ML040230196: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
 
Line 23: Line 23:
Nuclear Management Company, LLC
Nuclear Management Company, LLC
27780 Blue Star Memorial Highway
27780 Blue Star Memorial Highway
Covert, MI 49043-9530
Covert, MI 49043-9530
SUBJECT:       PALISADES NUCLEAR GENERATING PLANT
SUBJECT:
                NRC INSPECTION REPORT 05000255/2003008
PALISADES NUCLEAR GENERATING PLANT
NRC INSPECTION REPORT 05000255/2003008
Dear Mr. Malone:
Dear Mr. Malone:
On December 31, 2003, the U. S. Nuclear Regulatory Commission (NRC) completed an
On December 31, 2003, the U. S. Nuclear Regulatory Commission (NRC) completed an
inspection at your Palisades Nuclear Generating Plant. The enclosed report documents the
inspection at your Palisades Nuclear Generating Plant. The enclosed report documents the
inspection findings which were discussed on January 9, 2004, with you and other members of
inspection findings which were discussed on January 9, 2004, with you and other members of
your staff.
your staff.
The inspection examined activities conducted under your license as they relate to safety and
The inspection examined activities conducted under your license as they relate to safety and  
compliance with the Commissions rules and regulations and with the conditions of your license.
compliance with the Commissions rules and regulations and with the conditions of your license.  
The inspectors reviewed selected procedures and records, observed activities, and interviewed
The inspectors reviewed selected procedures and records, observed activities, and interviewed
personnel.
personnel.
Based on the results of this inspection, two findings of very low safety significance (Green) were
Based on the results of this inspection, two findings of very low safety significance (Green) were
identified, which were determined to involve violations of NRC requirements. However,
identified, which were determined to involve violations of NRC requirements. However,
because these findings were of very low safety significance and because the findings have
because these findings were of very low safety significance and because the findings have
been entered into your corrective action program, the NRC is treating these violations as
been entered into your corrective action program, the NRC is treating these violations as
Line 42: Line 43:
If you contest the subject or severity of a Non-Cited Violation, you should provide a response
If you contest the subject or severity of a Non-Cited Violation, you should provide a response
with a basis for your denial, within 30 days of the date of this inspection report, to the U.S.
with a basis for your denial, within 30 days of the date of this inspection report, to the U.S.
Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-
Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-
0001, with a copy to the Regional Administrator, U.S. Nuclear Regulatory Commission -
0001, with a copy to the Regional Administrator, U.S. Nuclear Regulatory Commission -  
Region III, 801 Warrenville Road, Lisle, IL 60532-4351; the Director, Office of Enforcement,
Region III, 801 Warrenville Road, Lisle, IL 60532-4351; the Director, Office of Enforcement,
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident
Inspector at the Palisades facility.
Inspector at the Palisades facility.


D. Malone                                       -2-
D. Malone
-2-
In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter
In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter
and its enclosure will be available electronically for public inspection in the NRC Public
and its enclosure will be available electronically for public inspection in the NRC Public
Document Room or from the Publicly Available Records (PARS) component of NRC's
Document Room or from the Publicly Available Records (PARS) component of NRC's
document system (ADAMS). ADAMS is accessible from the NRC Web site at
document system (ADAMS). ADAMS is accessible from the NRC Web site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
                                              Sincerely,
Sincerely,
                                              /RA/
/RA/
                                              Eric R. Duncan, Chief
Eric R. Duncan, Chief
                                              Branch 6
Branch 6
                                              Division of Reactor Projects
Division of Reactor Projects
Docket No. 50-255
Docket No. 50-255
License No. DPR-20
License No. DPR-20
Enclosure:     Inspection Report 05000255/2003008
Enclosure:
                w/Attachment: Supplemental Information
Inspection Report 05000255/2003008
cc w/encl:     J. Cowan, Executive Vice President
  w/Attachment: Supplemental Information
                and Chief Nuclear Officer
cc w/encl:
              R. Fenech, Senior Vice President, Nuclear
J. Cowan, Executive Vice President
                Fossil and Hydro Operations
  and Chief Nuclear Officer
              D. Cooper, Senior Vice President - Group Operations
R. Fenech, Senior Vice President, Nuclear
              Manager, Regulatory Affairs
  Fossil and Hydro Operations
              J. Rogoff, Vice President, Counsel and Secretary
D. Cooper, Senior Vice President - Group Operations
              A. Udrys, Esquire, Consumers Energy Company
Manager, Regulatory Affairs
              Director of Nuclear Assets, Consumers Energy Company
J. Rogoff, Vice President, Counsel and Secretary
              Supervisor, Covert Township
A. Udrys, Esquire, Consumers Energy Company
              Office of the Governor
Director of Nuclear Assets, Consumers Energy Company
              Michigan Department of Environmental Quality -
Supervisor, Covert Township
                Waste and Hazardous Materials Division
Office of the Governor
              Michigan Department of Attorney General
Michigan Department of Environmental Quality -
  Waste and Hazardous Materials Division
Michigan Department of Attorney General


DOCUMENT NAME: S:\ADMIN\Karen's Docs\ML040230196.wpd
DOCUMENT NAME: S:\\ADMIN\\Karen's Docs\\ML040230196.wpd
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure   "E" = Copy with attachment/enclosure   "N" = No copy
OFFICE             RIII
OFFICE
NAME               EDuncan:dtp
RIII
DATE               01/22/03
NAME
                                                          OFFICIAL RECORD COPY
EDuncan:dtp
DATE
01/22/03
OFFICIAL RECORD COPY


D. Malone                               -2-
D. Malone
-2-
ADAMS Distribution:
ADAMS Distribution:
WDR
WDR  
DFT
DFT  
JHE
JHE
RidsNrrDipmIipb
RidsNrrDipmIipb
Line 101: Line 109:
JRK1
JRK1


          U.S. NUCLEAR REGULATORY COMMISSION
Enclosure
                          REGION III
U.S. NUCLEAR REGULATORY COMMISSION
Docket No:         50-255
REGION III
License No:         DPR-20
Docket No:
Report No:         050000255/2003008
50-255
Licensee:           Nuclear Management Company, LLC
License No:
Facility:           Palisades Nuclear Generating Plant
DPR-20
Location:           27780 Blue Star Memorial Highway
Report No:
                    Covert, MI 49043-9530
050000255/2003008
Dates:             October 1 through December 31, 2003
Licensee:
Inspectors:         J. Lennartz, Senior Resident Inspector
Nuclear Management Company, LLC
                    M. Garza, Resident Inspector
Facility:
                    R. Alexander, Radiation Specialist
Palisades Nuclear Generating Plant
                    A. Dunlop, Reactor Engineer
Location:
                    R. Jickling, Emergency Preparedness Analyst
27780 Blue Star Memorial Highway
Approved by:       Eric R. Duncan, Chief
Covert, MI 49043-9530
                    Branch 6
Dates:
                    Division of Reactor Projects
October 1 through December 31, 2003
                                                                Enclosure
Inspectors:
J. Lennartz, Senior Resident Inspector
M. Garza, Resident Inspector
R. Alexander, Radiation Specialist
A. Dunlop, Reactor Engineer
R. Jickling, Emergency Preparedness Analyst
Approved by:
Eric R. Duncan, Chief
Branch 6
Division of Reactor Projects


                                    SUMMARY OF FINDINGS
Enclosure
1
SUMMARY OF FINDINGS
IR 05000255/2003008; 10/01/2003 - 12/31/2003; Palisades Nuclear Generating Plant;
IR 05000255/2003008; 10/01/2003 - 12/31/2003; Palisades Nuclear Generating Plant;
Equipment Availability, Reliability and Functional Capability (71111.EP).
Equipment Availability, Reliability and Functional Capability (71111.EP).
This report covers a 3-month period of baseline resident inspections, two announced baseline
This report covers a 3-month period of baseline resident inspections, two announced baseline
inspections in radiation protection, an announced heat sink performance inspection and a
inspections in radiation protection, an announced heat sink performance inspection and a
routine baseline emergency preparedness inspection. The inspections were conducted by
routine baseline emergency preparedness inspection. The inspections were conducted by
resident inspectors, a regional inspector, a radiation specialist inspector, and an emergency
resident inspectors, a regional inspector, a radiation specialist inspector, and an emergency
preparedness analyst. Two Green findings with associated Non-Cited Violations (NCVs) were
preparedness analyst. Two Green findings with associated Non-Cited Violations (NCVs) were
identified during the inspection. The significance of most findings is indicated by their color
identified during the inspection. The significance of most findings is indicated by their color
(Green, White, Yellow, Red) using Inspection Manual Chapter 0609, Significance
(Green, White, Yellow, Red) using Inspection Manual Chapter 0609, Significance
Determination Process, (SDP). Findings for which the SDP does not apply may be Green or
Determination Process, (SDP). Findings for which the SDP does not apply may be Green or
be assigned a severity level after NRC management review. The NRCs program for
be assigned a severity level after NRC management review. The NRCs program for
overseeing the safe operation of commercial nuclear power reactors is described in
overseeing the safe operation of commercial nuclear power reactors is described in
NUREG-1649, Reactor Oversight Process, Revision 3, dated July 2000.
NUREG-1649, Reactor Oversight Process, Revision 3, dated July 2000.
A.     Inspector Identified Findings
A.  
        Cornerstone: Mitigating Systems
Inspector Identified Findings
C       Green. A finding of very low safety significance was self-revealed when High Pressure
Cornerstone: Mitigating Systems
        Safety Injection Pump P-66B Subcooling Valve CV-3070 failed to stroke open during
C
        surveillance testing. Licensee personnel improperly installed a flow control valve in the
Green. A finding of very low safety significance was self-revealed when High Pressure
        operating air system which contributed to the valve failing to stroke open. The finding
Safety Injection Pump P-66B Subcooling Valve CV-3070 failed to stroke open during
        was more than minor because the availability and capability of High Pressure Safety
surveillance testing. Licensee personnel improperly installed a flow control valve in the
        Injection Pump P-66B was adversely affected. The finding was of very low safety
operating air system which contributed to the valve failing to stroke open. The finding
        significance because there was not an actual loss of safety function for High Pressure
was more than minor because the availability and capability of High Pressure Safety
        Safety Injection Pump P-66B for greater than the Technical Specification allowed outage
Injection Pump P-66B was adversely affected. The finding was of very low safety
        time.
significance because there was not an actual loss of safety function for High Pressure
        Corrective actions to address this issue included reinstalling the flow control valve in the
Safety Injection Pump P-66B for greater than the Technical Specification allowed outage
        proper direction, testing CV-3070 during a mid-surveillance cycle stroke test, and
time.
        generating a work order to inspect the CV-3070 valve internals at the earliest opportunity.
Corrective actions to address this issue included reinstalling the flow control valve in the
        One Non-Cited Violation of 10 CFR 50, Appendix B, Criterion V, Instructions,
proper direction, testing CV-3070 during a mid-surveillance cycle stroke test, and
        Procedures and Drawings, was identified. (Section 1REP)
generating a work order to inspect the CV-3070 valve internals at the earliest opportunity.  
Cornerstone: Barrier Integrity
One Non-Cited Violation of 10 CFR 50, Appendix B, Criterion V, Instructions,
C       Green. A finding of very low safety significance was self-revealed when the
Procedures and Drawings, was identified. (Section 1REP)
        Containment Spray Pump P-54C inboard motor bearing failed on August 21, 2003.
Cornerstone: Barrier Integrity
        Following a scheduled oil change on the motor bearing, the bearing housing drain plug
C
        was also replaced and enough oil was lost during this drain plug replacement to uncover
Green. A finding of very low safety significance was self-revealed when the  
        the bearing; however, the vent on the oiler had been plugged when the pump was
Containment Spray Pump P-54C inboard motor bearing failed on August 21, 2003.  
        painted in June 2002 which resulted in an erroneous level indication in the oiler for the
Following a scheduled oil change on the motor bearing, the bearing housing drain plug
        bearing housing. Consequently, the operator did not add sufficient oil through the oiler to
was also replaced and enough oil was lost during this drain plug replacement to uncover
        the bearing housing after the drain plug was replaced. As a result, the inboard motor
the bearing; however, the vent on the oiler had been plugged when the pump was
        bearing was inadequately lubricated which caused the bearing to fail when Containment
painted in June 2002 which resulted in an erroneous level indication in the oiler for the
                                                  1                                        Enclosure
bearing housing. Consequently, the operator did not add sufficient oil through the oiler to
the bearing housing after the drain plug was replaced. As a result, the inboard motor
bearing was inadequately lubricated which caused the bearing to fail when Containment


  Spray Pump P-54C was started. This finding was more than minor because if left
Enclosure
  uncorrected, it would become a more significant safety concern. Specifically, the painted
2
  vent hole on the motor bearing oiler resulted in erroneous oil level indication and
Spray Pump P-54C was started. This finding was more than minor because if left
  prevented the oiler from adding oil to the bearing housing when the level decreased.
uncorrected, it would become a more significant safety concern. Specifically, the painted
  Consequently, an inadequately lubricated bearing would not be detected until the bearing
vent hole on the motor bearing oiler resulted in erroneous oil level indication and
  failed. The finding was of very low safety significance because it did not represent an
prevented the oiler from adding oil to the bearing housing when the level decreased.  
  actual reduction of the atmospheric pressure control function of the reactor containment.
Consequently, an inadequately lubricated bearing would not be detected until the bearing
  Corrective actions to address this issue included clearing the vent hole on the bearing
failed. The finding was of very low safety significance because it did not represent an
  oiler, verifying that the oiler vent holes on other safety-related pump motors were not
actual reduction of the atmospheric pressure control function of the reactor containment.
  painted over and replacing the inboard motor bearing on Containment Spray Pump
Corrective actions to address this issue included clearing the vent hole on the bearing
  P-54C. One Non-Cited Violation of 10 CFR 50, Appendix B, Criterion V, Instructions,
oiler, verifying that the oiler vent holes on other safety-related pump motors were not
  Procedures and Drawings, was identified. (Section 1REP)
painted over and replacing the inboard motor bearing on Containment Spray Pump
B. Licensee Identified Findings
P-54C. One Non-Cited Violation of 10 CFR 50, Appendix B, Criterion V, Instructions,
  None.
Procedures and Drawings, was identified. (Section 1REP)
                                                2                                    Enclosure
B.
Licensee Identified Findings
None.


                                        REPORT DETAILS
Enclosure
3
REPORT DETAILS
A list of documents reviewed within each inspection area is included at the end of the report.
A list of documents reviewed within each inspection area is included at the end of the report.
Summary of Plant Status
Summary of Plant Status
The plant operated at full power during the inspection period with the following exception:
The plant operated at full power during the inspection period with the following exception:
C       On November 8, 2003, power was reduced to 85 percent to conduct scheduled turbine
C
        valve testing. During these activities, Heater Drain Pump P-10B unexpectedly tripped
On November 8, 2003, power was reduced to 85 percent to conduct scheduled turbine
        due to low level in Moisture Separator and Heater Drain Tank T-5. Site personnel
valve testing. During these activities, Heater Drain Pump P-10B unexpectedly tripped
        subsequently identified that T-5 Level Control Valve CV-0608 was not operating
due to low level in Moisture Separator and Heater Drain Tank T-5. Site personnel
        properly. A trip of one heater drain pump with power at 85 percent did not require any
subsequently identified that T-5 Level Control Valve CV-0608 was not operating
        mitigating actions.
properly. A trip of one heater drain pump with power at 85 percent did not require any
        On November 9, 2003, during emergent maintenance on Moisture Separator Reheater
mitigating actions.
        Stop Valve CV-0537, control room operators noted that Tank T-5 level was lowering
On November 9, 2003, during emergent maintenance on Moisture Separator Reheater
        again. As a result, Heater Drain Pump P-10A tripped. Operators subsequently
Stop Valve CV-0537, control room operators noted that Tank T-5 level was lowering
        stabilized power at 72 percent.
again. As a result, Heater Drain Pump P-10A tripped. Operators subsequently
        After the second heater drain pump tripped, operations personnel identified that the
stabilized power at 72 percent.
        discharge check valve on Heater Drain Pump P-10A was not fully seated and repairs
After the second heater drain pump tripped, operations personnel identified that the
        were required. While completing necessary repairs to the discharge check valve,
discharge check valve on Heater Drain Pump P-10A was not fully seated and repairs
        Heater Drain Pump P-10B was restarted on November 10, 2003, and power was
were required. While completing necessary repairs to the discharge check valve,
        increased to 90 percent.
Heater Drain Pump P-10B was restarted on November 10, 2003, and power was
        Following repairs, Heater Drain Pump P-10A was returned to service and the plant
increased to 90 percent.
        returned to full power on November 13, 2003.
Following repairs, Heater Drain Pump P-10A was returned to service and the plant
1.       REACTOR SAFETY
returned to full power on November 13, 2003.
        Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, and
1.
        Emergency Preparedness
REACTOR SAFETY
1R01 Adverse Weather Protection (71111.01)
Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, and
.1       Cold Weather Preparations
Emergency Preparedness
   a.     Inspection Scope
1R01
        The inspectors reviewed the sites Cold Weather Checklists that were completed from
Adverse Weather Protection (71111.01)
        October through November 2003 to assess the actions taken to prepare for the onset of
.1
        cold weather. The inspectors also performed walkdowns to verify the physical condition
Cold Weather Preparations
        of weather protection features for risk significant systems and components.
   a.
        The inspectors reviewed selected condition reports related to cold weather preparation
Inspection Scope
        problems and verified that identified problems were entered into the corrective action
The inspectors reviewed the sites Cold Weather Checklists that were completed from
                                                  3                                    Enclosure
October through November 2003 to assess the actions taken to prepare for the onset of
cold weather. The inspectors also performed walkdowns to verify the physical condition
of weather protection features for risk significant systems and components.
The inspectors reviewed selected condition reports related to cold weather preparation
problems and verified that identified problems were entered into the corrective action


    program with the appropriate significance characterization and that planned and
Enclosure
    completed corrective actions were appropriate.
4
   b. Findings
program with the appropriate significance characterization and that planned and
    No findings of significance were identified.
completed corrective actions were appropriate.
.2   Entry into Off-Normal Procedure Because of High Winds
   b.
   a. Inspection Scope
Findings
    The inspectors assessed the actions taken for one emergent adverse weather condition.
No findings of significance were identified.
    On November 12, 2003, operations personnel entered Off-Normal Procedure-12, Acts
.2
    of Nature, after the control room received a weather warning regarding sustained wind
Entry into Off-Normal Procedure Because of High Winds
    speeds of 40 miles per hour and wind gusts to 50 miles per hour. The inspectors
   a.
    verified that the actions specified in Off-Normal Procedure-12 were being accomplished
Inspection Scope
    to the extent possible for this emergent adverse weather condition. Off-Normal
The inspectors assessed the actions taken for one emergent adverse weather condition.
    Procedure-12 was exited on November 13, 2003, after the high winds diminished.
On November 12, 2003, operations personnel entered Off-Normal Procedure-12, Acts
   b. Findings
of Nature, after the control room received a weather warning regarding sustained wind
    No findings of significance were identified.
speeds of 40 miles per hour and wind gusts to 50 miles per hour. The inspectors
1R04 Equipment Alignment
verified that the actions specified in Off-Normal Procedure-12 were being accomplished
.1   Quarterly Equipment Alignment Walkdowns (71111.04Q)
to the extent possible for this emergent adverse weather condition. Off-Normal
   a. Inspection Scope
Procedure-12 was exited on November 13, 2003, after the high winds diminished.
    The inspectors performed two equipment alignment walkdowns to verify that the
   b.
    following systems were properly aligned:
Findings
    C       Instrument Air Compressors C-2A and C-2C
No findings of significance were identified.
    C       Control Room Heating, Ventilation and Air Conditioning Train B
1R04
    For these systems, the inspectors verified that power was available, that accessible
Equipment Alignment
    equipment and components were appropriately aligned, and that no discrepancies
.1
    existed which would impact system function.
Quarterly Equipment Alignment Walkdowns (71111.04Q)
    The inspectors also reviewed selected condition reports related to equipment alignment
   a.
    problems and verified that identified problems were entered into the corrective action
Inspection Scope
    program with the appropriate significance characterization and that planned and
The inspectors performed two equipment alignment walkdowns to verify that the
    completed corrective actions were appropriate.
following systems were properly aligned:
   b. Findings
C
    No findings of significance were identified.
Instrument Air Compressors C-2A and C-2C
                                                4                                    Enclosure
C
Control Room Heating, Ventilation and Air Conditioning Train B
For these systems, the inspectors verified that power was available, that accessible
equipment and components were appropriately aligned, and that no discrepancies
existed which would impact system function.
The inspectors also reviewed selected condition reports related to equipment alignment
problems and verified that identified problems were entered into the corrective action
program with the appropriate significance characterization and that planned and
completed corrective actions were appropriate.
   b.
Findings
No findings of significance were identified.


1R05 Fire Protection
Enclosure
.1   Fire Area Walkdowns (71111.05Q)
5
   a. Inspection Scope
1R05
    The inspectors toured the following six areas in which a fire could affect safety-related
Fire Protection
    equipment:
.1
    C       Battery Room #1 (Fire Area 12)
Fire Area Walkdowns (71111.05Q)
    C       Electrical Equipment Room (Fire Area 21)
   a.
    C       East Engineered Safeguards Room (Fire Area 10)
Inspection Scope
    C       West Mechanical Equipment Room (Fire Area 31)
The inspectors toured the following six areas in which a fire could affect safety-related
    C       East Mechanical Equipment Room (Fire Area 30)
equipment:
    *       Auxiliary Building Level 590 Corridor (Fire Area 13)
C
    The inspectors verified that transient combustibles and ignition sources were
Battery Room #1 (Fire Area 12)
    appropriately controlled, and assessed the material condition of fire suppression
C
    systems, manual fire fighting equipment, smoke detection systems, and fire barriers.
Electrical Equipment Room (Fire Area 21)
    The inspectors also reviewed documentation for completed surveillances to verify that
C
    fire protection equipment and fire barriers were tested as required to ensure availability.
East Engineered Safeguards Room (Fire Area 10)
    The inspectors verified that the installed fire protection equipment in the fire areas
C
    corresponded with the equipment which was referenced in the applicable portions of the
West Mechanical Equipment Room (Fire Area 31)
    Updated Final Safety Analysis Report, Section 9.6, Fire Protection.
C
    The inspectors reviewed selected condition reports related to fire protection problems
East Mechanical Equipment Room (Fire Area 30)
    and verified that identified problems were entered into the corrective action program with
*
    the appropriate significance characterization and that planned and completed corrective
Auxiliary Building Level 590 Corridor (Fire Area 13)
    actions were appropriate.
The inspectors verified that transient combustibles and ignition sources were
   b. Findings
appropriately controlled, and assessed the material condition of fire suppression
    No findings of significance were identified.
systems, manual fire fighting equipment, smoke detection systems, and fire barriers.  
1R06 Flood Protection (71111.06A)
The inspectors also reviewed documentation for completed surveillances to verify that
   a. Inspection Scope
fire protection equipment and fire barriers were tested as required to ensure availability.
    The inspectors performed one inspection sample of internal flood protection features for
The inspectors verified that the installed fire protection equipment in the fire areas
    the safety-related batteries which the Updated Final Safety Analysis Report designated
corresponded with the equipment which was referenced in the applicable portions of the
    as equipment that required protection from flooding due to failures of nonsafety-related
Updated Final Safety Analysis Report, Section 9.6, Fire Protection.
    systems.
The inspectors reviewed selected condition reports related to fire protection problems
                                              5                                        Enclosure
and verified that identified problems were entered into the corrective action program with
the appropriate significance characterization and that planned and completed corrective
actions were appropriate.
   b.
Findings
No findings of significance were identified.
1R06
Flood Protection (71111.06A)
   a.
Inspection Scope
The inspectors performed one inspection sample of internal flood protection features for
the safety-related batteries which the Updated Final Safety Analysis Report designated
as equipment that required protection from flooding due to failures of nonsafety-related
systems.


    The inspectors conducted walkdowns noting the following attributes associated with the
Enclosure
    battery rooms:
6
    C       Holes or unsealed penetrations in floors, ceilings and walls;
The inspectors conducted walkdowns noting the following attributes associated with the
    C       Common drain system and sumps, including floor drain piping and check valves
battery rooms:
              where credited for isolation of flood areas; and
C
    C       Sources of potential internal flooding that were not analyzed or were not
Holes or unsealed penetrations in floors, ceilings and walls;  
              adequately maintained.
C
    The inspectors also assessed condition reports related to flood protection problems to
Common drain system and sumps, including floor drain piping and check valves
    verify that identified problems were entered into the corrective action program with the
where credited for isolation of flood areas; and
    appropriate significance characterization and that corrective actions were appropriate
C
    and implemented as scheduled.
Sources of potential internal flooding that were not analyzed or were not
b. Findings
adequately maintained.
    No findings of significance were identified.
The inspectors also assessed condition reports related to flood protection problems to
1R07 Heat Sink Performance (71111.07B)
verify that identified problems were entered into the corrective action program with the
a. Inspection Scope
appropriate significance characterization and that corrective actions were appropriate
    The regional specialist inspector reviewed documents associated with maintenance,
and implemented as scheduled.
    inspection, and thermal performance testing of the containment air coolers and the
  b.
    control room heating, ventilation and air conditioning condensers (the heat exchangers
Findings
    represented two inspection samples). These heat exchangers and coolers were chosen
No findings of significance were identified.
    based on previous corrosion and tube plugging concerns. While onsite, the inspector
1R07
    reviewed completed surveillances, associated calculations, instrument calibration
Heat Sink Performance (71111.07B)
    records, and maintenance work orders, and performed independent calculations to
  a.
    verify that these activities adequately ensured proper heat transfer. The inspector
Inspection Scope
    reviewed the documentation to confirm that the test methodology was consistent with
The regional specialist inspector reviewed documents associated with maintenance,
    accepted industry practices, that test acceptance criteria were consistent with design
inspection, and thermal performance testing of the containment air coolers and the
    basis values, and that the test results appropriately considered differences between test
control room heating, ventilation and air conditioning condensers (the heat exchangers
    and design conditions.
represented two inspection samples). These heat exchangers and coolers were chosen
    The inspector also reviewed documentation to confirm that methods used to inspect the
based on previous corrosion and tube plugging concerns. While onsite, the inspector
    heat exchangers were consistent with expected degradation and that the established
reviewed completed surveillances, associated calculations, instrument calibration
    acceptance criteria were consistent with accepted industry standards. The inspector
records, and maintenance work orders, and performed independent calculations to
    verified that systems and sub-components were free from clogging due to macrofouling
verify that these activities adequately ensured proper heat transfer. The inspector
    and that the licensee had adequate controls in place for biotic fouling.
reviewed the documentation to confirm that the test methodology was consistent with
    In addition, the inspectors reviewed condition reports concerning heat exchanger and
accepted industry practices, that test acceptance criteria were consistent with design
    heat sink performance issues to verify that the licensee had an appropriate threshold for
basis values, and that the test results appropriately considered differences between test
    identifying issues and to evaluate the effectiveness of the licensees corrective actions
and design conditions.
    to address the identified issues.
The inspector also reviewed documentation to confirm that methods used to inspect the
b   Findings
heat exchangers were consistent with expected degradation and that the established
    No findings of significance were identified.
acceptance criteria were consistent with accepted industry standards. The inspector
                                                6                                    Enclosure
verified that systems and sub-components were free from clogging due to macrofouling
and that the licensee had adequate controls in place for biotic fouling.
In addition, the inspectors reviewed condition reports concerning heat exchanger and
heat sink performance issues to verify that the licensee had an appropriate threshold for
identifying issues and to evaluate the effectiveness of the licensees corrective actions
to address the identified issues.  
  b
Findings
No findings of significance were identified.


1R11 Licensed Operator Requalification (71111.11Q)
Enclosure
a. Inspection Scope
7
    The inspectors observed one crew of licensed operators during simulator training on
1R11
    December 3, 2003. The inspectors assessed the operators ability to use Off-Normal
Licensed Operator Requalification (71111.11Q)
    and Emergency Operating plant procedures to mitigate the following simulated events:
  a.
    C       loss of two offsite power sources which resulted in a rise in switchyard voltage
Inspection Scope
            concurrent with a failure of the automatic voltage adjuster on the main generator;
The inspectors observed one crew of licensed operators during simulator training on
    C       sequential high differential pressures in service water basket strainers due to
December 3, 2003. The inspectors assessed the operators ability to use Off-Normal
            debris intrusion;
and Emergency Operating plant procedures to mitigate the following simulated events:
    C       loss of one switchyard bus during a plant trip which resulted in emergency diesel
C
            generators starting and energizing safety-related electrical loads; and
loss of two offsite power sources which resulted in a rise in switchyard voltage
    C       blockage of service water traveling screens due to frazil ice resulting in a loss of
concurrent with a failure of the automatic voltage adjuster on the main generator;
            service water.
C
    The inspectors also verified that the Shift Manager implemented the Emergency Plan
sequential high differential pressures in service water basket strainers due to
    Implementing Procedures in an accurate and timely manner when classifying the events
debris intrusion;
    and notifying off-site authorities. In addition, the inspectors observed the post-scenario
C
    critique to assess the licensee evaluators and the crews ability to self-identify
loss of one switchyard bus during a plant trip which resulted in emergency diesel
    performance weaknesses.
generators starting and energizing safety-related electrical loads; and
b. Findings
C
    No findings of significance were identified.
blockage of service water traveling screens due to frazil ice resulting in a loss of
1R13 Maintenance Risk Assessments and Emergent Work Evaluation (71111.13Q)
service water.
a. Inspection Scope
The inspectors also verified that the Shift Manager implemented the Emergency Plan
    The inspectors reviewed Operators Risk Reports, the Operations Log, and daily
Implementing Procedures in an accurate and timely manner when classifying the events
    maintenance schedules to verify that equipment necessary to minimize plant risk was
and notifying off-site authorities. In addition, the inspectors observed the post-scenario
    operable or available as required during planned and emergent maintenance activities.
critique to assess the licensee evaluators and the crews ability to self-identify
    The inspectors also conducted plant walkdowns to verify that equipment necessary to
performance weaknesses.
    minimize risk was available for use. The following four activities were reviewed:
  b.
    C       Scheduled outage for Emergency Diesel Generator 1-2 during the week of
Findings
            September 29, 2003;
No findings of significance were identified.
    C       Scheduled surveillance testing for the Reactor Protection System during the
1R13
            week of November 10, 2003;
Maintenance Risk Assessments and Emergent Work Evaluation (71111.13Q)
    C       Scheduled surveillance testing for Emergency Diesel Generator 1-2 on
  a.
            November 18-19, 2003; and
Inspection Scope
    C       Emergent maintenance on Emergency Diesel Generator 1-1 on December 7-10,
The inspectors reviewed Operators Risk Reports, the Operations Log, and daily
            2003.
maintenance schedules to verify that equipment necessary to minimize plant risk was
b. Findings
operable or available as required during planned and emergent maintenance activities.
    No findings of significance were identified.
The inspectors also conducted plant walkdowns to verify that equipment necessary to
                                                7                                        Enclosure
minimize risk was available for use. The following four activities were reviewed:
C
Scheduled outage for Emergency Diesel Generator 1-2 during the week of
September 29, 2003;
C
Scheduled surveillance testing for the Reactor Protection System during the
week of November 10, 2003;
C
Scheduled surveillance testing for Emergency Diesel Generator 1-2 on
November 18-19, 2003; and
C
Emergent maintenance on Emergency Diesel Generator 1-1 on December 7-10,
2003.
  b.
Findings
No findings of significance were identified.


1R14 Operator Performance During Non-Routine Evolutions and Events (71111.14)
Enclosure
a. Inspection Scope
8
    On November 8, 2003, the inspectors observed portions of main turbine governor and
1R14
    stop valve testing to verify that the evolution was effectively controlled and conducted in
Operator Performance During Non-Routine Evolutions and Events (71111.14)
    accordance with System Operating Procedure-8, Main Turbine and Generating
  a.
    Systems.
Inspection Scope
    The inspectors also reviewed the events and circumstances that resulted in the
On November 8, 2003, the inspectors observed portions of main turbine governor and
    unexpected trip of one nonsafety-related heater drain pump which occurred during
stop valve testing to verify that the evolution was effectively controlled and conducted in
    turbine valve testing. In addition, the inspectors reviewed the events and circumstances
accordance with System Operating Procedure-8, Main Turbine and Generating
    which necessitated a downpower from 82 percent to 72 percent in response to an
Systems.
    imminent unplanned trip of the second heater drain pump after turbine valve testing
The inspectors also reviewed the events and circumstances that resulted in the
    activities had been completed. The inspectors reviewed control room logs, annunciator
unexpected trip of one nonsafety-related heater drain pump which occurred during
    response procedures, and off-normal operating procedures to verify that the control
turbine valve testing. In addition, the inspectors reviewed the events and circumstances
    room operators responded as required.
which necessitated a downpower from 82 percent to 72 percent in response to an
    The inspectors also assessed condition reports related to the turbine valve testing and
imminent unplanned trip of the second heater drain pump after turbine valve testing
    verified that the problems were entered into the corrective action program with the
activities had been completed. The inspectors reviewed control room logs, annunciator
    appropriate significance characterization and that the licensees immediate corrective
response procedures, and off-normal operating procedures to verify that the control
    actions were appropriate.
room operators responded as required.
b. Findings
The inspectors also assessed condition reports related to the turbine valve testing and
    No findings of significance were identified.
verified that the problems were entered into the corrective action program with the
1R17 Permanent Plant Modifications (71111.17)
appropriate significance characterization and that the licensees immediate corrective
a. Inspection Scope
actions were appropriate.
    The inspectors reviewed one permanent plant modification which provided an alternate
  b.
    flowpath of borated water to the primary coolant system to safely shut down the plant to
Findings
    cold shutdown following a seismic event. The modification included the following
No findings of significance were identified.
    Engineering Assistance Request (EAR) design documents:
1R17
    *       EAR-2000-0345, Seismic Qualification Utility Group (SQUG) Outlier Resolution
Permanent Plant Modifications (71111.17)
              for Safety Injection Refueling Water Tank T-58;
  a.
    C       EAR-2002-017, for modifications to the service water system and spent fuel pool
Inspection Scope
              cooling system; and
The inspectors reviewed one permanent plant modification which provided an alternate
    C       EAR-2002-0293, for modifications to the charging system header.
flowpath of borated water to the primary coolant system to safely shut down the plant to
    The inspectors reviewed the associated safety analyses and design change information
cold shutdown following a seismic event. The modification included the following
    to verify that the design basis and performance capability of the spent fuel pool cooling
Engineering Assistance Request (EAR) design documents:
    system and charging system was not degraded. The inspectors also verified that the
*
    modification was installed in the plant as designed; the plant operating procedures and
EAR-2000-0345, Seismic Qualification Utility Group (SQUG) Outlier Resolution
    plant drawings were revised appropriately; and the required lengths of fire hoses, tools
for Safety Injection Refueling Water Tank T-58;
    and connectors necessary to establish the alternate flowpath were pre-staged and
C
    available for use if needed.
EAR-2002-017, for modifications to the service water system and spent fuel pool
                                                8                                      Enclosure
cooling system; and
C
EAR-2002-0293, for modifications to the charging system header.
The inspectors reviewed the associated safety analyses and design change information
to verify that the design basis and performance capability of the spent fuel pool cooling
system and charging system was not degraded. The inspectors also verified that the
modification was installed in the plant as designed; the plant operating procedures and
plant drawings were revised appropriately; and the required lengths of fire hoses, tools
and connectors necessary to establish the alternate flowpath were pre-staged and
available for use if needed.


    Further, the inspectors verified that identified problems associated with plant
Enclosure
    modifications were entered into the licensees corrective action program with the
9
    appropriate significance characterization, and that corrective actions were appropriate
Further, the inspectors verified that identified problems associated with plant
    and implemented as scheduled.
modifications were entered into the licensees corrective action program with the
b. Findings
appropriate significance characterization, and that corrective actions were appropriate
    No findings of significance were identified.
and implemented as scheduled.
1R19 Post Maintenance Testing (71111.19)
  b.
a. Inspection Scope
Findings
    The inspectors observed portions of post maintenance testing and reviewed
No findings of significance were identified.
    documented testing activities to verify that the tests were adequately performed for the
1R19
    following three activities:
Post Maintenance Testing (71111.19)
    C       Service Water Pump P-7C repack
  a.
    C       Emergency Diesel Generator 1-2 maintenance outage
Inspection Scope
    C       Low Pressure Safety Injection Pump P-67B breaker 152-111 replacement
The inspectors observed portions of post maintenance testing and reviewed
    The inspectors verified that applicable testing prerequisites were met prior to the start of
documented testing activities to verify that the tests were adequately performed for the
    the tests and that the effect of testing on plant conditions was adequately addressed by
following three activities:
    the control room operators.
C
    The inspectors also reviewed post maintenance testing criteria to verify that the test
Service Water Pump P-7C repack
    criteria and acceptance criteria were appropriate for the scope of work performed;
C
    reviewed completed tests and associated procedures to verify that the tests adequately
Emergency Diesel Generator 1-2 maintenance outage
    verified system operability; and reviewed documented test data to verify that the data
C
    was complete and that the equipment met the testing acceptance criteria.
Low Pressure Safety Injection Pump P-67B breaker 152-111 replacement
    Further, the inspectors reviewed condition reports to verify that post maintenance testing
The inspectors verified that applicable testing prerequisites were met prior to the start of
    problems were entered into the corrective action program with the appropriate
the tests and that the effect of testing on plant conditions was adequately addressed by
    significance characterization.
the control room operators.
b. Findings
The inspectors also reviewed post maintenance testing criteria to verify that the test
    No findings of significance were identified.
criteria and acceptance criteria were appropriate for the scope of work performed;
1R22 Surveillance Testing (71111.22)
reviewed completed tests and associated procedures to verify that the tests adequately
a. Inspection Scope
verified system operability; and reviewed documented test data to verify that the data
    The inspectors reviewed three surveillance testing activities conducted on the following
was complete and that the equipment met the testing acceptance criteria.
    risk-significant plant equipment:
Further, the inspectors reviewed condition reports to verify that post maintenance testing
    C       Safety Injection Initiation Circuitry
problems were entered into the corrective action program with the appropriate
    C       Control Room Heating, Ventilation and Air Conditioning System
significance characterization.
    C       Service Water Pump P-7A
  b.
                                                  9                                  Enclosure
Findings
No findings of significance were identified.
1R22
Surveillance Testing (71111.22)
  a.
Inspection Scope
The inspectors reviewed three surveillance testing activities conducted on the following
risk-significant plant equipment:
C
Safety Injection Initiation Circuitry
C
Control Room Heating, Ventilation and Air Conditioning System
C
Service Water Pump P-7A


    The inspectors observed portions of the testing to verify that the testing was conducted
Enclosure
    in accordance with prescribed procedures. The inspectors also reviewed the
10
    documented test data for the Technical Specification Surveillance Test procedures and
The inspectors observed portions of the testing to verify that the testing was conducted
    the associated basis documents to verify that testing acceptance criteria were satisfied.
in accordance with prescribed procedures. The inspectors also reviewed the
    In addition, the inspectors reviewed applicable portions of Technical Specifications, the
documented test data for the Technical Specification Surveillance Test procedures and
    Updated Final Safety Analysis Report, and design basis documents to verify that the
the associated basis documents to verify that testing acceptance criteria were satisfied.
    surveillance tests adequately demonstrated that system components could perform
In addition, the inspectors reviewed applicable portions of Technical Specifications, the
    required safety functions.
Updated Final Safety Analysis Report, and design basis documents to verify that the
    Further, the inspectors reviewed selected condition reports regarding surveillance
surveillance tests adequately demonstrated that system components could perform
    testing activities to verify that the identified problems were entered into the licensees
required safety functions.
    corrective action program with the appropriate significance characterization and that the
Further, the inspectors reviewed selected condition reports regarding surveillance
    planned and completed corrective actions were appropriate.
testing activities to verify that the identified problems were entered into the licensees
   b. Findings
corrective action program with the appropriate significance characterization and that the
    No findings of significance were identified.
planned and completed corrective actions were appropriate.
   b.
Findings
No findings of significance were identified.
1REP Equipment Availability, Reliability and Functional Capability (71111.EP)
1REP Equipment Availability, Reliability and Functional Capability (71111.EP)
.1   Quarterly Maintenance Effectiveness Reviews
.1
   a. Inspection Scope
Quarterly Maintenance Effectiveness Reviews  
    The inspectors conducted three maintenance effectiveness reviews for the following:
   a.
    C       Containment Spray Pump P-54C
Inspection Scope
    C       2400 Volt and 4160 Volt Station Power Systems
The inspectors conducted three maintenance effectiveness reviews for the following:
    C       High Pressure Safety Injection Pump Subcooling Valve CV-3070
C
    The inspectors reviewed the licensee's implementation of the maintenance rule
Containment Spray Pump P-54C
    requirements to verify that component and equipment failures were identified and
C
    appropriately dispositioned. The inspectors also verified that select systems and
2400 Volt and 4160 Volt Station Power Systems
    components were properly categorized and classified as (a)(1) or (a)(2) in accordance
C
    with 10 CFR 50.65.
High Pressure Safety Injection Pump Subcooling Valve CV-3070
    The inspectors reviewed the licensees maintenance rule performance indicators to
The inspectors reviewed the licensee's implementation of the maintenance rule
    verify that the system status had been appropriately categorized in accordance with the
requirements to verify that component and equipment failures were identified and
    maintenance rule program; reviewed work order histories and selected condition reports
appropriately dispositioned. The inspectors also verified that select systems and
    written against the system over the last 2 years to verify that maintenance and identified
components were properly categorized and classified as (a)(1) or (a)(2) in accordance
    problems had been appropriately addressed; and reviewed completed work orders to
with 10 CFR 50.65.
    determine if there was an adverse trend in system performance that could be attributed
The inspectors reviewed the licensees maintenance rule performance indicators to
    to inappropriate work practices and to determine if there were any common cause
verify that the system status had been appropriately categorized in accordance with the
    issues that had not been addressed. Additionally, the inspectors reviewed the
maintenance rule program; reviewed work order histories and selected condition reports
    licensees performance criteria to verify that the criteria adequately monitored equipment
written against the system over the last 2 years to verify that maintenance and identified
    performance.
problems had been appropriately addressed; and reviewed completed work orders to
                                                  10                                    Enclosure
determine if there was an adverse trend in system performance that could be attributed
to inappropriate work practices and to determine if there were any common cause
issues that had not been addressed. Additionally, the inspectors reviewed the
licensees performance criteria to verify that the criteria adequately monitored equipment
performance.


      In addition, the inspectors reviewed selected condition reports and associated
Enclosure
      maintenance rule evaluations to verify that identified problems were appropriately
11
      characterized and dispositioned in accordance with the licensees maintenance rule
In addition, the inspectors reviewed selected condition reports and associated
      program. The inspectors also verified that planned corrective actions were appropriate
maintenance rule evaluations to verify that identified problems were appropriately
      and had been implemented as scheduled.
characterized and dispositioned in accordance with the licensees maintenance rule
b.   Findings
program. The inspectors also verified that planned corrective actions were appropriate
  1. Containment Spray Pump P-54C
and had been implemented as scheduled.
      Introduction
  b.
      The inspectors identified a finding of very low safety significance (Green) and an
Findings
      associated Non-Cited Violation of 10 CFR 50, Appendix B, Criterion V, Instructions,
    1.
      Procedures, and Drawings, when the inboard motor bearing on Containment Spray
Containment Spray Pump P-54C
      Pump P-54C failed on August 21, 2003.
Introduction
      Description
The inspectors identified a finding of very low safety significance (Green) and an
      During a planned breaker replacement for Containment Spray Pump P-54C, licensee
associated Non-Cited Violation of 10 CFR 50, Appendix B, Criterion V, Instructions,
      personnel also replaced the inboard motor bearing oil. An operator performed the motor
Procedures, and Drawings, when the inboard motor bearing on Containment Spray
      bearing oil replacement in accordance with the applicable work instruction on August 21,
Pump P-54C failed on August 21, 2003.
      2003. After the oil was replaced, the operator noticed that the drain plug to the bearing
Description
      housing was set too far into the housing. Therefore, the operator requested and
During a planned breaker replacement for Containment Spray Pump P-54C, licensee
      obtained permission to replace the drain plug. After the new drain plug was installed,
personnel also replaced the inboard motor bearing oil. An operator performed the motor
      the operator added oil to the bearing housing through the inboard motor bearing oiler to
bearing oil replacement in accordance with the applicable work instruction on August 21,
      replace the oil that was drained when the drain plug was removed.
2003. After the oil was replaced, the operator noticed that the drain plug to the bearing
      However, during post maintenance testing following Containment Spray Pump P-54C
housing was set too far into the housing. Therefore, the operator requested and
      breaker replacement, operators observed smoke from the inboard motor bearing area
obtained permission to replace the drain plug. After the new drain plug was installed,
      and heard abnormal metallic noises. Therefore, the operators secured Containment
the operator added oil to the bearing housing through the inboard motor bearing oiler to
      Spray Pump P-54C to investigate a potentially failed motor bearing. During the
replace the oil that was drained when the drain plug was removed.
      investigation, licensee personnel determined that the oil level in the motor bearing
However, during post maintenance testing following Containment Spray Pump P-54C
      housing was below the slinger ring and that the inboard motor bearing had failed due to
breaker replacement, operators observed smoke from the inboard motor bearing area
      a lack of lubrication. After further review, licensee personnel identified that the vent hole
and heard abnormal metallic noises. Therefore, the operators secured Containment
      on the oiler for the inboard motor bearing on Containment Spray Pump P-54C was
Spray Pump P-54C to investigate a potentially failed motor bearing. During the
      covered with paint. Licensee personnel subsequently determined that the motor for
investigation, licensee personnel determined that the oil level in the motor bearing
      Containment Spray Pump P-54C was painted in June 2002 under a general work order
housing was below the slinger ring and that the inboard motor bearing had failed due to
      for miscellaneous painting.
a lack of lubrication. After further review, licensee personnel identified that the vent hole
      Through the root cause evaluation, licensee personnel determined that the plugged vent
on the oiler for the inboard motor bearing on Containment Spray Pump P-54C was
      caused the oiler to become air bound and unable to adequately add oil to the bearing
covered with paint. Licensee personnel subsequently determined that the motor for
      housing when the level decreased. Licensee personnel also determined that when the
Containment Spray Pump P-54C was painted in June 2002 under a general work order
      drain plug was replaced, enough oil was lost to uncover the bearing; however, the
for miscellaneous painting.
      plugged vent on the oiler resulted in an erroneous level indication in the oiler for the
Through the root cause evaluation, licensee personnel determined that the plugged vent
      bearing housing. Consequently, the operator did not add enough oil through the oiler to
caused the oiler to become air bound and unable to adequately add oil to the bearing
      the bearing housing after the drain plug was replaced. As a result, the inboard motor
housing when the level decreased. Licensee personnel also determined that when the
      bearing was inadequately lubricated which caused the bearing to fail when Containment
drain plug was replaced, enough oil was lost to uncover the bearing; however, the
      Spray Pump P-54C was started.
plugged vent on the oiler resulted in an erroneous level indication in the oiler for the
                                                11                                      Enclosure
bearing housing. Consequently, the operator did not add enough oil through the oiler to
the bearing housing after the drain plug was replaced. As a result, the inboard motor
bearing was inadequately lubricated which caused the bearing to fail when Containment
Spray Pump P-54C was started.


Enclosure
12
Analysis
Analysis
The inspectors determined that painting over the vent hole on the Containment Spray
The inspectors determined that painting over the vent hole on the Containment Spray
Pump P-54C inboard motor bearing oiler was a licensee performance deficiency which
Pump P-54C inboard motor bearing oiler was a licensee performance deficiency which
warranted a significance evaluation. The inspectors did not identify any examples of
warranted a significance evaluation. The inspectors did not identify any examples of
minor issues in Inspection Manual Chapter (IMC) 0612, Power Reactor Inspection
minor issues in Inspection Manual Chapter (IMC) 0612, Power Reactor Inspection
Reports, Appendix E, Examples of Minor Issues that appropriately described this
Reports, Appendix E, Examples of Minor Issues that appropriately described this
Line 525: Line 635:
The inspectors determined that the finding was more than minor in accordance with
The inspectors determined that the finding was more than minor in accordance with
IMC 0612, Appendix B, Issue Disposition Screening because if left uncorrected, the
IMC 0612, Appendix B, Issue Disposition Screening because if left uncorrected, the
issue could become a more significant safety concern. Specifically, the painted vent
issue could become a more significant safety concern. Specifically, the painted vent
hole on the bearing oiler resulted in erroneous oil level indication and prevented the oiler
hole on the bearing oiler resulted in erroneous oil level indication and prevented the oiler
from adding oil to the bearing housing when the level decreased. Consequently, an
from adding oil to the bearing housing when the level decreased. Consequently, an
inadequately lubricated bearing would not be detected until the bearing failed.
inadequately lubricated bearing would not be detected until the bearing failed.
The inspectors also determined that the finding could be evaluated using IMC 0609,
The inspectors also determined that the finding could be evaluated using IMC 0609,
Significance Determination Process, (SDP) because the finding was associated with
Significance Determination Process, (SDP) because the finding was associated with
the integrity of reactor containment. Using IMC 0609, Appendix A, SDP Phase 1
the integrity of reactor containment. Using IMC 0609, Appendix A, SDP Phase 1
Screening Worksheet for IE [Initiating Events], MS [Mitigating Systems], and B [Barrier
Screening Worksheet for IE [Initiating Events], MS [Mitigating Systems], and B [Barrier
Integrity] Cornerstones, the inspectors determined that the Barrier Integrity cornerstone
Integrity] Cornerstones, the inspectors determined that the Barrier Integrity cornerstone
Line 547: Line 657:
part, that activities affecting quality shall be prescribed by documented instructions of a
part, that activities affecting quality shall be prescribed by documented instructions of a
type appropriate to the circumstances and shall be accomplished in accordance with
type appropriate to the circumstances and shall be accomplished in accordance with
these instructions. Contrary to this requirement, painting of Containment Spray Pump
these instructions. Contrary to this requirement, painting of Containment Spray Pump
P-54C in June 2002, an activity affecting quality, did not have written instructions
P-54C in June 2002, an activity affecting quality, did not have written instructions
appropriate to the circumstances. Consequently, the vent hole on the oiler was plugged
appropriate to the circumstances. Consequently, the vent hole on the oiler was plugged
with paint which caused an erroneous oil level indication and the subsequent motor
with paint which caused an erroneous oil level indication and the subsequent motor
bearing failure due to an inadequately lubricated bearing on August 21, 2003. However,
bearing failure due to an inadequately lubricated bearing on August 21, 2003. However,
because this violation was associated with a finding of very low safety significance and
because this violation was associated with a finding of very low safety significance and
because the finding was entered into the licensees corrective action program, this
because the finding was entered into the licensees corrective action program, this
violation is being treated as a Non-Cited Violation, consistent with Section VI.A of the
violation is being treated as a Non-Cited Violation, consistent with Section VI.A of the
NRC Enforcement Policy (NCV 05000255/2003008-01). This issue was entered into the
NRC Enforcement Policy (NCV 05000255/2003008-01). This issue was entered into the
licensees corrective action program as CAP037180.
licensees corrective action program as CAP037180.
                                            12                                    Enclosure


  As part of the licensees corrective actions, licensee personnel cleared the vent hole on
Enclosure
  the inboard motor bearing oiler for Containment Spray Pump P-54C and verified the
13
  oiler vent holes on other safety-related pump motors were not painted over. In addition,
As part of the licensees corrective actions, licensee personnel cleared the vent hole on
  the inboard motor bearing on Containment Spray Pump P-54C was replaced, and the
the inboard motor bearing oiler for Containment Spray Pump P-54C and verified the
  pump was subsequently tested satisfactorily.
oiler vent holes on other safety-related pump motors were not painted over. In addition,
2. High Pressure Safety Injection Pump P-66B Subcooling Valve CV-3070
the inboard motor bearing on Containment Spray Pump P-54C was replaced, and the
  Introduction
pump was subsequently tested satisfactorily.
  The inspectors identified a finding of very low safety significance (Green) and an
    2.
  associated Non-Cited Violation of 10 CFR 50, Appendix B, Criterion V, Instructions,
High Pressure Safety Injection Pump P-66B Subcooling Valve CV-3070
  Procedures, and Drawings, when High Pressure Safety Injection Pump P-66B
Introduction
  Subcooling Valve CV-3070 failed to stroke open during surveillance testing.
The inspectors identified a finding of very low safety significance (Green) and an
  Description
associated Non-Cited Violation of 10 CFR 50, Appendix B, Criterion V, Instructions,
  On August 10, 2003, during surveillance testing, air operated High Pressure Safety
Procedures, and Drawings, when High Pressure Safety Injection Pump P-66B
  Injection Pump P-66B Subcooling Control Valve CV-3070 failed to stroke open with the
Subcooling Valve CV-3070 failed to stroke open during surveillance testing.
  control switch held in the open position. Control Valve CV-3070 was required to open in
Description
  less than 2 seconds and had a safety-related support function for High Pressure Safety
On August 10, 2003, during surveillance testing, air operated High Pressure Safety
  Injection Pump P-66B during long term core cooling.
Injection Pump P-66B Subcooling Control Valve CV-3070 failed to stroke open with the
  During troubleshooting activities on August 11, 2003, licensee personnel discovered that
control switch held in the open position. Control Valve CV-3070 was required to open in
  a flow control valve in the operating air system was installed backwards which caused
less than 2 seconds and had a safety-related support function for High Pressure Safety
  CV-3070 to close faster than intended. The faster closing rate provided higher than
Injection Pump P-66B during long term core cooling.
  intended seating forces when the valve was closed. After further investigation, licensee
During troubleshooting activities on August 11, 2003, licensee personnel discovered that
  personnel concluded that the flow control valve was most likely installed backwards
a flow control valve in the operating air system was installed backwards which caused
  when the valve actuator was rebuilt in July 1995 through Work Order 24412938. This
CV-3070 to close faster than intended. The faster closing rate provided higher than
  conclusion was based on: (1) there were no additional work orders for the valve
intended seating forces when the valve was closed. After further investigation, licensee
  actuator since the flow control valve was initially installed in January 1986; (2) the
personnel concluded that the flow control valve was most likely installed backwards
  closing time for CV-3070 after the flow control valve was initially installed in 1986 was
when the valve actuator was rebuilt in July 1995 through Work Order 24412938. This
  20 seconds; (3) one-time stem thrust data taken in February 1998 indicated that
conclusion was based on: (1) there were no additional work orders for the valve
  CV-3070 closed in 0.8 seconds; and (4) the as-found closing time on August 11 for
actuator since the flow control valve was initially installed in January 1986; (2) the
  CV-3070 was 1.2 seconds. Because CV-3070 did not have a safety function to close,
closing time for CV-3070 after the flow control valve was initially installed in 1986 was
  the valve was not timed in the closed direction during quarterly testing. Therefore, no
20 seconds; (3) one-time stem thrust data taken in February 1998 indicated that
  additional closing time data was available.
CV-3070 closed in 0.8 seconds; and (4) the as-found closing time on August 11 for
  Consequently, licensee personnel concluded that the seating force on the valve disc
CV-3070 was 1.2 seconds. Because CV-3070 did not have a safety function to close,
  from the faster than intended closing rate prevented the valve from opening during the
the valve was not timed in the closed direction during quarterly testing. Therefore, no
  surveillance test. However, licensee personnel determined that the faster closing rate
additional closing time data was available.
  was not conclusively the cause since the valve stroked open successfully each time it
Consequently, licensee personnel concluded that the seating force on the valve disc
  had been tested since the flow control valve was installed backwards in 1995. Also,
from the faster than intended closing rate prevented the valve from opening during the
  there were no work activities performed on CV-3070 after the last successful
surveillance test. However, licensee personnel determined that the faster closing rate
  surveillance test in May 2003. In addition, on August 11, 2003, licensee personnel were
was not conclusively the cause since the valve stroked open successfully each time it
  able to open CV-3070 using minor mechanical agitation during troubleshooting activities
had been tested since the flow control valve was installed backwards in 1995. Also,
  and the valve was then stroked open successfully several times after the valve was
there were no work activities performed on CV-3070 after the last successful
  closed with the same fast closing rate.
surveillance test in May 2003. In addition, on August 11, 2003, licensee personnel were
                                            13                                        Enclosure
able to open CV-3070 using minor mechanical agitation during troubleshooting activities
and the valve was then stroked open successfully several times after the valve was
closed with the same fast closing rate.


Enclosure
14
Licensee personnel subsequently repositioned the flow control valve in the proper
Licensee personnel subsequently repositioned the flow control valve in the proper
direction and the as-left closing time for CV-3070 was 5.0 seconds. On August 12,
direction and the as-left closing time for CV-3070 was 5.0 seconds. On August 12,
2003, CV-3070 opened within 2 seconds when tested and was declared operable.
2003, CV-3070 opened within 2 seconds when tested and was declared operable.  
However, because licensee personnel could not definitively conclude that the short
However, because licensee personnel could not definitively conclude that the short
closing time caused CV-3070 to not open on August 10, Work Order 24323139 was
closing time caused CV-3070 to not open on August 10, Work Order 24323139 was
generated to disassemble and inspect CV-3070 at the earliest opportunity. In addition,
generated to disassemble and inspect CV-3070 at the earliest opportunity. In addition,
to provide confidence that CV-3070 could open as required, a mid-surveillance cycle
to provide confidence that CV-3070 could open as required, a mid-surveillance cycle
stroke test was performed on September 9, 2003, successfully.
stroke test was performed on September 9, 2003, successfully.
Line 614: Line 727:
was a licensee performance deficiency warranting a significance evaluation in
was a licensee performance deficiency warranting a significance evaluation in
accordance with IMC 0612, Power Reactor Inspection Reports, Appendix B, Issue
accordance with IMC 0612, Power Reactor Inspection Reports, Appendix B, Issue
Disposition Screening. The inspectors did not identify any examples of minor issues in
Disposition Screening. The inspectors did not identify any examples of minor issues in
IMC 0612, Appendix E, Examples of Minor Issues, that appropriately described this
IMC 0612, Appendix E, Examples of Minor Issues, that appropriately described this
finding.
finding.
The inspectors concluded that the finding was more than minor because it was
The inspectors concluded that the finding was more than minor because it was
associated with the Procedure Quality attribute of the Mitigating Systems cornerstone
associated with the Procedure Quality attribute of the Mitigating Systems cornerstone
Line 624: Line 737:
The inspectors determined that the finding could be evaluated using IMC 0609,
The inspectors determined that the finding could be evaluated using IMC 0609,
Significance Determination Process, (SDP) because the finding was associated with
Significance Determination Process, (SDP) because the finding was associated with
the availability of a mitigating system. Using IMC 0609, Appendix A, SDP Phase 1
the availability of a mitigating system. Using IMC 0609, Appendix A, SDP Phase 1
Screening Worksheet for IE [Initiating Events], MS [Mitigating Systems], and B [Barrier
Screening Worksheet for IE [Initiating Events], MS [Mitigating Systems], and B [Barrier
Integrity] Cornerstones, the inspectors determined that the Mitigating Systems
Integrity] Cornerstones, the inspectors determined that the Mitigating Systems
Line 639: Line 752:
in part, that activities affecting quality shall be prescribed by documented instructions of
in part, that activities affecting quality shall be prescribed by documented instructions of
a type appropriate to the circumstances and shall be accomplished in accordance with
a type appropriate to the circumstances and shall be accomplished in accordance with
those instructions. Contrary to this requirement, the work instructions for the
those instructions. Contrary to this requirement, the work instructions for the
maintenance performed in July 1995 to rebuild the actuator for CV-3070, an activity
maintenance performed in July 1995 to rebuild the actuator for CV-3070, an activity
affecting quality, were not of a type appropriate to the circumstances. Specifically, the
affecting quality, were not of a type appropriate to the circumstances. Specifically, the
work instructions did not contain adequate guidance to ensure that the flow control valve
work instructions did not contain adequate guidance to ensure that the flow control valve
                                            14                                      Enclosure


    was installed with the correct orientation in the operating air system for the valve
Enclosure
    actuator.
15
    Consequently, the flow control valve was installed backwards which resulted in faster
was installed with the correct orientation in the operating air system for the valve
    than intended closing times which contributed to valve CV-3070 failing to stroke open as
actuator.
    required on August 10, 2003. However, because this violation was associated with a
Consequently, the flow control valve was installed backwards which resulted in faster
    finding of very low safety significance and because the finding was entered into the
than intended closing times which contributed to valve CV-3070 failing to stroke open as
    licensees corrective action program, this violation is being treated as a Non-Cited
required on August 10, 2003. However, because this violation was associated with a
    Violation, consistent with Section VI.A of the NRC Enforcement Policy
finding of very low safety significance and because the finding was entered into the
    (NCV 05000255/2003008-02). This issue was entered into the licensees corrective
licensees corrective action program, this violation is being treated as a Non-Cited
    action program as CAP037030.
Violation, consistent with Section VI.A of the NRC Enforcement Policy
    Corrective actions to address the finding included reinstalling the flow control valve in
(NCV 05000255/2003008-02). This issue was entered into the licensees corrective
    the proper position, testing CV-3070 during a mid-surveillance cycle stroke test, and
action program as CAP037030.  
    generating a work order to inspect the valve internals at the earliest opportunity.
Corrective actions to address the finding included reinstalling the flow control valve in
.2   Biennial Assessment of Maintenance Rule Periodic Evaluations
the proper position, testing CV-3070 during a mid-surveillance cycle stroke test, and
   a. Inspection Scope
generating a work order to inspect the valve internals at the earliest opportunity.
    The inspectors reviewed the Maintenance Rule Periodic Refueling Assessment Report
.2
    for the period of August 1, 2000, to July 31, 2002. The inspectors verified that: (1) the
Biennial Assessment of Maintenance Rule Periodic Evaluations
    periodic evaluation had been completed as required by 10 CFR 50.65(a)(3);
   a.
    (2) maintenance rule (a)(1) goals and (a)(2) performance criteria were reviewed by the
Inspection Scope
    licensee; (3) industry operating experience was taken into account when appropriate;
The inspectors reviewed the Maintenance Rule Periodic Refueling Assessment Report
    (4) balancing of availability and reliability was reviewed; and (5) appropriate adjustments
for the period of August 1, 2000, to July 31, 2002. The inspectors verified that: (1) the
    were made as a result of the periodic evaluation.
periodic evaluation had been completed as required by 10 CFR 50.65(a)(3);
    The inspectors also reviewed the following four systems to assess how performance
(2) maintenance rule (a)(1) goals and (a)(2) performance criteria were reviewed by the
    problems were addressed within the maintenance rule program:
licensee; (3) industry operating experience was taken into account when appropriate;
    C       Concentrated Boric Acid System
(4) balancing of availability and reliability was reviewed; and (5) appropriate adjustments
    C       Control Room Heating, Ventilation, and Air Conditioning (HVAC) System
were made as a result of the periodic evaluation.
    C       High Pressure Air System
The inspectors also reviewed the following four systems to assess how performance
    C       Fire Protection System
problems were addressed within the maintenance rule program:
    As applicable to the four systems, the inspectors verified that: (1) maintenance rule
    (a)(1) goals and activities were reviewed and adjusted as necessary; (2) corrective
C
    actions for (a)(1) activities were appropriate; (3) maintenance rule (a)(2) performance
Concentrated Boric Acid System
    criteria was appropriate and met; (4) evaluations for placing the system in maintenance
C
    rule (a)(1) were completed when performance criteria was not met; (5) equipment
Control Room Heating, Ventilation, and Air Conditioning (HVAC) System
    failures were evaluated and appropriately dispositioned as functional failures,
C
    maintenance preventable functional failures or repeat maintenance preventable
High Pressure Air System
    functional failures; and (6) preventive maintenance activities were adjusted as
C
    necessary.
Fire Protection System
    The inspectors also reviewed a sample of condition reports to verify that the significance
As applicable to the four systems, the inspectors verified that: (1) maintenance rule
    of identified problems was appropriately characterized. For select condition reports, the
(a)(1) goals and activities were reviewed and adjusted as necessary; (2) corrective
                                                15                                    Enclosure
actions for (a)(1) activities were appropriate; (3) maintenance rule (a)(2) performance
criteria was appropriate and met; (4) evaluations for placing the system in maintenance
rule (a)(1) were completed when performance criteria was not met; (5) equipment
failures were evaluated and appropriately dispositioned as functional failures,
maintenance preventable functional failures or repeat maintenance preventable
functional failures; and (6) preventive maintenance activities were adjusted as
necessary.
The inspectors also reviewed a sample of condition reports to verify that the significance
of identified problems was appropriately characterized. For select condition reports, the


    inspectors verified that the corrective actions were appropriate and implemented in a
Enclosure
    timely manner commensurate with the significance of the problem.
16
   b. Findings
inspectors verified that the corrective actions were appropriate and implemented in a
    No findings of significance were identified.
timely manner commensurate with the significance of the problem.
.3   Operability Evaluations
   b.
   a. Inspection Scope
Findings
    The inspectors reviewed three operability assessments as documented in the
No findings of significance were identified.
    associated condition reports for the following risk significant plant equipment:
.3
    C       Emergency Core Cooling System
Operability Evaluations  
    C       Steam Generator Low Pressure Bypass signal
   a.
    C       High Pressure Safety Injection Pump P-66B Subcooling Valve CV-3070
Inspection Scope
    The inspectors interviewed the cognizant engineers and reviewed the supporting
The inspectors reviewed three operability assessments as documented in the
    documents to assess the adequacy of the operability assessments for the current plant
associated condition reports for the following risk significant plant equipment:
    mode. The inspectors also reviewed the applicable sections of the Technical
C
    Specifications, Updated Final Safety Analysis Report, and design basis documents to
Emergency Core Cooling System
    verify that the operability assessments were technically adequate and that the
C
    components remained available, such that no unrecognized increase in plant risk had
Steam Generator Low Pressure Bypass signal
    occurred.
C
    In addition, the inspectors reviewed selected condition reports regarding operability
High Pressure Safety Injection Pump P-66B Subcooling Valve CV-3070
    determinations to verify that the identified problems were entered into the licensees
The inspectors interviewed the cognizant engineers and reviewed the supporting
    corrective action program with the appropriate significance characterization and that
documents to assess the adequacy of the operability assessments for the current plant
    planned and completed corrective actions were commensurate with the significance.
mode. The inspectors also reviewed the applicable sections of the Technical
   b. Findings
Specifications, Updated Final Safety Analysis Report, and design basis documents to
    No findings of significance were identified.
verify that the operability assessments were technically adequate and that the
.4   Operator Workarounds (OWAs)
components remained available, such that no unrecognized increase in plant risk had
   a. Inspection Scope
occurred.
    The Inspectors reviewed the following three risk significant operator workarounds:
In addition, the inspectors reviewed selected condition reports regarding operability
    *       Control Room Indicator Light Failure
determinations to verify that the identified problems were entered into the licensees
    *       Warm Water Recirculation Pump P-5 Vacuum Piping System
corrective action program with the appropriate significance characterization and that
    *       Start-up Transformer 1-2 Load
planned and completed corrective actions were commensurate with the significance.
    The inspectors evaluated whether the workarounds would adversely affect the operators
   b.
    ability to implement abnormal and emergency operating procedures. The inspectors
Findings
    reviewed the planned actions to correct the workarounds to verify that the priority to
No findings of significance were identified.  
                                              16                                    Enclosure
.4
Operator Workarounds (OWAs)
   a.
Inspection Scope
The Inspectors reviewed the following three risk significant operator workarounds:
*
Control Room Indicator Light Failure
*
Warm Water Recirculation Pump P-5 Vacuum Piping System
*
Start-up Transformer 1-2 Load
The inspectors evaluated whether the workarounds would adversely affect the operators
ability to implement abnormal and emergency operating procedures. The inspectors
reviewed the planned actions to correct the workarounds to verify that the priority to


    resolve the deficiencies was reasonable when considering the potential impact on plant
Enclosure
    risk and safety.
17
    The inspectors also completed an aggregate assessment of the operator workarounds,
resolve the deficiencies was reasonable when considering the potential impact on plant
    operator challenges, and control room deficiencies that were previously identified by
risk and safety.
    licensee personnel. The inspectors verified that the cumulative effects did not create
The inspectors also completed an aggregate assessment of the operator workarounds,
    significant adverse consequences regarding the reliability, availability and operation of
operator challenges, and control room deficiencies that were previously identified by
    risk significant systems. The inspectors also verified that the cumulative effects did not
licensee personnel. The inspectors verified that the cumulative effects did not create
    adversely impact the operators ability to implement abnormal and emergency response
significant adverse consequences regarding the reliability, availability and operation of
    procedures in a timely manner when responding to plant transients and accidents.
risk significant systems. The inspectors also verified that the cumulative effects did not
   b. Findings
adversely impact the operators ability to implement abnormal and emergency response
    No findings of significance were identified.
procedures in a timely manner when responding to plant transients and accidents.
.5   Temporary Plant Modifications
   b.
   .a Inspection Scope
Findings
    The inspectors reviewed the modification documentation and the associated
No findings of significance were identified.
    10 CFR 50.59 evaluation for temporary modification TM-2000-024. This temporary
.5
    modification was developed to provide an alternate water supply that could be used, if
Temporary Plant Modifications
    necessary, to backwash the service water traveling screens. The inspectors verified
   .a
    that the temporary modification would not adversely impact other safety-related
Inspection Scope
    equipment and that testing activities for the temporary modification were adequate to
The inspectors reviewed the modification documentation and the associated
    ensure that the modification would function as intended.
10 CFR 50.59 evaluation for temporary modification TM-2000-024. This temporary
    The inspectors also verified that System Operating Procedure - 15, Attachment 11,
modification was developed to provide an alternate water supply that could be used, if
    Alternate Water Supply To Clean Traveling Screens, provided adequate guidance to
necessary, to backwash the service water traveling screens. The inspectors verified
    the operators for using the alternate water supply.
that the temporary modification would not adversely impact other safety-related
   b. Findings
equipment and that testing activities for the temporary modification were adequate to
    No findings of significance were identified.
ensure that the modification would function as intended.
1EP4 Emergency Action Level and Emergency Plan Changes (71114.04)
The inspectors also verified that System Operating Procedure - 15, Attachment 11,
   a. Inspection Scope
Alternate Water Supply To Clean Traveling Screens, provided adequate guidance to
    The inspectors reviewed Revisions 6, 7, and 8 of the Palisades Nuclear Plant Site
the operators for using the alternate water supply.
    Emergency Plan to determine if changes identified in these revisions reduced the plans
   b.
    effectiveness, pending on-site inspection of the implementation of these changes.
Findings
   b. Findings
No findings of significance were identified.
    The inspectors identified that the licensee had incorporated NUMARC/NESP-007,
1EP4
    Methodology for Development of Emergency Action Levels, (NUMARC-007)
Emergency Action Level and Emergency Plan Changes (71114.04)
    emergency action levels (EALs) into its approved standardized classification scheme
   a.
    which were based on NUREG-0654/FEMA-REP-1, Criteria for Preparation and
Inspection Scope
                                              17                                      Enclosure
The inspectors reviewed Revisions 6, 7, and 8 of the Palisades Nuclear Plant Site
Emergency Plan to determine if changes identified in these revisions reduced the plans
effectiveness, pending on-site inspection of the implementation of these changes.
   b.
Findings
The inspectors identified that the licensee had incorporated NUMARC/NESP-007,
Methodology for Development of Emergency Action Levels, (NUMARC-007)
emergency action levels (EALs) into its approved standardized classification scheme
which were based on NUREG-0654/FEMA-REP-1, Criteria for Preparation and


Enclosure
18
Evaluation of Radiological Emergency Response Plans and Preparedness in Support of
Evaluation of Radiological Emergency Response Plans and Preparedness in Support of
Nuclear Power Plants, (NUREG-0654). This was identified as an Unresolved Item
Nuclear Power Plants, (NUREG-0654). This was identified as an Unresolved Item
(URI) pending determination whether any violation of NRC requirements occurred, and a
(URI) pending determination whether any violation of NRC requirements occurred, and a
determination as to the significance, if any violation is determined to have occurred.
determination as to the significance, if any violation is determined to have occurred.
During the in-office review of the licensees emergency plan changes, it was identified
During the in-office review of the licensees emergency plan changes, it was identified
that the revisions to the emergency plan deleted EALs and replaced certain of the
that the revisions to the emergency plan deleted EALs and replaced certain of the
deleted EALs with NUMARC-007 EALs. Additional information provided by the licensee
deleted EALs with NUMARC-007 EALs. Additional information provided by the licensee
indicated these changes resulted from a condition report initiated when the licensees
indicated these changes resulted from a condition report initiated when the licensees
shift supervisors were making different classification decisions for the same incident
shift supervisors were making different classification decisions for the same incident
presented on the simulator. To make the classification implementing procedure more
presented on the simulator. To make the classification implementing procedure more
user friendly the licensee incorporated certain NUMARC EALs. The licensee indicated
user friendly the licensee incorporated certain NUMARC EALs. The licensee indicated
in certain cases the incorporation of specific NUMARC-007 EALs allowed elimination of
in certain cases the incorporation of specific NUMARC-007 EALs allowed elimination of
NUREG-0654 EALs because the same information was covered in other parts of the
NUREG-0654 EALs because the same information was covered in other parts of the
Line 774: Line 917:
A brief listing of examples of emergency plan EALs that had been deleted and
A brief listing of examples of emergency plan EALs that had been deleted and
NUMARC-007 EALs added, included the following:
NUMARC-007 EALs added, included the following:
        Revision 6 of the emergency plan:
Revision 6 of the emergency plan:
        *       Table 4-2, page 36, Engineered Safety Features, the Unusual
*
                Event EAL for reactor protection system (RPS) failure was deleted and
Table 4-2, page 36, Engineered Safety Features, the Unusual
                inability to reach a required mode within Technical Specification limits
Event EAL for reactor protection system (RPS) failure was deleted and
                (NUMARC-007 #SU2) was added.
inability to reach a required mode within Technical Specification limits
        *       Table 4-2, page 36, Engineered Safety Features, the Alert EAL for
(NUMARC-007 #SU2) was added.
                complete loss of auxiliary feedwater system was deleted.
*
        *       Table 4-2, page 36, Engineered Safety Features, the Site Area
Table 4-2, page 36, Engineered Safety Features, the Alert EAL for
                Emergency EAL for transient requiring operation of shutdown
complete loss of auxiliary feedwater system was deleted.
                systems with failure to trip was deleted and failure of the RPS
*
                instrumentation to complete or initiate an automatic reactor scram
Table 4-2, page 36, Engineered Safety Features, the Site Area
                and a RPS setpoint has been exceeded and a manual scram was
Emergency EAL for transient requiring operation of shutdown
                not successful (NUMARC-007 #SS2) was added.
systems with failure to trip was deleted and failure of the RPS
        *       Table 4-2, page 36, Engineered Safety Features, the General
instrumentation to complete or initiate an automatic reactor scram
                Emergency EAL for transient requiring operation of shutdown system
and a RPS setpoint has been exceeded and a manual scram was
                with failure to trip which results in core damage or additional failure of
not successful (NUMARC-007 #SS2) was added.
                core cooling and makeup systems (NUREG 0654 #G-5.c) was deleted
*
                and failure of the RPS to complete an automatic scram and manual
Table 4-2, page 36, Engineered Safety Features, the General
                scram was not successful and there is indication of an extreme challenge
Emergency EAL for transient requiring operation of shutdown system
                to the ability to cool the core (NUMARC-007 #SG2) was added.
with failure to trip which results in core damage or additional failure of
        *       Table 4-2, page 36, Engineered Safety Features, the General
core cooling and makeup systems (NUREG 0654 #G-5.c) was deleted
                Emergency EAL for transient initiated by loss of feedwater and
and failure of the RPS to complete an automatic scram and manual
                condensate system followed by failure of auxiliary feedwater system for
scram was not successful and there is indication of an extreme challenge
                an extended period (NUREG 0654 #G-5.b) was deleted.
to the ability to cool the core (NUMARC-007 #SG2) was added.
                                            18                                      Enclosure
*
Table 4-2, page 36, Engineered Safety Features, the General
Emergency EAL for transient initiated by loss of feedwater and
condensate system followed by failure of auxiliary feedwater system for
an extended period (NUREG 0654 #G-5.b) was deleted.


    The inspectors identified that the intermingling of classification schemes deviated from
Enclosure
    Regulatory Guide 1.101, Revision 3, which states, in part, that licensees may use either
19
    NUREG-0654 or NUMARC-007 in their EAL scheme, but may not use portions of both
The inspectors identified that the intermingling of classification schemes deviated from
    methodologies. Regulatory Guide 1.101 also states that licensees who propose to
Regulatory Guide 1.101, Revision 3, which states, in part, that licensees may use either
    revise their currently approved EAL classification scheme using the NUMARC-007
NUREG-0654 or NUMARC-007 in their EAL scheme, but may not use portions of both
    method adhere to the requirements in Section IV.B of Appendix E to 10 CFR Part 50
methodologies. Regulatory Guide 1.101 also states that licensees who propose to
    which states, in part, that these emergency action levels shall be discussed and agreed
revise their currently approved EAL classification scheme using the NUMARC-007
    on by the applicant and State and local government authorities and approved by the
method adhere to the requirements in Section IV.B of Appendix E to 10 CFR Part 50
    NRC.
which states, in part, that these emergency action levels shall be discussed and agreed
    This issue is considered an URI pending further review by the NRC. In accordance with
on by the applicant and State and local government authorities and approved by the
    NRC Inspection Procedure 71114.04, Emergency Action Level and Emergency Plan
NRC.
    Changes, these changes potentially result in a reduction of emergency plan
This issue is considered an URI pending further review by the NRC. In accordance with
    effectiveness and will be referred to the Office of Nuclear Reactor Regulation for further
NRC Inspection Procedure 71114.04, Emergency Action Level and Emergency Plan
    review. Pending completion of these activities, the issue is considered an URI
Changes, these changes potentially result in a reduction of emergency plan
    (URI 05000255/2003008-03). The licensee has entered this issue into their corrective
effectiveness and will be referred to the Office of Nuclear Reactor Regulation for further
    action program as CAP 039195.
review. Pending completion of these activities, the issue is considered an URI
1EP6 Emergency Plan Drill Evaluation (71114.06)
(URI 05000255/2003008-03). The licensee has entered this issue into their corrective
a. Inspection Scope
action program as CAP 039195.
    The inspectors observed a simulator training session for one crew of licensed operators
1EP6
    on December 17, 2003, in which the Shift Manager was required to implement the
Emergency Plan Drill Evaluation (71114.06)
    emergency plan in response to simulated plant conditions. Licensee Emergency
  a.
    Preparedness personnel had pre-designated that the opportunities for the Shift Manager
Inspection Scope
    to classify the event and make required notifications would be evaluated and included in
The inspectors observed a simulator training session for one crew of licensed operators
    the Drill and Exercise Performance performance indicator data.
on December 17, 2003, in which the Shift Manager was required to implement the
    The inspectors verified that the Shift Manager classified the emergency condition and
emergency plan in response to simulated plant conditions. Licensee Emergency
    completed the required notifications to State and Local Police authorities in an accurate
Preparedness personnel had pre-designated that the opportunities for the Shift Manager
    and timely manner as required by the emergency plan implementing procedures. The
to classify the event and make required notifications would be evaluated and included in
    inspectors also reviewed the Emergency Preparedness Evaluators summary report to
the Drill and Exercise Performance performance indicator data.
    verify that the data included in the Drill and Exercise Performance performance indicator
The inspectors verified that the Shift Manager classified the emergency condition and
    was accurate.
completed the required notifications to State and Local Police authorities in an accurate
b. Findings
and timely manner as required by the emergency plan implementing procedures. The
    No findings of significance were identified.
inspectors also reviewed the Emergency Preparedness Evaluators summary report to
                                                19                                    Enclosure
verify that the data included in the Drill and Exercise Performance performance indicator
was accurate.
  b.
Findings
No findings of significance were identified.


2.   RADIATION SAFETY
Enclosure
    Cornerstone: Occupational Radiation Safety
20
2.
RADIATION SAFETY
Cornerstone: Occupational Radiation Safety
2OS3 Radiation Monitoring Instrumentation and Protective Equipment (71121.03)
2OS3 Radiation Monitoring Instrumentation and Protective Equipment (71121.03)
.1   Self-Contained Breathing Apparatus (SCBA) Maintenance
.1
   a. Inspection Scope
Self-Contained Breathing Apparatus (SCBA) Maintenance
    The inspectors reviewed the vital component maintenance records over the past 5 years
   a.
    for three SCBA units currently designated as ready for service. The inspectors also
Inspection Scope
    ensured that the required, periodic air cylinder hydrostatic testing was documented and
The inspectors reviewed the vital component maintenance records over the past 5 years
    up-to-date, and that the Department of Transportation required retest air cylinder
for three SCBA units currently designated as ready for service. The inspectors also
    markings were in place for these three units: OCR-42 (located in the Ops Conference
ensured that the required, periodic air cylinder hydrostatic testing was documented and
    Room by the Control Room Viewing Gallery); T625-47 (located along the east wall of the
up-to-date, and that the Department of Transportation required retest air cylinder
    Turbine Deck); and RPO-11 (located on the 611 foot elevation near the Radiation
markings were in place for these three units: OCR-42 (located in the Ops Conference
    Protection Offices). As the licensee did not itself conduct maintenance of vital
Room by the Control Room Viewing Gallery); T625-47 (located along the east wall of the
    components of SCBA units, the inspectors reviewed licensee and vendor maintenance
Turbine Deck); and RPO-11 (located on the 611 foot elevation near the Radiation
    procedures, including those for the low-pressure alarm and pressure-demand air
Protection Offices). As the licensee did not itself conduct maintenance of vital
    regulator, and the SCBA manufacturers recommended practices to determine if there
components of SCBA units, the inspectors reviewed licensee and vendor maintenance
    were inconsistencies between them.
procedures, including those for the low-pressure alarm and pressure-demand air
    These reviews represented one inspection sample.
regulator, and the SCBA manufacturers recommended practices to determine if there
   b. Findings
were inconsistencies between them.  
    No findings of significance were identified.
These reviews represented one inspection sample.
    Cornerstone: Public Radiation Safety
   b.
2PS1 Radioactive Gaseous And Liquid Effluent Treatment And Monitoring Systems
Findings
    (71122.01)
No findings of significance were identified.
.1   Inspection Planning
Cornerstone: Public Radiation Safety
   a. Inspection Scope
2PS1
    The inspectors reviewed the calendar years 2001 and 2002 Radiological Effluent
Radioactive Gaseous And Liquid Effluent Treatment And Monitoring Systems
    Release Reports to verify that the program was implemented as described in
(71122.01)
    Radiological Effluent Technical Specifications (RETS)/Offsite Dose Calculation Manual
.1
    (ODCM) and to determine if ODCM changes were made in accordance with Regulatory
Inspection Planning
    Guide 1.109 and NUREG-0133. The inspectors reviewed the Radiological Effluent
   a.
    Release Reports and ODCM, to determine if any changes to the design and/or
Inspection Scope
    operation of the radioactive waste systems changed the dose consequence to the
The inspectors reviewed the calendar years 2001 and 2002 Radiological Effluent
    public. The inspectors also reviewed technical and/or 10 CFR 50.59 evaluations
Release Reports to verify that the program was implemented as described in
    performed, when required, for any such modifications and determined whether
Radiological Effluent Technical Specifications (RETS)/Offsite Dose Calculation Manual
    radioactive liquid and gaseous effluent radiation monitor setpoint calculation
(ODCM) and to determine if ODCM changes were made in accordance with Regulatory
                                              20                                      Enclosure
Guide 1.109 and NUREG-0133. The inspectors reviewed the Radiological Effluent
Release Reports and ODCM, to determine if any changes to the design and/or
operation of the radioactive waste systems changed the dose consequence to the
public. The inspectors also reviewed technical and/or 10 CFR 50.59 evaluations
performed, when required, for any such modifications and determined whether
radioactive liquid and gaseous effluent radiation monitor setpoint calculation


    methodology changed since completion of the modifications. The inspectors
Enclosure
    determined if anomalous results reported in the current Radiological Effluent Release
21
    Report were adequately resolved.
methodology changed since completion of the modifications. The inspectors
    The inspectors reviewed RETS/ODCM to identify the effluent radiation monitoring
determined if anomalous results reported in the current Radiological Effluent Release
    systems and its flow measurement devices, effluent radiological occurrence
Report were adequately resolved.
    performance indicator incidents in preparation for onsite follow-up, and the Final Safety
The inspectors reviewed RETS/ODCM to identify the effluent radiation monitoring
    Analysis Report (FSAR) description of all radioactive waste systems.
systems and its flow measurement devices, effluent radiological occurrence
    These reviews represented one inspection sample.
performance indicator incidents in preparation for onsite follow-up, and the Final Safety
   b. Findings
Analysis Report (FSAR) description of all radioactive waste systems.
    No findings of significance were identified.
These reviews represented one inspection sample.
.2   Onsite Inspection - Walk-down of Effluent Control Systems, System/Program
   b.
    Modifications, Air Cleaning System Surveillances, and Instrument Calibrations
Findings
   a. Inspection Scope
No findings of significance were identified.
    The inspectors walked down the major components of the gaseous and liquid release
.2
    systems (e.g., radiation and flow monitors, demineralizers and filters, tanks, and
Onsite Inspection - Walk-down of Effluent Control Systems, System/Program
    vessels) to observe current system configuration with respect to the description in the
Modifications, Air Cleaning System Surveillances, and Instrument Calibrations
    FSAR, ongoing activities, and equipment material condition.
   a.
    The inspectors reviewed the licensees technical justification for changes made by the
Inspection Scope
    licensee to the ODCM, as well as to the liquid or gaseous radioactive waste system design,
The inspectors walked down the major components of the gaseous and liquid release
    procedures, or operation since the last inspection to determine whether the changes
systems (e.g., radiation and flow monitors, demineralizers and filters, tanks, and
    affected the licensees ability to maintain effluents as-low-as-reasonably-achievable and
vessels) to observe current system configuration with respect to the description in the
    whether changes made to monitoring instrumentation resulted in a non-representative
FSAR, ongoing activities, and equipment material condition.
    monitoring of effluents.
The inspectors reviewed the licensees technical justification for changes made by the
    The inspectors reviewed air cleaning system surveillance test results to ensure that the
licensee to the ODCM, as well as to the liquid or gaseous radioactive waste system design,
    system was operating within the licensees acceptance criteria. Specifically, the
procedures, or operation since the last inspection to determine whether the changes
    inspectors reviewed the most recent results of the Ventilation Filter Testing Program for
affected the licensees ability to maintain effluents as-low-as-reasonably-achievable and
    the Control Room Ventilation System to verify that test methodology, frequency and test
whether changes made to monitoring instrumentation resulted in a non-representative
    results met Technical Specification requirements. The inspectors reviewed and
monitoring of effluents.  
    discussed the test results of in-place high efficiency particulate air (HEPA) and charcoal
The inspectors reviewed air cleaning system surveillance test results to ensure that the
    absorber penetration tests, laboratory tests of charcoal absorber methyl iodide
system was operating within the licensees acceptance criteria. Specifically, the
    penetration, and in-place combined HEPA filter and charcoal absorber train pressure
inspectors reviewed the most recent results of the Ventilation Filter Testing Program for
    drop tests for the systems with system engineering staff.
the Control Room Ventilation System to verify that test methodology, frequency and test
    The inspectors reviewed records of instrument calibrations performed since the last
results met Technical Specification requirements. The inspectors reviewed and
    inspection for each point of discharge effluent radiation monitor and flow measurement
discussed the test results of in-place high efficiency particulate air (HEPA) and charcoal
    device and reviewed any completed system modifications and the current effluent radiation
absorber penetration tests, laboratory tests of charcoal absorber methyl iodide
    monitor alarm setpoint value for conformance with RETS/ODCM requirements. The
penetration, and in-place combined HEPA filter and charcoal absorber train pressure
    inspectors also reviewed calibration records of radiation measurement (i.e., counting room)
drop tests for the systems with system engineering staff.
    instrumentation associated with effluent monitoring and release activities and the quality
The inspectors reviewed records of instrument calibrations performed since the last
    control records for the radiation measurement instruments.
inspection for each point of discharge effluent radiation monitor and flow measurement
                                              21                                    Enclosure
device and reviewed any completed system modifications and the current effluent radiation
monitor alarm setpoint value for conformance with RETS/ODCM requirements. The
inspectors also reviewed calibration records of radiation measurement (i.e., counting room)
instrumentation associated with effluent monitoring and release activities and the quality
control records for the radiation measurement instruments.


  These reviews represented four inspection samples: one for the walk down of the
Enclosure
  effluent control systems, one for the program/system modification reviews, one for the
22
  air cleaning system surveillance review, and one for the review of instrument calibration
These reviews represented four inspection samples: one for the walk down of the
  records.
effluent control systems, one for the program/system modification reviews, one for the
b. Findings
air cleaning system surveillance review, and one for the review of instrument calibration
  During a walk down of the Radioactive Gaseous Effluent Monitoring (RGEM) system,
records.
  the inspectors identified that the as installed configuration of the sample piping
  b.
  running from the isokinetic sampling head within the stations stack leading to the
Findings
  RGEM radiological monitors contained at least four piping bends (i.e., elbows) of
During a walk down of the Radioactive Gaseous Effluent Monitoring (RGEM) system,
  approximately 90 degrees each. This was identified as an Unresolved Item (URI)
the inspectors identified that the as installed configuration of the sample piping
  pending determination whether any violation of NRC requirements occurred, and a
running from the isokinetic sampling head within the stations stack leading to the
  determination as to the significance, if any violation is determined to have occurred.
RGEM radiological monitors contained at least four piping bends (i.e., elbows) of
  Upon this observation, the inspectors inquired of the licensee as to what assurances
approximately 90 degrees each. This was identified as an Unresolved Item (URI)
  there were that the piping configuration did not promote plate-out of iodines and
pending determination whether any violation of NRC requirements occurred, and a
  particulates from the effluent stream and that the system was obtaining a representative
determination as to the significance, if any violation is determined to have occurred.
  sample of the stations gaseous effluents. Prior to the end of the on-site portion of the
Upon this observation, the inspectors inquired of the licensee as to what assurances
  inspection, the licensee provided the inspectors a copy of the RGEM system design
there were that the piping configuration did not promote plate-out of iodines and
  documentation (circa 1982), which indicated that the system was designed and installed
particulates from the effluent stream and that the system was obtaining a representative
  such that it receives a representative isokinetic sample of plant gaseous effluent and
sample of the stations gaseous effluents. Prior to the end of the on-site portion of the
  that the sample piping from the stack to the RGEM system is heat traced and insulated
inspection, the licensee provided the inspectors a copy of the RGEM system design
  to prevent condensation and plating out of the effluent sample. The inspectors
documentation (circa 1982), which indicated that the system was designed and installed
  walked-down the sample piping to verify that it was insulated and the heat tracing
such that it receives a representative isokinetic sample of plant gaseous effluent and
  was operable.
that the sample piping from the stack to the RGEM system is heat traced and insulated
  During in-office review of the design documentation, the inspectors identified that the
to prevent condensation and plating out of the effluent sample. The inspectors
  RGEM Design Criteria (Section 3.0) for the system included ANSI N13.1-1969, Guide
walked-down the sample piping to verify that it was insulated and the heat tracing
  to Sampling Airborne Radioactive Materials in Nuclear Facilities. Section B5 of
was operable.  
  Appendix B of ANSI N13.1-1969 indicates that elbows in sampling lines should be
During in-office review of the design documentation, the inspectors identified that the
  avoided if at all possible, but when they are required, the bend radius of the elbow
RGEM Design Criteria (Section 3.0) for the system included ANSI N13.1-1969, Guide
  should be as long as practicable, and design flow rates through any line containing an
to Sampling Airborne Radioactive Materials in Nuclear Facilities. Section B5 of
  elbow should be kept low. The inspectors also noted that the ANSI standard did not
Appendix B of ANSI N13.1-1969 indicates that elbows in sampling lines should be
  address the use of piping insulation or heat tracing as methods to mitigate iodine and
avoided if at all possible, but when they are required, the bend radius of the elbow
  particulate plate-out.
should be as long as practicable, and design flow rates through any line containing an
  Therefore, the inspectors preliminarily determined that the as installed configuration of
elbow should be kept low. The inspectors also noted that the ANSI standard did not
  the RGEM sampling piping did not appear to meet the design criteria of the ANSI
address the use of piping insulation or heat tracing as methods to mitigate iodine and
  standard. However, the inspectors were unable to determine if the as installed
particulate plate-out.
  configuration of the RGEM system prevented the collection of representative gaseous
Therefore, the inspectors preliminarily determined that the as installed configuration of
  effluent samples, and the significance the plate-out had, if any, on the public dose
the RGEM sampling piping did not appear to meet the design criteria of the ANSI
  consequences from the stations gaseous effluents. The licensee captured this issue in
standard. However, the inspectors were unable to determine if the as installed
  its corrective action program as CAP 039097. Pending the completion of the licensees
configuration of the RGEM system prevented the collection of representative gaseous
  evaluation of this issue and the NRCs review of the licensees evaluation, this issue is
effluent samples, and the significance the plate-out had, if any, on the public dose
  considered a URI (URI 05000255/2003008-04).
consequences from the stations gaseous effluents. The licensee captured this issue in
                                            22                                      Enclosure
its corrective action program as CAP 039097. Pending the completion of the licensees
evaluation of this issue and the NRCs review of the licensees evaluation, this issue is
considered a URI (URI 05000255/2003008-04).  


.3   Onsite Inspection - Effluent Release Packages, Abnormal Releases, Dose Calculations,
Enclosure
    and Laboratory Quality Control and Assurance
23
   a. Inspection Scope
.3
    As there were no routine radioactive liquid releases conducted during the on-site
Onsite Inspection - Effluent Release Packages, Abnormal Releases, Dose Calculations,
    inspection, the inspectors reviewed several radioactive liquid waste release permits,
and Laboratory Quality Control and Assurance  
    including the projected doses to members of the public, to verify that appropriate
   a.
    treatment equipment was used and that radioactive liquid waste was processed and
Inspection Scope
    released in accordance with RETS/ODCM and procedure requirements. The inspectors
As there were no routine radioactive liquid releases conducted during the on-site
    observed the routine processing (including sample collection and analysis) of radioactive
inspection, the inspectors reviewed several radioactive liquid waste release permits,
    gaseous effluent from Waste Gas Decay Tank T-101A, and reviewed several other
including the projected doses to members of the public, to verify that appropriate
    radioactive gaseous effluent release permits, to verify that appropriate treatment
treatment equipment was used and that radioactive liquid waste was processed and
    equipment was used and that the radioactive gaseous effluent was processed and
released in accordance with RETS/ODCM and procedure requirements. The inspectors
    released in accordance with RETS/ODCM and procedure requirements.
observed the routine processing (including sample collection and analysis) of radioactive
    The inspectors reviewed the records of abnormal releases, or releases made with
gaseous effluent from Waste Gas Decay Tank T-101A, and reviewed several other
    inoperable effluent radiation monitors, and reviewed the licensees actions for these
radioactive gaseous effluent release permits, to verify that appropriate treatment
    releases to ensure an adequate defense-in-depth was maintained against an
equipment was used and that the radioactive gaseous effluent was processed and
    unmonitored, unanticipated release of radioactive material to the environment.
released in accordance with RETS/ODCM and procedure requirements.  
    The inspectors reviewed a selection of monthly, quarterly, and annual dose calculations
The inspectors reviewed the records of abnormal releases, or releases made with
    to ensure that the licensee properly calculated the offsite dose from radiological effluent
inoperable effluent radiation monitors, and reviewed the licensees actions for these
    releases and to determine if any annual RETS/ODCM (i.e., Appendix I to 10 CFR
releases to ensure an adequate defense-in-depth was maintained against an
    Part 50 values) limits were exceeded.
unmonitored, unanticipated release of radioactive material to the environment.
    The inspectors reviewed the results of the interlaboratory comparison program to verify
The inspectors reviewed a selection of monthly, quarterly, and annual dose calculations
    the quality of radioactive effluent sample analyses performed by the licensee. The
to ensure that the licensee properly calculated the offsite dose from radiological effluent
    inspectors reviewed the licensees quality control evaluation of the interlaboratory
releases and to determine if any annual RETS/ODCM (i.e., Appendix I to 10 CFR
    comparison test and associated corrective actions for any deficiencies identified. The
Part 50 values) limits were exceeded.
    inspectors reviewed the licensees assessment of any identified bias in the sample
The inspectors reviewed the results of the interlaboratory comparison program to verify
    analysis results and the overall effect on calculated projected doses to members of the
the quality of radioactive effluent sample analyses performed by the licensee. The
    public. In addition, the inspectors reviewed the results from the licensees Quality
inspectors reviewed the licensees quality control evaluation of the interlaboratory
    Assurance audits to determine whether the licensee met the requirements of the
comparison test and associated corrective actions for any deficiencies identified. The
    RETS/ODCM.
inspectors reviewed the licensees assessment of any identified bias in the sample
    These reviews represented four inspection samples: one for the review of effluent
analysis results and the overall effect on calculated projected doses to members of the
    release packages, one for the abnormal release reviews, one for the dose calculation
public. In addition, the inspectors reviewed the results from the licensees Quality
    reviews, and one for the review of laboratory quality control and assurance.
Assurance audits to determine whether the licensee met the requirements of the
   b. Findings
RETS/ODCM.
    No findings of significance were identified.
These reviews represented four inspection samples: one for the review of effluent
                                              23                                      Enclosure
release packages, one for the abnormal release reviews, one for the dose calculation  
reviews, and one for the review of laboratory quality control and assurance.
   b.
Findings
No findings of significance were identified.


.4   Identification and Resolution of Problems
Enclosure
   a. Inspection Scope
24
    The inspectors reviewed licensee self-assessments, audits, and Special Reports related
.4
    to the radioactive effluent treatment and monitoring program since the last inspection to
Identification and Resolution of Problems
    determine if identified problems were entered into the corrective action program for
   a.
    resolution. The inspectors also verified that the licensee's self-assessment program
Inspection Scope
    was capable of identifying repetitive deficiencies or significant individual deficiencies in
The inspectors reviewed licensee self-assessments, audits, and Special Reports related
    problem identification and resolution.
to the radioactive effluent treatment and monitoring program since the last inspection to
    The inspectors also reviewed corrective action reports from the radioactive effluent
determine if identified problems were entered into the corrective action program for
    treatment and monitoring program since the previous inspection, interviewed staff, and
resolution. The inspectors also verified that the licensee's self-assessment program
    reviewed documents to determine if the following activities were being conducted in an
was capable of identifying repetitive deficiencies or significant individual deficiencies in
    effective and timely manner commensurate with their importance to safety and risk:
problem identification and resolution.  
    1.       Initial problem identification, characterization, and tracking;
The inspectors also reviewed corrective action reports from the radioactive effluent
    2.       Disposition of operability/reportability issues;
treatment and monitoring program since the previous inspection, interviewed staff, and
    3.       Evaluation of safety significance/risk and priority for resolution;
reviewed documents to determine if the following activities were being conducted in an
    4.       Identification of repetitive problems;
effective and timely manner commensurate with their importance to safety and risk:  
    5.       Identification of contributing causes;
1.
    6.       Identification and implementation of effective corrective actions;
Initial problem identification, characterization, and tracking;
    7.       Resolution of Non-Cited Violations (NCVs) tracked in the corrective action system;
2.
              and
Disposition of operability/reportability issues;
    8.       Implementation/consideration of risk significant operational experience feedback.
3.
    These reviews represented one inspection sample.
Evaluation of safety significance/risk and priority for resolution;
   b. Findings
4.
    No findings of significance were identified.
Identification of repetitive problems;
2PS3 Radiological Environmental Monitoring Program (REMP) and Radioactive Material
5.
    Control Program (71122.03)
Identification of contributing causes;
.1   Inspection Planning
6.
   a. Inspection Scope
Identification and implementation of effective corrective actions;
    The inspectors reviewed the most current Annual Radiological Environmental Operating
7.
    Report (for calendar year 2002) and licensee assessment results to verify that the
Resolution of Non-Cited Violations (NCVs) tracked in the corrective action system;
    REMP was implemented as required by Technical Specifications and the Offsite Dose
and
    Calculation Manual (ODCM). The inspectors reviewed the report for changes to the
8.
    ODCM with respect to environmental monitoring, commitments in terms of sampling
Implementation/consideration of risk significant operational experience feedback.
    locations, monitoring and measurement frequencies, land use census, interlaboratory
These reviews represented one inspection sample.
    comparison program, and analysis of data. The inspectors reviewed the Updated Final
   b.
    Safety Analysis Report (UFSAR) for information regarding the environmental monitoring
Findings
                                                24                                      Enclosure
No findings of significance were identified.
2PS3
Radiological Environmental Monitoring Program (REMP) and Radioactive Material
Control Program (71122.03)
.1
Inspection Planning
   a.
Inspection Scope
The inspectors reviewed the most current Annual Radiological Environmental Operating
Report (for calendar year 2002) and licensee assessment results to verify that the
REMP was implemented as required by Technical Specifications and the Offsite Dose
Calculation Manual (ODCM). The inspectors reviewed the report for changes to the
ODCM with respect to environmental monitoring, commitments in terms of sampling
locations, monitoring and measurement frequencies, land use census, interlaboratory
comparison program, and analysis of data. The inspectors reviewed the Updated Final
Safety Analysis Report (UFSAR) for information regarding the environmental monitoring  


    program and meteorological monitoring instrumentation. The inspectors reviewed the
Enclosure
    scope of the licensees audit program to verify that it met the requirements of
25
    10 CFR 20.1101(c).
program and meteorological monitoring instrumentation. The inspectors reviewed the
    These reviews represented one inspection sample.
scope of the licensees audit program to verify that it met the requirements of
   b. Findings
10 CFR 20.1101(c).
    No findings of significance were identified.
These reviews represented one inspection sample.
.2   Onsite Inspection
   b.
   a. Inspection Scope
Findings
    The inspectors walked down 75 percent of the air sampling stations and approximately
No findings of significance were identified.
    23 percent of the thermoluminescence dosimeter (TLD) monitoring stations to determine
.2
    whether they were located as described in the ODCM and to assess the sampling
Onsite Inspection
    capability and material condition of the equipment.
   a.
    The inspectors observed the collection and preparation of selected environmental
Inspection Scope
    samples (e.g., ground and surface water, milk, vegetation, sediment, and soil) to verify
The inspectors walked down 75 percent of the air sampling stations and approximately
    that environmental sampling was representative of the release pathways as specified in
23 percent of the thermoluminescence dosimeter (TLD) monitoring stations to determine
    the ODCM and that sampling techniques were conducted in accordance with licensee
whether they were located as described in the ODCM and to assess the sampling
    procedures.
capability and material condition of the equipment.
    The inspectors reviewed the operation of the stations meteorological instruments,
The inspectors observed the collection and preparation of selected environmental
    including data readout and recording instrumentation at the tower and in the control
samples (e.g., ground and surface water, milk, vegetation, sediment, and soil) to verify
    room, to verify that they were as described, operable, calibrated, and maintained in
that environmental sampling was representative of the release pathways as specified in
    accordance with guidance contained in the UFSAR, NRC Safety Guide 23, and licensee
the ODCM and that sampling techniques were conducted in accordance with licensee
    procedures. The inspectors compared real-time data collected at the meteorological
procedures.
    tower, such as wind speed, wind direction, and differential temperature, to the time-
The inspectors reviewed the operation of the stations meteorological instruments,
    average data transmitted to the control room to verify data integrity.
including data readout and recording instrumentation at the tower and in the control
    The inspectors reviewed each event documented in the 2002 Annual Radiological
room, to verify that they were as described, operable, calibrated, and maintained in
    Environmental Operating Report which involved a missed sample, inoperable sampler,
accordance with guidance contained in the UFSAR, NRC Safety Guide 23, and licensee
    lost TLD, or anomalous measurement for the cause and corrective actions, and
procedures. The inspectors compared real-time data collected at the meteorological
    conducted a review of the licensees assessment of any positive sample results
tower, such as wind speed, wind direction, and differential temperature, to the time-
    (i.e., licensed radioactive material detected above the lower limits of detection (LLDs)).
average data transmitted to the control room to verify data integrity.
    The inspectors reviewed the associated radioactive effluent release data that was the
The inspectors reviewed each event documented in the 2002 Annual Radiological
    likely source of the released material identified by the REMP sample.
Environmental Operating Report which involved a missed sample, inoperable sampler,
    The inspectors reviewed significant changes, if any, made by the licensee to the ODCM
lost TLD, or anomalous measurement for the cause and corrective actions, and
    as the result of changes to the land census or sampler station modifications since the
conducted a review of the licensees assessment of any positive sample results
    last inspection. In particular, the inspectors reviewed technical justifications for the
(i.e., licensed radioactive material detected above the lower limits of detection (LLDs)).  
    recently changed sampling locations for two outer-ring TLD stations. The inspectors
The inspectors reviewed the associated radioactive effluent release data that was the
    assessed the licensees ODCM change evaluations to verify that the changes did not
likely source of the released material identified by the REMP sample.
    adversely affect the licensees ability to monitor the impacts of radioactive effluent
The inspectors reviewed significant changes, if any, made by the licensee to the ODCM
    releases on the environment.
as the result of changes to the land census or sampler station modifications since the
                                              25                                      Enclosure
last inspection. In particular, the inspectors reviewed technical justifications for the
recently changed sampling locations for two outer-ring TLD stations. The inspectors
assessed the licensees ODCM change evaluations to verify that the changes did not
adversely affect the licensees ability to monitor the impacts of radioactive effluent
releases on the environment.


    The inspectors reviewed the calibration and maintenance records for all twelve air
Enclosure
    samplers and focused on the air flow meter and particulate filter/charcoal cartridge
26
    components of the samplers. Because the licensee did not conduct analyses of REMP
The inspectors reviewed the calibration and maintenance records for all twelve air
    samples on-site, the inspectors were not able to review licensee calibration records for
samplers and focused on the air flow meter and particulate filter/charcoal cartridge
    environmental sample radiation measurement instrumentation (i.e., count room
components of the samplers. Because the licensee did not conduct analyses of REMP
    equipment), or review quality control charts for count room instrumentation.
samples on-site, the inspectors were not able to review licensee calibration records for
    However, the inspectors reviewed the results of the REMP sample vendors quality
environmental sample radiation measurement instrumentation (i.e., count room
    control program, including the vendors interlaboratory comparison program results, to
equipment), or review quality control charts for count room instrumentation.
    verify the adequacy of the vendors program and corrective actions taken for any
However, the inspectors reviewed the results of the REMP sample vendors quality
    identified deficiencies. The inspectors reviewed the detection sensitivities utilized by the
control program, including the vendors interlaboratory comparison program results, to
    REMP sample vendor for counting samples to verify that the samples met the
verify the adequacy of the vendors program and corrective actions taken for any
    TS/ODCM required LLDs. The inspectors reviewed audits and technical evaluations the
identified deficiencies. The inspectors reviewed the detection sensitivities utilized by the
    licensee performed on the vendors program. The inspectors reviewed quality
REMP sample vendor for counting samples to verify that the samples met the
    assurance audit results of the program to determine whether the licensee met Technical
TS/ODCM required LLDs. The inspectors reviewed audits and technical evaluations the
    Specification and ODCM requirements.
licensee performed on the vendors program. The inspectors reviewed quality
    These reviews represented six inspection samples.
assurance audit results of the program to determine whether the licensee met Technical
   b. Findings
Specification and ODCM requirements.
    No findings of significance were identified.
These reviews represented six inspection samples.
.3   Unrestricted Release of Material from the Radiologically Controlled Area (RCA)
   b.
   a. Inspection Scope
Findings
    The inspectors observed several locations where the licensee monitored potentially
No findings of significance were identified.
    contaminated material leaving the RCA, and inspected the methods used for control,
.3
    survey, and release from these areas. The inspectors observed the performance of
Unrestricted Release of Material from the Radiologically Controlled Area (RCA)
    personnel surveying and releasing material for unrestricted use to verify that the work
   a.
    was performed in accordance with plant procedures.
Inspection Scope
    The inspectors assessed the radiation monitoring instrumentation utilized for the
The inspectors observed several locations where the licensee monitored potentially
    unrestricted release of material from the RCA to verify that it was appropriate for the
contaminated material leaving the RCA, and inspected the methods used for control,
    radiation types present and was calibrated with the requisite radiation sources. The
survey, and release from these areas. The inspectors observed the performance of
    inspectors reviewed the licensees criteria for the survey and release of potentially
personnel surveying and releasing material for unrestricted use to verify that the work
    contaminated material and verified that there was guidance on how to respond to
was performed in accordance with plant procedures.
    indications of the presence of licensed radioactive material. The inspectors reviewed
The inspectors assessed the radiation monitoring instrumentation utilized for the
    the licensees equipment to ensure the radiation detection sensitivities were consistent
unrestricted release of material from the RCA to verify that it was appropriate for the
    with the NRC guidance contained in IE Circular 81-07 and IE Information Notice 85-92
radiation types present and was calibrated with the requisite radiation sources. The
    for surface contamination and HPPOS-221 for volumetrically contaminated material.
inspectors reviewed the licensees criteria for the survey and release of potentially
    The inspectors reviewed the licensees program to determine if it adequately identified
contaminated material and verified that there was guidance on how to respond to
    the potential for difficult-to-detect radionuclides (i.e., radionuclides that decay via
indications of the presence of licensed radioactive material. The inspectors reviewed
    electron capture) and accounted for those radionuclides during routine unrestricted
the licensees equipment to ensure the radiation detection sensitivities were consistent
    release surveys. Finally, the inspectors reviewed the licensees procedures and records
with the NRC guidance contained in IE Circular 81-07 and IE Information Notice 85-92
    to verify that the radiation detection instrumentation was used at its typical sensitivity
for surface contamination and HPPOS-221 for volumetrically contaminated material.  
    level based on appropriate counting parameters (i.e., counting times and background
The inspectors reviewed the licensees program to determine if it adequately identified
    radiation levels), and that the licensee had not established a release limit by altering
the potential for difficult-to-detect radionuclides (i.e., radionuclides that decay via
                                                26                                      Enclosure
electron capture) and accounted for those radionuclides during routine unrestricted
release surveys. Finally, the inspectors reviewed the licensees procedures and records
to verify that the radiation detection instrumentation was used at its typical sensitivity
level based on appropriate counting parameters (i.e., counting times and background
radiation levels), and that the licensee had not established a release limit by altering


    instrumentation typical sensitivities through such methods as raising the energy
Enclosure
    discriminator level or locating the instrument in a high radiation background area.
27
    These reviews represented two inspection samples.
instrumentation typical sensitivities through such methods as raising the energy
   b. Findings
discriminator level or locating the instrument in a high radiation background area.
    No findings of significance were identified.
These reviews represented two inspection samples.
.4   Identification and Resolution of Problems
   b.
   a. Inspection Scope
Findings
    The inspectors reviewed the licensees self-assessments, audits, Licensee Event
No findings of significance were identified.
    Reports, and Special Reports, as available, related to the Radiological Environmental
.4
    Monitoring Program since the last inspection to determine if identified problems were
Identification and Resolution of Problems
    entered into the corrective action program for resolution. The inspectors also reviewed
   a.
    the licensee's self-assessment program to determine if it was capable of identifying
Inspection Scope
    repetitive deficiencies or significant individual deficiencies in problem identification and
The inspectors reviewed the licensees self-assessments, audits, Licensee Event
    resolution.
Reports, and Special Reports, as available, related to the Radiological Environmental
    The inspectors also reviewed corrective action reports related to the REMP and
Monitoring Program since the last inspection to determine if identified problems were
    radioactive material control program since the previous inspection, interviewed staff, and
entered into the corrective action program for resolution. The inspectors also reviewed  
    reviewed documents to determine if the following activities were being conducted in an
the licensee's self-assessment program to determine if it was capable of identifying
    effective and timely manner commensurate with their importance to safety and risk:
repetitive deficiencies or significant individual deficiencies in problem identification and
    1.       Initial problem identification, characterization, and tracking.
resolution.
    2.       Disposition of operability and reportability issues.
The inspectors also reviewed corrective action reports related to the REMP and
    3.       Evaluation of safety significance, risk, and priority for resolution.
radioactive material control program since the previous inspection, interviewed staff, and
    4.       Identification of repetitive problems.
reviewed documents to determine if the following activities were being conducted in an
    5.       Identification of contributing causes.
effective and timely manner commensurate with their importance to safety and risk:
    6.       Identification and implementation of effective corrective actions.
1.
    7.       Resolution of Non-Cited Violations tracked in the corrective action system.
Initial problem identification, characterization, and tracking.
    8.       Implementation and consideration of risk significant operational experience
2.
              feedback.
Disposition of operability and reportability issues.
    These reviews represented one inspection sample.
3.
   b. Findings
Evaluation of safety significance, risk, and priority for resolution.
    No findings of significance were identified.
4.
                                                27                                      Enclosure
Identification of repetitive problems.
5.
Identification of contributing causes.
6.
Identification and implementation of effective corrective actions.
7.
Resolution of Non-Cited Violations tracked in the corrective action system.
8.
Implementation and consideration of risk significant operational experience
feedback.
These reviews represented one inspection sample.
   b.
Findings
No findings of significance were identified.


4.   OTHER ACTIVITIES (OA)
Enclosure
28
4.
OTHER ACTIVITIES (OA)
4OA1 Performance Indicator Verification (71151)
4OA1 Performance Indicator Verification (71151)
.1   Reactor Safety Performance Indicators
.1
   a. Inspection Scope
Reactor Safety Performance Indicators
    The inspectors used definitions and guidance contained in Revision 2 of Nuclear Energy
   a.
    Institute Document 99-02, Regulatory Assessment Performance Indicator Guideline, to
Inspection Scope
    verify the accuracy of the data submitted for the following three performance indicators:
The inspectors used definitions and guidance contained in Revision 2 of Nuclear Energy
    *       Unplanned Power Changes Per 7,000 Critical Hours
Institute Document 99-02, Regulatory Assessment Performance Indicator Guideline, to
    *       Reactor Coolant System (RCS) Specific Activity
verify the accuracy of the data submitted for the following three performance indicators:
    *       RCS Leakage
*
    The inspectors reviewed the data submitted by licensee personnel for October 2002
Unplanned Power Changes Per 7,000 Critical Hours
    through September 2003 to verify that the Unplanned Power Changes per 7,000 Critical
*
    Hours and Reactor Coolant System Leakage Performance Indicators were reported
Reactor Coolant System (RCS) Specific Activity
    accurately. The inspectors also reviewed samples of records regarding primary coolant
*
    system leakage calculations, control room logs and monthly operating data reports.
RCS Leakage
    The inspectors reviewed the licensees assessment of its performance indicator for RCS
The inspectors reviewed the data submitted by licensee personnel for October 2002
    specific activity by reviewing Chemistry Department records and selected isotopic
through September 2003 to verify that the Unplanned Power Changes per 7,000 Critical
    analyses (July 2002 through March 2003) to verify that the greatest Dose Equivalent
Hours and Reactor Coolant System Leakage Performance Indicators were reported
    Iodine (DEI) value obtained during those months corresponded with the value reported
accurately. The inspectors also reviewed samples of records regarding primary coolant
    to the NRC. The inspectors also reviewed selected DEI calculations to verify that the
system leakage calculations, control room logs and monthly operating data reports.
    appropriate conversion factors were used in the assessment as required by Technical
The inspectors reviewed the licensees assessment of its performance indicator for RCS
    Specifications. Additionally, on October 22, 2003, the inspectors observed a chemistry
specific activity by reviewing Chemistry Department records and selected isotopic
    technician obtain and analyze a reactor coolant sample for DEI to verify adherence with
analyses (July 2002 through March 2003) to verify that the greatest Dose Equivalent
    licensee procedures for the collection and analysis of reactor coolant system samples.
Iodine (DEI) value obtained during those months corresponded with the value reported
    Further, the inspectors reviewed condition reports regarding problems with performance
to the NRC. The inspectors also reviewed selected DEI calculations to verify that the
    indicator data to verify that the issue was entered into the corrective action program with
appropriate conversion factors were used in the assessment as required by Technical
    the appropriate significance level. The inspectors also verified that planned corrective
Specifications. Additionally, on October 22, 2003, the inspectors observed a chemistry
    actions were appropriate and implemented as scheduled.
technician obtain and analyze a reactor coolant sample for DEI to verify adherence with
   b. Findings
licensee procedures for the collection and analysis of reactor coolant system samples.
    No findings of significance were identified.
Further, the inspectors reviewed condition reports regarding problems with performance
.2   Radiation Protection Strategic Area
indicator data to verify that the issue was entered into the corrective action program with
   a. Inspection Scope
the appropriate significance level. The inspectors also verified that planned corrective
    The inspectors sampled the licensees submittals for performance indicators (PIs) and
actions were appropriate and implemented as scheduled.
    periods listed below. The inspectors used PI definitions and guidance contained in
   b.
    Revision 2 of Nuclear Energy Institute Document 99-02, Regulatory Assessment
Findings
                                              28                                      Enclosure
No findings of significance were identified.
.2
Radiation Protection Strategic Area
   a.
Inspection Scope
The inspectors sampled the licensees submittals for performance indicators (PIs) and
periods listed below. The inspectors used PI definitions and guidance contained in
Revision 2 of Nuclear Energy Institute Document 99-02, Regulatory Assessment


    Performance Indicator Guideline, to verify the accuracy of the PI data. The following PI
Enclosure
    was reviewed:
29
    *       RETS/ODCM Radiological Effluent Occurrence
Performance Indicator Guideline, to verify the accuracy of the PI data. The following PI
    Since no reportable occurrences were identified by the licensee for 3rd Quarter 2002
was reviewed:
    through 3rd Quarter 2003, the inspectors compared the licensees data and reviewed
*
    corrective action documents generated during the time period to identify any potential
RETS/ODCM Radiological Effluent Occurrence
    occurrences such as unmonitored, uncontrolled or improperly calculated effluent
Since no reportable occurrences were identified by the licensee for 3rd Quarter 2002
    releases that may have impacted offsite dose. Also, the inspectors evaluated the
through 3rd Quarter 2003, the inspectors compared the licensees data and reviewed
    licensees methods for determining offsite dose and selectively verified that liquid and
corrective action documents generated during the time period to identify any potential
    gaseous effluent release data and associated offsite dose calculations performed since
occurrences such as unmonitored, uncontrolled or improperly calculated effluent
    this indicator was last reviewed were accurate.
releases that may have impacted offsite dose. Also, the inspectors evaluated the
b. Findings
licensees methods for determining offsite dose and selectively verified that liquid and
    No findings of significance were identified.
gaseous effluent release data and associated offsite dose calculations performed since
this indicator was last reviewed were accurate.
  b.
Findings
 
No findings of significance were identified.
4OA2 Identification and Resolution of Problems (71152)
4OA2 Identification and Resolution of Problems (71152)
a. Inspection Scope
  a.
    On August 10, 2003, during scheduled quarterly surveillance testing, High Pressure
Inspection Scope
    Safety Injection Pump Subcooling Valve CV-3070 failed to stroke open as required.
On August 10, 2003, during scheduled quarterly surveillance testing, High Pressure
    Consequently, High Pressure Safety Injection Pump P-66B was declared inoperable and
Safety Injection Pump Subcooling Valve CV-3070 failed to stroke open as required.
    Technical Specification 3.5.2.B.1 action was entered which required the pump to be
Consequently, High Pressure Safety Injection Pump P-66B was declared inoperable and
    restored to operable status within 72 hours.
Technical Specification 3.5.2.B.1 action was entered which required the pump to be
    The inspectors reviewed the apparent cause evaluation for Condition Report
restored to operable status within 72 hours.
    CAP037030, Subcooling Valve CV-3070 Failed to Open During QO-5 Valve Test
The inspectors reviewed the apparent cause evaluation for Condition Report
    Procedure, to verify that: (1) the problem was accurately identified; (2) the apparent
CAP037030, Subcooling Valve CV-3070 Failed to Open During QO-5 Valve Test
    cause was adequately justified; (2) extent of condition and generic implications were
Procedure, to verify that: (1) the problem was accurately identified; (2) the apparent
    appropriately addressed; and (3) corrective actions were appropriately focused to
cause was adequately justified; (2) extent of condition and generic implications were
    address the problem and implemented commensurate with the safety significance of the
appropriately addressed; and (3) corrective actions were appropriately focused to
    issue.
address the problem and implemented commensurate with the safety significance of the
b. Findings
issue.
    No findings of significance were identified. However, the inspectors noted one
  b.
    weakness regarding the evaluation and resultant corrective actions.
Findings
    Licensee personnel concluded that the apparent cause for CV-3070 to not open was a
No findings of significance were identified. However, the inspectors noted one
    flow control valve in the operating air system which had been installed backwards in
weakness regarding the evaluation and resultant corrective actions.
    1995. Licensee personnel also concluded that human error was the cause of the flow
Licensee personnel concluded that the apparent cause for CV-3070 to not open was a
    control valve being installed incorrectly. However, the evaluation did not identify that the
flow control valve in the operating air system which had been installed backwards in
    work order and work instructions utilized in 1995 during the maintenance activity to
1995. Licensee personnel also concluded that human error was the cause of the flow
    disassemble and then rebuild the actuator to CV-3070 did not provide any guidance to
control valve being installed incorrectly. However, the evaluation did not identify that the
    maintenance personnel regarding proper orientation for the flow control valve.
work order and work instructions utilized in 1995 during the maintenance activity to
                                              29                                      Enclosure
disassemble and then rebuild the actuator to CV-3070 did not provide any guidance to
maintenance personnel regarding proper orientation for the flow control valve.


    Consequently, there was no corrective action developed to revise the work instruction to
Enclosure
    ensure adequate guidance was provided to the maintenance personnel during any
30
    subsequent CV-3070 actuator maintenance activities. However, this issue was of minor
Consequently, there was no corrective action developed to revise the work instruction to
    significance since maintenance on the valve actuators had not been performed since
ensure adequate guidance was provided to the maintenance personnel during any
    the evaluation was completed. Therefore, the failure to develop a corrective action to
subsequent CV-3070 actuator maintenance activities. However, this issue was of minor
    review and revise the work instructions had not resulted in any actual adverse
significance since maintenance on the valve actuators had not been performed since
    consequences.
the evaluation was completed. Therefore, the failure to develop a corrective action to
.2   Routine Review of Identification and Resolution of Problems
review and revise the work instructions had not resulted in any actual adverse
   a. Inspection Scope
consequences.
    As discussed in previous sections of this report, the inspectors routinely reviewed issues
.2
    during baseline inspection activities and plant status reviews to verify that condition
Routine Review of Identification and Resolution of Problems
    reports were being generated and entered into the corrective action program with the
   a.
    appropriate significance characterization. For select condition reports, the inspectors
Inspection Scope
    also verified that identified corrective actions were appropriate, and had been
As discussed in previous sections of this report, the inspectors routinely reviewed issues
    implemented or were scheduled to be implemented in a manner commensurate with the
during baseline inspection activities and plant status reviews to verify that condition
    significance of the identified problem.
reports were being generated and entered into the corrective action program with the
   b. Findings
appropriate significance characterization. For select condition reports, the inspectors
    No findings of significance were identified.
also verified that identified corrective actions were appropriate, and had been
implemented or were scheduled to be implemented in a manner commensurate with the
significance of the identified problem.
   b.
Findings
No findings of significance were identified.
4OA3 Event Follow-up (71153)
4OA3 Event Follow-up (71153)
    The inspectors reviewed two Licensee Event Reports to verify that the events were
The inspectors reviewed two Licensee Event Reports to verify that the events were
    accurately described, to determine if any violations of NRC requirements occurred, and
accurately described, to determine if any violations of NRC requirements occurred, and
    to assess the appropriateness of identified corrective actions.
to assess the appropriateness of identified corrective actions.
.1   (Closed) Licensee Event Report (LER) 50-255/03-005: Emergency Diesel Generators
.1
    Start on Low Voltage Condition.
(Closed) Licensee Event Report (LER) 50-255/03-005: Emergency Diesel Generators
    On August 14, 2003, with the plant operating at 100 percent power, an electrical power
Start on Low Voltage Condition.
    grid disturbance occurred that momentarily lowered voltage on 2400 volt safety-related
On August 14, 2003, with the plant operating at 100 percent power, an electrical power
    Buses 1C and 1D which caused both Emergency Diesel Generators to start. However,
grid disturbance occurred that momentarily lowered voltage on 2400 volt safety-related
    Buses 1C and 1D remained energized from offsite power throughout the event as
Buses 1C and 1D which caused both Emergency Diesel Generators to start. However,
    designed. Local grid conditions stabilized within 5 minutes and both Emergency Diesel
Buses 1C and 1D remained energized from offsite power throughout the event as
    Generators were subsequently secured. The inspectors did not identify any issues of
designed. Local grid conditions stabilized within 5 minutes and both Emergency Diesel
    significance. This LER is closed.
Generators were subsequently secured. The inspectors did not identify any issues of
.2   (Closed) LER 03-004: Inoperable Train of Containment Cooling - Condition Prohibited
significance. This LER is closed.
    by Technical Specifications.
.2
    This issue was previously documented in NRC Integrated Inspection Report
(Closed) LER 03-004: Inoperable Train of Containment Cooling - Condition Prohibited
    05000255/2003006, Section 1R15, as a self-revealed finding of very low safety
by Technical Specifications.
    significance (Green) with an associated Non-Cited Violation for exceeding the
This issue was previously documented in NRC Integrated Inspection Report
    completion time for required actions in Technical Specification 3.6.6, Containment
05000255/2003006, Section 1R15, as a self-revealed finding of very low safety
                                                30                                    Enclosure
significance (Green) with an associated Non-Cited Violation for exceeding the
completion time for required actions in Technical Specification 3.6.6, Containment


    Cooling Systems. The inspectors did not identify any new information of significance.
Enclosure
    This LER is closed.
31
Cooling Systems. The inspectors did not identify any new information of significance.  
This LER is closed.
4OA6 Meetings
4OA6 Meetings
.1   Exit Meeting
.1
    The inspectors presented the inspection results to Mr. D. J. Malone and other members
Exit Meeting
    of licensee management on January 9, 2004. Licensee personnel acknowledged the
The inspectors presented the inspection results to Mr. D. J. Malone and other members
    findings presented. The inspectors asked licensee personnel whether any materials
of licensee management on January 9, 2004. Licensee personnel acknowledged the
    examined during the inspection should be considered proprietary. No proprietary
findings presented. The inspectors asked licensee personnel whether any materials
    information was identified.
examined during the inspection should be considered proprietary. No proprietary
.2   Interim Exit Meetings
information was identified.
    The following Interim Exit Meetings were conducted:
.2
    *       Radiation Protection (RETS/ODCM) inspection with Mr. R. Remus on
Interim Exit Meetings
            December 19, 2003. A telephonic re-exit was conducted with Messrs. J. Beer
The following Interim Exit Meetings were conducted:
            and D. G. Malone on December 31, 2003, to discuss the establishment of the
*
            URI related to the RGEM system (see Section 2PS1.2).
Radiation Protection (RETS/ODCM) inspection with Mr. R. Remus on
    *       Radiation Protection (REMP and Radioactive Material Control) inspection with
December 19, 2003. A telephonic re-exit was conducted with Messrs. J. Beer
            Mr. M. Carlson on October 24, 2003.
and D. G. Malone on December 31, 2003, to discuss the establishment of the
    *       Biennial Heat Sink inspection with Mr. D. Cooper on November 21, 2003.
URI related to the RGEM system (see Section 2PS1.2).
    *       Emergency Preparedness inspection with Mr. T. Blake on December 22, 2003.
*
ATTACHMENT: SUPPLEMENTAL INFORMATION
Radiation Protection (REMP and Radioactive Material Control) inspection with
                                            31                                    Enclosure
Mr. M. Carlson on October 24, 2003.
*
Biennial Heat Sink inspection with Mr. D. Cooper on November 21, 2003.
*
Emergency Preparedness inspection with Mr. T. Blake on December 22, 2003.
ATTACHMENT: SUPPLEMENTAL INFORMATION


                              SUPPLEMENTAL INFORMATION
Attachment
                                KEY POINTS OF CONTACT
1
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee
Licensee
D. Cooper, Senior Vice President Group Operations
D. Cooper, Senior Vice President Group Operations
Line 1,298: Line 1,534:
D. Hood, Project Manager, NRR
D. Hood, Project Manager, NRR
S. Klementowicz, NRR, Public Radiation Safety Cornerstone Lead Health Physicist
S. Klementowicz, NRR, Public Radiation Safety Cornerstone Lead Health Physicist
                                            1                                  Attachment


                LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
Attachment
2
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
Opened
Opened
05000255/2003008-01     NCV Failure of Containment Spray Pump P-54C Inboard Motor
05000255/2003008-01
                              Bearing
NCV
05000255/2003008-02     NCV Failure of High Pressure Safety Injection Pump P-66B
Failure of Containment Spray Pump P-54C Inboard Motor
                              Subcooling Valve CV-3070 to Open
Bearing
05000255/2003008-03     URI Emergency Action Level and Emergency Plan Changes
05000255/2003008-02
05000255/2003008-04     URI RGEM System Configuration May Not Obtain a
NCV
                              Representative Gaseous Effluent Sample
Failure of High Pressure Safety Injection Pump P-66B
Subcooling Valve CV-3070 to Open
05000255/2003008-03
URI
Emergency Action Level and Emergency Plan Changes
05000255/2003008-04
URI
RGEM System Configuration May Not Obtain a
Representative Gaseous Effluent Sample
Closed
Closed
05000255/2003008-01     NCV Failure of Containment Spray Pump P-54C Inboard Motor
05000255/2003008-01
                              Bearing
NCV
05000255/2003008-02     NCV Failure of High Pressure Safety Injection Pump P-66B
Failure of Containment Spray Pump P-54C Inboard Motor
                              Subcooling Valve CV-3070 to Open
Bearing
50-255/03-004           LER Inoperable Train of Containment Cooling - Condition
05000255/2003008-02
                              Prohibited by Technical Specifications
NCV
50-255/03-005           LER Emergency Diesel Generators Start on Low Voltage
Failure of High Pressure Safety Injection Pump P-66B
                              Condition
Subcooling Valve CV-3070 to Open
                                        2                                  Attachment
50-255/03-004
LER
Inoperable Train of Containment Cooling - Condition
Prohibited by Technical Specifications
50-255/03-005
LER
Emergency Diesel Generators Start on Low Voltage
Condition


                                LIST OF DOCUMENTS REVIEWED
Attachment
The following is a list of documents reviewed during the inspection. Inclusion on this list does
3
LIST OF DOCUMENTS REVIEWED
The following is a list of documents reviewed during the inspection. Inclusion on this list does
not imply that the NRC inspectors reviewed the documents in their entirety but rather that
not imply that the NRC inspectors reviewed the documents in their entirety but rather that
selected sections of portions of the documents ere evaluated as part of the overall inspection
selected sections of portions of the documents ere evaluated as part of the overall inspection
effort. Inclusion of a documents on this list does not imply NRC acceptance of the document or
effort. Inclusion of a documents on this list does not imply NRC acceptance of the document or
any part of it, unless this is stated in the body of the inspection report.
any part of it, unless this is stated in the body of the inspection report.
1R01 Adverse Weather Protection
1R01
        Off-Normal Procedure-12; Acts of Nature; Revision 18 Murray and Trettel Storm
Adverse Weather Protection
          Warning, November 12, 2003
Off-Normal Procedure-12; Acts of Nature; Revision 18 Murray and Trettel Storm
        Alarm Response Procedure-7; Auxiliary Systems Scheme EK-11 (C-13); Windows 24,
  Warning, November 12, 2003
          29, 32, 38 and 44; Revision 65
Alarm Response Procedure-7; Auxiliary Systems Scheme EK-11 (C-13); Windows 24,
        System Operating Procedure-16, Attachment 10; Frazil Ice - Information / Prevention /
  29, 32, 38 and 44; Revision 65
          Mitigation; Revision 31
System Operating Procedure-16, Attachment 10; Frazil Ice - Information / Prevention /
        System Operating Procedure-23, Attachment 8; Cold weather Checklist; Revision 17
  Mitigation; Revision 31
        System Operating Procedure-23, Attachment 9; Cold weather Checklist-Electrical;
System Operating Procedure-23, Attachment 8; Cold weather Checklist; Revision 17
          Revision 17
System Operating Procedure-23, Attachment 9; Cold weather Checklist-Electrical;
  Revision 17
Condition Reports Reviewed to Assess Significance Characterization of Identified Problems
Condition Reports Reviewed to Assess Significance Characterization of Identified Problems
        CAP038280; Evaluate Whether MV-ES3243, SIRW Tank Level Transmitter Isolation,
CAP038280; Evaluate Whether MV-ES3243, SIRW Tank Level Transmitter Isolation,
          Cold Weather Protection is Adequate
  Cold Weather Protection is Adequate
        CAP038315; Work Week 2344: Cold Weather Checklist Not Completed in a Timely
CAP038315; Work Week 2344: Cold Weather Checklist Not Completed in a Timely
          Manner
  Manner
Condition Reports Reviewed To Assess Corrective Actions
Condition Reports Reviewed To Assess Corrective Actions
        CAP033427; Received ED-1129 Service Water Bay Low Level Alarm
CAP033427; Received ED-1129 Service Water Bay Low Level Alarm
        CAP038281; LT-0331, SIRW Tank Level Transmitter, Not Checked in SOP-23,
CAP038281; LT-0331, SIRW Tank Level Transmitter, Not Checked in SOP-23,
          Attachment 8, Cold Weather Checklist
  Attachment 8, Cold Weather Checklist
        CAP038000; Intake Structure Ventilation Operation Contrary to Updated Final Safety
CAP038000; Intake Structure Ventilation Operation Contrary to Updated Final Safety
          Analysis Report Described Operation
  Analysis Report Described Operation
1R04 Equipment Alignment
1R04
Equipment Alignment
Plant Procedures and Miscellaneous Documents
Plant Procedures and Miscellaneous Documents
        SOP-19; Instrument and Service Air System Checklist; Revision 29
SOP-19; Instrument and Service Air System Checklist; Revision 29
        SOP-24 Ventilation and Air Conditioning System; Revision 37
SOP-24 Ventilation and Air Conditioning System; Revision 37
        WO24323843; Clean All Blockages on P-66A Bearing Housing Caps
WO24323843; Clean All Blockages on P-66A Bearing Housing Caps
        M218; Piping and Instrument Diagram for the Control Room Heating, Ventilation and Air
M218; Piping and Instrument Diagram for the Control Room Heating, Ventilation and Air
          Conditioning
  Conditioning
                                                  3                                  Attachment


Attachment
4
Condition Reports Reviewed to Assess Corrective Actions
Condition Reports Reviewed to Assess Corrective Actions
      CAP037656; Potential Loss of High Pressure Safety Injection Pump Bearing Housing
CAP037656; Potential Loss of High Pressure Safety Injection Pump Bearing Housing
        Vent Path
  Vent Path
      CAP037659; P-67A Low Pressure Safety Injection Pump Bearing Housing Vent
CAP037659; P-67A Low Pressure Safety Injection Pump Bearing Housing Vent
        Inspection
  Inspection
Condition Reports Reviewed to Assess Significance Characterization of Identified Problems
Condition Reports Reviewed to Assess Significance Characterization of Identified Problems
      CAP038709; East Mechanical Equipment Room Deficiencies Noted by NRC
CAP038709; East Mechanical Equipment Room Deficiencies Noted by NRC
1R05 Fire Protection
1R05
Fire Protection
Plant Procedures
Plant Procedures
      ONP25.2; Off-Normal Procedure - Fire Which Threatens Safety-Related Equipment Fire
ONP25.2; Off-Normal Procedure - Fire Which Threatens Safety-Related Equipment Fire
        Areas 12, 10, 30, 31; Revision 12
  Areas 12, 10, 30, 31; Revision 12
      FPSP-SI-1; Data Sheet for Alarm Bells and Ionization Smoke Detectors for Fire Areas
FPSP-SI-1; Data Sheet for Alarm Bells and Ionization Smoke Detectors for Fire Areas
        12, 10, 30, 31, Revision 3
  12, 10, 30, 31, Revision 3
      FPSP-RP-11; Fire Barrier Penetration Seal/Conduit Seal Inspection Form for Fire Areas
FPSP-RP-11; Fire Barrier Penetration Seal/Conduit Seal Inspection Form for Fire Areas
        12, 10 30, 31; Revision 5
  12, 10 30, 31; Revision 5
      FPSP-RM-5; Palisades Fire Damper Sheet for Fire Areas 12; Revision 2
FPSP-RM-5; Palisades Fire Damper Sheet for Fire Areas 12; Revision 2
      FPSP-SO-2; Safety-Related Fire Door Data Sheet for Fire Areas 12, 10, 30, 31;
FPSP-SO-2; Safety-Related Fire Door Data Sheet for Fire Areas 12, 10, 30, 31;
        Revision 0
  Revision 0
      FPSP-WP-1; Safety-Related Fire Door Data Sheet Fire Areas 12, 10, 30, 31; Revision 1
FPSP-WP-1; Safety-Related Fire Door Data Sheet Fire Areas 12, 10, 30, 31; Revision 1
Condition Reports Reviewed to Assess Corrective Actions
Condition Reports Reviewed to Assess Corrective Actions
      CAP029787; Containment Fire Detection does Not Meet Code of Record
CAP029787; Containment Fire Detection does Not Meet Code of Record
      CAP029676; Technical Inaccuracies In the Fire protection Program Report
CAP029676; Technical Inaccuracies In the Fire protection Program Report
Condition Reports Reviewed to Assess Significance Characterization of Identified Problems
Condition Reports Reviewed to Assess Significance Characterization of Identified Problems
      CAP038727; Emergency Lighting Unit ELU-67 is Directed Slightly Upward (Above
CAP038727; Emergency Lighting Unit ELU-67 is Directed Slightly Upward (Above
        Horizontal)
  Horizontal)
      CAP039240; "Fire Detectors Not Installed as Outlined in the Modification Package"
CAP039240; "Fire Detectors Not Installed as Outlined in the Modification Package"
Miscellaneous Documents
Miscellaneous Documents
      FSAR; Section 9.6, Fire Protection; Revision 23
FSAR; Section 9.6, Fire Protection; Revision 23
      FSAR; Section 9, Fire Detection Instrumentation; Revision 24
FSAR; Section 9, Fire Detection Instrumentation; Revision 24
      Fire Hazards Analysis Report; Revision 4
Fire Hazards Analysis Report; Revision 4
      Palisades Plant Post Fire Safe Shut-down Summary Report; September 1, 1978
Palisades Plant Post Fire Safe Shut-down Summary Report; September 1, 1978
      Fire Protection Safety Evaluation Report by the Office of NRR in the Matter of
Fire Protection Safety Evaluation Report by the Office of NRR in the Matter of
        Consumers Power Company Palisades Plant Docket 50-255; September 1, 1978
  Consumers Power Company Palisades Plant Docket 50-255; September 1, 1978
                                              4                                    Attachment


1R06 Flood Protection
Attachment
      Final Safety Analysis Report; Table 5.4-1; Safety Related Equipment That Requires
5
        Protection From Flooding Due to Failures of Nonclass 1 Systems; Revision 21
1R06
      Final Safety Analysis Report; Section 5.4.2; Flooding and Wetting From Plant Sources;
Flood Protection
        Revision 24
Final Safety Analysis Report; Table 5.4-1; Safety Related Equipment That Requires
  Protection From Flooding Due to Failures of Nonclass 1 Systems; Revision 21
Final Safety Analysis Report; Section 5.4.2; Flooding and Wetting From Plant Sources;
  Revision 24
Condition Reports Reviewed to Assess Corrective Actions
Condition Reports Reviewed to Assess Corrective Actions
      CAP035933; Expansion Joint Inspection Fails to Identify Known Deficiency
CAP035933; Expansion Joint Inspection Fails to Identify Known Deficiency
      CAP034759; Water Tight Door #58 Failed Inspection (Doghouse Door)
CAP034759; Water Tight Door #58 Failed Inspection (Doghouse Door)
      CAP034720; Water Tight Door #51 Failed Inspection Criteria
CAP034720; Water Tight Door #51 Failed Inspection Criteria
Work Orders
Work Orders
      WO24321400; Door 58, East Engineered Safeguards Doghouse Door
WO24321400; Door 58, East Engineered Safeguards Doghouse Door
      WO24321399; Door 51, Engineering Safeguards Entrance
WO24321399; Door 51, Engineering Safeguards Entrance
1R07 Heat Sink Performance
1R07
      CH 1.11; MIC Control Program Inspection Report - VC-10; dated April 18, 2001,
Heat Sink Performance
        October 24, 2002, and February 24, 2003
CH 1.11; MIC Control Program Inspection Report - VC-10; dated April 18, 2001,  
      CH 1.11; MIC Control Program Inspection Report - VC-10 Service Water Piping; dated
  October 24, 2002, and February 24, 2003
        October 24, 2002
CH 1.11; MIC Control Program Inspection Report - VC-10 Service Water Piping; dated
      CH 1.11; MIC Control Program Inspection Report - VC-11; dated October 1, 2001, and
  October 24, 2002
        July 29, 2003
CH 1.11; MIC Control Program Inspection Report - VC-11; dated October 1, 2001, and
      CH 1.11; MIC Control Program Inspection Report - VC-11 Service Water Piping; dated
  July 29, 2003
        December 4, 2001
CH 1.11; MIC Control Program Inspection Report - VC-11 Service Water Piping; dated
      CH 1.11; MIC Control Program Inspection Report - VC-11 Service Water Valve
  December 4, 2001
        MV-SW281; dated December 4, 2001
CH 1.11; MIC Control Program Inspection Report - VC-11 Service Water Valve
      CH 1.11; MIC Control Program Inspection Report - VHX-2; dated April 12, 2001
  MV-SW281; dated December 4, 2001
      CH 1.11; MIC Control Program Inspection Report - VHX-3; dated March 30, 2003
CH 1.11; MIC Control Program Inspection Report - VHX-2; dated April 12, 2001
      CH 1.11; Biofouling and MIC Control Program; Revision 1
CH 1.11; MIC Control Program Inspection Report - VHX-3; dated March 30, 2003
      DBD-1.06; Control Room HVAC System; Revision 7
CH 1.11; Biofouling and MIC Control Program; Revision 1
      DBD-2.08; Containment Air Coolers; Revision 2
DBD-1.06; Control Room HVAC System; Revision 7
      EA-D-PAL-93-272E-02; Control Room HVAC Refrigeration Unit Performance at
DBD-2.08; Containment Air Coolers; Revision 2
        85 Degrees Fahrenheit Entering Service Water Temperature; Revision 0
EA-D-PAL-93-272E-02; Control Room HVAC Refrigeration Unit Performance at  
      EA-LOCA-2001-01; Containment Response to a LOCA Using CONTEMPT-LT/28;
  85 Degrees Fahrenheit Entering Service Water Temperature; Revision 0
        Revision 1
EA-LOCA-2001-01; Containment Response to a LOCA Using CONTEMPT-LT/28;
      EA-LTP-99-01; Methodology for Capacity Testing and Analysis of the Control Room
  Revision 1
        HVAC System; Revision 0
EA-LTP-99-01; Methodology for Capacity Testing and Analysis of the Control Room
      EA-VC10/11-2000; Uncertainty Analysis for the Control Room HVAC System
  HVAC System; Revision 0
        Surveillance Procedure; Revision 1
EA-VC10/11-2000; Uncertainty Analysis for the Control Room HVAC System
      EM-09-15; Raw Water Corrosion Program; Revision 4
  Surveillance Procedure; Revision 1
      EM-09-16; Heat Exchanger Condition Assessment Program; Revision 3
EM-09-15; Raw Water Corrosion Program; Revision 4
      EM-09-16; Heat Exchanger Visual Testing Checklist - VC-11; completed July 29, 2003
EM-09-16; Heat Exchanger Condition Assessment Program; Revision 3
      RO-216; Service Water Flow Verification; Revision 2; completed April 4, 2003
EM-09-16; Heat Exchanger Visual Testing Checklist - VC-11; completed July 29, 2003
      RT-202, Basis Document; Control Room Heat Removal Capability; Revision 1
RO-216; Service Water Flow Verification; Revision 2; completed April 4, 2003
                                              5                                  Attachment
RT-202, Basis Document; Control Room Heat Removal Capability; Revision 1


      RT-202; Control Room Heat Removal Capability (Train A); Revision 2; completed
Attachment
        August 19, 2003
6
      RT-202; Control Room Heat Removal Capability (Train B); Revision 2; completed
RT-202; Control Room Heat Removal Capability (Train A); Revision 2; completed  
        August 19, 2003
  August 19, 2003
      Palisades 2001 Refuel Outage Report by Underwater Construction Corporation; dated
RT-202; Control Room Heat Removal Capability (Train B); Revision 2; completed  
        May 15, 2001
  August 19, 2003
      Palisades 2003 Refuel Outage Report by Underwater Construction Corporation; dated
Palisades 2001 Refuel Outage Report by Underwater Construction Corporation; dated
        April 5, 2003
  May 15, 2001
      Raw Water Corrosion Program Report Operational Cycle 15 and 2001 Refueling Outage
Palisades 2003 Refuel Outage Report by Underwater Construction Corporation; dated
        Report; dated August 13, 2001
  April 5, 2003
      Raw Water Corrosion Program Report Operational Cycle 16 and 2003 Refueling Outage
Raw Water Corrosion Program Report Operational Cycle 15 and 2001 Refueling Outage
        Report; dated July 22, 2003
  Report; dated August 13, 2001
      NMC Letter to NRC; Resolution of Generic Letter 96-06 Waterhammer Issues; dated
Raw Water Corrosion Program Report Operational Cycle 16 and 2003 Refueling Outage
        February 28, 2003
  Report; dated July 22, 2003
      NMC Letter to NRC; Resolution of Generic Letter 96-06 Two-Phase Flow Issues; dated
NMC Letter to NRC; Resolution of Generic Letter 96-06 Waterhammer Issues; dated
        July 24, 2003
  February 28, 2003
      M123; Heating & Ventilation Reactor Containment Building Coolers-Unit V-3; Revision 0
NMC Letter to NRC; Resolution of Generic Letter 96-06 Two-Phase Flow Issues; dated
      M124; Heating & Ventilation Reactor Containment Building Coolers-Unit V-1 and
  July 24, 2003
        Unit V-2; Revision 6
M123; Heating & Ventilation Reactor Containment Building Coolers-Unit V-3; Revision 0
      M218; HTG. Vent. & Air Cond. Control Room; Revision 9
M124; Heating & Ventilation Reactor Containment Building Coolers-Unit V-1 and
      VEN-M-60A, Sheet 1; Type R Coil 36 Tube Face, 4'-11 1/2 NTL, 12 Row, 4 Pass;
  Unit V-2; Revision 6
        Revision 1
M218; HTG. Vent. & Air Cond. Control Room; Revision 9
      VEN-M-60A, Sheet 2; Type R Coil 36 Tube Face, 4'-11 1/2 NTL, 12 Row, 4 Pass;
VEN-M-60A, Sheet 1; Type R Coil 36 Tube Face, 4'-11 1/2 NTL, 12 Row, 4 Pass;
        Revision 0
  Revision 1
      VEN-M-60A, Sheet 7; Containment Air Coolers VHX-1, VHX-2, and VHX-3 Cooling Coil
VEN-M-60A, Sheet 2; Type R Coil 36 Tube Face, 4'-11 1/2 NTL, 12 Row, 4 Pass;
        Tube Map; Revision 0
  Revision 0
      C-PAL-00-3205; Apparent Tube Blockage on Containment Air Cooler Coil VHX-3; dated
VEN-M-60A, Sheet 7; Containment Air Coolers VHX-1, VHX-2, and VHX-3 Cooling Coil
        October 26, 2000
  Tube Map; Revision 0
      C-PAL-00-3664; Thermography Scanning Finds More Containment Air Cooler Tubing
C-PAL-00-3205; Apparent Tube Blockage on Containment Air Cooler Coil VHX-3; dated
        Plugged; dated December 20, 2000
  October 26, 2000
1R11 Licensed Operator Requalification
C-PAL-00-3664; Thermography Scanning Finds More Containment Air Cooler Tubing
      Simulator Performance Exercise - 42; Licensed Operator Requalification; Course
  Plugged; dated December 20, 2000
        N00320; Revision 0
1R11
      Simulator Performance Evaluation; Crew 1; December 3, 2003
Licensed Operator Requalification
1R13 Maintenance Risk Assessments and Emergent Work Evaluation
Simulator Performance Exercise - 42; Licensed Operator Requalification; Course
  N00320; Revision 0
Simulator Performance Evaluation; Crew 1; December 3, 2003
1R13
Maintenance Risk Assessments and Emergent Work Evaluation
Miscellaneous Documents
Miscellaneous Documents
      Operators Risk Reports; September 29 through October 3, November 10-13 and 18-19,
Operators Risk Reports; September 29 through October 3, November 10-13 and 18-19,
        and December 7-10
  and December 7-10
      Daily Maintenance Work Schedules; September 29 through October 3, November 10-13
Daily Maintenance Work Schedules; September 29 through October 3, November 10-13
        and 18-19, and December 7-10
  and 18-19, and December 7-10
      Operations Log entries; September 29 through October 3, November 10-13 and 18-19,
Operations Log entries; September 29 through October 3, November 10-13 and 18-19,
        and December 7-10
  and December 7-10
                                              6                                  Attachment


1R14 Non-Routine Plant Evolutions and Events
Attachment
7
1R14
Non-Routine Plant Evolutions and Events
Plant Procedures
Plant Procedures
      Alarm Response Procedure - 1; Turbine Condenser and Feedwater Scheme EK-01;
Alarm Response Procedure - 1; Turbine Condenser and Feedwater Scheme EK-01;
        Window 60; Feedwater Pumps Lo Suction; Revision 52
  Window 60; Feedwater Pumps Lo Suction; Revision 52
      Alarm Response Procedure - 1;Turbine Condenser and Feedwater Scheme EK-01;
Alarm Response Procedure - 1;Turbine Condenser and Feedwater Scheme EK-01;
        Window 72; Moisture Separator Drain Tank Hi-Lo Level; Revision 52
  Window 72; Moisture Separator Drain Tank Hi-Lo Level; Revision 52
      Off Normal Procedure - 3; Loss of Main Feedwater; Revision 19
Off Normal Procedure - 3; Loss of Main Feedwater; Revision 19
      Off Normal Procedure - 26; Rapid Power Reduction; Revision 1
Off Normal Procedure - 26; Rapid Power Reduction; Revision 1
      System Operation Procedure - 8, Attachment 2; Main Turbine and Generating Systems,
System Operation Procedure - 8, Attachment 2; Main Turbine and Generating Systems,
        System Testing; Revision 65
  System Testing; Revision 65
Condition Reports Reviewed to Assess Significance Characterization for Identified Problems
Condition Reports Reviewed to Assess Significance Characterization for Identified Problems
      CAP038519; Unanticipated Trip of A Heater Drain Pump During Turbine Valve Testing
CAP038519; Unanticipated Trip of A Heater Drain Pump During Turbine Valve Testing
      CAP038508; Unexpected Alarm EK-0172 Moisture Separator Drain Tank Hi-Lo Level
CAP038508; Unexpected Alarm EK-0172 Moisture Separator Drain Tank Hi-Lo Level
      CAP038512; E-9A MSR Reheat Stop Valve CV-0537 Failed to Close During Turbine
CAP038512; E-9A MSR Reheat Stop Valve CV-0537 Failed to Close During Turbine
        Valve Testing
  Valve Testing
      CAP038514; Heater Drain Pump P-10A Discharge Check Valve Stuck Open
CAP038514; Heater Drain Pump P-10A Discharge Check Valve Stuck Open
      CAP038511; E-9B MSR Intercept Valve CV-0535 Failed to Reopen During Turbine
CAP038511; E-9B MSR Intercept Valve CV-0535 Failed to Reopen During Turbine
        Valve Testing
  Valve Testing
      CAP038509; Received Alarm EK-0105, Turbine High Vibration, Unexpectedly
CAP038509; Received Alarm EK-0105, Turbine High Vibration, Unexpectedly
      CAP038513; Plant Challenges Due to Closure of MSR E-9A Reheat Sop Valve CV-0537
CAP038513; Plant Challenges Due to Closure of MSR E-9A Reheat Sop Valve CV-0537
1R17 Permanent Plant Modifications
1R17
Permanent Plant Modifications
Engineering Assistance Requests
Engineering Assistance Requests
      EAR-2000-0345; Seismic Qualification Utility Group Outlier Resolution for Safety
EAR-2000-0345; Seismic Qualification Utility Group Outlier Resolution for Safety
        Injection Refueling Water Tank, T-58; June 18, 2003
  Injection Refueling Water Tank, T-58; June 18, 2003
      EAR-2000-017; Alternate Safe-Shutdown Pathway for Cold-Shutdown Using Service
EAR-2000-017; Alternate Safe-Shutdown Pathway for Cold-Shutdown Using Service
        Water; May 30, 2003
  Water; May 30, 2003
      EAR-2002-0293; Piping Modifications to Charging Pump Suction Piping to Facilitate
EAR-2002-0293; Piping Modifications to Charging Pump Suction Piping to Facilitate
        Crosstie Via Fire Hose from the Spent Fuel Pool Piping for Alternate Safe-Shutdown
  Crosstie Via Fire Hose from the Spent Fuel Pool Piping for Alternate Safe-Shutdown
        Pathway for Hot-Shutdown; May 9, 2003
  Pathway for Hot-Shutdown; May 9, 2003
Plant Procedures
Plant Procedures
      PCSO-5; Special Operating Procedure, Alternate Source for Charging to PCS;
PCSO-5; Special Operating Procedure, Alternate Source for Charging to PCS;
        Revision 0
  Revision 0
      COP-27; Chemistry Operating Procedure, Spent Fuel Pool System Chemistry;
COP-27; Chemistry Operating Procedure, Spent Fuel Pool System Chemistry;
        Revision 17
  Revision 17
      PPAC X-OPSADM02; Preventive Maintenance Work Order - Alternate Safe Shutdown
PPAC X-OPSADM02; Preventive Maintenance Work Order - Alternate Safe Shutdown
        Pathway Inspect
  Pathway Inspect
                                              7                                    Attachment


Attachment
8
Condition Reports Reviewed to Assess Significance Characterization of Identified Problems
Condition Reports Reviewed to Assess Significance Characterization of Identified Problems
      CAP038236; Spent Fuel Pool Boron Administrative Limit Not Timely Incorporated in
CAP038236; Spent Fuel Pool Boron Administrative Limit Not Timely Incorporated in
        Chemistry Procedures
  Chemistry Procedures
      CAP036336; Closeout Item EAR-2000-0345 - SFP Boron Concentration During
CAP036336; Closeout Item EAR-2000-0345 - SFP Boron Concentration During
        Maintenance
  Maintenance
      CAP036337; Closeout Items EAR-2000-0345 - Q-List Interpretations
CAP036337; Closeout Items EAR-2000-0345 - Q-List Interpretations
      CAP038956; Inadequate Documentation of Justification for Design Change
CAP038956; Inadequate Documentation of Justification for Design Change
Piping and Instrument Diagrams
Piping and Instrument Diagrams
      M-202; Sheet 1B; Chemical and Volume Control System; Revision 50
M-202; Sheet 1B; Chemical and Volume Control System; Revision 50
      M-208; Sheet 1A; Service Water System; Revision 52
M-208; Sheet 1A; Service Water System; Revision 52
      M-221; Sheet 2; Spent Fuel Pool Cooling System; Revision 50
M-221; Sheet 2; Spent Fuel Pool Cooling System; Revision 50
1R19 Post Maintenance Testing
1R19
Post Maintenance Testing
Work Orders
Work Orders
      WO24322197; Service Water Pump P-7C; October 29, 2003
WO24322197; Service Water Pump P-7C; October 29, 2003
      WO24323161; EDG 1-2 K-6B Starting Air Pressure Control; September 29, 2003
WO24323161; EDG 1-2 K-6B Starting Air Pressure Control; September 29, 2003
      WO24321782; EDG Air Starting Motor (ASM-2B); September 29, 2003
WO24321782; EDG Air Starting Motor (ASM-2B); September 29, 2003
      WO24213350; Replace SV-1452 (K-6B/Fuel Oil); September 29, 2003
WO24213350; Replace SV-1452 (K-6B/Fuel Oil); September 29, 2003
      WO24323928; Wire 1B on Terminal Block TC Pinched; September 30, 2003
WO24323928; Wire 1B on Terminal Block TC Pinched; September 30, 2003
      WO24112283; EDG 1-2 to Bus 1D; September 30, 2003
WO24112283; EDG 1-2 to Bus 1D; September 30, 2003
      WO24213073; EDG 1-2 Air Start Motor ASM-2A Isolation; September 29, 2003
WO24213073; EDG 1-2 Air Start Motor ASM-2A Isolation; September 29, 2003
      WO24113680 Attachment B; functional Test of Breaker 152-111
WO24113680 Attachment B; functional Test of Breaker 152-111
Plant Procedures
Plant Procedures
      SWS-M-12; Service Water Pumps P-7A, P-7B and P-7C Repack; Revision 1
SWS-M-12; Service Water Pumps P-7A, P-7B and P-7C Repack; Revision 1
      MO7A2; Emergency Diesel Generator 1-2; Revision 56
MO7A2; Emergency Diesel Generator 1-2; Revision 56
      SOP-22; Emergency Diesel Generators; Revision 35
SOP-22; Emergency Diesel Generators; Revision 35
      QO-20B; Inservice Test: Low Pressure Safety Injection Pumps; Revision 12
QO-20B; Inservice Test: Low Pressure Safety Injection Pumps; Revision 12
Miscellaneous Documents
Miscellaneous Documents
      Final Safety Analysis Report, Section 6.1; Safety Injection System; Revision 23
Final Safety Analysis Report, Section 6.1; Safety Injection System; Revision 23
      Technical Specifications 3.5.2; Emergency Core Cooling System
Technical Specifications 3.5.2; Emergency Core Cooling System
      Technical Specifications Bases 3.5.2; Emergency Core Cooling System
Technical Specifications Bases 3.5.2; Emergency Core Cooling System
Condition Reports Reviewed to Assess Significance Characterization of Identified Problems
Condition Reports Reviewed to Assess Significance Characterization of Identified Problems
      CAP038299; Siemens Breaker S/N R-300511A-8 Failed to Close During Testing
CAP038299; Siemens Breaker S/N R-300511A-8 Failed to Close During Testing
      CAP038302; Insufficient Cooling for Packing on Service Water P-7C After Repack
CAP038302; Insufficient Cooling for Packing on Service Water P-7C After Repack
      CAP038317; Service Water Pump Repacked With Larger Than Required Packing
CAP038317; Service Water Pump Repacked With Larger Than Required Packing
      CAP038320; Maintenance Violated the Procedural Step Requirement in Step 5.3.2 in
CAP038320; Maintenance Violated the Procedural Step Requirement in Step 5.3.2 in
        SWS-M-12
  SWS-M-12
                                              8                                    Attachment


1R22 Surveillance Testing
Attachment
9
1R22
Surveillance Testing
Completed Surveillance Test Procedures
Completed Surveillance Test Procedures
      QO-1; Safety Injection System; Revision 49
QO-1; Safety Injection System; Revision 49
      MO-33; Control Room Ventilation Emergency Operation; Revision 9
MO-33; Control Room Ventilation Emergency Operation; Revision 9
      QO-14; Inservice Test Procedure - Service Water Pumps; Revision 21
QO-14; Inservice Test Procedure - Service Water Pumps; Revision 21
Miscellaneous Documents
Miscellaneous Documents
      FSAR 7.3; Engineered Safeguards Controls; Revision 23
FSAR 7.3; Engineered Safeguards Controls; Revision 23
      Reg Guide 1.52; Design, Inspection and Testing Criteria for Air Filtration and Adsorption
Reg Guide 1.52; Design, Inspection and Testing Criteria for Air Filtration and Adsorption
        Units of Post-Accident ESF Atmosphere Cleanup System in Light Water-Cooled
  Units of Post-Accident ESF Atmosphere Cleanup System in Light Water-Cooled
        Nuclear Power Plants; Revision 3
  Nuclear Power Plants; Revision 3
      NUREG/CR-496; Control Room Habitability Survey of Licensed Commercial Nuclear
NUREG/CR-496; Control Room Habitability Survey of Licensed Commercial Nuclear
        Power Generating Stations
  Power Generating Stations
Condition Reports Reviewed to Assess Significance Characterization of Identified Problems
Condition Reports Reviewed to Assess Significance Characterization of Identified Problems
      CAP038044; Unexpected Containment Air Cooler Service Water System Leak Alarm
CAP038044; Unexpected Containment Air Cooler Service Water System Leak Alarm
        Received During QO-1 SIS Testing
  Received During QO-1 SIS Testing
      CAP038110; Missed Sign Off for AC&O Sheet in Body of Procedure
CAP038110; Missed Sign Off for AC&O Sheet in Body of Procedure
Condition Reports Reviewed to Assess Corrective Actions
Condition Reports Reviewed to Assess Corrective Actions
      CAP037153; Palisades Control Room Habitability Not in Complete Conformance With
CAP037153; Palisades Control Room Habitability Not in Complete Conformance With
        NRC Guidance
  NRC Guidance
1REP Equipment Availability and Functional Capability
1REP Equipment Availability and Functional Capability  
Maintenance Effectiveness
Maintenance Effectiveness
Plant Procedures
Plant Procedures
      WI-ESS-O-02; Containment Spray Pump/Motor Oil Sample and Change; Revision 0
WI-ESS-O-02; Containment Spray Pump/Motor Oil Sample and Change; Revision 0
      ESS-E-36; Component Cooling and Containment Spray Motor Maintenance; Revision 6
ESS-E-36; Component Cooling and Containment Spray Motor Maintenance; Revision 6
      VTD-0322-0005; Louis-Allis Co. Instruction Manual for Large Motors
VTD-0322-0005; Louis-Allis Co. Instruction Manual for Large Motors
      EGAD-EP-10; Maintenance Rule Scoping Document for 2400V AC Power and 4160V
EGAD-EP-10; Maintenance Rule Scoping Document for 2400V AC Power and 4160V
        AC Power Systems; Revision 2
  AC Power Systems; Revision 2
Miscellaneous Documents
Miscellaneous Documents
      Containment Spray Pump Motor Oil Change Out History
Containment Spray Pump Motor Oil Change Out History
      Daily Checklists for Painting Floors/Walls/Equipment
Daily Checklists for Painting Floors/Walls/Equipment
      Palisades Maintenance Rule Performance Indicators for 2400V AC Power and 4160V
Palisades Maintenance Rule Performance Indicators for 2400V AC Power and 4160V  
        AC Power Systems
  AC Power Systems
      Palisades Maintenance Rule Performance Monitoring Results for 2400V AC Power and
Palisades Maintenance Rule Performance Monitoring Results for 2400V AC Power and
        4160V AC Power Systems
  4160V AC Power Systems
                                                9                                    Attachment


      Health and Status Report for 2400V AC Power and 4160V AC Power Systems
Attachment
      FSAR; Chapter 8, Electrical Systems; Revision 23
10
Health and Status Report for 2400V AC Power and 4160V AC Power Systems
FSAR; Chapter 8, Electrical Systems; Revision 23
Work Orders
Work Orders
      PPAC X-OPS310; EEQ Required P-54A, B, C Motor Oil Change and Containment
PPAC X-OPS310; EEQ Required P-54A, B, C Motor Oil Change and Containment
        Spray Pump Motor Oil Change P-54A, B, C
  Spray Pump Motor Oil Change P-54A, B, C
      WO24320008; Miscellaneous Mechanical System Work
WO24320008; Miscellaneous Mechanical System Work
Condition Reports Reviewed to Assess Maintenance Rule Evaluations and Corrective Actions
Condition Reports Reviewed to Assess Maintenance Rule Evaluations and Corrective Actions
      CAP037180; Smoke Observed Coming From Containment Spray Pump P-54C Inboard
CAP037180; Smoke Observed Coming From Containment Spray Pump P-54C Inboard
        Motor Bearing
  Motor Bearing
      CAP034584; Undervoltage Relays on F and G Busses Failed to Reset
CAP034584; Undervoltage Relays on F and G Busses Failed to Reset
      CAP031363; Breaker 152-306 Failed to Close From Control Room
CAP031363; Breaker 152-306 Failed to Close From Control Room
Biennial Assessment of Maintenance Rule Periodic Evaluations
Biennial Assessment of Maintenance Rule Periodic Evaluations
Miscellaneous Documents
Miscellaneous Documents
      EGAD-EP-10, Attachment 2; Maintenance Rule Scoping Document For Concentrated
EGAD-EP-10, Attachment 2; Maintenance Rule Scoping Document For Concentrated
        Boric Acid System, Control Room HVAC System, High Pressure Air System and the
  Boric Acid System, Control Room HVAC System, High Pressure Air System and the
        Fire Protection System; Revision 2
  Fire Protection System; Revision 2
      Health and Status Reports for Concentrated Boric Acid System, Control Room HVAC
Health and Status Reports for Concentrated Boric Acid System, Control Room HVAC
        System, High Pressure Air System and the Fire Protection System
  System, High Pressure Air System and the Fire Protection System
      Palisades Plant - Maintenance Rule Periodic Refueling Assessment; August 21, 2000 to
Palisades Plant - Maintenance Rule Periodic Refueling Assessment; August 21, 2000 to
        July 31, 2002
  July 31, 2002
Condition Reports Reviewed to Assess Maintenance Rule Evaluations and Corrective Actions
Condition Reports Reviewed to Assess Maintenance Rule Evaluations and Corrective Actions
      CAP036655; Received EK-0726 Boric Acid Pumps P-56A and P-56B Overload
CAP036655; Received EK-0726 Boric Acid Pumps P-56A and P-56B Overload
        Unexpectedly
  Unexpectedly
Condition Reports Reviewed to Assess Corrective Actions
Condition Reports Reviewed to Assess Corrective Actions
      CAP036114; Boric Acid Availability Does Not Meet Maintenance Rule Criteria
CAP036114; Boric Acid Availability Does Not Meet Maintenance Rule Criteria
      CAP03583; Maintenance Rule Performance Criteria Exceeded for Control Room HVAC
CAP03583; Maintenance Rule Performance Criteria Exceeded for Control Room HVAC
        System
  System
      CAP015712; Unusual Noise and Smoke Coming from VC-11, Control Room HVAC
CAP015712; Unusual Noise and Smoke Coming from VC-11, Control Room HVAC
        condensing unit
  condensing unit
      CAP031618; Door 16 Mechanical Equipment Room Results in TS3.7.10 A/B Entry
CAP031618; Door 16 Mechanical Equipment Room Results in TS3.7.10 A/B Entry
      CAP032834; Inoperable B Train Control Room Ventilation Cooling
CAP032834; Inoperable B Train Control Room Ventilation Cooling
      CAP034899; Control Room Cooling Train (VC-11) Inoperable
CAP034899; Control Room Cooling Train (VC-11) Inoperable
      CAP031633; High Pressure Air Compressor C-6A Inoperable Due to Failed Oil Level
CAP031633; High Pressure Air Compressor C-6A Inoperable Due to Failed Oil Level
        Switch
  Switch
      CAP037303; Oil Cap Unsecure On High Pressure Air Compressor C-6C
CAP037303; Oil Cap Unsecure On High Pressure Air Compressor C-6C
      CPAL990984; Maintenance Rule Category (a)(1) Performance Improvement of the High
CPAL990984; Maintenance Rule Category (a)(1) Performance Improvement of the High  
        Pressure Air System
  Pressure Air System  
      CAP031907; Evaluate Returning P-9B to Maintenance Rule Category (a)(2)
CAP031907; Evaluate Returning P-9B to Maintenance Rule Category (a)(2)
                                            10                                  Attachment


      CAP029995; Fire Pump P-9B Unavailability Exceeds Maintenance Rule Performance
Attachment
        Indicators
11
      CPAL0200457; Fire Protection Maintenance Preventable Functional Failure of Electric
CAP029995; Fire Pump P-9B Unavailability Exceeds Maintenance Rule Performance
        Fire Pump P-9A Exceeds Performance Criteria
  Indicators
      CPAL0200497; Electric Fire Pump P-9A Fails to Meet Maintenance rule Availability
CPAL0200457; Fire Protection Maintenance Preventable Functional Failure of Electric
        Requirements
  Fire Pump P-9A Exceeds Performance Criteria
      CPAL0200059; Fire Pump P-9A Tripped After Running For Approximately 3 Minutes
CPAL0200497; Electric Fire Pump P-9A Fails to Meet Maintenance rule Availability
      CAP032600; Fire Protection System Exceeds Maintenance Rule Reliability Performance
  Requirements
        Criteria
CPAL0200059; Fire Pump P-9A Tripped After Running For Approximately 3 Minutes
      CAP033278; Compressor Related System Performance Issues
CAP032600; Fire Protection System Exceeds Maintenance Rule Reliability Performance  
      CAP032927; Weakness in Timely Resolution of Maintenance Rule (a)(1) Issues
  Criteria
      CAP033280; Maintenance Rule Availability Performance Criteria Limitations in the
CAP033278; Compressor Related System Performance Issues
        Scheduling Process
CAP032927; Weakness in Timely Resolution of Maintenance Rule (a)(1) Issues
CAP033280; Maintenance Rule Availability Performance Criteria Limitations in the
  Scheduling Process
Operability Evaluations
Operability Evaluations
Plant Procedures
Plant Procedures
      EM-18-02; Interim Operability Criteria Evaluation For Palisades Plant Safety-Related
EM-18-02; Interim Operability Criteria Evaluation For Palisades Plant Safety-Related
        Piping Systems; Revision 1
  Piping Systems; Revision 1
Condition Reports Associated with Operabililty Determinations
Condition Reports Associated with Operabililty Determinations
      CAP038087; Change the Source CAP for the Operable But Degraded Piping Feeding
CAP038087; Change the Source CAP for the Operable But Degraded Piping Feeding
        CVCS [Chemical Volume Control System]
  CVCS [Chemical Volume Control System]
      CAP032550; Steam Generator Low Pressure Bypass Not Calibrated in Appropriate
CAP032550; Steam Generator Low Pressure Bypass Not Calibrated in Appropriate
        Direction
  Direction
      CAP037030; Subcooling CV-3070 Failed to Open During QO-5 Valve Test Procedure
CAP037030; Subcooling CV-3070 Failed to Open During QO-5 Valve Test Procedure
Miscellaneous Documents
Miscellaneous Documents
      Final Safety Analysis Report; Section 5.10.1.4; Interim Operability Criteria; Revision 21
Final Safety Analysis Report; Section 5.10.1.4; Interim Operability Criteria; Revision 21
      Technical Specifications 3.3.3; Engineered Safety Features Instrumentation
Technical Specifications 3.3.3; Engineered Safety Features Instrumentation
      Final Safety Analysis Report; Section 7.2.3.8; Low Steam Generator Pressure;
Final Safety Analysis Report; Section 7.2.3.8; Low Steam Generator Pressure;  
        Revision 23
  Revision 23
Condition Reports Reviewed to Assess Corrective Actions
Condition Reports Reviewed to Assess Corrective Actions
      CAP030037; Incorrect Operability Determinations
CAP030037; Incorrect Operability Determinations
Operator Workarounds
Operator Workarounds
Plant Procedures
Plant Procedures
      Admin Proc No 4.12; Operator Work-Around Program; Revision 1
Admin Proc No 4.12; Operator Work-Around Program; Revision 1
                                              11                                      Attachment


Attachment
12
Miscellaneous Documents
Miscellaneous Documents
      Palisades Operator Workarounds List; as of October 29, 2003
Palisades Operator Workarounds List; as of October 29, 2003
      Operations Concerns List; as of October 29, 2003
Operations Concerns List; as of October 29, 2003
      Control Room Deficiencies List; as of October 29, 2003
Control Room Deficiencies List; as of October 29, 2003
      Palisades Operations Concerns List; as of October 29, 2003
Palisades Operations Concerns List; as of October 29, 2003
      Aggregate Assessment Factor; as of June 30, July 24, August 15, September 19 and
Aggregate Assessment Factor; as of June 30, July 24, August 15, September 19 and
        October 27, 2003
  October 27, 2003
Temporary Plant Modifications
Temporary Plant Modifications
Plant Procedures
Plant Procedures
      SOP-15, Attachment 11; Alternate Water Supply to Clean Traveling Screens;
SOP-15, Attachment 11; Alternate Water Supply to Clean Traveling Screens;
        Revision 32
  Revision 32
Modification Documents
Modification Documents
      EDC-TM-2000-024-03; Engineering Design Change for TM-2000-024; 50.59 Screen;
EDC-TM-2000-024-03; Engineering Design Change for TM-2000-024; 50.59 Screen;
        November 13, 2003
  November 13, 2003
      TM-2000-024; Temporary Modification, Alternate Supply of Water to Traveling Screens;
TM-2000-024; Temporary Modification, Alternate Supply of Water to Traveling Screens;
        November 11, 2003
  November 11, 2003
1EP4 Emergency Action Level and Emergency Plan Changes
1EP4
      Palisades Nuclear Plant Site Emergency Plan; Revisions 5, 6, 7, and 8
Emergency Action Level and Emergency Plan Changes
1EP6 Emergency Preparedness Drill Evaluation
Palisades Nuclear Plant Site Emergency Plan; Revisions 5, 6, 7, and 8
1EP6
Emergency Preparedness Drill Evaluation
Plant Procedures
Plant Procedures
      EI-3, Attachment 1; Palisades Event Notification Form; Revision 19
EI-3, Attachment 1; Palisades Event Notification Form; Revision 19
      EI-1; Emergency Classifications and Actions; Revision 42
EI-1; Emergency Classifications and Actions; Revision 42
      EI-3; Communications and Notifications; Revision 19
EI-3; Communications and Notifications; Revision 19
Condition Reports Reviewed to Assess Significance Characterization of Identified Problems
Condition Reports Reviewed to Assess Significance Characterization of Identified Problems
      CAP039186; Investigate Potential Missed Drill / Exercise Performance Opportunity
CAP039186; Investigate Potential Missed Drill / Exercise Performance Opportunity
2OS3 Radiation Monitoring Instrumentation and Protective Equipment
2OS3 Radiation Monitoring Instrumentation and Protective Equipment
      SurvivAir SCBA Maintenance Record File for OCR-42 (including cylinder hydrostatic test
SurvivAir SCBA Maintenance Record File for OCR-42 (including cylinder hydrostatic test  
        data); dated through August 6, 2003
  data); dated through August 6, 2003
      SurvivAir SCBA Maintenance Record File for RPO-11 (including cylinder hydrostatic test
SurvivAir SCBA Maintenance Record File for RPO-11 (including cylinder hydrostatic test  
        data); dated through August 4, 2003
  data); dated through August 4, 2003
      SurvivAir SCBA Maintenance Record File for T625-47 (including cylinder hydrostatic test
SurvivAir SCBA Maintenance Record File for T625-47 (including cylinder hydrostatic test  
        data); dated through August 6, 2003
  data); dated through August 6, 2003
                                              12                                  Attachment


    HP 7.5; Self-Contained Breathing Apparatus (SCBA) SurvivAir Mark-2 Model 9842;
Attachment
      Revision 4
13
    HP 7.6; Inspection and Testing of SurvivAir (SCBA) Breathing Air Cylinders ; Revision 4
HP 7.5; Self-Contained Breathing Apparatus (SCBA) SurvivAir Mark-2 Model 9842;
2PS1 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems
  Revision 4
    2001 Annual Radioactive Effluent and Waste Disposal Report; dated March 26, 2002
HP 7.6; Inspection and Testing of SurvivAir (SCBA) Breathing Air Cylinders ; Revision 4
    2002 Annual Radioactive Effluent and Waste Disposal Report; dated March 24, 2003
2PS1
    Calibration File for High Purity Germanium Detector #1 (S/N 6983983); dated January 9,
Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems
      1999
2001 Annual Radioactive Effluent and Waste Disposal Report; dated March 26, 2002
    Calibration File for High Purity Germanium Detector #2 (S/N 1924); dated May 13, 1999
2002 Annual Radioactive Effluent and Waste Disposal Report; dated March 24, 2003
    Calibration File for High Purity Germanium Detector #3 (S/N 1221); dated January 9,
Calibration File for High Purity Germanium Detector #1 (S/N 6983983); dated January 9,  
      1999
  1999
    Palisades Final Safety Analysis Report (FSAR), Chapter 11; Radioactive Waste
Calibration File for High Purity Germanium Detector #2 (S/N 1924); dated May 13, 1999
      Management and Radiation Protection; Revision 24
Calibration File for High Purity Germanium Detector #3 (S/N 1221); dated January 9,
    Quarterly Liquid and Gaseous Release Calculations (LADTAP and GASPAR Results)
  1999
      for 3rd Quarter 2001, 2nd and 4th Quarter 2002, and 1st through 3rd Quarter 2003;
Palisades Final Safety Analysis Report (FSAR), Chapter 11; Radioactive Waste
      dated October 3, 2001, July 2, 2002, and January 9, April 5, July 3, September 26,
  Management and Radiation Protection; Revision 24
      2003
Quarterly Liquid and Gaseous Release Calculations (LADTAP and GASPAR Results)
    Results of Radiochemistry Cross Check Program (Analytics), Consumers Power
  for 3rd Quarter 2001, 2nd and 4th Quarter 2002, and 1st through 3rd Quarter 2003;
      Company, Palisades Nuclear Plant, 2nd Quarter 2003; dated November 10, 2003
  dated October 3, 2001, July 2, 2002, and January 9, April 5, July 3, September 26,
    Results of Radiochemistry Cross Check Program (Analytics), Consumers Power
  2003
      Company, Palisades Nuclear Plant, 3rd Quarter 2003; dated November 10, 2003
Results of Radiochemistry Cross Check Program (Analytics), Consumers Power
    Special Report of Inoperability of One Channel of Stack Gas Effluent System; dated
  Company, Palisades Nuclear Plant, 2nd Quarter 2003; dated November 10, 2003
      September 4, 2003
Results of Radiochemistry Cross Check Program (Analytics), Consumers Power
    Special Report of Inoperability of One Channel of Stack Gas Effluent System - Hi Range
  Company, Palisades Nuclear Plant, 3rd Quarter 2003; dated November 10, 2003
      Noble Gas Monitor RIA-2327; dated September 20, 2002
Special Report of Inoperability of One Channel of Stack Gas Effluent System; dated
    ANSI N13.1-1969; Guide to Sampling Airborne Radioactive Materials in Nuclear
  September 4, 2003
      Facilities; dated February 19, 1969
Special Report of Inoperability of One Channel of Stack Gas Effluent System - Hi Range  
    CAP 033600/ACE 002935; Higher than Expected Noble Gas Activity During Breach of
  Noble Gas Monitor RIA-2327; dated September 20, 2002
      Waste Gas System; dated February 26, 2003
ANSI N13.1-1969; Guide to Sampling Airborne Radioactive Materials in Nuclear
    CAP 036988/MRE 000158; Radioactive Gas Effluent Monitoring System Tripped; dated
  Facilities; dated February 19, 1969
      August 6 and 11, 2003
CAP 033600/ACE 002935; Higher than Expected Noble Gas Activity During Breach of    
    CAP 037027; Counting Geometry Unavailable; dated August 10, 2003
  Waste Gas System; dated February 26, 2003
    CAP 037574; Clarification/Enhancement Needed for ODCM Compensatory Measures;
CAP 036988/MRE 000158; Radioactive Gas Effluent Monitoring System Tripped; dated
      dated September 15, 2003
  August 6 and 11, 2003
    CAP 039097; Question Concerning Plant Stack Sample Line; dated December 17, 2003
CAP 037027; Counting Geometry Unavailable; dated August 10, 2003
    CAP 039128; Evaluate Sampling/Handling of the Weekly Plant Stack Effluent Sample
CAP 037574; Clarification/Enhancement Needed for ODCM Compensatory Measures;  
      Media; dated December 18, 2003 [NRC-Identified Issue]
  dated September 15, 2003
    CH 4.39; Gamma Ray Spectroscopy System; Revision 14
CAP 039097; Question Concerning Plant Stack Sample Line; dated December 17, 2003  
    CE 005907; I-131 Release During 2003 Re-Fueling Outage Higher Than 2001
CAP 039128; Evaluate Sampling/Handling of the Weekly Plant Stack Effluent Sample    
      Re-Fueling Outage; dated June 9, 2003
  Media; dated December 18, 2003 [NRC-Identified Issue]
    DWR-10; Stack Effluent Sampling, Calculations, and Records; Revision 22
CH 4.39; Gamma Ray Spectroscopy System; Revision 14
    Gaseous Release Batch 03-052ST; Week 52 of CY2003 Stack Release Calculations;
CE 005907; I-131 Release During 2003 Re-Fueling Outage Higher Than 2001
      dated December 17, 2003
  Re-Fueling Outage; dated June 9, 2003
    Gaseous Release Batch 03-052-G; Waste Gas Decay Tank T-101A Release
DWR-10; Stack Effluent Sampling, Calculations, and Records; Revision 22
      Calculations; dated December 18, 2003
Gaseous Release Batch 03-052ST; Week 52 of CY2003 Stack Release Calculations;    
    Gilbert/Commonwealth System Design No. 771; Post-Accident Monitoring - Palisades
  dated December 17, 2003
      Plant, Radioactive Gaseous Effluent Monitoring; dated September 8, 1982
Gaseous Release Batch 03-052-G; Waste Gas Decay Tank T-101A Release
                                            13                                  Attachment
  Calculations; dated December 18, 2003
Gilbert/Commonwealth System Design No. 771; Post-Accident Monitoring - Palisades    
  Plant, Radioactive Gaseous Effluent Monitoring; dated September 8, 1982


    HP 6.4; Radioactive Liquid Calculation and Release Authorization; Revision 23
Attachment
    HP 6.5; Sampling Waste Gas Decay Tank; Revision 12
14
    HP 6.6; Evaluation and Release of Waste Gas Decay Tank; Revision 16
HP 6.4; Radioactive Liquid Calculation and Release Authorization; Revision 23
    Liquid Release Batch 02-024-R; T-90 Tank Release; dated October 21, 2002
HP 6.5; Sampling Waste Gas Decay Tank; Revision 12
    Liquid Release Batch 03-001-R; T-91 Tank Release; dated January 14, 2003
HP 6.6; Evaluation and Release of Waste Gas Decay Tank; Revision 16
    Liquid Release Batch 03-011-R; T-91 Tank Release; dated April 17, 2003
Liquid Release Batch 02-024-R; T-90 Tank Release; dated October 21, 2002
    Nuclear Oversight Observation Report No. 2003-001-8-013; Radiological Environmental
Liquid Release Batch 03-001-R; T-91 Tank Release; dated January 14, 2003
      Monitoring Program: Process Monitor Function Checks, Milk Sample Collection, Waste
Liquid Release Batch 03-011-R; T-91 Tank Release; dated April 17, 2003
      Gas Decay Tank, and Stack Gas Analysis; dated March 18, 2003
Nuclear Oversight Observation Report No. 2003-001-8-013; Radiological Environmental
    Nuclear Oversight Observation Report No. 2003-001-8-067; Review of the Radiological
  Monitoring Program: Process Monitor Function Checks, Milk Sample Collection, Waste  
      Environmental Monitoring Program and Radiological Environmental Technical
  Gas Decay Tank, and Stack Gas Analysis; dated March 18, 2003
      Specifications; dated April 23, 2003
Nuclear Oversight Observation Report No. 2003-001-8-067; Review of the Radiological  
    ODCM; Palisades Nuclear Plant Offsite Dose Calculation Manual; Revisions 17 and 18
  Environmental Monitoring Program and Radiological Environmental Technical
    RR-9B; Radwaste Discharge Monitor (RIA-1049) Calibration; dated July 28, 2003
  Specifications; dated April 23, 2003
    RR-84A; Radioactive Gaseous Iodine/Part Effluent Monitor RIA-2325 Calibration; dated
ODCM; Palisades Nuclear Plant Offsite Dose Calculation Manual; Revisions 17 and 18
      August 6, 2002
RR-9B; Radwaste Discharge Monitor (RIA-1049) Calibration; dated July 28, 2003
    RR-84B; Radioactive Noble Gas Effluent Monitor RIA-2326 Calibration; dated
RR-84A; Radioactive Gaseous Iodine/Part Effluent Monitor RIA-2325 Calibration; dated
      August 19, 2002
  August 6, 2002
    RR-84C; High Range Noble Gas Effluent Monitor (RIA-2327) Calibration; dated
RR-84B; Radioactive Noble Gas Effluent Monitor RIA-2326 Calibration; dated
      December 10, 2002
  August 19, 2002
    Self-Assessment Report I03-33; Radiological Effluent Monitoring - Pre NRC
RR-84C; High Range Noble Gas Effluent Monitor (RIA-2327) Calibration; dated
      Assessment; dated October 21, 2003
  December 10, 2002
2PS3 Radiological Environmental Monitoring and Radioactive Material Control Programs
Self-Assessment Report I03-33; Radiological Effluent Monitoring - Pre NRC
    Environmental Department Meteorological Equipment Temperature / Delta-T Calibration
  Assessment; dated October 21, 2003
      Form, T/TD-1 (60M); dated September 10, 2003
2PS3
    Environmental Department Meteorological Equipment Wind Speed Calibration Form,
Radiological Environmental Monitoring and Radioactive Material Control Programs
      WS-1 (10A); dated September 10, 2003
Environmental Department Meteorological Equipment Temperature / Delta-T Calibration
    Environmental Department Meteorological Equipment Wind Direction Calibration Form,
  Form, T/TD-1 (60M); dated September 10, 2003
      WD-1 (10A); dated September 10, 2003
Environmental Department Meteorological Equipment Wind Speed Calibration Form,
    Environmental Department Meteorological Equipment Wind Speed Calibration Form,
  WS-1 (10A); dated September 10, 2003
      WS-1 (10B); dated September 8, 2003
Environmental Department Meteorological Equipment Wind Direction Calibration Form,
    Environmental Department Meteorological Equipment Wind Direction Calibration Form,
  WD-1 (10A); dated September 10, 2003
      WD-1 (10B); dated September 8, 2003
Environmental Department Meteorological Equipment Wind Speed Calibration Form,
    Environmental Department Meteorological Equipment Wind Speed Calibration Form,
  WS-1 (10B); dated September 8, 2003
      WS-1 (60M); dated September 10, 2003
Environmental Department Meteorological Equipment Wind Direction Calibration Form,
    Environmental Department Meteorological Equipment Wind Direction Calibration Form,
  WD-1 (10B); dated September 8, 2003
      WD-1 (60M); dated September 10, 2003
Environmental Department Meteorological Equipment Wind Speed Calibration Form,
    Palisades Nuclear Plant 2002 Annual Radiological Environmental Operating Report;
  WS-1 (60M); dated September 10, 2003
      dated May 12, 2003
Environmental Department Meteorological Equipment Wind Direction Calibration Form,
    Palisades Nuclear Plant Offsite Dose Calculation Manual; Revision 17
  WD-1 (60M); dated September 10, 2003
    Palisades Nuclear Plant Offsite Dose Calculation Manual, Appendix A, Relocated
Palisades Nuclear Plant 2002 Annual Radiological Environmental Operating Report;
      Technical Specifications per NRC Generic Letter 89-01 (TAC No. 75060); Revision 10
  dated May 12, 2003
    Palisades Part 61 Isotopic Analysis Results Evaluated for Hard-to-Detect Nuclides;
Palisades Nuclear Plant Offsite Dose Calculation Manual; Revision 17
      dated November 13, 2002
Palisades Nuclear Plant Offsite Dose Calculation Manual, Appendix A, Relocated
    Palisades Personnel Contamination Monitor (PCM-2) Commissioning Study; dated
  Technical Specifications per NRC Generic Letter 89-01 (TAC No. 75060); Revision 10
      February 17, 2003
Palisades Part 61 Isotopic Analysis Results Evaluated for Hard-to-Detect Nuclides;
    Palisades Personnel Contamination Monitor (PCM-2) Sum Zone Setup and Operation;
  dated November 13, 2002
                                            14                                  Attachment
Palisades Personnel Contamination Monitor (PCM-2) Commissioning Study; dated
  February 17, 2003
Palisades Personnel Contamination Monitor (PCM-2) Sum Zone Setup and Operation;


        dated March 6, 2003
Attachment
      Radiological Environmental Monitoring Program - Pre NRC Assessment; dated
15
        October 21, 2003
  dated March 6, 2003
      AP 7.15; Contamination Control; Revision 9
Radiological Environmental Monitoring Program - Pre NRC Assessment; dated
      EA-JBB-99-001; Plant Radionuclide Mixture and Calibration Sources; dated
  October 21, 2003
        March 10, 1999
AP 7.15; Contamination Control; Revision 9
      Form 116; Gas Meter Test and Repair (for Air Sampling Stations 1 - 12); dated
EA-JBB-99-001; Plant Radionuclide Mixture and Calibration Sources; dated
        November 22, 2002 through September 19, 2003
  March 10, 1999
      HP 9.80; Operation and Calibration of the SAM9; Revision 1
Form 116; Gas Meter Test and Repair (for Air Sampling Stations 1 - 12); dated
      HP 10.1; Radiological Environmental Monitoring Program Surveillance; Revision 8
  November 22, 2002 through September 19, 2003
      MM-121; Meteorological Monitoring Project Plan; dated June 8, 1998
HP 9.80; Operation and Calibration of the SAM9; Revision 1
      Nuclear Oversight Observation Report No. 2003-001-8-013; Radiological Environmental
HP 10.1; Radiological Environmental Monitoring Program Surveillance; Revision 8
        Monitoring Program: Process Monitor Function Checks, Milk Sample Collection, Waste
MM-121; Meteorological Monitoring Project Plan; dated June 8, 1998
        Gas Decay Tank, and Stack Gas Analysis; dated March 18, 2003
Nuclear Oversight Observation Report No. 2003-001-8-013; Radiological Environmental
      Nuclear Oversight Observation Report No. 2003-001-8-067; Review of the Radiological
  Monitoring Program: Process Monitor Function Checks, Milk Sample Collection, Waste
        Environmental Monitoring Program and Radiological Environmental Technical
  Gas Decay Tank, and Stack Gas Analysis; dated March 18, 2003
        Specifications; dated April 23, 2003
Nuclear Oversight Observation Report No. 2003-001-8-067; Review of the Radiological
      SR-2001-341; Nuclear Utilities Procurement Issues Committee (NUPIC) Joint Quality
  Environmental Monitoring Program and Radiological Environmental Technical
        Assurance Program Audit Report (of Environmental, Incorporated); dated
  Specifications; dated April 23, 2003
        July 27, 2001
SR-2001-341; Nuclear Utilities Procurement Issues Committee (NUPIC) Joint Quality
      Updated/Final Safety Analysis Report Chapter 2; Section 2.5.2, Meteorological
  Assurance Program Audit Report (of Environmental, Incorporated); dated
        Program History; Revision 22
  July 27, 2001
      WI-RSD-H-010; Release of Items; Revision 6
Updated/Final Safety Analysis Report Chapter 2; Section 2.5.2, Meteorological
  Program History; Revision 22
WI-RSD-H-010; Release of Items; Revision 6
4OA1 Performance Indicator Verification
4OA1 Performance Indicator Verification
      DWO-1, Attachment 8; Primary Coolant System Inventory Form; October 2002 through
DWO-1, Attachment 8; Primary Coolant System Inventory Form; October 2002 through
        September 2003
  September 2003
      Licensee Report of Monthly Operating Data; Palisades Nuclear Plant; October 2002
Licensee Report of Monthly Operating Data; Palisades Nuclear Plant; October 2002
        through September 2003
  through September 2003
      NEI 99-02; Regulatory Assessment Performance Indicator Guideline; Revision 2
NEI 99-02; Regulatory Assessment Performance Indicator Guideline; Revision 2
      Chemistry Department Analyses Database for DEI-131 versus Reactor Power; dated
Chemistry Department Analyses Database for DEI-131 versus Reactor Power; dated
        July 1, 2002 through June 30, 2003
  July 1, 2002 through June 30, 2003
      COP-1; Primary Coolant System Chemistry, Attachment 19; Revision 52
COP-1; Primary Coolant System Chemistry, Attachment 19; Revision 52
      DWC-2; PCS Radiochemistry Analysis; Revision 18
DWC-2; PCS Radiochemistry Analysis; Revision 18
      NRC Indicator RETS/ODCM Radiological Effluent Occurrence (PR-01); dated 3rd
NRC Indicator RETS/ODCM Radiological Effluent Occurrence (PR-01); dated 3rd    
      Quarter 2002, January 9, April 5, July 3, and September 26, 2003
Quarter 2002, January 9, April 5, July 3, and September 26, 2003
Condition Reports Reviewed to Assess Significance Characterization of Problems
Condition Reports Reviewed to Assess Significance Characterization of Problems
      CAP038667; NRC PI Database Not Corrected With Revised Data
CAP038667; NRC PI Database Not Corrected With Revised Data
Condition Reports Reviewed to Assess Corrective Actions
Condition Reports Reviewed to Assess Corrective Actions
      CAP031806; Incorrect Data Reported on May 2002 NRC Performance Indicator BI-02
CAP031806; Incorrect Data Reported on May 2002 NRC Performance Indicator BI-02
4OA2 Identification and Resolution of Problems
4OA2 Identification and Resolution of Problems
      ACE003132; Apparent Cause Evaluation; Subcooling Valve CV-3070 Failed to Open
ACE003132; Apparent Cause Evaluation; Subcooling Valve CV-3070 Failed to Open
        During QO-5 Valve Test Procedure
  During QO-5 Valve Test Procedure
                                              15                                  Attachment


    WO24412938; Work Order, High Pressure Safety Injection P-66B Subcooling;
Attachment
      July 11, 1995
16
    ESS-M-40; Permanent Maintenance Procedure; Maintenance of Miller Operators for
WO24412938; Work Order, High Pressure Safety Injection P-66B Subcooling;  
      High Pressure Safety Injection Subcooling Valves CV-3070 and CV-3071
  July 11, 1995
ESS-M-40; Permanent Maintenance Procedure; Maintenance of Miller Operators for
  High Pressure Safety Injection Subcooling Valves CV-3070 and CV-3071
4OA3 Event Follow-up
4OA3 Event Follow-up
    CAP038019, Re-assess Timing of CRS Fan V-4A Inoperability with Regard to
CAP038019, Re-assess Timing of CRS Fan V-4A Inoperability with Regard to
      Reportability
  Reportability
                                          16                                Attachment


                  LIST OF ACRONYMS USED
Attachment
AA   Access Authorization
17
ARM   Area Radiation Monitor
LIST OF ACRONYMS USED
CAM   Continuous Air Monitor
AA
CAP   Corrective Action Program
Access Authorization
CFR   Code of Federal Regulations
ARM
CR   Condition Report
Area Radiation Monitor
DEI   Dose Equivalent Iodine
CAM
DRP   Division of Reactor Projects
Continuous Air Monitor
DRS   Division of Reactor Safety
CAP
EAL   Emergency Action Level
Corrective Action Program
EAR   Engineering Assistance Request
CFR
LER   Licensee Event Report
Code of Federal Regulations
LLD   Lower Limit of Detection
CR
NCV   Non-Cited Violation
Condition Report
NMC   Nuclear Management Company
DEI
NRC   Nuclear Regulatory Commission
Dose Equivalent Iodine
ODCM Offsite Dose Calculation Manual
DRP
RCA   Radiologically Controlled Area
Division of Reactor Projects
RCS   Reactor Coolant System
DRS
REMP Radiological Environmental Monitoring Program
Division of Reactor Safety
RETS Radiological Effluent Technical Specifications
EAL
RGEM Radiological Gaseous Effluent Monitoring
Emergency Action Level
RPS   Reactor Protection System
EAR
SCBA Self-Contained Breathing Apparatus
Engineering Assistance Request
SDP   Significance Determination Process
LER
SM&CS System Maintenance and Construction Services
Licensee Event Report
SQUG Seismic Qualification Utility Group
LLD
TLD   Thermoluminescent Dosimeter
Lower Limit of Detection
UFSAR Updated Final Safety Analysis Report
NCV
URI   Unresolved Item
Non-Cited Violation
                              17                    Attachment
NMC
Nuclear Management Company
NRC
Nuclear Regulatory Commission
ODCM
Offsite Dose Calculation Manual
RCA
Radiologically Controlled Area
RCS
Reactor Coolant System
REMP
Radiological Environmental Monitoring Program
RETS
Radiological Effluent Technical Specifications
RGEM
Radiological Gaseous Effluent Monitoring
RPS
Reactor Protection System
SCBA
Self-Contained Breathing Apparatus
SDP
Significance Determination Process
SM&CS
System Maintenance and Construction Services
SQUG
Seismic Qualification Utility Group
TLD
Thermoluminescent Dosimeter
UFSAR
Updated Final Safety Analysis Report
URI
Unresolved Item
}}
}}

Latest revision as of 05:26, 16 January 2025

IR 05000255-03-008; on 10/01/2003 - 12/31/2003; Palisades Nuclear Generating Plant; Equipment Availability, Reliability and Functional Capability (71111.EP). Non-Cited Violations Noted
ML040230196
Person / Time
Site: Palisades Entergy icon.png
Issue date: 01/22/2004
From: Eric Duncan
NRC/RGN-III/DRP/RPB6
To: Domonique Malone
Nuclear Management Co
References
IR-03-008
Download: ML040230196 (60)


See also: IR 05000255/2003008

Text

January 22, 2004

Mr. Daniel J. Malone

Site Vice President

Palisades Nuclear Plant

Nuclear Management Company, LLC

27780 Blue Star Memorial Highway

Covert, MI 49043-9530

SUBJECT:

PALISADES NUCLEAR GENERATING PLANT

NRC INSPECTION REPORT 05000255/2003008

Dear Mr. Malone:

On December 31, 2003, the U. S. Nuclear Regulatory Commission (NRC) completed an

inspection at your Palisades Nuclear Generating Plant. The enclosed report documents the

inspection findings which were discussed on January 9, 2004, with you and other members of

your staff.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed

personnel.

Based on the results of this inspection, two findings of very low safety significance (Green) were

identified, which were determined to involve violations of NRC requirements. However,

because these findings were of very low safety significance and because the findings have

been entered into your corrective action program, the NRC is treating these violations as

Non-Cited Violations in accordance with Section VI.A.1 of the NRCs Enforcement Policy.

If you contest the subject or severity of a Non-Cited Violation, you should provide a response

with a basis for your denial, within 30 days of the date of this inspection report, to the U.S.

Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-

0001, with a copy to the Regional Administrator, U.S. Nuclear Regulatory Commission -

Region III, 801 Warrenville Road, Lisle, IL 60532-4351; the Director, Office of Enforcement,

U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident

Inspector at the Palisades facility.

D. Malone

-2-

In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter

and its enclosure will be available electronically for public inspection in the NRC Public

Document Room or from the Publicly Available Records (PARS) component of NRC's

document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Eric R. Duncan, Chief

Branch 6

Division of Reactor Projects

Docket No. 50-255

License No. DPR-20

Enclosure:

Inspection Report 05000255/2003008

w/Attachment: Supplemental Information

cc w/encl:

J. Cowan, Executive Vice President

and Chief Nuclear Officer

R. Fenech, Senior Vice President, Nuclear

Fossil and Hydro Operations

D. Cooper, Senior Vice President - Group Operations

Manager, Regulatory Affairs

J. Rogoff, Vice President, Counsel and Secretary

A. Udrys, Esquire, Consumers Energy Company

Director of Nuclear Assets, Consumers Energy Company

Supervisor, Covert Township

Office of the Governor

Michigan Department of Environmental Quality -

Waste and Hazardous Materials Division

Michigan Department of Attorney General

DOCUMENT NAME: S:\\ADMIN\\Karen's Docs\\ML040230196.wpd

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy

OFFICE

RIII

NAME

EDuncan:dtp

DATE

01/22/03

OFFICIAL RECORD COPY

D. Malone

-2-

ADAMS Distribution:

WDR

DFT

JHE

RidsNrrDipmIipb

GEG

HBC

JAL3

C. Ariano (hard copy)

C. Pederson, DRS (hard copy - IRs only)

DRPIII

DRSIII

PLB1

JRK1

Enclosure

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Docket No:

50-255

License No:

DPR-20

Report No:

050000255/2003008

Licensee:

Nuclear Management Company, LLC

Facility:

Palisades Nuclear Generating Plant

Location:

27780 Blue Star Memorial Highway

Covert, MI 49043-9530

Dates:

October 1 through December 31, 2003

Inspectors:

J. Lennartz, Senior Resident Inspector

M. Garza, Resident Inspector

R. Alexander, Radiation Specialist

A. Dunlop, Reactor Engineer

R. Jickling, Emergency Preparedness Analyst

Approved by:

Eric R. Duncan, Chief

Branch 6

Division of Reactor Projects

Enclosure

1

SUMMARY OF FINDINGS

IR 05000255/2003008; 10/01/2003 - 12/31/2003; Palisades Nuclear Generating Plant;

Equipment Availability, Reliability and Functional Capability (71111.EP).

This report covers a 3-month period of baseline resident inspections, two announced baseline

inspections in radiation protection, an announced heat sink performance inspection and a

routine baseline emergency preparedness inspection. The inspections were conducted by

resident inspectors, a regional inspector, a radiation specialist inspector, and an emergency

preparedness analyst. Two Green findings with associated Non-Cited Violations (NCVs) were

identified during the inspection. The significance of most findings is indicated by their color

(Green, White, Yellow, Red) using Inspection Manual Chapter 0609, Significance

Determination Process, (SDP). Findings for which the SDP does not apply may be Green or

be assigned a severity level after NRC management review. The NRCs program for

overseeing the safe operation of commercial nuclear power reactors is described in

NUREG-1649, Reactor Oversight Process, Revision 3, dated July 2000.

A.

Inspector Identified Findings

Cornerstone: Mitigating Systems

C

Green. A finding of very low safety significance was self-revealed when High Pressure

Safety Injection Pump P-66B Subcooling Valve CV-3070 failed to stroke open during

surveillance testing. Licensee personnel improperly installed a flow control valve in the

operating air system which contributed to the valve failing to stroke open. The finding

was more than minor because the availability and capability of High Pressure Safety

Injection Pump P-66B was adversely affected. The finding was of very low safety

significance because there was not an actual loss of safety function for High Pressure

Safety Injection Pump P-66B for greater than the Technical Specification allowed outage

time.

Corrective actions to address this issue included reinstalling the flow control valve in the

proper direction, testing CV-3070 during a mid-surveillance cycle stroke test, and

generating a work order to inspect the CV-3070 valve internals at the earliest opportunity.

One Non-Cited Violation of 10 CFR 50, Appendix B, Criterion V, Instructions,

Procedures and Drawings, was identified. (Section 1REP)

Cornerstone: Barrier Integrity

C

Green. A finding of very low safety significance was self-revealed when the

Containment Spray Pump P-54C inboard motor bearing failed on August 21, 2003.

Following a scheduled oil change on the motor bearing, the bearing housing drain plug

was also replaced and enough oil was lost during this drain plug replacement to uncover

the bearing; however, the vent on the oiler had been plugged when the pump was

painted in June 2002 which resulted in an erroneous level indication in the oiler for the

bearing housing. Consequently, the operator did not add sufficient oil through the oiler to

the bearing housing after the drain plug was replaced. As a result, the inboard motor

bearing was inadequately lubricated which caused the bearing to fail when Containment

Enclosure

2

Spray Pump P-54C was started. This finding was more than minor because if left

uncorrected, it would become a more significant safety concern. Specifically, the painted

vent hole on the motor bearing oiler resulted in erroneous oil level indication and

prevented the oiler from adding oil to the bearing housing when the level decreased.

Consequently, an inadequately lubricated bearing would not be detected until the bearing

failed. The finding was of very low safety significance because it did not represent an

actual reduction of the atmospheric pressure control function of the reactor containment.

Corrective actions to address this issue included clearing the vent hole on the bearing

oiler, verifying that the oiler vent holes on other safety-related pump motors were not

painted over and replacing the inboard motor bearing on Containment Spray Pump

P-54C. One Non-Cited Violation of 10 CFR 50, Appendix B, Criterion V, Instructions,

Procedures and Drawings, was identified. (Section 1REP)

B.

Licensee Identified Findings

None.

Enclosure

3

REPORT DETAILS

A list of documents reviewed within each inspection area is included at the end of the report.

Summary of Plant Status

The plant operated at full power during the inspection period with the following exception:

C

On November 8, 2003, power was reduced to 85 percent to conduct scheduled turbine

valve testing. During these activities, Heater Drain Pump P-10B unexpectedly tripped

due to low level in Moisture Separator and Heater Drain Tank T-5. Site personnel

subsequently identified that T-5 Level Control Valve CV-0608 was not operating

properly. A trip of one heater drain pump with power at 85 percent did not require any

mitigating actions.

On November 9, 2003, during emergent maintenance on Moisture Separator Reheater

Stop Valve CV-0537, control room operators noted that Tank T-5 level was lowering

again. As a result, Heater Drain Pump P-10A tripped. Operators subsequently

stabilized power at 72 percent.

After the second heater drain pump tripped, operations personnel identified that the

discharge check valve on Heater Drain Pump P-10A was not fully seated and repairs

were required. While completing necessary repairs to the discharge check valve,

Heater Drain Pump P-10B was restarted on November 10, 2003, and power was

increased to 90 percent.

Following repairs, Heater Drain Pump P-10A was returned to service and the plant

returned to full power on November 13, 2003.

1.

REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, and

Emergency Preparedness

1R01

Adverse Weather Protection (71111.01)

.1

Cold Weather Preparations

a.

Inspection Scope

The inspectors reviewed the sites Cold Weather Checklists that were completed from

October through November 2003 to assess the actions taken to prepare for the onset of

cold weather. The inspectors also performed walkdowns to verify the physical condition

of weather protection features for risk significant systems and components.

The inspectors reviewed selected condition reports related to cold weather preparation

problems and verified that identified problems were entered into the corrective action

Enclosure

4

program with the appropriate significance characterization and that planned and

completed corrective actions were appropriate.

b.

Findings

No findings of significance were identified.

.2

Entry into Off-Normal Procedure Because of High Winds

a.

Inspection Scope

The inspectors assessed the actions taken for one emergent adverse weather condition.

On November 12, 2003, operations personnel entered Off-Normal Procedure-12, Acts

of Nature, after the control room received a weather warning regarding sustained wind

speeds of 40 miles per hour and wind gusts to 50 miles per hour. The inspectors

verified that the actions specified in Off-Normal Procedure-12 were being accomplished

to the extent possible for this emergent adverse weather condition. Off-Normal

Procedure-12 was exited on November 13, 2003, after the high winds diminished.

b.

Findings

No findings of significance were identified.

1R04

Equipment Alignment

.1

Quarterly Equipment Alignment Walkdowns (71111.04Q)

a.

Inspection Scope

The inspectors performed two equipment alignment walkdowns to verify that the

following systems were properly aligned:

C

Instrument Air Compressors C-2A and C-2C

C

Control Room Heating, Ventilation and Air Conditioning Train B

For these systems, the inspectors verified that power was available, that accessible

equipment and components were appropriately aligned, and that no discrepancies

existed which would impact system function.

The inspectors also reviewed selected condition reports related to equipment alignment

problems and verified that identified problems were entered into the corrective action

program with the appropriate significance characterization and that planned and

completed corrective actions were appropriate.

b.

Findings

No findings of significance were identified.

Enclosure

5

1R05

Fire Protection

.1

Fire Area Walkdowns (71111.05Q)

a.

Inspection Scope

The inspectors toured the following six areas in which a fire could affect safety-related

equipment:

C

Battery Room #1 (Fire Area 12)

C

Electrical Equipment Room (Fire Area 21)

C

East Engineered Safeguards Room (Fire Area 10)

C

West Mechanical Equipment Room (Fire Area 31)

C

East Mechanical Equipment Room (Fire Area 30)

Auxiliary Building Level 590 Corridor (Fire Area 13)

The inspectors verified that transient combustibles and ignition sources were

appropriately controlled, and assessed the material condition of fire suppression

systems, manual fire fighting equipment, smoke detection systems, and fire barriers.

The inspectors also reviewed documentation for completed surveillances to verify that

fire protection equipment and fire barriers were tested as required to ensure availability.

The inspectors verified that the installed fire protection equipment in the fire areas

corresponded with the equipment which was referenced in the applicable portions of the

Updated Final Safety Analysis Report, Section 9.6, Fire Protection.

The inspectors reviewed selected condition reports related to fire protection problems

and verified that identified problems were entered into the corrective action program with

the appropriate significance characterization and that planned and completed corrective

actions were appropriate.

b.

Findings

No findings of significance were identified.

1R06

Flood Protection (71111.06A)

a.

Inspection Scope

The inspectors performed one inspection sample of internal flood protection features for

the safety-related batteries which the Updated Final Safety Analysis Report designated

as equipment that required protection from flooding due to failures of nonsafety-related

systems.

Enclosure

6

The inspectors conducted walkdowns noting the following attributes associated with the

battery rooms:

C

Holes or unsealed penetrations in floors, ceilings and walls;

C

Common drain system and sumps, including floor drain piping and check valves

where credited for isolation of flood areas; and

C

Sources of potential internal flooding that were not analyzed or were not

adequately maintained.

The inspectors also assessed condition reports related to flood protection problems to

verify that identified problems were entered into the corrective action program with the

appropriate significance characterization and that corrective actions were appropriate

and implemented as scheduled.

b.

Findings

No findings of significance were identified.

1R07

Heat Sink Performance (71111.07B)

a.

Inspection Scope

The regional specialist inspector reviewed documents associated with maintenance,

inspection, and thermal performance testing of the containment air coolers and the

control room heating, ventilation and air conditioning condensers (the heat exchangers

represented two inspection samples). These heat exchangers and coolers were chosen

based on previous corrosion and tube plugging concerns. While onsite, the inspector

reviewed completed surveillances, associated calculations, instrument calibration

records, and maintenance work orders, and performed independent calculations to

verify that these activities adequately ensured proper heat transfer. The inspector

reviewed the documentation to confirm that the test methodology was consistent with

accepted industry practices, that test acceptance criteria were consistent with design

basis values, and that the test results appropriately considered differences between test

and design conditions.

The inspector also reviewed documentation to confirm that methods used to inspect the

heat exchangers were consistent with expected degradation and that the established

acceptance criteria were consistent with accepted industry standards. The inspector

verified that systems and sub-components were free from clogging due to macrofouling

and that the licensee had adequate controls in place for biotic fouling.

In addition, the inspectors reviewed condition reports concerning heat exchanger and

heat sink performance issues to verify that the licensee had an appropriate threshold for

identifying issues and to evaluate the effectiveness of the licensees corrective actions

to address the identified issues.

b

Findings

No findings of significance were identified.

Enclosure

7

1R11

Licensed Operator Requalification (71111.11Q)

a.

Inspection Scope

The inspectors observed one crew of licensed operators during simulator training on

December 3, 2003. The inspectors assessed the operators ability to use Off-Normal

and Emergency Operating plant procedures to mitigate the following simulated events:

C

loss of two offsite power sources which resulted in a rise in switchyard voltage

concurrent with a failure of the automatic voltage adjuster on the main generator;

C

sequential high differential pressures in service water basket strainers due to

debris intrusion;

C

loss of one switchyard bus during a plant trip which resulted in emergency diesel

generators starting and energizing safety-related electrical loads; and

C

blockage of service water traveling screens due to frazil ice resulting in a loss of

service water.

The inspectors also verified that the Shift Manager implemented the Emergency Plan

Implementing Procedures in an accurate and timely manner when classifying the events

and notifying off-site authorities. In addition, the inspectors observed the post-scenario

critique to assess the licensee evaluators and the crews ability to self-identify

performance weaknesses.

b.

Findings

No findings of significance were identified.

1R13

Maintenance Risk Assessments and Emergent Work Evaluation (71111.13Q)

a.

Inspection Scope

The inspectors reviewed Operators Risk Reports, the Operations Log, and daily

maintenance schedules to verify that equipment necessary to minimize plant risk was

operable or available as required during planned and emergent maintenance activities.

The inspectors also conducted plant walkdowns to verify that equipment necessary to

minimize risk was available for use. The following four activities were reviewed:

C

Scheduled outage for Emergency Diesel Generator 1-2 during the week of

September 29, 2003;

C

Scheduled surveillance testing for the Reactor Protection System during the

week of November 10, 2003;

C

Scheduled surveillance testing for Emergency Diesel Generator 1-2 on

November 18-19, 2003; and

C

Emergent maintenance on Emergency Diesel Generator 1-1 on December 7-10,

2003.

b.

Findings

No findings of significance were identified.

Enclosure

8

1R14

Operator Performance During Non-Routine Evolutions and Events (71111.14)

a.

Inspection Scope

On November 8, 2003, the inspectors observed portions of main turbine governor and

stop valve testing to verify that the evolution was effectively controlled and conducted in

accordance with System Operating Procedure-8, Main Turbine and Generating

Systems.

The inspectors also reviewed the events and circumstances that resulted in the

unexpected trip of one nonsafety-related heater drain pump which occurred during

turbine valve testing. In addition, the inspectors reviewed the events and circumstances

which necessitated a downpower from 82 percent to 72 percent in response to an

imminent unplanned trip of the second heater drain pump after turbine valve testing

activities had been completed. The inspectors reviewed control room logs, annunciator

response procedures, and off-normal operating procedures to verify that the control

room operators responded as required.

The inspectors also assessed condition reports related to the turbine valve testing and

verified that the problems were entered into the corrective action program with the

appropriate significance characterization and that the licensees immediate corrective

actions were appropriate.

b.

Findings

No findings of significance were identified.

1R17

Permanent Plant Modifications (71111.17)

a.

Inspection Scope

The inspectors reviewed one permanent plant modification which provided an alternate

flowpath of borated water to the primary coolant system to safely shut down the plant to

cold shutdown following a seismic event. The modification included the following

Engineering Assistance Request (EAR) design documents:

EAR-2000-0345, Seismic Qualification Utility Group (SQUG) Outlier Resolution

for Safety Injection Refueling Water Tank T-58;

C

EAR-2002-017, for modifications to the service water system and spent fuel pool

cooling system; and

C

EAR-2002-0293, for modifications to the charging system header.

The inspectors reviewed the associated safety analyses and design change information

to verify that the design basis and performance capability of the spent fuel pool cooling

system and charging system was not degraded. The inspectors also verified that the

modification was installed in the plant as designed; the plant operating procedures and

plant drawings were revised appropriately; and the required lengths of fire hoses, tools

and connectors necessary to establish the alternate flowpath were pre-staged and

available for use if needed.

Enclosure

9

Further, the inspectors verified that identified problems associated with plant

modifications were entered into the licensees corrective action program with the

appropriate significance characterization, and that corrective actions were appropriate

and implemented as scheduled.

b.

Findings

No findings of significance were identified.

1R19

Post Maintenance Testing (71111.19)

a.

Inspection Scope

The inspectors observed portions of post maintenance testing and reviewed

documented testing activities to verify that the tests were adequately performed for the

following three activities:

C

Service Water Pump P-7C repack

C

Emergency Diesel Generator 1-2 maintenance outage

C

Low Pressure Safety Injection Pump P-67B breaker 152-111 replacement

The inspectors verified that applicable testing prerequisites were met prior to the start of

the tests and that the effect of testing on plant conditions was adequately addressed by

the control room operators.

The inspectors also reviewed post maintenance testing criteria to verify that the test

criteria and acceptance criteria were appropriate for the scope of work performed;

reviewed completed tests and associated procedures to verify that the tests adequately

verified system operability; and reviewed documented test data to verify that the data

was complete and that the equipment met the testing acceptance criteria.

Further, the inspectors reviewed condition reports to verify that post maintenance testing

problems were entered into the corrective action program with the appropriate

significance characterization.

b.

Findings

No findings of significance were identified.

1R22

Surveillance Testing (71111.22)

a.

Inspection Scope

The inspectors reviewed three surveillance testing activities conducted on the following

risk-significant plant equipment:

C

Safety Injection Initiation Circuitry

C

Control Room Heating, Ventilation and Air Conditioning System

C

Service Water Pump P-7A

Enclosure

10

The inspectors observed portions of the testing to verify that the testing was conducted

in accordance with prescribed procedures. The inspectors also reviewed the

documented test data for the Technical Specification Surveillance Test procedures and

the associated basis documents to verify that testing acceptance criteria were satisfied.

In addition, the inspectors reviewed applicable portions of Technical Specifications, the

Updated Final Safety Analysis Report, and design basis documents to verify that the

surveillance tests adequately demonstrated that system components could perform

required safety functions.

Further, the inspectors reviewed selected condition reports regarding surveillance

testing activities to verify that the identified problems were entered into the licensees

corrective action program with the appropriate significance characterization and that the

planned and completed corrective actions were appropriate.

b.

Findings

No findings of significance were identified.

1REP Equipment Availability, Reliability and Functional Capability (71111.EP)

.1

Quarterly Maintenance Effectiveness Reviews

a.

Inspection Scope

The inspectors conducted three maintenance effectiveness reviews for the following:

C

Containment Spray Pump P-54C

C

2400 Volt and 4160 Volt Station Power Systems

C

High Pressure Safety Injection Pump Subcooling Valve CV-3070

The inspectors reviewed the licensee's implementation of the maintenance rule

requirements to verify that component and equipment failures were identified and

appropriately dispositioned. The inspectors also verified that select systems and

components were properly categorized and classified as (a)(1) or (a)(2) in accordance

with 10 CFR 50.65.

The inspectors reviewed the licensees maintenance rule performance indicators to

verify that the system status had been appropriately categorized in accordance with the

maintenance rule program; reviewed work order histories and selected condition reports

written against the system over the last 2 years to verify that maintenance and identified

problems had been appropriately addressed; and reviewed completed work orders to

determine if there was an adverse trend in system performance that could be attributed

to inappropriate work practices and to determine if there were any common cause

issues that had not been addressed. Additionally, the inspectors reviewed the

licensees performance criteria to verify that the criteria adequately monitored equipment

performance.

Enclosure

11

In addition, the inspectors reviewed selected condition reports and associated

maintenance rule evaluations to verify that identified problems were appropriately

characterized and dispositioned in accordance with the licensees maintenance rule

program. The inspectors also verified that planned corrective actions were appropriate

and had been implemented as scheduled.

b.

Findings

1.

Containment Spray Pump P-54C

Introduction

The inspectors identified a finding of very low safety significance (Green) and an

associated Non-Cited Violation of 10 CFR 50, Appendix B, Criterion V, Instructions,

Procedures, and Drawings, when the inboard motor bearing on Containment Spray

Pump P-54C failed on August 21, 2003.

Description

During a planned breaker replacement for Containment Spray Pump P-54C, licensee

personnel also replaced the inboard motor bearing oil. An operator performed the motor

bearing oil replacement in accordance with the applicable work instruction on August 21,

2003. After the oil was replaced, the operator noticed that the drain plug to the bearing

housing was set too far into the housing. Therefore, the operator requested and

obtained permission to replace the drain plug. After the new drain plug was installed,

the operator added oil to the bearing housing through the inboard motor bearing oiler to

replace the oil that was drained when the drain plug was removed.

However, during post maintenance testing following Containment Spray Pump P-54C

breaker replacement, operators observed smoke from the inboard motor bearing area

and heard abnormal metallic noises. Therefore, the operators secured Containment

Spray Pump P-54C to investigate a potentially failed motor bearing. During the

investigation, licensee personnel determined that the oil level in the motor bearing

housing was below the slinger ring and that the inboard motor bearing had failed due to

a lack of lubrication. After further review, licensee personnel identified that the vent hole

on the oiler for the inboard motor bearing on Containment Spray Pump P-54C was

covered with paint. Licensee personnel subsequently determined that the motor for

Containment Spray Pump P-54C was painted in June 2002 under a general work order

for miscellaneous painting.

Through the root cause evaluation, licensee personnel determined that the plugged vent

caused the oiler to become air bound and unable to adequately add oil to the bearing

housing when the level decreased. Licensee personnel also determined that when the

drain plug was replaced, enough oil was lost to uncover the bearing; however, the

plugged vent on the oiler resulted in an erroneous level indication in the oiler for the

bearing housing. Consequently, the operator did not add enough oil through the oiler to

the bearing housing after the drain plug was replaced. As a result, the inboard motor

bearing was inadequately lubricated which caused the bearing to fail when Containment

Spray Pump P-54C was started.

Enclosure

12

Analysis

The inspectors determined that painting over the vent hole on the Containment Spray

Pump P-54C inboard motor bearing oiler was a licensee performance deficiency which

warranted a significance evaluation. The inspectors did not identify any examples of

minor issues in Inspection Manual Chapter (IMC) 0612, Power Reactor Inspection

Reports, Appendix E, Examples of Minor Issues that appropriately described this

finding.

The inspectors determined that the finding was more than minor in accordance with

IMC 0612, Appendix B, Issue Disposition Screening because if left uncorrected, the

issue could become a more significant safety concern. Specifically, the painted vent

hole on the bearing oiler resulted in erroneous oil level indication and prevented the oiler

from adding oil to the bearing housing when the level decreased. Consequently, an

inadequately lubricated bearing would not be detected until the bearing failed.

The inspectors also determined that the finding could be evaluated using IMC 0609,

Significance Determination Process, (SDP) because the finding was associated with

the integrity of reactor containment. Using IMC 0609, Appendix A, SDP Phase 1

Screening Worksheet for IE [Initiating Events], MS [Mitigating Systems], and B [Barrier

Integrity] Cornerstones, the inspectors determined that the Barrier Integrity cornerstone

was the only affected area.

Using the Barrier Integrity column on the SDP Phase 1 worksheet, the inspectors

determined that since the finding did not represent a degradation of the radiological

barrier function provided for the control room, or auxiliary building, or spent fuel pool; did

not represent a degradation of the barrier function of the control room against smoke or

a toxic atmosphere; and did not represent an actual open pathway in the physical

integrity of reactor containment or an actual reduction of the atmospheric pressure

control function of the reactor containment, the finding screened as Green and was

considered to be of very low safety significance.

Enforcement

10 CFR 50, Appendix B, Criterion V, Instructions, Procedures and Drawings states, in

part, that activities affecting quality shall be prescribed by documented instructions of a

type appropriate to the circumstances and shall be accomplished in accordance with

these instructions. Contrary to this requirement, painting of Containment Spray Pump

P-54C in June 2002, an activity affecting quality, did not have written instructions

appropriate to the circumstances. Consequently, the vent hole on the oiler was plugged

with paint which caused an erroneous oil level indication and the subsequent motor

bearing failure due to an inadequately lubricated bearing on August 21, 2003. However,

because this violation was associated with a finding of very low safety significance and

because the finding was entered into the licensees corrective action program, this

violation is being treated as a Non-Cited Violation, consistent with Section VI.A of the

NRC Enforcement Policy (NCV 05000255/2003008-01). This issue was entered into the

licensees corrective action program as CAP037180.

Enclosure

13

As part of the licensees corrective actions, licensee personnel cleared the vent hole on

the inboard motor bearing oiler for Containment Spray Pump P-54C and verified the

oiler vent holes on other safety-related pump motors were not painted over. In addition,

the inboard motor bearing on Containment Spray Pump P-54C was replaced, and the

pump was subsequently tested satisfactorily.

2.

High Pressure Safety Injection Pump P-66B Subcooling Valve CV-3070

Introduction

The inspectors identified a finding of very low safety significance (Green) and an

associated Non-Cited Violation of 10 CFR 50, Appendix B, Criterion V, Instructions,

Procedures, and Drawings, when High Pressure Safety Injection Pump P-66B

Subcooling Valve CV-3070 failed to stroke open during surveillance testing.

Description

On August 10, 2003, during surveillance testing, air operated High Pressure Safety

Injection Pump P-66B Subcooling Control Valve CV-3070 failed to stroke open with the

control switch held in the open position. Control Valve CV-3070 was required to open in

less than 2 seconds and had a safety-related support function for High Pressure Safety

Injection Pump P-66B during long term core cooling.

During troubleshooting activities on August 11, 2003, licensee personnel discovered that

a flow control valve in the operating air system was installed backwards which caused

CV-3070 to close faster than intended. The faster closing rate provided higher than

intended seating forces when the valve was closed. After further investigation, licensee

personnel concluded that the flow control valve was most likely installed backwards

when the valve actuator was rebuilt in July 1995 through Work Order 24412938. This

conclusion was based on: (1) there were no additional work orders for the valve

actuator since the flow control valve was initially installed in January 1986; (2) the

closing time for CV-3070 after the flow control valve was initially installed in 1986 was

20 seconds; (3) one-time stem thrust data taken in February 1998 indicated that

CV-3070 closed in 0.8 seconds; and (4) the as-found closing time on August 11 for

CV-3070 was 1.2 seconds. Because CV-3070 did not have a safety function to close,

the valve was not timed in the closed direction during quarterly testing. Therefore, no

additional closing time data was available.

Consequently, licensee personnel concluded that the seating force on the valve disc

from the faster than intended closing rate prevented the valve from opening during the

surveillance test. However, licensee personnel determined that the faster closing rate

was not conclusively the cause since the valve stroked open successfully each time it

had been tested since the flow control valve was installed backwards in 1995. Also,

there were no work activities performed on CV-3070 after the last successful

surveillance test in May 2003. In addition, on August 11, 2003, licensee personnel were

able to open CV-3070 using minor mechanical agitation during troubleshooting activities

and the valve was then stroked open successfully several times after the valve was

closed with the same fast closing rate.

Enclosure

14

Licensee personnel subsequently repositioned the flow control valve in the proper

direction and the as-left closing time for CV-3070 was 5.0 seconds. On August 12,

2003, CV-3070 opened within 2 seconds when tested and was declared operable.

However, because licensee personnel could not definitively conclude that the short

closing time caused CV-3070 to not open on August 10, Work Order 24323139 was

generated to disassemble and inspect CV-3070 at the earliest opportunity. In addition,

to provide confidence that CV-3070 could open as required, a mid-surveillance cycle

stroke test was performed on September 9, 2003, successfully.

Analysis

The inspectors determined that the incorrect installation of the flow control valve in 1995

was a licensee performance deficiency warranting a significance evaluation in

accordance with IMC 0612, Power Reactor Inspection Reports, Appendix B, Issue

Disposition Screening. The inspectors did not identify any examples of minor issues in

IMC 0612, Appendix E, Examples of Minor Issues, that appropriately described this

finding.

The inspectors concluded that the finding was more than minor because it was

associated with the Procedure Quality attribute of the Mitigating Systems cornerstone

and affected the cornerstone objective of ensuring the availability, reliability, and

capability of a system that responds to an initiating event to prevent undesirable

consequences.

The inspectors determined that the finding could be evaluated using IMC 0609,

Significance Determination Process, (SDP) because the finding was associated with

the availability of a mitigating system. Using IMC 0609, Appendix A, SDP Phase 1

Screening Worksheet for IE [Initiating Events], MS [Mitigating Systems], and B [Barrier

Integrity] Cornerstones, the inspectors determined that the Mitigating Systems

cornerstone was the only affected area.

Using the Mitigating Systems column on the SDP Phase 1 worksheet, the inspectors

determined that since the failure of CV-3070 to open during surveillance testing was not

a design or qualification deficiency; did not represent an actual loss of safety function for

a system or for a single train for greater than the Technical Specification allowed outage

time; and did not screen as potentially risk significant due to a seismic, fire, flooding, or

severe weather initiating event, the finding screened out as Green and was considered

to be of very low safety significance.

Enforcement

10 CFR 50, Appendix B, Criterion V, Instructions, Procedures and Drawings, requires,

in part, that activities affecting quality shall be prescribed by documented instructions of

a type appropriate to the circumstances and shall be accomplished in accordance with

those instructions. Contrary to this requirement, the work instructions for the

maintenance performed in July 1995 to rebuild the actuator for CV-3070, an activity

affecting quality, were not of a type appropriate to the circumstances. Specifically, the

work instructions did not contain adequate guidance to ensure that the flow control valve

Enclosure

15

was installed with the correct orientation in the operating air system for the valve

actuator.

Consequently, the flow control valve was installed backwards which resulted in faster

than intended closing times which contributed to valve CV-3070 failing to stroke open as

required on August 10, 2003. However, because this violation was associated with a

finding of very low safety significance and because the finding was entered into the

licensees corrective action program, this violation is being treated as a Non-Cited

Violation, consistent with Section VI.A of the NRC Enforcement Policy

(NCV 05000255/2003008-02). This issue was entered into the licensees corrective

action program as CAP037030.

Corrective actions to address the finding included reinstalling the flow control valve in

the proper position, testing CV-3070 during a mid-surveillance cycle stroke test, and

generating a work order to inspect the valve internals at the earliest opportunity.

.2

Biennial Assessment of Maintenance Rule Periodic Evaluations

a.

Inspection Scope

The inspectors reviewed the Maintenance Rule Periodic Refueling Assessment Report

for the period of August 1, 2000, to July 31, 2002. The inspectors verified that: (1) the

periodic evaluation had been completed as required by 10 CFR 50.65(a)(3);

(2) maintenance rule (a)(1) goals and (a)(2) performance criteria were reviewed by the

licensee; (3) industry operating experience was taken into account when appropriate;

(4) balancing of availability and reliability was reviewed; and (5) appropriate adjustments

were made as a result of the periodic evaluation.

The inspectors also reviewed the following four systems to assess how performance

problems were addressed within the maintenance rule program:

C

Concentrated Boric Acid System

C

Control Room Heating, Ventilation, and Air Conditioning (HVAC) System

C

High Pressure Air System

C

Fire Protection System

As applicable to the four systems, the inspectors verified that: (1) maintenance rule

(a)(1) goals and activities were reviewed and adjusted as necessary; (2) corrective

actions for (a)(1) activities were appropriate; (3) maintenance rule (a)(2) performance

criteria was appropriate and met; (4) evaluations for placing the system in maintenance

rule (a)(1) were completed when performance criteria was not met; (5) equipment

failures were evaluated and appropriately dispositioned as functional failures,

maintenance preventable functional failures or repeat maintenance preventable

functional failures; and (6) preventive maintenance activities were adjusted as

necessary.

The inspectors also reviewed a sample of condition reports to verify that the significance

of identified problems was appropriately characterized. For select condition reports, the

Enclosure

16

inspectors verified that the corrective actions were appropriate and implemented in a

timely manner commensurate with the significance of the problem.

b.

Findings

No findings of significance were identified.

.3

Operability Evaluations

a.

Inspection Scope

The inspectors reviewed three operability assessments as documented in the

associated condition reports for the following risk significant plant equipment:

C

Emergency Core Cooling System

C

Steam Generator Low Pressure Bypass signal

C

High Pressure Safety Injection Pump P-66B Subcooling Valve CV-3070

The inspectors interviewed the cognizant engineers and reviewed the supporting

documents to assess the adequacy of the operability assessments for the current plant

mode. The inspectors also reviewed the applicable sections of the Technical

Specifications, Updated Final Safety Analysis Report, and design basis documents to

verify that the operability assessments were technically adequate and that the

components remained available, such that no unrecognized increase in plant risk had

occurred.

In addition, the inspectors reviewed selected condition reports regarding operability

determinations to verify that the identified problems were entered into the licensees

corrective action program with the appropriate significance characterization and that

planned and completed corrective actions were commensurate with the significance.

b.

Findings

No findings of significance were identified.

.4

Operator Workarounds (OWAs)

a.

Inspection Scope

The Inspectors reviewed the following three risk significant operator workarounds:

Control Room Indicator Light Failure

Warm Water Recirculation Pump P-5 Vacuum Piping System

Start-up Transformer 1-2 Load

The inspectors evaluated whether the workarounds would adversely affect the operators

ability to implement abnormal and emergency operating procedures. The inspectors

reviewed the planned actions to correct the workarounds to verify that the priority to

Enclosure

17

resolve the deficiencies was reasonable when considering the potential impact on plant

risk and safety.

The inspectors also completed an aggregate assessment of the operator workarounds,

operator challenges, and control room deficiencies that were previously identified by

licensee personnel. The inspectors verified that the cumulative effects did not create

significant adverse consequences regarding the reliability, availability and operation of

risk significant systems. The inspectors also verified that the cumulative effects did not

adversely impact the operators ability to implement abnormal and emergency response

procedures in a timely manner when responding to plant transients and accidents.

b.

Findings

No findings of significance were identified.

.5

Temporary Plant Modifications

.a

Inspection Scope

The inspectors reviewed the modification documentation and the associated

10 CFR 50.59 evaluation for temporary modification TM-2000-024. This temporary

modification was developed to provide an alternate water supply that could be used, if

necessary, to backwash the service water traveling screens. The inspectors verified

that the temporary modification would not adversely impact other safety-related

equipment and that testing activities for the temporary modification were adequate to

ensure that the modification would function as intended.

The inspectors also verified that System Operating Procedure - 15, Attachment 11,

Alternate Water Supply To Clean Traveling Screens, provided adequate guidance to

the operators for using the alternate water supply.

b.

Findings

No findings of significance were identified.

1EP4

Emergency Action Level and Emergency Plan Changes (71114.04)

a.

Inspection Scope

The inspectors reviewed Revisions 6, 7, and 8 of the Palisades Nuclear Plant Site

Emergency Plan to determine if changes identified in these revisions reduced the plans

effectiveness, pending on-site inspection of the implementation of these changes.

b.

Findings

The inspectors identified that the licensee had incorporated NUMARC/NESP-007,

Methodology for Development of Emergency Action Levels, (NUMARC-007)

emergency action levels (EALs) into its approved standardized classification scheme

which were based on NUREG-0654/FEMA-REP-1, Criteria for Preparation and

Enclosure

18

Evaluation of Radiological Emergency Response Plans and Preparedness in Support of

Nuclear Power Plants, (NUREG-0654). This was identified as an Unresolved Item

(URI) pending determination whether any violation of NRC requirements occurred, and a

determination as to the significance, if any violation is determined to have occurred.

During the in-office review of the licensees emergency plan changes, it was identified

that the revisions to the emergency plan deleted EALs and replaced certain of the

deleted EALs with NUMARC-007 EALs. Additional information provided by the licensee

indicated these changes resulted from a condition report initiated when the licensees

shift supervisors were making different classification decisions for the same incident

presented on the simulator. To make the classification implementing procedure more

user friendly the licensee incorporated certain NUMARC EALs. The licensee indicated

in certain cases the incorporation of specific NUMARC-007 EALs allowed elimination of

NUREG-0654 EALs because the same information was covered in other parts of the

classification procedure.

A brief listing of examples of emergency plan EALs that had been deleted and

NUMARC-007 EALs added, included the following:

Revision 6 of the emergency plan:

Table 4-2, page 36, Engineered Safety Features, the Unusual

Event EAL for reactor protection system (RPS) failure was deleted and

inability to reach a required mode within Technical Specification limits

(NUMARC-007 #SU2) was added.

Table 4-2, page 36, Engineered Safety Features, the Alert EAL for

complete loss of auxiliary feedwater system was deleted.

Table 4-2, page 36, Engineered Safety Features, the Site Area

Emergency EAL for transient requiring operation of shutdown

systems with failure to trip was deleted and failure of the RPS

instrumentation to complete or initiate an automatic reactor scram

and a RPS setpoint has been exceeded and a manual scram was

not successful (NUMARC-007 #SS2) was added.

Table 4-2, page 36, Engineered Safety Features, the General

Emergency EAL for transient requiring operation of shutdown system

with failure to trip which results in core damage or additional failure of

core cooling and makeup systems (NUREG 0654 #G-5.c) was deleted

and failure of the RPS to complete an automatic scram and manual

scram was not successful and there is indication of an extreme challenge

to the ability to cool the core (NUMARC-007 #SG2) was added.

Table 4-2, page 36, Engineered Safety Features, the General

Emergency EAL for transient initiated by loss of feedwater and

condensate system followed by failure of auxiliary feedwater system for

an extended period (NUREG 0654 #G-5.b) was deleted.

Enclosure

19

The inspectors identified that the intermingling of classification schemes deviated from

Regulatory Guide 1.101, Revision 3, which states, in part, that licensees may use either

NUREG-0654 or NUMARC-007 in their EAL scheme, but may not use portions of both

methodologies. Regulatory Guide 1.101 also states that licensees who propose to

revise their currently approved EAL classification scheme using the NUMARC-007

method adhere to the requirements in Section IV.B of Appendix E to 10 CFR Part 50

which states, in part, that these emergency action levels shall be discussed and agreed

on by the applicant and State and local government authorities and approved by the

NRC.

This issue is considered an URI pending further review by the NRC. In accordance with

NRC Inspection Procedure 71114.04, Emergency Action Level and Emergency Plan

Changes, these changes potentially result in a reduction of emergency plan

effectiveness and will be referred to the Office of Nuclear Reactor Regulation for further

review. Pending completion of these activities, the issue is considered an URI

(URI 05000255/2003008-03). The licensee has entered this issue into their corrective

action program as CAP 039195.

1EP6

Emergency Plan Drill Evaluation (71114.06)

a.

Inspection Scope

The inspectors observed a simulator training session for one crew of licensed operators

on December 17, 2003, in which the Shift Manager was required to implement the

emergency plan in response to simulated plant conditions. Licensee Emergency

Preparedness personnel had pre-designated that the opportunities for the Shift Manager

to classify the event and make required notifications would be evaluated and included in

the Drill and Exercise Performance performance indicator data.

The inspectors verified that the Shift Manager classified the emergency condition and

completed the required notifications to State and Local Police authorities in an accurate

and timely manner as required by the emergency plan implementing procedures. The

inspectors also reviewed the Emergency Preparedness Evaluators summary report to

verify that the data included in the Drill and Exercise Performance performance indicator

was accurate.

b.

Findings

No findings of significance were identified.

Enclosure

20

2.

RADIATION SAFETY

Cornerstone: Occupational Radiation Safety

2OS3 Radiation Monitoring Instrumentation and Protective Equipment (71121.03)

.1

Self-Contained Breathing Apparatus (SCBA) Maintenance

a.

Inspection Scope

The inspectors reviewed the vital component maintenance records over the past 5 years

for three SCBA units currently designated as ready for service. The inspectors also

ensured that the required, periodic air cylinder hydrostatic testing was documented and

up-to-date, and that the Department of Transportation required retest air cylinder

markings were in place for these three units: OCR-42 (located in the Ops Conference

Room by the Control Room Viewing Gallery); T625-47 (located along the east wall of the

Turbine Deck); and RPO-11 (located on the 611 foot elevation near the Radiation

Protection Offices). As the licensee did not itself conduct maintenance of vital

components of SCBA units, the inspectors reviewed licensee and vendor maintenance

procedures, including those for the low-pressure alarm and pressure-demand air

regulator, and the SCBA manufacturers recommended practices to determine if there

were inconsistencies between them.

These reviews represented one inspection sample.

b.

Findings

No findings of significance were identified.

Cornerstone: Public Radiation Safety

2PS1

Radioactive Gaseous And Liquid Effluent Treatment And Monitoring Systems

(71122.01)

.1

Inspection Planning

a.

Inspection Scope

The inspectors reviewed the calendar years 2001 and 2002 Radiological Effluent

Release Reports to verify that the program was implemented as described in

Radiological Effluent Technical Specifications (RETS)/Offsite Dose Calculation Manual

(ODCM) and to determine if ODCM changes were made in accordance with Regulatory

Guide 1.109 and NUREG-0133. The inspectors reviewed the Radiological Effluent

Release Reports and ODCM, to determine if any changes to the design and/or

operation of the radioactive waste systems changed the dose consequence to the

public. The inspectors also reviewed technical and/or 10 CFR 50.59 evaluations

performed, when required, for any such modifications and determined whether

radioactive liquid and gaseous effluent radiation monitor setpoint calculation

Enclosure

21

methodology changed since completion of the modifications. The inspectors

determined if anomalous results reported in the current Radiological Effluent Release

Report were adequately resolved.

The inspectors reviewed RETS/ODCM to identify the effluent radiation monitoring

systems and its flow measurement devices, effluent radiological occurrence

performance indicator incidents in preparation for onsite follow-up, and the Final Safety

Analysis Report (FSAR) description of all radioactive waste systems.

These reviews represented one inspection sample.

b.

Findings

No findings of significance were identified.

.2

Onsite Inspection - Walk-down of Effluent Control Systems, System/Program

Modifications, Air Cleaning System Surveillances, and Instrument Calibrations

a.

Inspection Scope

The inspectors walked down the major components of the gaseous and liquid release

systems (e.g., radiation and flow monitors, demineralizers and filters, tanks, and

vessels) to observe current system configuration with respect to the description in the

FSAR, ongoing activities, and equipment material condition.

The inspectors reviewed the licensees technical justification for changes made by the

licensee to the ODCM, as well as to the liquid or gaseous radioactive waste system design,

procedures, or operation since the last inspection to determine whether the changes

affected the licensees ability to maintain effluents as-low-as-reasonably-achievable and

whether changes made to monitoring instrumentation resulted in a non-representative

monitoring of effluents.

The inspectors reviewed air cleaning system surveillance test results to ensure that the

system was operating within the licensees acceptance criteria. Specifically, the

inspectors reviewed the most recent results of the Ventilation Filter Testing Program for

the Control Room Ventilation System to verify that test methodology, frequency and test

results met Technical Specification requirements. The inspectors reviewed and

discussed the test results of in-place high efficiency particulate air (HEPA) and charcoal

absorber penetration tests, laboratory tests of charcoal absorber methyl iodide

penetration, and in-place combined HEPA filter and charcoal absorber train pressure

drop tests for the systems with system engineering staff.

The inspectors reviewed records of instrument calibrations performed since the last

inspection for each point of discharge effluent radiation monitor and flow measurement

device and reviewed any completed system modifications and the current effluent radiation

monitor alarm setpoint value for conformance with RETS/ODCM requirements. The

inspectors also reviewed calibration records of radiation measurement (i.e., counting room)

instrumentation associated with effluent monitoring and release activities and the quality

control records for the radiation measurement instruments.

Enclosure

22

These reviews represented four inspection samples: one for the walk down of the

effluent control systems, one for the program/system modification reviews, one for the

air cleaning system surveillance review, and one for the review of instrument calibration

records.

b.

Findings

During a walk down of the Radioactive Gaseous Effluent Monitoring (RGEM) system,

the inspectors identified that the as installed configuration of the sample piping

running from the isokinetic sampling head within the stations stack leading to the

RGEM radiological monitors contained at least four piping bends (i.e., elbows) of

approximately 90 degrees each. This was identified as an Unresolved Item (URI)

pending determination whether any violation of NRC requirements occurred, and a

determination as to the significance, if any violation is determined to have occurred.

Upon this observation, the inspectors inquired of the licensee as to what assurances

there were that the piping configuration did not promote plate-out of iodines and

particulates from the effluent stream and that the system was obtaining a representative

sample of the stations gaseous effluents. Prior to the end of the on-site portion of the

inspection, the licensee provided the inspectors a copy of the RGEM system design

documentation (circa 1982), which indicated that the system was designed and installed

such that it receives a representative isokinetic sample of plant gaseous effluent and

that the sample piping from the stack to the RGEM system is heat traced and insulated

to prevent condensation and plating out of the effluent sample. The inspectors

walked-down the sample piping to verify that it was insulated and the heat tracing

was operable.

During in-office review of the design documentation, the inspectors identified that the

RGEM Design Criteria (Section 3.0) for the system included ANSI N13.1-1969, Guide

to Sampling Airborne Radioactive Materials in Nuclear Facilities. Section B5 of

Appendix B of ANSI N13.1-1969 indicates that elbows in sampling lines should be

avoided if at all possible, but when they are required, the bend radius of the elbow

should be as long as practicable, and design flow rates through any line containing an

elbow should be kept low. The inspectors also noted that the ANSI standard did not

address the use of piping insulation or heat tracing as methods to mitigate iodine and

particulate plate-out.

Therefore, the inspectors preliminarily determined that the as installed configuration of

the RGEM sampling piping did not appear to meet the design criteria of the ANSI

standard. However, the inspectors were unable to determine if the as installed

configuration of the RGEM system prevented the collection of representative gaseous

effluent samples, and the significance the plate-out had, if any, on the public dose

consequences from the stations gaseous effluents. The licensee captured this issue in

its corrective action program as CAP 039097. Pending the completion of the licensees

evaluation of this issue and the NRCs review of the licensees evaluation, this issue is

considered a URI (URI 05000255/2003008-04).

Enclosure

23

.3

Onsite Inspection - Effluent Release Packages, Abnormal Releases, Dose Calculations,

and Laboratory Quality Control and Assurance

a.

Inspection Scope

As there were no routine radioactive liquid releases conducted during the on-site

inspection, the inspectors reviewed several radioactive liquid waste release permits,

including the projected doses to members of the public, to verify that appropriate

treatment equipment was used and that radioactive liquid waste was processed and

released in accordance with RETS/ODCM and procedure requirements. The inspectors

observed the routine processing (including sample collection and analysis) of radioactive

gaseous effluent from Waste Gas Decay Tank T-101A, and reviewed several other

radioactive gaseous effluent release permits, to verify that appropriate treatment

equipment was used and that the radioactive gaseous effluent was processed and

released in accordance with RETS/ODCM and procedure requirements.

The inspectors reviewed the records of abnormal releases, or releases made with

inoperable effluent radiation monitors, and reviewed the licensees actions for these

releases to ensure an adequate defense-in-depth was maintained against an

unmonitored, unanticipated release of radioactive material to the environment.

The inspectors reviewed a selection of monthly, quarterly, and annual dose calculations

to ensure that the licensee properly calculated the offsite dose from radiological effluent

releases and to determine if any annual RETS/ODCM (i.e., Appendix I to 10 CFR Part 50 values) limits were exceeded.

The inspectors reviewed the results of the interlaboratory comparison program to verify

the quality of radioactive effluent sample analyses performed by the licensee. The

inspectors reviewed the licensees quality control evaluation of the interlaboratory

comparison test and associated corrective actions for any deficiencies identified. The

inspectors reviewed the licensees assessment of any identified bias in the sample

analysis results and the overall effect on calculated projected doses to members of the

public. In addition, the inspectors reviewed the results from the licensees Quality

Assurance audits to determine whether the licensee met the requirements of the

RETS/ODCM.

These reviews represented four inspection samples: one for the review of effluent

release packages, one for the abnormal release reviews, one for the dose calculation

reviews, and one for the review of laboratory quality control and assurance.

b.

Findings

No findings of significance were identified.

Enclosure

24

.4

Identification and Resolution of Problems

a.

Inspection Scope

The inspectors reviewed licensee self-assessments, audits, and Special Reports related

to the radioactive effluent treatment and monitoring program since the last inspection to

determine if identified problems were entered into the corrective action program for

resolution. The inspectors also verified that the licensee's self-assessment program

was capable of identifying repetitive deficiencies or significant individual deficiencies in

problem identification and resolution.

The inspectors also reviewed corrective action reports from the radioactive effluent

treatment and monitoring program since the previous inspection, interviewed staff, and

reviewed documents to determine if the following activities were being conducted in an

effective and timely manner commensurate with their importance to safety and risk:

1.

Initial problem identification, characterization, and tracking;

2.

Disposition of operability/reportability issues;

3.

Evaluation of safety significance/risk and priority for resolution;

4.

Identification of repetitive problems;

5.

Identification of contributing causes;

6.

Identification and implementation of effective corrective actions;

7.

Resolution of Non-Cited Violations (NCVs) tracked in the corrective action system;

and

8.

Implementation/consideration of risk significant operational experience feedback.

These reviews represented one inspection sample.

b.

Findings

No findings of significance were identified.

2PS3

Radiological Environmental Monitoring Program (REMP) and Radioactive Material

Control Program (71122.03)

.1

Inspection Planning

a.

Inspection Scope

The inspectors reviewed the most current Annual Radiological Environmental Operating

Report (for calendar year 2002) and licensee assessment results to verify that the

REMP was implemented as required by Technical Specifications and the Offsite Dose

Calculation Manual (ODCM). The inspectors reviewed the report for changes to the

ODCM with respect to environmental monitoring, commitments in terms of sampling

locations, monitoring and measurement frequencies, land use census, interlaboratory

comparison program, and analysis of data. The inspectors reviewed the Updated Final

Safety Analysis Report (UFSAR) for information regarding the environmental monitoring

Enclosure

25

program and meteorological monitoring instrumentation. The inspectors reviewed the

scope of the licensees audit program to verify that it met the requirements of

10 CFR 20.1101(c).

These reviews represented one inspection sample.

b.

Findings

No findings of significance were identified.

.2

Onsite Inspection

a.

Inspection Scope

The inspectors walked down 75 percent of the air sampling stations and approximately

23 percent of the thermoluminescence dosimeter (TLD) monitoring stations to determine

whether they were located as described in the ODCM and to assess the sampling

capability and material condition of the equipment.

The inspectors observed the collection and preparation of selected environmental

samples (e.g., ground and surface water, milk, vegetation, sediment, and soil) to verify

that environmental sampling was representative of the release pathways as specified in

the ODCM and that sampling techniques were conducted in accordance with licensee

procedures.

The inspectors reviewed the operation of the stations meteorological instruments,

including data readout and recording instrumentation at the tower and in the control

room, to verify that they were as described, operable, calibrated, and maintained in

accordance with guidance contained in the UFSAR, NRC Safety Guide 23, and licensee

procedures. The inspectors compared real-time data collected at the meteorological

tower, such as wind speed, wind direction, and differential temperature, to the time-

average data transmitted to the control room to verify data integrity.

The inspectors reviewed each event documented in the 2002 Annual Radiological

Environmental Operating Report which involved a missed sample, inoperable sampler,

lost TLD, or anomalous measurement for the cause and corrective actions, and

conducted a review of the licensees assessment of any positive sample results

(i.e., licensed radioactive material detected above the lower limits of detection (LLDs)).

The inspectors reviewed the associated radioactive effluent release data that was the

likely source of the released material identified by the REMP sample.

The inspectors reviewed significant changes, if any, made by the licensee to the ODCM

as the result of changes to the land census or sampler station modifications since the

last inspection. In particular, the inspectors reviewed technical justifications for the

recently changed sampling locations for two outer-ring TLD stations. The inspectors

assessed the licensees ODCM change evaluations to verify that the changes did not

adversely affect the licensees ability to monitor the impacts of radioactive effluent

releases on the environment.

Enclosure

26

The inspectors reviewed the calibration and maintenance records for all twelve air

samplers and focused on the air flow meter and particulate filter/charcoal cartridge

components of the samplers. Because the licensee did not conduct analyses of REMP

samples on-site, the inspectors were not able to review licensee calibration records for

environmental sample radiation measurement instrumentation (i.e., count room

equipment), or review quality control charts for count room instrumentation.

However, the inspectors reviewed the results of the REMP sample vendors quality

control program, including the vendors interlaboratory comparison program results, to

verify the adequacy of the vendors program and corrective actions taken for any

identified deficiencies. The inspectors reviewed the detection sensitivities utilized by the

REMP sample vendor for counting samples to verify that the samples met the

TS/ODCM required LLDs. The inspectors reviewed audits and technical evaluations the

licensee performed on the vendors program. The inspectors reviewed quality

assurance audit results of the program to determine whether the licensee met Technical

Specification and ODCM requirements.

These reviews represented six inspection samples.

b.

Findings

No findings of significance were identified.

.3

Unrestricted Release of Material from the Radiologically Controlled Area (RCA)

a.

Inspection Scope

The inspectors observed several locations where the licensee monitored potentially

contaminated material leaving the RCA, and inspected the methods used for control,

survey, and release from these areas. The inspectors observed the performance of

personnel surveying and releasing material for unrestricted use to verify that the work

was performed in accordance with plant procedures.

The inspectors assessed the radiation monitoring instrumentation utilized for the

unrestricted release of material from the RCA to verify that it was appropriate for the

radiation types present and was calibrated with the requisite radiation sources. The

inspectors reviewed the licensees criteria for the survey and release of potentially

contaminated material and verified that there was guidance on how to respond to

indications of the presence of licensed radioactive material. The inspectors reviewed

the licensees equipment to ensure the radiation detection sensitivities were consistent

with the NRC guidance contained in IE Circular 81-07 and IE Information Notice 85-92

for surface contamination and HPPOS-221 for volumetrically contaminated material.

The inspectors reviewed the licensees program to determine if it adequately identified

the potential for difficult-to-detect radionuclides (i.e., radionuclides that decay via

electron capture) and accounted for those radionuclides during routine unrestricted

release surveys. Finally, the inspectors reviewed the licensees procedures and records

to verify that the radiation detection instrumentation was used at its typical sensitivity

level based on appropriate counting parameters (i.e., counting times and background

radiation levels), and that the licensee had not established a release limit by altering

Enclosure

27

instrumentation typical sensitivities through such methods as raising the energy

discriminator level or locating the instrument in a high radiation background area.

These reviews represented two inspection samples.

b.

Findings

No findings of significance were identified.

.4

Identification and Resolution of Problems

a.

Inspection Scope

The inspectors reviewed the licensees self-assessments, audits, Licensee Event

Reports, and Special Reports, as available, related to the Radiological Environmental

Monitoring Program since the last inspection to determine if identified problems were

entered into the corrective action program for resolution. The inspectors also reviewed

the licensee's self-assessment program to determine if it was capable of identifying

repetitive deficiencies or significant individual deficiencies in problem identification and

resolution.

The inspectors also reviewed corrective action reports related to the REMP and

radioactive material control program since the previous inspection, interviewed staff, and

reviewed documents to determine if the following activities were being conducted in an

effective and timely manner commensurate with their importance to safety and risk:

1.

Initial problem identification, characterization, and tracking.

2.

Disposition of operability and reportability issues.

3.

Evaluation of safety significance, risk, and priority for resolution.

4.

Identification of repetitive problems.

5.

Identification of contributing causes.

6.

Identification and implementation of effective corrective actions.

7.

Resolution of Non-Cited Violations tracked in the corrective action system.

8.

Implementation and consideration of risk significant operational experience

feedback.

These reviews represented one inspection sample.

b.

Findings

No findings of significance were identified.

Enclosure

28

4.

OTHER ACTIVITIES (OA)

4OA1 Performance Indicator Verification (71151)

.1

Reactor Safety Performance Indicators

a.

Inspection Scope

The inspectors used definitions and guidance contained in Revision 2 of Nuclear Energy

Institute Document 99-02, Regulatory Assessment Performance Indicator Guideline, to

verify the accuracy of the data submitted for the following three performance indicators:

Unplanned Power Changes Per 7,000 Critical Hours

Reactor Coolant System (RCS) Specific Activity

RCS Leakage

The inspectors reviewed the data submitted by licensee personnel for October 2002

through September 2003 to verify that the Unplanned Power Changes per 7,000 Critical

Hours and Reactor Coolant System Leakage Performance Indicators were reported

accurately. The inspectors also reviewed samples of records regarding primary coolant

system leakage calculations, control room logs and monthly operating data reports.

The inspectors reviewed the licensees assessment of its performance indicator for RCS

specific activity by reviewing Chemistry Department records and selected isotopic

analyses (July 2002 through March 2003) to verify that the greatest Dose Equivalent

Iodine (DEI) value obtained during those months corresponded with the value reported

to the NRC. The inspectors also reviewed selected DEI calculations to verify that the

appropriate conversion factors were used in the assessment as required by Technical

Specifications. Additionally, on October 22, 2003, the inspectors observed a chemistry

technician obtain and analyze a reactor coolant sample for DEI to verify adherence with

licensee procedures for the collection and analysis of reactor coolant system samples.

Further, the inspectors reviewed condition reports regarding problems with performance

indicator data to verify that the issue was entered into the corrective action program with

the appropriate significance level. The inspectors also verified that planned corrective

actions were appropriate and implemented as scheduled.

b.

Findings

No findings of significance were identified.

.2

Radiation Protection Strategic Area

a.

Inspection Scope

The inspectors sampled the licensees submittals for performance indicators (PIs) and

periods listed below. The inspectors used PI definitions and guidance contained in

Revision 2 of Nuclear Energy Institute Document 99-02, Regulatory Assessment

Enclosure

29

Performance Indicator Guideline, to verify the accuracy of the PI data. The following PI

was reviewed:

RETS/ODCM Radiological Effluent Occurrence

Since no reportable occurrences were identified by the licensee for 3rd Quarter 2002

through 3rd Quarter 2003, the inspectors compared the licensees data and reviewed

corrective action documents generated during the time period to identify any potential

occurrences such as unmonitored, uncontrolled or improperly calculated effluent

releases that may have impacted offsite dose. Also, the inspectors evaluated the

licensees methods for determining offsite dose and selectively verified that liquid and

gaseous effluent release data and associated offsite dose calculations performed since

this indicator was last reviewed were accurate.

b.

Findings

No findings of significance were identified.

4OA2 Identification and Resolution of Problems (71152)

a.

Inspection Scope

On August 10, 2003, during scheduled quarterly surveillance testing, High Pressure

Safety Injection Pump Subcooling Valve CV-3070 failed to stroke open as required.

Consequently, High Pressure Safety Injection Pump P-66B was declared inoperable and

Technical Specification 3.5.2.B.1 action was entered which required the pump to be

restored to operable status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />.

The inspectors reviewed the apparent cause evaluation for Condition Report

CAP037030, Subcooling Valve CV-3070 Failed to Open During QO-5 Valve Test

Procedure, to verify that: (1) the problem was accurately identified; (2) the apparent

cause was adequately justified; (2) extent of condition and generic implications were

appropriately addressed; and (3) corrective actions were appropriately focused to

address the problem and implemented commensurate with the safety significance of the

issue.

b.

Findings

No findings of significance were identified. However, the inspectors noted one

weakness regarding the evaluation and resultant corrective actions.

Licensee personnel concluded that the apparent cause for CV-3070 to not open was a

flow control valve in the operating air system which had been installed backwards in

1995. Licensee personnel also concluded that human error was the cause of the flow

control valve being installed incorrectly. However, the evaluation did not identify that the

work order and work instructions utilized in 1995 during the maintenance activity to

disassemble and then rebuild the actuator to CV-3070 did not provide any guidance to

maintenance personnel regarding proper orientation for the flow control valve.

Enclosure

30

Consequently, there was no corrective action developed to revise the work instruction to

ensure adequate guidance was provided to the maintenance personnel during any

subsequent CV-3070 actuator maintenance activities. However, this issue was of minor

significance since maintenance on the valve actuators had not been performed since

the evaluation was completed. Therefore, the failure to develop a corrective action to

review and revise the work instructions had not resulted in any actual adverse

consequences.

.2

Routine Review of Identification and Resolution of Problems

a.

Inspection Scope

As discussed in previous sections of this report, the inspectors routinely reviewed issues

during baseline inspection activities and plant status reviews to verify that condition

reports were being generated and entered into the corrective action program with the

appropriate significance characterization. For select condition reports, the inspectors

also verified that identified corrective actions were appropriate, and had been

implemented or were scheduled to be implemented in a manner commensurate with the

significance of the identified problem.

b.

Findings

No findings of significance were identified.

4OA3 Event Follow-up (71153)

The inspectors reviewed two Licensee Event Reports to verify that the events were

accurately described, to determine if any violations of NRC requirements occurred, and

to assess the appropriateness of identified corrective actions.

.1

(Closed) Licensee Event Report (LER) 50-255/03-005: Emergency Diesel Generators

Start on Low Voltage Condition.

On August 14, 2003, with the plant operating at 100 percent power, an electrical power

grid disturbance occurred that momentarily lowered voltage on 2400 volt safety-related

Buses 1C and 1D which caused both Emergency Diesel Generators to start. However,

Buses 1C and 1D remained energized from offsite power throughout the event as

designed. Local grid conditions stabilized within 5 minutes and both Emergency Diesel

Generators were subsequently secured. The inspectors did not identify any issues of

significance. This LER is closed.

.2

(Closed) LER 03-004: Inoperable Train of Containment Cooling - Condition Prohibited

by Technical Specifications.

This issue was previously documented in NRC Integrated Inspection Report 05000255/2003006, Section 1R15, as a self-revealed finding of very low safety

significance (Green) with an associated Non-Cited Violation for exceeding the

completion time for required actions in Technical Specification 3.6.6, Containment

Enclosure

31

Cooling Systems. The inspectors did not identify any new information of significance.

This LER is closed.

4OA6 Meetings

.1

Exit Meeting

The inspectors presented the inspection results to Mr. D. J. Malone and other members

of licensee management on January 9, 2004. Licensee personnel acknowledged the

findings presented. The inspectors asked licensee personnel whether any materials

examined during the inspection should be considered proprietary. No proprietary

information was identified.

.2

Interim Exit Meetings

The following Interim Exit Meetings were conducted:

Radiation Protection (RETS/ODCM) inspection with Mr. R. Remus on

December 19, 2003. A telephonic re-exit was conducted with Messrs. J. Beer

and D. G. Malone on December 31, 2003, to discuss the establishment of the

URI related to the RGEM system (see Section 2PS1.2).

Radiation Protection (REMP and Radioactive Material Control) inspection with

Mr. M. Carlson on October 24, 2003.

Biennial Heat Sink inspection with Mr. D. Cooper on November 21, 2003.

Emergency Preparedness inspection with Mr. T. Blake on December 22, 2003.

ATTACHMENT: SUPPLEMENTAL INFORMATION

Attachment

1

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee

D. Cooper, Senior Vice President Group Operations

D. Malone, Site Vice President

P. Harden, Site Director

R. Remus, Plant Manager

M. Carlson, Engineering Director

T. Blake, Emergency Preparedness Supervisor

L. Lahti, Licensing Manager

G. Hettel, Manager, Maintenance and Construction

G. Packard, Operations Manager

D. Williams, Chemistry and Radiation Safety Manager

Nuclear Regulatory Commission

D. Hood, Project Manager, NRR

S. Klementowicz, NRR, Public Radiation Safety Cornerstone Lead Health Physicist

Attachment

2

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

05000255/2003008-01

NCV

Failure of Containment Spray Pump P-54C Inboard Motor

Bearing

05000255/2003008-02

NCV

Failure of High Pressure Safety Injection Pump P-66B

Subcooling Valve CV-3070 to Open

05000255/2003008-03

URI

Emergency Action Level and Emergency Plan Changes05000255/2003008-04

URI

RGEM System Configuration May Not Obtain a

Representative Gaseous Effluent Sample

Closed

05000255/2003008-01

NCV

Failure of Containment Spray Pump P-54C Inboard Motor

Bearing

05000255/2003008-02

NCV

Failure of High Pressure Safety Injection Pump P-66B

Subcooling Valve CV-3070 to Open

50-255/03-004

LER

Inoperable Train of Containment Cooling - Condition

Prohibited by Technical Specifications

50-255/03-005

LER

Emergency Diesel Generators Start on Low Voltage

Condition

Attachment

3

LIST OF DOCUMENTS REVIEWED

The following is a list of documents reviewed during the inspection. Inclusion on this list does

not imply that the NRC inspectors reviewed the documents in their entirety but rather that

selected sections of portions of the documents ere evaluated as part of the overall inspection

effort. Inclusion of a documents on this list does not imply NRC acceptance of the document or

any part of it, unless this is stated in the body of the inspection report.

1R01

Adverse Weather Protection

Off-Normal Procedure-12; Acts of Nature; Revision 18 Murray and Trettel Storm

Warning, November 12, 2003

Alarm Response Procedure-7; Auxiliary Systems Scheme EK-11 (C-13); Windows 24,

29, 32, 38 and 44; Revision 65

System Operating Procedure-16, Attachment 10; Frazil Ice - Information / Prevention /

Mitigation; Revision 31

System Operating Procedure-23, Attachment 8; Cold weather Checklist; Revision 17

System Operating Procedure-23, Attachment 9; Cold weather Checklist-Electrical;

Revision 17

Condition Reports Reviewed to Assess Significance Characterization of Identified Problems

CAP038280; Evaluate Whether MV-ES3243, SIRW Tank Level Transmitter Isolation,

Cold Weather Protection is Adequate

CAP038315; Work Week 2344: Cold Weather Checklist Not Completed in a Timely

Manner

Condition Reports Reviewed To Assess Corrective Actions

CAP033427; Received ED-1129 Service Water Bay Low Level Alarm

CAP038281; LT-0331, SIRW Tank Level Transmitter, Not Checked in SOP-23,

Attachment 8, Cold Weather Checklist

CAP038000; Intake Structure Ventilation Operation Contrary to Updated Final Safety

Analysis Report Described Operation

1R04

Equipment Alignment

Plant Procedures and Miscellaneous Documents

SOP-19; Instrument and Service Air System Checklist; Revision 29

SOP-24 Ventilation and Air Conditioning System; Revision 37

WO24323843; Clean All Blockages on P-66A Bearing Housing Caps

M218; Piping and Instrument Diagram for the Control Room Heating, Ventilation and Air

Conditioning

Attachment

4

Condition Reports Reviewed to Assess Corrective Actions

CAP037656; Potential Loss of High Pressure Safety Injection Pump Bearing Housing

Vent Path

CAP037659; P-67A Low Pressure Safety Injection Pump Bearing Housing Vent

Inspection

Condition Reports Reviewed to Assess Significance Characterization of Identified Problems

CAP038709; East Mechanical Equipment Room Deficiencies Noted by NRC

1R05

Fire Protection

Plant Procedures

ONP25.2; Off-Normal Procedure - Fire Which Threatens Safety-Related Equipment Fire

Areas 12, 10, 30, 31; Revision 12

FPSP-SI-1; Data Sheet for Alarm Bells and Ionization Smoke Detectors for Fire Areas

12, 10, 30, 31, Revision 3

FPSP-RP-11; Fire Barrier Penetration Seal/Conduit Seal Inspection Form for Fire Areas

12, 10 30, 31; Revision 5

FPSP-RM-5; Palisades Fire Damper Sheet for Fire Areas 12; Revision 2

FPSP-SO-2; Safety-Related Fire Door Data Sheet for Fire Areas 12, 10, 30, 31;

Revision 0

FPSP-WP-1; Safety-Related Fire Door Data Sheet Fire Areas 12, 10, 30, 31; Revision 1

Condition Reports Reviewed to Assess Corrective Actions

CAP029787; Containment Fire Detection does Not Meet Code of Record

CAP029676; Technical Inaccuracies In the Fire protection Program Report

Condition Reports Reviewed to Assess Significance Characterization of Identified Problems

CAP038727; Emergency Lighting Unit ELU-67 is Directed Slightly Upward (Above

Horizontal)

CAP039240; "Fire Detectors Not Installed as Outlined in the Modification Package"

Miscellaneous Documents

FSAR; Section 9.6, Fire Protection; Revision 23

FSAR; Section 9, Fire Detection Instrumentation; Revision 24

Fire Hazards Analysis Report; Revision 4

Palisades Plant Post Fire Safe Shut-down Summary Report; September 1, 1978

Fire Protection Safety Evaluation Report by the Office of NRR in the Matter of

Consumers Power Company Palisades Plant Docket 50-255; September 1, 1978

Attachment

5

1R06

Flood Protection

Final Safety Analysis Report; Table 5.4-1; Safety Related Equipment That Requires

Protection From Flooding Due to Failures of Nonclass 1 Systems; Revision 21

Final Safety Analysis Report; Section 5.4.2; Flooding and Wetting From Plant Sources;

Revision 24

Condition Reports Reviewed to Assess Corrective Actions

CAP035933; Expansion Joint Inspection Fails to Identify Known Deficiency

CAP034759; Water Tight Door #58 Failed Inspection (Doghouse Door)

CAP034720; Water Tight Door #51 Failed Inspection Criteria

Work Orders

WO24321400; Door 58, East Engineered Safeguards Doghouse Door

WO24321399; Door 51, Engineering Safeguards Entrance

1R07

Heat Sink Performance

CH 1.11; MIC Control Program Inspection Report - VC-10; dated April 18, 2001,

October 24, 2002, and February 24, 2003

CH 1.11; MIC Control Program Inspection Report - VC-10 Service Water Piping; dated

October 24, 2002

CH 1.11; MIC Control Program Inspection Report - VC-11; dated October 1, 2001, and

July 29, 2003

CH 1.11; MIC Control Program Inspection Report - VC-11 Service Water Piping; dated

December 4, 2001

CH 1.11; MIC Control Program Inspection Report - VC-11 Service Water Valve

MV-SW281; dated December 4, 2001

CH 1.11; MIC Control Program Inspection Report - VHX-2; dated April 12, 2001

CH 1.11; MIC Control Program Inspection Report - VHX-3; dated March 30, 2003

CH 1.11; Biofouling and MIC Control Program; Revision 1

DBD-1.06; Control Room HVAC System; Revision 7

DBD-2.08; Containment Air Coolers; Revision 2

EA-D-PAL-93-272E-02; Control Room HVAC Refrigeration Unit Performance at

85 Degrees Fahrenheit Entering Service Water Temperature; Revision 0

EA-LOCA-2001-01; Containment Response to a LOCA Using CONTEMPT-LT/28;

Revision 1

EA-LTP-99-01; Methodology for Capacity Testing and Analysis of the Control Room

HVAC System; Revision 0

EA-VC10/11-2000; Uncertainty Analysis for the Control Room HVAC System

Surveillance Procedure; Revision 1

EM-09-15; Raw Water Corrosion Program; Revision 4

EM-09-16; Heat Exchanger Condition Assessment Program; Revision 3

EM-09-16; Heat Exchanger Visual Testing Checklist - VC-11; completed July 29, 2003

RO-216; Service Water Flow Verification; Revision 2; completed April 4, 2003

RT-202, Basis Document; Control Room Heat Removal Capability; Revision 1

Attachment

6

RT-202; Control Room Heat Removal Capability (Train A); Revision 2; completed

August 19, 2003

RT-202; Control Room Heat Removal Capability (Train B); Revision 2; completed

August 19, 2003

Palisades 2001 Refuel Outage Report by Underwater Construction Corporation; dated

May 15, 2001

Palisades 2003 Refuel Outage Report by Underwater Construction Corporation; dated

April 5, 2003

Raw Water Corrosion Program Report Operational Cycle 15 and 2001 Refueling Outage

Report; dated August 13, 2001

Raw Water Corrosion Program Report Operational Cycle 16 and 2003 Refueling Outage

Report; dated July 22, 2003

NMC Letter to NRC; Resolution of Generic Letter 96-06 Waterhammer Issues; dated

February 28, 2003

NMC Letter to NRC; Resolution of Generic Letter 96-06 Two-Phase Flow Issues; dated

July 24, 2003

M123; Heating & Ventilation Reactor Containment Building Coolers-Unit V-3; Revision 0

M124; Heating & Ventilation Reactor Containment Building Coolers-Unit V-1 and

Unit V-2; Revision 6

M218; HTG. Vent. & Air Cond. Control Room; Revision 9

VEN-M-60A, Sheet 1; Type R Coil 36 Tube Face, 4'-11 1/2 NTL, 12 Row, 4 Pass;

Revision 1

VEN-M-60A, Sheet 2; Type R Coil 36 Tube Face, 4'-11 1/2 NTL, 12 Row, 4 Pass;

Revision 0

VEN-M-60A, Sheet 7; Containment Air Coolers VHX-1, VHX-2, and VHX-3 Cooling Coil

Tube Map; Revision 0

C-PAL-00-3205; Apparent Tube Blockage on Containment Air Cooler Coil VHX-3; dated

October 26, 2000

C-PAL-00-3664; Thermography Scanning Finds More Containment Air Cooler Tubing

Plugged; dated December 20, 2000

1R11

Licensed Operator Requalification

Simulator Performance Exercise - 42; Licensed Operator Requalification; Course

N00320; Revision 0

Simulator Performance Evaluation; Crew 1; December 3, 2003

1R13

Maintenance Risk Assessments and Emergent Work Evaluation

Miscellaneous Documents

Operators Risk Reports; September 29 through October 3, November 10-13 and 18-19,

and December 7-10

Daily Maintenance Work Schedules; September 29 through October 3, November 10-13

and 18-19, and December 7-10

Operations Log entries; September 29 through October 3, November 10-13 and 18-19,

and December 7-10

Attachment

7

1R14

Non-Routine Plant Evolutions and Events

Plant Procedures

Alarm Response Procedure - 1; Turbine Condenser and Feedwater Scheme EK-01;

Window 60; Feedwater Pumps Lo Suction; Revision 52

Alarm Response Procedure - 1;Turbine Condenser and Feedwater Scheme EK-01;

Window 72; Moisture Separator Drain Tank Hi-Lo Level; Revision 52

Off Normal Procedure - 3; Loss of Main Feedwater; Revision 19

Off Normal Procedure - 26; Rapid Power Reduction; Revision 1

System Operation Procedure - 8, Attachment 2; Main Turbine and Generating Systems,

System Testing; Revision 65

Condition Reports Reviewed to Assess Significance Characterization for Identified Problems

CAP038519; Unanticipated Trip of A Heater Drain Pump During Turbine Valve Testing

CAP038508; Unexpected Alarm EK-0172 Moisture Separator Drain Tank Hi-Lo Level

CAP038512; E-9A MSR Reheat Stop Valve CV-0537 Failed to Close During Turbine

Valve Testing

CAP038514; Heater Drain Pump P-10A Discharge Check Valve Stuck Open

CAP038511; E-9B MSR Intercept Valve CV-0535 Failed to Reopen During Turbine

Valve Testing

CAP038509; Received Alarm EK-0105, Turbine High Vibration, Unexpectedly

CAP038513; Plant Challenges Due to Closure of MSR E-9A Reheat Sop Valve CV-0537

1R17

Permanent Plant Modifications

Engineering Assistance Requests

EAR-2000-0345; Seismic Qualification Utility Group Outlier Resolution for Safety

Injection Refueling Water Tank, T-58; June 18, 2003

EAR-2000-017; Alternate Safe-Shutdown Pathway for Cold-Shutdown Using Service

Water; May 30, 2003

EAR-2002-0293; Piping Modifications to Charging Pump Suction Piping to Facilitate

Crosstie Via Fire Hose from the Spent Fuel Pool Piping for Alternate Safe-Shutdown

Pathway for Hot-Shutdown; May 9, 2003

Plant Procedures

PCSO-5; Special Operating Procedure, Alternate Source for Charging to PCS;

Revision 0

COP-27; Chemistry Operating Procedure, Spent Fuel Pool System Chemistry;

Revision 17

PPAC X-OPSADM02; Preventive Maintenance Work Order - Alternate Safe Shutdown

Pathway Inspect

Attachment

8

Condition Reports Reviewed to Assess Significance Characterization of Identified Problems

CAP038236; Spent Fuel Pool Boron Administrative Limit Not Timely Incorporated in

Chemistry Procedures

CAP036336; Closeout Item EAR-2000-0345 - SFP Boron Concentration During

Maintenance

CAP036337; Closeout Items EAR-2000-0345 - Q-List Interpretations

CAP038956; Inadequate Documentation of Justification for Design Change

Piping and Instrument Diagrams

M-202; Sheet 1B; Chemical and Volume Control System; Revision 50

M-208; Sheet 1A; Service Water System; Revision 52

M-221; Sheet 2; Spent Fuel Pool Cooling System; Revision 50

1R19

Post Maintenance Testing

Work Orders

WO24322197; Service Water Pump P-7C; October 29, 2003

WO24323161; EDG 1-2 K-6B Starting Air Pressure Control; September 29, 2003

WO24321782; EDG Air Starting Motor (ASM-2B); September 29, 2003

WO24213350; Replace SV-1452 (K-6B/Fuel Oil); September 29, 2003

WO24323928; Wire 1B on Terminal Block TC Pinched; September 30, 2003

WO24112283; EDG 1-2 to Bus 1D; September 30, 2003

WO24213073; EDG 1-2 Air Start Motor ASM-2A Isolation; September 29, 2003

WO24113680 Attachment B; functional Test of Breaker 152-111

Plant Procedures

SWS-M-12; Service Water Pumps P-7A, P-7B and P-7C Repack; Revision 1

MO7A2; Emergency Diesel Generator 1-2; Revision 56

SOP-22; Emergency Diesel Generators; Revision 35

QO-20B; Inservice Test: Low Pressure Safety Injection Pumps; Revision 12

Miscellaneous Documents

Final Safety Analysis Report, Section 6.1; Safety Injection System; Revision 23

Technical Specifications 3.5.2; Emergency Core Cooling System

Technical Specifications Bases 3.5.2; Emergency Core Cooling System

Condition Reports Reviewed to Assess Significance Characterization of Identified Problems

CAP038299; Siemens Breaker S/N R-300511A-8 Failed to Close During Testing

CAP038302; Insufficient Cooling for Packing on Service Water P-7C After Repack

CAP038317; Service Water Pump Repacked With Larger Than Required Packing

CAP038320; Maintenance Violated the Procedural Step Requirement in Step 5.3.2 in

SWS-M-12

Attachment

9

1R22

Surveillance Testing

Completed Surveillance Test Procedures

QO-1; Safety Injection System; Revision 49

MO-33; Control Room Ventilation Emergency Operation; Revision 9

QO-14; Inservice Test Procedure - Service Water Pumps; Revision 21

Miscellaneous Documents

FSAR 7.3; Engineered Safeguards Controls; Revision 23

Reg Guide 1.52; Design, Inspection and Testing Criteria for Air Filtration and Adsorption

Units of Post-Accident ESF Atmosphere Cleanup System in Light Water-Cooled

Nuclear Power Plants; Revision 3

NUREG/CR-496; Control Room Habitability Survey of Licensed Commercial Nuclear

Power Generating Stations

Condition Reports Reviewed to Assess Significance Characterization of Identified Problems

CAP038044; Unexpected Containment Air Cooler Service Water System Leak Alarm

Received During QO-1 SIS Testing

CAP038110; Missed Sign Off for AC&O Sheet in Body of Procedure

Condition Reports Reviewed to Assess Corrective Actions

CAP037153; Palisades Control Room Habitability Not in Complete Conformance With

NRC Guidance

1REP Equipment Availability and Functional Capability

Maintenance Effectiveness

Plant Procedures

WI-ESS-O-02; Containment Spray Pump/Motor Oil Sample and Change; Revision 0

ESS-E-36; Component Cooling and Containment Spray Motor Maintenance; Revision 6

VTD-0322-0005; Louis-Allis Co. Instruction Manual for Large Motors

EGAD-EP-10; Maintenance Rule Scoping Document for 2400V AC Power and 4160V

AC Power Systems; Revision 2

Miscellaneous Documents

Containment Spray Pump Motor Oil Change Out History

Daily Checklists for Painting Floors/Walls/Equipment

Palisades Maintenance Rule Performance Indicators for 2400V AC Power and 4160V

AC Power Systems

Palisades Maintenance Rule Performance Monitoring Results for 2400V AC Power and

4160V AC Power Systems

Attachment

10

Health and Status Report for 2400V AC Power and 4160V AC Power Systems

FSAR; Chapter 8, Electrical Systems; Revision 23

Work Orders

PPAC X-OPS310; EEQ Required P-54A, B, C Motor Oil Change and Containment

Spray Pump Motor Oil Change P-54A, B, C

WO24320008; Miscellaneous Mechanical System Work

Condition Reports Reviewed to Assess Maintenance Rule Evaluations and Corrective Actions

CAP037180; Smoke Observed Coming From Containment Spray Pump P-54C Inboard

Motor Bearing

CAP034584; Undervoltage Relays on F and G Busses Failed to Reset

CAP031363; Breaker 152-306 Failed to Close From Control Room

Biennial Assessment of Maintenance Rule Periodic Evaluations

Miscellaneous Documents

EGAD-EP-10, Attachment 2; Maintenance Rule Scoping Document For Concentrated

Boric Acid System, Control Room HVAC System, High Pressure Air System and the

Fire Protection System; Revision 2

Health and Status Reports for Concentrated Boric Acid System, Control Room HVAC

System, High Pressure Air System and the Fire Protection System

Palisades Plant - Maintenance Rule Periodic Refueling Assessment; August 21, 2000 to

July 31, 2002

Condition Reports Reviewed to Assess Maintenance Rule Evaluations and Corrective Actions

CAP036655; Received EK-0726 Boric Acid Pumps P-56A and P-56B Overload

Unexpectedly

Condition Reports Reviewed to Assess Corrective Actions

CAP036114; Boric Acid Availability Does Not Meet Maintenance Rule Criteria

CAP03583; Maintenance Rule Performance Criteria Exceeded for Control Room HVAC

System

CAP015712; Unusual Noise and Smoke Coming from VC-11, Control Room HVAC

condensing unit

CAP031618; Door 16 Mechanical Equipment Room Results in TS3.7.10 A/B Entry

CAP032834; Inoperable B Train Control Room Ventilation Cooling

CAP034899; Control Room Cooling Train (VC-11) Inoperable

CAP031633; High Pressure Air Compressor C-6A Inoperable Due to Failed Oil Level

Switch

CAP037303; Oil Cap Unsecure On High Pressure Air Compressor C-6C

CPAL990984; Maintenance Rule Category (a)(1) Performance Improvement of the High

Pressure Air System

CAP031907; Evaluate Returning P-9B to Maintenance Rule Category (a)(2)

Attachment

11

CAP029995; Fire Pump P-9B Unavailability Exceeds Maintenance Rule Performance

Indicators

CPAL0200457; Fire Protection Maintenance Preventable Functional Failure of Electric

Fire Pump P-9A Exceeds Performance Criteria

CPAL0200497; Electric Fire Pump P-9A Fails to Meet Maintenance rule Availability

Requirements

CPAL0200059; Fire Pump P-9A Tripped After Running For Approximately 3 Minutes

CAP032600; Fire Protection System Exceeds Maintenance Rule Reliability Performance

Criteria

CAP033278; Compressor Related System Performance Issues

CAP032927; Weakness in Timely Resolution of Maintenance Rule (a)(1) Issues

CAP033280; Maintenance Rule Availability Performance Criteria Limitations in the

Scheduling Process

Operability Evaluations

Plant Procedures

EM-18-02; Interim Operability Criteria Evaluation For Palisades Plant Safety-Related

Piping Systems; Revision 1

Condition Reports Associated with Operabililty Determinations

CAP038087; Change the Source CAP for the Operable But Degraded Piping Feeding

CVCS [Chemical Volume Control System]

CAP032550; Steam Generator Low Pressure Bypass Not Calibrated in Appropriate

Direction

CAP037030; Subcooling CV-3070 Failed to Open During QO-5 Valve Test Procedure

Miscellaneous Documents

Final Safety Analysis Report; Section 5.10.1.4; Interim Operability Criteria; Revision 21

Technical Specifications 3.3.3; Engineered Safety Features Instrumentation

Final Safety Analysis Report; Section 7.2.3.8; Low Steam Generator Pressure;

Revision 23

Condition Reports Reviewed to Assess Corrective Actions

CAP030037; Incorrect Operability Determinations

Operator Workarounds

Plant Procedures

Admin Proc No 4.12; Operator Work-Around Program; Revision 1

Attachment

12

Miscellaneous Documents

Palisades Operator Workarounds List; as of October 29, 2003

Operations Concerns List; as of October 29, 2003

Control Room Deficiencies List; as of October 29, 2003

Palisades Operations Concerns List; as of October 29, 2003

Aggregate Assessment Factor; as of June 30, July 24, August 15, September 19 and

October 27, 2003

Temporary Plant Modifications

Plant Procedures

SOP-15, Attachment 11; Alternate Water Supply to Clean Traveling Screens;

Revision 32

Modification Documents

EDC-TM-2000-024-03; Engineering Design Change for TM-2000-024; 50.59 Screen;

November 13, 2003

TM-2000-024; Temporary Modification, Alternate Supply of Water to Traveling Screens;

November 11, 2003

1EP4

Emergency Action Level and Emergency Plan Changes

Palisades Nuclear Plant Site Emergency Plan; Revisions 5, 6, 7, and 8

1EP6

Emergency Preparedness Drill Evaluation

Plant Procedures

EI-3, Attachment 1; Palisades Event Notification Form; Revision 19

EI-1; Emergency Classifications and Actions; Revision 42

EI-3; Communications and Notifications; Revision 19

Condition Reports Reviewed to Assess Significance Characterization of Identified Problems

CAP039186; Investigate Potential Missed Drill / Exercise Performance Opportunity

2OS3 Radiation Monitoring Instrumentation and Protective Equipment

SurvivAir SCBA Maintenance Record File for OCR-42 (including cylinder hydrostatic test

data); dated through August 6, 2003

SurvivAir SCBA Maintenance Record File for RPO-11 (including cylinder hydrostatic test

data); dated through August 4, 2003

SurvivAir SCBA Maintenance Record File for T625-47 (including cylinder hydrostatic test

data); dated through August 6, 2003

Attachment

13

HP 7.5; Self-Contained Breathing Apparatus (SCBA) SurvivAir Mark-2 Model 9842;

Revision 4

HP 7.6; Inspection and Testing of SurvivAir (SCBA) Breathing Air Cylinders ; Revision 4

2PS1

Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems

2001 Annual Radioactive Effluent and Waste Disposal Report; dated March 26, 2002

2002 Annual Radioactive Effluent and Waste Disposal Report; dated March 24, 2003

Calibration File for High Purity Germanium Detector #1 (S/N 6983983); dated January 9,

1999

Calibration File for High Purity Germanium Detector #2 (S/N 1924); dated May 13, 1999

Calibration File for High Purity Germanium Detector #3 (S/N 1221); dated January 9,

1999

Palisades Final Safety Analysis Report (FSAR), Chapter 11; Radioactive Waste

Management and Radiation Protection; Revision 24

Quarterly Liquid and Gaseous Release Calculations (LADTAP and GASPAR Results)

for 3rd Quarter 2001, 2nd and 4th Quarter 2002, and 1st through 3rd Quarter 2003;

dated October 3, 2001, July 2, 2002, and January 9, April 5, July 3, September 26,

2003

Results of Radiochemistry Cross Check Program (Analytics), Consumers Power

Company, Palisades Nuclear Plant, 2nd Quarter 2003; dated November 10, 2003

Results of Radiochemistry Cross Check Program (Analytics), Consumers Power

Company, Palisades Nuclear Plant, 3rd Quarter 2003; dated November 10, 2003

Special Report of Inoperability of One Channel of Stack Gas Effluent System; dated

September 4, 2003

Special Report of Inoperability of One Channel of Stack Gas Effluent System - Hi Range

Noble Gas Monitor RIA-2327; dated September 20, 2002

ANSI N13.1-1969; Guide to Sampling Airborne Radioactive Materials in Nuclear

Facilities; dated February 19, 1969

CAP 033600/ACE 002935; Higher than Expected Noble Gas Activity During Breach of

Waste Gas System; dated February 26, 2003

CAP 036988/MRE 000158; Radioactive Gas Effluent Monitoring System Tripped; dated

August 6 and 11, 2003

CAP 037027; Counting Geometry Unavailable; dated August 10, 2003

CAP 037574; Clarification/Enhancement Needed for ODCM Compensatory Measures;

dated September 15, 2003

CAP 039097; Question Concerning Plant Stack Sample Line; dated December 17, 2003

CAP 039128; Evaluate Sampling/Handling of the Weekly Plant Stack Effluent Sample

Media; dated December 18, 2003 [NRC-Identified Issue]

CH 4.39; Gamma Ray Spectroscopy System; Revision 14

CE 005907; I-131 Release During 2003 Re-Fueling Outage Higher Than 2001

Re-Fueling Outage; dated June 9, 2003

DWR-10; Stack Effluent Sampling, Calculations, and Records; Revision 22

Gaseous Release Batch 03-052ST; Week 52 of CY2003 Stack Release Calculations;

dated December 17, 2003

Gaseous Release Batch 03-052-G; Waste Gas Decay Tank T-101A Release

Calculations; dated December 18, 2003

Gilbert/Commonwealth System Design No. 771; Post-Accident Monitoring - Palisades

Plant, Radioactive Gaseous Effluent Monitoring; dated September 8, 1982

Attachment

14

HP 6.4; Radioactive Liquid Calculation and Release Authorization; Revision 23

HP 6.5; Sampling Waste Gas Decay Tank; Revision 12

HP 6.6; Evaluation and Release of Waste Gas Decay Tank; Revision 16

Liquid Release Batch 02-024-R; T-90 Tank Release; dated October 21, 2002

Liquid Release Batch 03-001-R; T-91 Tank Release; dated January 14, 2003

Liquid Release Batch 03-011-R; T-91 Tank Release; dated April 17, 2003

Nuclear Oversight Observation Report No. 2003-001-8-013; Radiological Environmental

Monitoring Program: Process Monitor Function Checks, Milk Sample Collection, Waste

Gas Decay Tank, and Stack Gas Analysis; dated March 18, 2003

Nuclear Oversight Observation Report No. 2003-001-8-067; Review of the Radiological

Environmental Monitoring Program and Radiological Environmental Technical

Specifications; dated April 23, 2003

ODCM; Palisades Nuclear Plant Offsite Dose Calculation Manual; Revisions 17 and 18

RR-9B; Radwaste Discharge Monitor (RIA-1049) Calibration; dated July 28, 2003

RR-84A; Radioactive Gaseous Iodine/Part Effluent Monitor RIA-2325 Calibration; dated

August 6, 2002

RR-84B; Radioactive Noble Gas Effluent Monitor RIA-2326 Calibration; dated

August 19, 2002

RR-84C; High Range Noble Gas Effluent Monitor (RIA-2327) Calibration; dated

December 10, 2002

Self-Assessment Report I03-33; Radiological Effluent Monitoring - Pre NRC

Assessment; dated October 21, 2003

2PS3

Radiological Environmental Monitoring and Radioactive Material Control Programs

Environmental Department Meteorological Equipment Temperature / Delta-T Calibration

Form, T/TD-1 (60M); dated September 10, 2003

Environmental Department Meteorological Equipment Wind Speed Calibration Form,

WS-1 (10A); dated September 10, 2003

Environmental Department Meteorological Equipment Wind Direction Calibration Form,

WD-1 (10A); dated September 10, 2003

Environmental Department Meteorological Equipment Wind Speed Calibration Form,

WS-1 (10B); dated September 8, 2003

Environmental Department Meteorological Equipment Wind Direction Calibration Form,

WD-1 (10B); dated September 8, 2003

Environmental Department Meteorological Equipment Wind Speed Calibration Form,

WS-1 (60M); dated September 10, 2003

Environmental Department Meteorological Equipment Wind Direction Calibration Form,

WD-1 (60M); dated September 10, 2003

Palisades Nuclear Plant 2002 Annual Radiological Environmental Operating Report;

dated May 12, 2003

Palisades Nuclear Plant Offsite Dose Calculation Manual; Revision 17

Palisades Nuclear Plant Offsite Dose Calculation Manual, Appendix A, Relocated

Technical Specifications per NRC Generic Letter 89-01 (TAC No. 75060); Revision 10

Palisades Part 61 Isotopic Analysis Results Evaluated for Hard-to-Detect Nuclides;

dated November 13, 2002

Palisades Personnel Contamination Monitor (PCM-2) Commissioning Study; dated

February 17, 2003

Palisades Personnel Contamination Monitor (PCM-2) Sum Zone Setup and Operation;

Attachment

15

dated March 6, 2003

Radiological Environmental Monitoring Program - Pre NRC Assessment; dated

October 21, 2003

AP 7.15; Contamination Control; Revision 9

EA-JBB-99-001; Plant Radionuclide Mixture and Calibration Sources; dated

March 10, 1999

Form 116; Gas Meter Test and Repair (for Air Sampling Stations 1 - 12); dated

November 22, 2002 through September 19, 2003

HP 9.80; Operation and Calibration of the SAM9; Revision 1

HP 10.1; Radiological Environmental Monitoring Program Surveillance; Revision 8

MM-121; Meteorological Monitoring Project Plan; dated June 8, 1998

Nuclear Oversight Observation Report No. 2003-001-8-013; Radiological Environmental

Monitoring Program: Process Monitor Function Checks, Milk Sample Collection, Waste

Gas Decay Tank, and Stack Gas Analysis; dated March 18, 2003

Nuclear Oversight Observation Report No. 2003-001-8-067; Review of the Radiological

Environmental Monitoring Program and Radiological Environmental Technical

Specifications; dated April 23, 2003

SR-2001-341; Nuclear Utilities Procurement Issues Committee (NUPIC) Joint Quality

Assurance Program Audit Report (of Environmental, Incorporated); dated

July 27, 2001

Updated/Final Safety Analysis Report Chapter 2; Section 2.5.2, Meteorological

Program History; Revision 22

WI-RSD-H-010; Release of Items; Revision 6

4OA1 Performance Indicator Verification

DWO-1, Attachment 8; Primary Coolant System Inventory Form; October 2002 through

September 2003

Licensee Report of Monthly Operating Data; Palisades Nuclear Plant; October 2002

through September 2003

NEI 99-02; Regulatory Assessment Performance Indicator Guideline; Revision 2

Chemistry Department Analyses Database for DEI-131 versus Reactor Power; dated

July 1, 2002 through June 30, 2003

COP-1; Primary Coolant System Chemistry, Attachment 19; Revision 52

DWC-2; PCS Radiochemistry Analysis; Revision 18

NRC Indicator RETS/ODCM Radiological Effluent Occurrence (PR-01); dated 3rd

Quarter 2002, January 9, April 5, July 3, and September 26, 2003

Condition Reports Reviewed to Assess Significance Characterization of Problems

CAP038667; NRC PI Database Not Corrected With Revised Data

Condition Reports Reviewed to Assess Corrective Actions

CAP031806; Incorrect Data Reported on May 2002 NRC Performance Indicator BI-02

4OA2 Identification and Resolution of Problems

ACE003132; Apparent Cause Evaluation; Subcooling Valve CV-3070 Failed to Open

During QO-5 Valve Test Procedure

Attachment

16

WO24412938; Work Order, High Pressure Safety Injection P-66B Subcooling;

July 11, 1995

ESS-M-40; Permanent Maintenance Procedure; Maintenance of Miller Operators for

High Pressure Safety Injection Subcooling Valves CV-3070 and CV-3071

4OA3 Event Follow-up

CAP038019, Re-assess Timing of CRS Fan V-4A Inoperability with Regard to

Reportability

Attachment

17

LIST OF ACRONYMS USED

AA

Access Authorization

ARM

Area Radiation Monitor

CAM

Continuous Air Monitor

CAP

Corrective Action Program

CFR

Code of Federal Regulations

CR

Condition Report

DEI

Dose Equivalent Iodine

DRP

Division of Reactor Projects

DRS

Division of Reactor Safety

EAL

Emergency Action Level

EAR

Engineering Assistance Request

LER

Licensee Event Report

LLD

Lower Limit of Detection

NCV

Non-Cited Violation

NMC

Nuclear Management Company

NRC

Nuclear Regulatory Commission

ODCM

Offsite Dose Calculation Manual

RCA

Radiologically Controlled Area

RCS

Reactor Coolant System

REMP

Radiological Environmental Monitoring Program

RETS

Radiological Effluent Technical Specifications

RGEM

Radiological Gaseous Effluent Monitoring

RPS

Reactor Protection System

SCBA

Self-Contained Breathing Apparatus

SDP

Significance Determination Process

SM&CS

System Maintenance and Construction Services

SQUG

Seismic Qualification Utility Group

TLD

Thermoluminescent Dosimeter

UFSAR

Updated Final Safety Analysis Report

URI

Unresolved Item