RA/ /RA/ /RA/ NAME JDodson DArnett LGarner EGuthrie DATE 2/28/08 2/27/08 3/3/08 3/3/08 3/ /2008 3/ /2008 3/ /2008 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO VEPCO 3 cc w/encl.:
Chris L. Funderburk
Director Nuclear Licensing and Operations Support Virginia Electric and Power Company Electronic Mail Distribution
Donald E. Jernigan
Site Vice President Surry Power Station Virginia Electric & Power Company Electronic Mail Distribution
Virginia State Corporation Commission Division of Energy Regulation P.O. Box 1197
Richmond, VA 23209
Lillian M. Cuoco, Esq.
Senior Counsel Dominion Resources Services, Inc.
Millstone Power Station Electronic Mail Distribution
VEPCO 4Letter to Jeffrey B. Archie from Eugene F. Guthrie dated March 3, 2008 SUBJECT: ANNUAL ASSESSMENT LETTER - SURRY POWER STATION NRC INSPECTION REPORT 05000280/2008001 AND 05000281/2008001 Distribution w/encl.:
C. Evans, RII EICS (Part 72 Only)
L. Slack, RII EICS OE Mail (email address if applicable)
S. P. Lingam, NRR Richard Jervey, NRR RIDSNRRDIRS
PUBLIC
SurryInspection / Activity Plan03/01/2008-06/30/2009InspectionTypeInspection ActivityPlanned DatesStart EndNo. of Staffon SiteTitleUnitNumberPage 1 of 203/03/200808:13:27Report 22 4OL EXAM-INITIAL EXAMNot ApplicableSURRY/MARCH 2008 EXAM AT POWER FACILITIES03/17/200803/28/20081 V23279 1EB1-SUMP-TI 2515/166 CONTAINMENT SUMP INSPECTIONSafety IssuesPressurized Water Reactor Containment Sump Blockage [NRC GENERIC LETTER 2004-02]05/05/200805/09/20082 2515/166IP 2EB3-ISI-UNIT 2 - ISIBaseline InspectionsInservice Inspection Activities - PWR05/05/200805/09/20082 7111108PIP 2EB3TI172-TI-172Generic Safety InspectionReactor Coolant System Dissimiliar Metal Butt Welds05/05/200805/09/20081, 2 2515/172IP 1EB3SGISI-U2 SG ISIBaseline InspectionsInservice Inspection Activities - PWR05/12/200805/16/20082 7111108PIP 1PSB1-RP-RADIATION PROTECTION PREINSPECTION VISITBaseline InspectionsAccess Control to Radiologically Significant Areas06/23/200806/25/20081, 2 7112101IP 1EB3-HS-HEAT SINKBaseline InspectionsHeat Sink Performance06/23/200806/27/20081, 2 7111107BIP 1PSB1-EP-EP INSPEP Baseline InspectionAlert and Notification System Testing07/14/200807/18/20081, 2 7111402IPEP Baseline InspectionEmergency Response Organization Augmentation Testing07/14/200807/18/20081, 2 7111403IPEP Baseline InspectionEmergency Action Level and Emergency Plan Changes07/14/200807/18/20081, 2 7111404IPEP Baseline InspectionCorrection of Emergency Preparedness Weaknesses and Deficiencies07/14/200807/18/20081, 2 7111405IPBaseline InspectionsDrill/Exercise Performance07/14/200807/18/20081, 2 71151-EP01IPBaseline InspectionsERO Drill Participation07/14/200807/18/20081, 2 71151-EP02IPBaseline InspectionsAlert & Notification System07/14/200807/18/20081, 2 71151-EP03IP 4PSB1-RP-RADIATION PROTECTION PUBLIC BASELINEBaseline InspectionsAccess Control to Radiologically Significant Areas07/28/200808/01/20081, 2 7112101IPBaseline InspectionsRadiation Monitoring Instrumentation and Protective Equipment07/28/200808/01/20081, 2 7112103IPBaseline InspectionsRadioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems07/28/200808/01/20081, 2 7112201IPBaseline InspectionsRadiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program07/28/200808/01/20081, 2 7112203IPBaseline InspectionsOccupational Exposure Control Effectiveness07/28/200808/01/20081, 2 71151-OR01IPBaseline InspectionsRETS/ODCM Radiological Effluent07/28/200808/01/20081, 2 71151-PR01IP 3TI-171-B.5.B PHASE 2&3Generic Safety InspectionVerification of Site Specific Implementation Of B.5.b Phase 2 & 3 Mitigating Strategies08/04/200808/08/20081, 2 2515/171IP 2OL RQ-REQUAL INSPECTIONBaseline InspectionsLicensed Operator Requalification Program04/06/200904/10/20091, 2 7111111BIP 1EB3ISI-UNIT 1 ISIBaseline InspectionsInservice Inspection Activities - PWR04/27/200905/01/20091 7111108PIPThis report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.
SurryInspection / Activity Plan03/01/2008-06/30/2009InspectionTypeInspection ActivityPlanned DatesStart EndNo. of Staffon SiteTitleUnitNumberPage 2 of 203/03/200808:13:27Report 22 6TFPI-TFPIBaseline InspectionsFire Protection [Triennial]06/08/200906/12/20091, 2 7111105TIPBaseline InspectionsFire Protection [Triennial]06/22/200906/26/20091, 2 7111105TIPThis report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.