SUBJECT: MID-CYCLE ASSESSMENT LETTER FOR CATAWBA NUCLEAR STATION UNITS 1 AND 2 (NRC INSPECTION REPORT 05000413/
SUBJECT: MID-CYCLE ASSESSMENT LETTER FOR CATAWBA NUCLEAR STATION UNITS 1 AND 2 (NRC INSPECTION REPORT 05000413/
2016005 AND 05000414/
201 6 00 5 AND 05000414/201 6 005)
2016005)


==Dear Mr. Henderson:==
==Dear Mr. Henderson:==
On August 9, 2016, the Nuclear Regulatory Commission (
On August 9 , 201 6, the Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of Catawba Nuclear Station
NRC) completed its mid-cycle performance review of Catawba Nuclear Station
, Units 1 and 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from J ul y 1, 20 1 5 through June 3 0 , 20 16. This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility.
, Units 1 and 2
. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2015 through June 30, 2016. This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility.


The NRC determined that overall, Catawba Nuclear Station, Units 1 and 2 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Catawba Units 1 and 2 during the most recent quarter was within the Licensee Response Column of the NRC
The NRC determined that overall, Catawba Nuclear Station, Units 1 and 2 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Catawba Units 1 and 2 during the most recent quarter was within the Licensee Response Column of the NRC
's Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e.,
's Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance
green) safety significance
, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
, and all PIs indicated that your performance was within the nominal, expected range (i.e.,
green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.


The enclosed inspection plan lists the inspections scheduled through June 30, 2018. Routine inspections performed by resident inspectors are not included in the inspection plan.
The enclosed inspection plan lists the inspections scheduled through June 3 0, 20 1 8. Routine inspections performed by resident inspectors are not included in the inspection plan.


The inspections listed during the second half of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
The inspections listed during the second half of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
Line 56: Line 51:
After the NRC staff receives the Final Compliance letter for the site, the Safety Evaluation will be issued.
After the NRC staff receives the Final Compliance letter for the site, the Safety Evaluation will be issued.


Then, the NRC staff will confirm through inspections the full implementation of the orders mentioned above by performing Temporary Instruction 191,  
Then, the NRC staff will confirm through inspections the full implementation of the orders mentioned above by performing Temporary Instruction 191, "Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi
"Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi
-Unit Dose Assessment Plans."
-Unit Dose Assessment Plans."


Line 76: Line 70:


===Enclosure:===
===Enclosure:===
Catawba Inspection/Activity Plan (09/01/2016 - 06/30/2018)
Catawba Inspection/Activity Plan (0 9/01/201 6 - 06/3 0/201 8)
cc distribution via ListServ
cc distribution via ListServ


_________________________
_________________________
SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRP RII:DRP RII:DRP SIGNATURE MMT2 JGW1 FJE NAME M. Toth J. Worosilo F. Ehrhardt DATE 8/25/2016 8/25/2016 8/25/2016 8/ /2016 8/ /2016 8/ /2016 8/ /2016 E-MAIL COPY?
SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRP RII:DRP RII:D RP SIGNATURE MMT2 JGW1 FJE NAME M. Toth J. Worosilo F. Ehrhardt DATE 8/25/2016 8/25/2016 8/25/2016 8/ /2016 8/ /2016 8/ /2016 8/ /2016 E-MAIL COPY?
YES NO YES NO YES NO YES NO YES NO YES NO YES NO Letter to Kelvin Henderson from Frank Ehrhardt dated August 31, 2016
YES NO YES NO YES NO YES NO YES NO YES NO YES NO Letter to Kelvin Henderson from Frank Ehrhardt dated August 31, 201 6


SUBJECT: MID-CYLCE ASSESSMENT LETTER FOR CATAWBA NUCLEAR STATION UNITS 1 AND 2 (NRC INSPECTION REPORT 05000413/
SUBJECT: MID-CYLCE ASSESSMENT LETTER FOR CATAWBA NUCLEAR STATION UNITS 1 AND 2 (NRC INSPECTION REPORT 05000413/
2016005 AND 05000414/
201 6 00 5 AND 05000414/201 6 00 5) DISTRIBUTION
2016005) DISTRIBUTION
: D. Gamberoni, RII L. Gibson, RII OE Mail RIDSNRRDIRS PUBLIC A. Adams, NRR
: D. Gamberoni, RII L. Gibson, RII OE Mail RIDSNRRDIRS PUBLIC A. Adams, NRR


RidsNrrPMCatawba Resource ROP Assessment ROP Reports Institute of Nuclear Power Operations (INPO)
RidsNrrPMCatawba Resource ROP Assessment ROP Reports Institute of Nuclear Power Operations (INPO)


Page 1 of 2 08/31/2016 06:54:13Report 22 UnitNumberPlanned Dates Start EndInspection ActivityTitleNo. of Staff on SiteCatawbaInspection / Activity Plan 09/01/2016
Page 1 of 2 08/31/2016 06:54:13 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on SiteCatawbaInspection / Activity Plan 09/01/2016
-06/30/2018 RP-RP OCCUPATIONAL INSPECTION WEEK 1 31,2 IPRadiological Hazard Assessment and Exposure Controls71124.0109/12/2016 09/16/2016 1,2 IPOccupational ALARA Planning and Controls71124.0209/12/2016 09/16/2016 1,2 IPIn-Plant Airborne Radioactivity Control and Mitigation71124.0309/12/2016 09/16/2016 1,2 IPOccupational Dose Assessment71124.0409/12/2016 09/16/2016 1,2 IPRadiation Monitoring Instrumentation71124.0509/12/2016 09/16/2016 1,2 IPPerformance Indicator Verification7115109/12/2016 09/16/2016 ISI-UNIT 2 IN-SERVICE INSPECTION 1 2 IPInservice Inspection Activities - PWR7111108P09/19/2016 09/23/2016 SGISI-UNIT 2 SG IN-SERVICE INSPECTION 1 2 IPInservice Inspection Activities - PWR7111108P09/26/2016 09/30/2016 RP-RP OCCUPATIONAL INSPECTION WEEK 2 21,2 IPRadiological Hazard Assessment and Exposure Controls71124.0109/26/2016 09/30/2016 1,2 IPOccupational ALARA Planning and Controls71124.0209/26/2016 09/30/2016 1,2 IPIn-Plant Airborne Radioactivity Control and Mitigation71124.0309/26/2016 09/30/2016 1,2 IPOccupational Dose Assessment71124.0409/26/2016 09/30/2016 1,2 IPRadiation Monitoring Instrumentation71124.0509/26/2016 09/30/2016 1,2 IPPerformance Indicator Verification7115109/26/2016 09/30/2016 PI&R-PROBLEM IDENTIFICATION AND RESOLUTION 71,2 IPProblem Identification and Resolution71152B10/24/2016 10/28/2016 1,2 IPProblem Identification and Resolution71152B11/07/201611/11/2016 MODS-PLANT MODIFICATIONS INSPECTION 31,2 IPEvaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T01/23/2017 01/27/2017 1,2 IPEvaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T02/06/2017 02/10/2017 EP-EP PROGRAM INSPECTION 41,2 IPAlert and Notification System Testing711140203/27/2017 03/31/2017 1,2 IPEmergency Preparedness Organization Staffing and Augmentation System711140303/27/2017 03/31/2017 1,2 IPEmergency Action Level and Emergency Plan Changes711140403/27/2017 03/31/2017 1,2 IPCorrection of Emergency Preparedness Weaknesses and Deficiencies711140503/27/2017 03/31/2017 1,2 IPPerformance Indicator Verification7115103/27/2017 03/31/2017 ISI-UNIT 1 IN-SERVICE INSPECTION 11 IPInservice Inspection Activities - PWR7111108P05/08/2017 05/12/2017 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.
-06/30/2018 RP-RP OCCUPATIONAL INSPECTION WEEK 1 3 1, 2 IP Radiological Hazard Assessment and Exposure Controls71124.01 09/12/2016 09/16/2016 1, 2 IP Occupational ALARA Planning and Controls71124.02 09/12/2016 09/16/2016 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation71124.03 09/12/2016 09/16/2016 1, 2 IP Occupational Dose Assessment71124.04 09/12/2016 09/16/2016 1, 2 IP Radiation Monitoring Instrumentation71124.05 09/12/2016 09/16/2016 1, 2 IP Performance Indicator Verification71151 09/12/2016 09/16/2016 ISI-UNIT 2 IN-SERVICE INSPECTION 1 2 IP Inservice Inspection Activities - PWR7111108P 09/19/2016 09/23/2016 SGISI-UNIT 2 SG IN-SERVICE INSPECTION 1 2 IP Inservice Inspection Activities - PWR7111108P 09/26/2016 09/30/2016 RP-RP OCCUPATIONAL INSPECTION WEEK 2 2 1, 2 IP Radiological Hazard Assessment and Exposure Controls71124.01 09/26/2016 09/30/2016 1, 2 IP Occupational ALARA Planning and Controls71124.02 09/26/2016 09/30/2016 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation71124.03 09/26/2016 09/30/2016 1, 2 IP Occupational Dose Assessment71124.04 09/26/2016 09/30/2016 1, 2 IP Radiation Monitoring Instrumentation71124.05 09/26/2016 09/30/2016 1, 2 IP Performance Indicator Verification71151 09/26/2016 09/30/2016 PI&R-PROBLEM IDENTIFICATION AND RESOLUTION 7 1, 2 IP Problem Identification and Resolution71152B 10/24/2016 10/28/2016 1, 2 IP Problem Identification and Resolution71152B11/07/201611/11/2016 MODS-PLANT MODIFICATIONS INSPECTION 3 1, 2 IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T 01/23/2017 01/27/2017 1, 2 IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T 02/06/2017 02/10/2017 EP-EP PROGRAM INSPECTION 4 1, 2 IP A lert and Notification System Testing7111402 03/27/2017 03/31/2017 1, 2 IP Emergency Preparedness Organization Staffing and Augmentation System7111403 03/27/2017 03/31/2017 1, 2 IP Emergency Action Level and Emergency Plan Changes7111404 03/27/2017 03/31/2017 1, 2 IP Correction of Emergency Preparedness Weaknesses and Deficiencies7111405 03/27/2017 03/31/2017 1, 2 IP Performance Indicator Verification71151 03/27/2017 03/31/2017 ISI-UNIT 1 IN-SERVICE INSPECTION 1 1 IP Inservice Inspection Activities - PWR7111108P 05/08/2017 05/12/2017 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.


Page 2 of 2 08/31/2016 06:54:13Report 22 UnitNumberPlanned Dates Start EndInspection ActivityTitleNo. of Staff on SiteCatawbaInspection / Activity Plan 09/01/2016
Page 2 of 2 08/31/2016 06:54:13 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on SiteCatawbaInspection / Activity Plan 09/01/2016
-06/30/2018 RP-RAD HAZARDS ANALYSIS AND TRANSPORTATION 21,2 IPRadiological Hazard Assessment and Exposure Controls71124.0105/08/2017 05/12/2017 1,2 IPRadioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation71124.0805/08/2017 05/12/2017OL EXAM-INITIAL LICENSE EXAM PREP 31 CATAWBA/JULY 2017 INITIAL EXAM AT POWER FACILITIES V2349505/29/2017 06/02/2017OL EXAM-INITIAL LICENSE EXAM 31 CATAWBA/JULY 2017 INITIAL EXAM AT POWER FACILITIES V2349506/26/2017 07/07/2017 RP-RP PUBLIC RAD SAFETY BASELINE 21,2 IPRadioactive Gaseous and Liquid Effluent Treatment71124.0607/24/2017 07/28/2017 1,2 IPRadiological Environmental Monitoring Program71124.0707/24/2017 07/28/2017 1,2 IPPerformance Indicator Verification7115107/24/2017 07/28/2017 TFPI-TRIENNIEL FIRE PROTECTION INSPECTION 51,2 IPFire Protection [Triennial]7111105T07/24/2017 07/28/2017 1,2 IPFire Protection [Triennial]7111105T08/07/201708/11/2017 ISI-UNIT 2 IN-SERVICE INSPECTION 1 2 IPInservice Inspection Activities - PWR7111108P03/26/2018 03/30/2018 SGISI-UNIT 2 SG IN-SERVICE INSPECTION 1 2 IPInservice Inspection Activities - PWR7111108P04/02/2018 04/06/2018 EP-EP EXERCISE 61,2 IPExercise Evaluation711140106/04/2018 06/08/2018 1,2 IPEmergency Action Level and Emergency Plan Changes711140406/04/2018 06/08/2018 1,2 IPExercise Evaluation - Scenario Review711140806/04/2018 06/08/2018 1,2 IPPerformance Indicator Verification7115106/04/2018 06/08/2018 CDBI-COMPONENT DESIGN BASES INSPECTION 61,2 IPComponent Design Bases Inspection711112106/04/2018 06/08/2018 1,2 IPComponent Design Bases Inspection711112106/25/2018 06/29/2018 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.
-06/30/2018 RP-RAD HAZARDS ANALYSIS AND TRANSPORTATION 2 1, 2 IP Radiological Hazard Assessment and Exposure Controls71124.01 05/08/2017 05/12/2017 1, 2 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation71124.08 05/08/2017 05/12/2017OL EXAM-INITIAL LICENSE EXAM PREP 3 1 CATAWBA/JULY 2017 INITIAL EXAM AT POWER FACILITIES V23495 05/29/2017 06/02/2017OL EXAM-INITIAL LICENSE EXAM 3 1 CATAWBA/JULY 2017 INITIAL EXAM AT POWER FACILITIES V23495 06/26/2017 07/07/2017 RP-RP PUBLIC RAD SAFETY BASELINE 2 1, 2 IP Radioactive Gaseous and Liquid Effluent Treatment71124.06 07/24/2017 07/28/2017 1, 2 IP Radiological Environmental Monitoring Program71124.07 07/24/2017 07/28/2017 1, 2 IP Performance Indicator Verification71151 07/24/2017 07/28/2017 TFPI-TRIENNIEL FIRE PROTECTION INSPECTION 5 1, 2 IP Fire Protection [Triennial]7111105T 07/24/2017 07/28/2017 1, 2 IP Fire Protection [Triennial]7111105T 08/07/201708/11/2017 ISI-UNIT 2 IN-SERVICE INSPECTION 1 2 IP Inservice Inspection Activities - PWR7111108P 03/26/2018 03/30/2018 SGISI-UNIT 2 SG IN-SERVICE INSPECTION 1 2 IP Inservice Inspection Activities - PWR7111108P 04/02/2018 04/06/2018 EP-EP EXERCISE 6 1, 2 IP Exercise Evaluation7111401 06/04/2018 06/08/2018 1, 2 IP Emergency Action Level and Emergency Plan Changes7111404 06/04/2018 06/08/2018 1, 2 IP Exercise Evaluation - Scenario Review7111408 06/04/2018 06/08/2018 1, 2 IP Performance Indicator Verification71151 06/04/2018 06/08/2018 CDBI-COMPONENT DESIGN BASES INSPECTION 6 1, 2 IP Component Design Bases Inspection7111121 06/04/2018 06/08/2018 1, 2 IP Component Design Bases Inspection7111121 06/25/2018 06/29/2018 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.
}}
}}

Revision as of 05:22, 8 July 2018

Mid-Cycle Assessment Letter for Catawba Nuclear Station Units 1 and 2 (NRC Inspection Report 05000413/2016005 and 05000414/2016005)
ML16244A127
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 08/31/2016
From: Ehrhardt F J
Division Reactor Projects II
To: Henderson K
Duke Energy Corp
References
IR 2016005
Download: ML16244A127 (6)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303

-1257 August 31, 2016 Mr. Kelvin Henderson

Site Vice President Duke Energy Corporation Catawba Nuclear Station 4800 Concord Road York, SC 29745

-9635

SUBJECT: MID-CYCLE ASSESSMENT LETTER FOR CATAWBA NUCLEAR STATION UNITS 1 AND 2 (NRC INSPECTION REPORT 05000413/

201 6 00 5 AND 05000414/201 6 005)

Dear Mr. Henderson:

On August 9 , 201 6, the Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of Catawba Nuclear Station

, Units 1 and 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from J ul y 1, 20 1 5 through June 3 0 , 20 16. This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility.

The NRC determined that overall, Catawba Nuclear Station, Units 1 and 2 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Catawba Units 1 and 2 during the most recent quarter was within the Licensee Response Column of the NRC

's Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance

, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through June 3 0, 20 1 8. Routine inspections performed by resident inspectors are not included in the inspection plan.

The inspections listed during the second half of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

This inspection plan does not include security related inspections which will be sent via separate, non

-publicly available correspondence.

In response to the accident at Fukushima, the Commission issued Order EA

-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond

-Design-Basis External Events," and Order EA

-12-051, "Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation."

The NRC conducted audits of licensee efforts towards compliance with these Orders, and the information gathered will aid staff in development of the ultimate Safety Evaluation for the site.

After the NRC staff receives the Final Compliance letter for the site, the Safety Evaluation will be issued.

Then, the NRC staff will confirm through inspections the full implementation of the orders mentioned above by performing Temporary Instruction 191, "Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi

-Unit Dose Assessment Plans."

In Staff Requirements Memorandum

- SECY 16-0009, "Recommendations Resulting from the Integrated Prioritization and Re

-Baselining of Agency Activities," the Commission approved the NRC staff recommendation to discontinue the formal mid

-cycle assessment process beginning in calendar year 2017. This will be the final mid

-cycle assessment letter. The staff will continue to conduct quarterly assessment meetings and communicate changes in the assessment of licensee performance in accordance with the guidance in Inspection Manual Chapter 0305, "Operating Reactor Assessment Program."

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading

-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 404-997-4611 with any questions you have regarding this letter.

Sincerely,/RA/ Frank Ehrhardt, Chief Reactor Projects Branch 1 Division of Reactor Projects Docket Nos.:

50-413, 50-414 License Nos.:

NPF-35, NPF-52

Enclosure:

Catawba Inspection/Activity Plan (0 9/01/201 6 - 06/3 0/201 8)

cc distribution via ListServ

_________________________

SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRP RII:DRP RII:D RP SIGNATURE MMT2 JGW1 FJE NAME M. Toth J. Worosilo F. Ehrhardt DATE 8/25/2016 8/25/2016 8/25/2016 8/ /2016 8/ /2016 8/ /2016 8/ /2016 E-MAIL COPY?

YES NO YES NO YES NO YES NO YES NO YES NO YES NO Letter to Kelvin Henderson from Frank Ehrhardt dated August 31, 201 6

SUBJECT: MID-CYLCE ASSESSMENT LETTER FOR CATAWBA NUCLEAR STATION UNITS 1 AND 2 (NRC INSPECTION REPORT 05000413/

201 6 00 5 AND 05000414/201 6 00 5) DISTRIBUTION

D. Gamberoni, RII L. Gibson, RII OE Mail RIDSNRRDIRS PUBLIC A. Adams, NRR

RidsNrrPMCatawba Resource ROP Assessment ROP Reports Institute of Nuclear Power Operations (INPO)

Page 1 of 2 08/31/2016 06:54:13 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on SiteCatawbaInspection / Activity Plan 09/01/2016

-06/30/2018 RP-RP OCCUPATIONAL INSPECTION WEEK 1 3 1, 2 IP Radiological Hazard Assessment and Exposure Controls71124.01 09/12/2016 09/16/2016 1, 2 IP Occupational ALARA Planning and Controls71124.02 09/12/2016 09/16/2016 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation71124.03 09/12/2016 09/16/2016 1, 2 IP Occupational Dose Assessment71124.04 09/12/2016 09/16/2016 1, 2 IP Radiation Monitoring Instrumentation71124.05 09/12/2016 09/16/2016 1, 2 IP Performance Indicator Verification71151 09/12/2016 09/16/2016 ISI-UNIT 2 IN-SERVICE INSPECTION 1 2 IP Inservice Inspection Activities - PWR7111108P 09/19/2016 09/23/2016 SGISI-UNIT 2 SG IN-SERVICE INSPECTION 1 2 IP Inservice Inspection Activities - PWR7111108P 09/26/2016 09/30/2016 RP-RP OCCUPATIONAL INSPECTION WEEK 2 2 1, 2 IP Radiological Hazard Assessment and Exposure Controls71124.01 09/26/2016 09/30/2016 1, 2 IP Occupational ALARA Planning and Controls71124.02 09/26/2016 09/30/2016 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation71124.03 09/26/2016 09/30/2016 1, 2 IP Occupational Dose Assessment71124.04 09/26/2016 09/30/2016 1, 2 IP Radiation Monitoring Instrumentation71124.05 09/26/2016 09/30/2016 1, 2 IP Performance Indicator Verification71151 09/26/2016 09/30/2016 PI&R-PROBLEM IDENTIFICATION AND RESOLUTION 7 1, 2 IP Problem Identification and Resolution71152B 10/24/2016 10/28/2016 1, 2 IP Problem Identification and Resolution71152B11/07/201611/11/2016 MODS-PLANT MODIFICATIONS INSPECTION 3 1, 2 IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T 01/23/2017 01/27/2017 1, 2 IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T 02/06/2017 02/10/2017 EP-EP PROGRAM INSPECTION 4 1, 2 IP A lert and Notification System Testing7111402 03/27/2017 03/31/2017 1, 2 IP Emergency Preparedness Organization Staffing and Augmentation System7111403 03/27/2017 03/31/2017 1, 2 IP Emergency Action Level and Emergency Plan Changes7111404 03/27/2017 03/31/2017 1, 2 IP Correction of Emergency Preparedness Weaknesses and Deficiencies7111405 03/27/2017 03/31/2017 1, 2 IP Performance Indicator Verification71151 03/27/2017 03/31/2017 ISI-UNIT 1 IN-SERVICE INSPECTION 1 1 IP Inservice Inspection Activities - PWR7111108P 05/08/2017 05/12/2017 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.

Page 2 of 2 08/31/2016 06:54:13 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on SiteCatawbaInspection / Activity Plan 09/01/2016

-06/30/2018 RP-RAD HAZARDS ANALYSIS AND TRANSPORTATION 2 1, 2 IP Radiological Hazard Assessment and Exposure Controls71124.01 05/08/2017 05/12/2017 1, 2 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation71124.08 05/08/2017 05/12/2017OL EXAM-INITIAL LICENSE EXAM PREP 3 1 CATAWBA/JULY 2017 INITIAL EXAM AT POWER FACILITIES V23495 05/29/2017 06/02/2017OL EXAM-INITIAL LICENSE EXAM 3 1 CATAWBA/JULY 2017 INITIAL EXAM AT POWER FACILITIES V23495 06/26/2017 07/07/2017 RP-RP PUBLIC RAD SAFETY BASELINE 2 1, 2 IP Radioactive Gaseous and Liquid Effluent Treatment71124.06 07/24/2017 07/28/2017 1, 2 IP Radiological Environmental Monitoring Program71124.07 07/24/2017 07/28/2017 1, 2 IP Performance Indicator Verification71151 07/24/2017 07/28/2017 TFPI-TRIENNIEL FIRE PROTECTION INSPECTION 5 1, 2 IP Fire Protection [Triennial]7111105T 07/24/2017 07/28/2017 1, 2 IP Fire Protection [Triennial]7111105T 08/07/201708/11/2017 ISI-UNIT 2 IN-SERVICE INSPECTION 1 2 IP Inservice Inspection Activities - PWR7111108P 03/26/2018 03/30/2018 SGISI-UNIT 2 SG IN-SERVICE INSPECTION 1 2 IP Inservice Inspection Activities - PWR7111108P 04/02/2018 04/06/2018 EP-EP EXERCISE 6 1, 2 IP Exercise Evaluation7111401 06/04/2018 06/08/2018 1, 2 IP Emergency Action Level and Emergency Plan Changes7111404 06/04/2018 06/08/2018 1, 2 IP Exercise Evaluation - Scenario Review7111408 06/04/2018 06/08/2018 1, 2 IP Performance Indicator Verification71151 06/04/2018 06/08/2018 CDBI-COMPONENT DESIGN BASES INSPECTION 6 1, 2 IP Component Design Bases Inspection7111121 06/04/2018 06/08/2018 1, 2 IP Component Design Bases Inspection7111121 06/25/2018 06/29/2018 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.