{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION une 24, 2015
{{#Wiki_filter:June 24, 2015


==SUBJECT:==
==SUBJECT:==
Line 28: Line 28:
In accordance with 10 Code of Federal Regulations (CFR) 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure, and your response (if any) will be made available electronically for public inspection in the NRC Public Document Room or from the NRC document system (ADAMS), accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response should not include any personal privacy, proprietary, or safeguards information so that it can be made available to the Public without redaction.
In accordance with 10 Code of Federal Regulations (CFR) 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure, and your response (if any) will be made available electronically for public inspection in the NRC Public Document Room or from the NRC document system (ADAMS), accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response should not include any personal privacy, proprietary, or safeguards information so that it can be made available to the Public without redaction.


Current NRC regulations and guidance are included on the NRC's website at www.nrc.gov; select Radioactive Waste; Storage of Spent Nuclear Fuel; then Regulations, Guidance and Communications. The current Enforcement Policy is included on the NRC's website at www.nrc.gov; select About NRC, Organizations & Functions; Office of Enforcement; Enforcement documents; then Enforcement Policy (Under 'Related Information'). You may also obtain these documents by contacting the Government Printing Office (GPO) toll-free at 1-866-512-1800. The GPO is open from 8:00 a.m. to 5:30 p.m. EST, Monday through Friday (except Federal holidays). No reply to this letter is required. Please contact Steve Hammann at 610-337-5399 if you have any questions regarding this matter.
Current NRC regulations and guidance are included on the NRC's website at www.nrc.gov; select Radioactive Waste; Storage of Spent Nuclear Fuel; then Regulations, Guidance and Communications. The current Enforcement Policy is included on the NRC's website at www.nrc.gov; select About NRC, Organizations & Functions; Office of Enforcement; Enforcement documents; then Enforcement Policy (Under 'Related Information'). You may also obtain these documents by contacting the Government Printing Office (GPO) toll-free at 1-866-512-1800. The GPO is open from 8:00 a.m. to 5:30 p.m. EST, Monday through Friday (except Federal holidays).
 
UNITED STATES NUCLEAR REGULATORY COMMISSION
 
==REGION I==
2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PA 19406-2713 No reply to this letter is required. Please contact Steve Hammann at 610-337-5399 if you have any questions regarding this matter.


Sincerely,
Sincerely,
/RA MRoberts f/
/RA MRoberts f/  
Marc S. Ferdas, Chief Decommissioning and Technical Support Branch Division of Nuclear Materials Safety Enclosure: NRC Inspection Report No.
 
Marc S. Ferdas, Chief Decommissioning and Technical Support Branch Division of Nuclear Materials Safety  


07200028/2014002 cc w/encl: Distribution via ListServ
Enclosure:
NRC Inspection Report No.
 
07200028/2014002  
 
cc w/encl:
Distribution via ListServ


=EXECUTIVE SUMMARY=
=EXECUTIVE SUMMARY=
NRC Inspection Report No. 07200028/2014002
NRC Inspection Report No. 07200028/2014002  


The inspectors reviewed SSESs activities associated with the repair of dry shielded canister (DSC) #83 after the identification of indications on the siphon/vent block base metal. The condition was documented in SSESs corrective action program in Condition Reports (CRs)2014-36107, 37018, and 37033. The inspectors interviewed SSES and Transnuclear, Inc. (TN)personnel, reviewed SSES and TN documents and procedures, and observed repairs to the DSC between December 2-5, 2014. The inspection continued through June 15, 2015, and consisted of in-office reviews of information provided by SSES. The inspectors also reviewed SSESs corrective actions and apparent cause investigation report.
The inspectors reviewed SSESs activities associated with the repair of dry shielded canister (DSC) #83 after the identification of indications on the siphon/vent block base metal. The condition was documented in SSESs corrective action program in Condition Reports (CRs)2014-36107, 37018, and 37033. The inspectors interviewed SSES and Transnuclear, Inc. (TN)personnel, reviewed SSES and TN documents and procedures, and observed repairs to the DSC between December 2-5, 2014. The inspection continued through June 15, 2015, and consisted of in-office reviews of information provided by SSES. The inspectors also reviewed SSESs corrective actions and apparent cause investigation report.
Line 45: Line 57:
=REPORT DETAILS=
=REPORT DETAILS=


1.0 Background On November 19, 2014, during the performance of nondestructive examination (NDE)dye penetrate testing (PT) on DSC #83, multiple indications (areas of potential imperfections in the base metal) were found in the heat-affected zone area around the siphon/vent block port cover welds. The NDE was performed after the completion of welding of the siphon/vent block port covers. In consultation with the dry cask vendor and CoC holder, TN, it was determined that the siphon/vent block should be repaired by grinding out the base metal indications. Upon completion of the repair work and successful completion of a PT on the vent and siphon port welds, the outer top cover (OTC) was installed and a helium leak rate test was re-performed on November 21, 2014, as required by the Technical Specifications (TS) for the CoC. The helium leak rate test did not pass the requirements specified in TS 1.2.4a. The test was repeated several times between November 21-22, 2014, and on each occasion did not meet the TS requirement. All activities associated with the processing of the DSC were placed on hold while SSES and TN developed a repair plan for DSC #83. Prior to implementing the repair plan, TN demonstrated to SSES, at their facility in Aiken, South Carolina, that they could remove the OTC by grinding out the welds without damaging the DSC. On December 2, 2014, SSES approved the final version of the repair plan, PTIP-30696-5.2, Rev.0, Susquehanna Weld Remediation, and repair activities commenced the same day.
1.0 Background  
 
On November 19, 2014, during the performance of nondestructive examination (NDE)dye penetrate testing (PT) on DSC #83, multiple indications (areas of potential imperfections in the base metal) were found in the heat-affected zone area around the siphon/vent block port cover welds. The NDE was performed after the completion of welding of the siphon/vent block port covers. In consultation with the dry cask vendor and CoC holder, TN, it was determined that the siphon/vent block should be repaired by grinding out the base metal indications. Upon completion of the repair work and successful completion of a PT on the vent and siphon port welds, the outer top cover (OTC) was installed and a helium leak rate test was re-performed on November 21, 2014, as required by the Technical Specifications (TS) for the CoC. The helium leak rate test did not pass the requirements specified in TS 1.2.4a. The test was repeated several times between November 21-22, 2014, and on each occasion did not meet the TS requirement. All activities associated with the processing of the DSC were placed on hold while SSES and TN developed a repair plan for DSC #83. Prior to implementing the repair plan, TN demonstrated to SSES, at their facility in Aiken, South Carolina, that they could remove the OTC by grinding out the welds without damaging the DSC. On December 2, 2014, SSES approved the final version of the repair plan, PTIP-30696-5.2, Rev.0, Susquehanna Weld Remediation, and repair activities commenced the same day.


2.0 Scope
2.0 Scope


====a. Inspection Scope====
====a. Inspection Scope====
(Inspection Procedures (IPs) 60855 and 60855.1 The inspectors reviewed SSESs activities associated with the repair of DSC #83 after the identification of indications on the siphon/vent block base metal. The condition was documented in SSESs corrective action program in CRs 2014-36107, 37018, and 37033. The inspectors interviewed SSES and TN personnel, reviewed SSES and TN documents and procedures, and observed repairs to the DSC between December 2-5, 2014. The inspection continued through June 15, 2015, and consisted of in-office reviews of information provided by SSES. The inspectors also reviewed SSESs corrective actions and apparent cause investigation report.
(Inspection Procedures (IPs) 60855 and 60855.1  
 
The inspectors reviewed SSESs activities associated with the repair of DSC #83 after the identification of indications on the siphon/vent block base metal. The condition was documented in SSESs corrective action program in CRs 2014-36107, 37018, and 37033. The inspectors interviewed SSES and TN personnel, reviewed SSES and TN documents and procedures, and observed repairs to the DSC between December 2-5, 2014. The inspection continued through June 15, 2015, and consisted of in-office reviews of information provided by SSES. The inspectors also reviewed SSESs corrective actions and apparent cause investigation report.


====b. Observations and Findings====
====b. Observations and Findings====
Line 59: Line 75:
====c. Conclusions====
====c. Conclusions====
Based on the results of this inspection, no findings of safety significance were identified.
Based on the results of this inspection, no findings of safety significance were identified.
3.0  
3.0  


=====Exit Meeting Summary=====
===Exit Meeting Summary===
On June 15, 2015, the inspectors presented the inspection results, via teleconference, to Duane Karchner, Refuel Floor Manager, and other members of SSESs staff.
On June 15, 2015, the inspectors presented the inspection results, via teleconference,  
 
to Duane Karchner, Refuel Floor Manager, and other members of SSESs staff.
 
PARTIAL LIST OF PERSONS CONTACTED


PARTIAL LIST OF PERSONS CONTACTED Susquehanna
Susquehanna
* Duane Karchner, Refuel Floor Manager
* Duane Karchner, Refuel Floor Manager  
*Justion Mirilovich, Refuel Floor Shift Manager
*Justion Mirilovich, Refuel Floor Shift Manager  
*Anthony Nestico, Refuel Floor Shift Manager Brenda ORourke, Senior Engineer Robert Rose, Engineering Robert Specht, NDE Transnuclear Mike Williams, Director of Operations Pam Waite, Work Package Coordinator David Wright, Project Coordinator
*Anthony Nestico, Refuel Floor Shift Manager Brenda ORourke, Senior Engineer Robert Rose, Engineering Robert Specht, NDE Transnuclear Mike Williams, Director of Operations Pam Waite, Work Package Coordinator David Wright, Project Coordinator
* Indicates attendance at the exit meeting ITEMS OPEN, CLOSED, AND DISCUSSED None LIST OF  
* Indicates attendance at the exit meeting  
 
ITEMS OPEN, CLOSED, AND DISCUSSED  
 
None  
 
LIST OF  


=DOCUMENTS REVIEWED=
=DOCUMENTS REVIEWED=
Line 90: Line 117:
Condition Reports
Condition Reports
CR 2014-35887, 2014-36107, 2014-37018, 2014-37033, 2014-37036
CR 2014-35887, 2014-36107, 2014-37018, 2014-37033, 2014-37036
Transnuclear Nonconformance Report No: 2014-313, Rev. 0
Transnuclear Nonconformance Report No: 2014-313, Rev. 0  


Procedures
Procedures
Line 116: Line 143:
WPS TN-P8-P8-GT2, Rev. 1
WPS TN-P8-P8-GT2, Rev. 1
LIST OF ACRONYMS USED
LIST OF ACRONYMS USED
CoC             Certificate of Compliance
CoC
DNMS           Division of Nuclear Material Safety
Certificate of Compliance
DSC             Dry Shielded Canister
DNMS
IP             Inspection Procedure
Division of Nuclear Material Safety
ISFSI           Independent Spent Fuel Storage Installation
DSC
NDE             Nondestructive Examination
Dry Shielded Canister
NRC             Nuclear Regulatory Commission
IP
OTC             Outer Top Cover
Inspection Procedure
PT             Dye Penetrant Test
ISFSI
SSES           Susquehanna Steam Electric Station
Independent Spent Fuel Storage Installation
TN             Transnuclear, Inc.
NDE
TS             Technical Specifications
Nondestructive Examination
UT             Ultrasonic Testing
NRC
Attachment
Nuclear Regulatory Commission
OTC
Outer Top Cover
PT
Dye Penetrant Test
SSES
Susquehanna Steam Electric Station
TN
Transnuclear, Inc.
TS
Technical Specifications
UT
Ultrasonic Testing
}}
}}

Latest revision as of 10:46, 10 January 2025

IR 07200028/2014002 on 12/2/14 - 6/15/15, NRC Independent Spent Fuel Storage Installation Inspection Report No. 07200028/2014002, Susquehanna Nuclear, LLC, Berwick, Pennsylvania
ML15175A212
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 06/24/2015
From: Marc Ferdas
Division of Nuclear Materials Safety I
To: Rausch T
Susquehanna
References
IR 2014002
Download: ML15175A212 (9)


Text

June 24, 2015

SUBJECT:

NRC INDEPENDENT SPENT FUEL STORAGE INSTALLATION INSPECTION REPORT NO. 07200028/2014002, SUSQUEHANNA NUCLEAR, LLC, BERWICK, PENNSYLVANIA

Dear Mr. Rausch:

This refers to the Independent Spent Fuel Storage Installation (ISFSI) reactive inspection conducted between December 2, 2014, and June 15, 2015, at Susquehanna Nuclear, LLCs Susquehanna Steam Electric Station (SSES) Unit 2. The purpose of the inspection was to follow-up on the identification of indications of the siphon/vent block base metal on dry storage canister (DSC) #83. The results of this inspection were discussed with Duane Karchner and other members of your staff at the conclusion of the inspection on June 15, 2015, and are described in the enclosed report. No findings of safety significance were identified.

In accordance with 10 Code of Federal Regulations (CFR) 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure, and your response (if any) will be made available electronically for public inspection in the NRC Public Document Room or from the NRC document system (ADAMS), accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response should not include any personal privacy, proprietary, or safeguards information so that it can be made available to the Public without redaction.

Current NRC regulations and guidance are included on the NRC's website at www.nrc.gov; select Radioactive Waste; Storage of Spent Nuclear Fuel; then Regulations, Guidance and Communications. The current Enforcement Policy is included on the NRC's website at www.nrc.gov; select About NRC, Organizations & Functions; Office of Enforcement; Enforcement documents; then Enforcement Policy (Under 'Related Information'). You may also obtain these documents by contacting the Government Printing Office (GPO) toll-free at 1-866-512-1800. The GPO is open from 8:00 a.m. to 5:30 p.m. EST, Monday through Friday (except Federal holidays).

UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION I

2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PA 19406-2713 No reply to this letter is required. Please contact Steve Hammann at 610-337-5399 if you have any questions regarding this matter.

Sincerely,

/RA MRoberts f/

Marc S. Ferdas, Chief Decommissioning and Technical Support Branch Division of Nuclear Materials Safety

Enclosure:

NRC Inspection Report No.

07200028/2014002

cc w/encl:

Distribution via ListServ

EXECUTIVE SUMMARY

NRC Inspection Report No. 07200028/2014002

The inspectors reviewed SSESs activities associated with the repair of dry shielded canister (DSC) #83 after the identification of indications on the siphon/vent block base metal. The condition was documented in SSESs corrective action program in Condition Reports (CRs)2014-36107, 37018, and 37033. The inspectors interviewed SSES and Transnuclear, Inc. (TN)personnel, reviewed SSES and TN documents and procedures, and observed repairs to the DSC between December 2-5, 2014. The inspection continued through June 15, 2015, and consisted of in-office reviews of information provided by SSES. The inspectors also reviewed SSESs corrective actions and apparent cause investigation report.

Based on the results of this inspection, no findings of safety significance were identified.

REPORT DETAILS

1.0 Background

On November 19, 2014, during the performance of nondestructive examination (NDE)dye penetrate testing (PT) on DSC #83, multiple indications (areas of potential imperfections in the base metal) were found in the heat-affected zone area around the siphon/vent block port cover welds. The NDE was performed after the completion of welding of the siphon/vent block port covers. In consultation with the dry cask vendor and CoC holder, TN, it was determined that the siphon/vent block should be repaired by grinding out the base metal indications. Upon completion of the repair work and successful completion of a PT on the vent and siphon port welds, the outer top cover (OTC) was installed and a helium leak rate test was re-performed on November 21, 2014, as required by the Technical Specifications (TS) for the CoC. The helium leak rate test did not pass the requirements specified in TS 1.2.4a. The test was repeated several times between November 21-22, 2014, and on each occasion did not meet the TS requirement. All activities associated with the processing of the DSC were placed on hold while SSES and TN developed a repair plan for DSC #83. Prior to implementing the repair plan, TN demonstrated to SSES, at their facility in Aiken, South Carolina, that they could remove the OTC by grinding out the welds without damaging the DSC. On December 2, 2014, SSES approved the final version of the repair plan, PTIP-30696-5.2, Rev.0, Susquehanna Weld Remediation, and repair activities commenced the same day.

2.0 Scope

a. Inspection Scope

(Inspection Procedures (IPs) 60855 and 60855.1

The inspectors reviewed SSESs activities associated with the repair of DSC #83 after the identification of indications on the siphon/vent block base metal. The condition was documented in SSESs corrective action program in CRs 2014-36107, 37018, and 37033. The inspectors interviewed SSES and TN personnel, reviewed SSES and TN documents and procedures, and observed repairs to the DSC between December 2-5, 2014. The inspection continued through June 15, 2015, and consisted of in-office reviews of information provided by SSES. The inspectors also reviewed SSESs corrective actions and apparent cause investigation report.

b. Observations and Findings

The inspectors reviewed the results of PT and ultrasonic testing (UT) of the edges of the DSC after the OTC was removed, and verified that the DSC was not damaged by the grinding out of the OTC welds. After the completion of localized helium leak rate testing, SSES determined the siphon/vent block was the source of the leakage. The inspectors observed the performance of a weld overlay of the entire top of the siphon/vent block up to within 3/16 of the edge of the siphon/vent block. A PT of the weld overlay showed additional indications on the siphon/vent block in the 3/16 edge that did not have the weld overlay. The inspectors reviewed the SSES and TN revised repair plan that placed a weld overlay on the portion of the siphon/vent block that had not previously had an overlay. Further localized helium leak rate testing did not indicate any further leaks after the completion of the weld overlays and SSES re-entered their procedure for processing of DSC #83. On December 12, 2014, processing of DSC #83 was completed and the inspectors confirmed that the DSC met all the TS requirements prior to it being moved to the ISFSI pad on December 16, 2014. The inspectors verified that throughout the repair the DSC was in a safe stable condition and all TS requirements were met.

The inspectors reviewed the root cause investigation report that documented the determination that the siphon/vent block had been fabricated from a thick rolled plate and contained inherent inclusions resulting during ingot solidification. The inclusions induced in the rolled plate were brought to the block face by weld-induced stresses. The inspectors confirmed that SSES has two unused canisters on-site that had their siphon/vent blocks fabricated from the same lot of rolled plate as DSC #83. Planned corrective actions include placing a weld overlay on the siphon/vent block of one of the unused canisters and returning the other canister to the manufacturer. These activities are being tracked in the corrective action program.

c. Conclusions

Based on the results of this inspection, no findings of safety significance were identified.

3.0

Exit Meeting Summary

On June 15, 2015, the inspectors presented the inspection results, via teleconference,

to Duane Karchner, Refuel Floor Manager, and other members of SSESs staff.

PARTIAL LIST OF PERSONS CONTACTED

Susquehanna

  • Duane Karchner, Refuel Floor Manager
  • Justion Mirilovich, Refuel Floor Shift Manager
  • Anthony Nestico, Refuel Floor Shift Manager Brenda ORourke, Senior Engineer Robert Rose, Engineering Robert Specht, NDE Transnuclear Mike Williams, Director of Operations Pam Waite, Work Package Coordinator David Wright, Project Coordinator
  • Indicates attendance at the exit meeting

ITEMS OPEN, CLOSED, AND DISCUSSED

None

LIST OF

DOCUMENTS REVIEWED

Analysis and Tests

AREVA Examination Summary Sheet, Ultrasonic Exam, SSE-61BTH-1-B-2-050, SSE-61BTH-1-

B-2-051

AREVA Root Cause Investigation of Siphon and Vent Block Base Metal Indications (AREVA TN

Root Cause Investigation 2014-339)

Helium Leak Rate Test, Inner Lid to Shell, Port Cover Plate & outer Top Cover, Canister 81

Helium Leak Rate Test, Vent and Siphon Port Cover Plates, Canister 81

Helium Leak Rate Test, Inner Lid to Shell, Port Cover Plate & outer Top Cover, Canister 82

Helium Leak Rate Test, Vent and Siphon Port Cover Plates, Canister 82

Liquid Penetrant Examination, Final Pass Welds for Inner Vent & Siphon Port Covers,

Canister 83

Liquid Penetrant Examination, Rework of Indication Areas at Vent & Siphon Port Covers,

Canister 81

Liquid Penetrant Examination, Root Pass Weld for Inner Top Cover Plate, Canister 81

Liquid Penetrant Examination, Root Pass Weld for Inner Top Cover Plate, Canister 82

Liquid Penetrant Examination, Top surface of Block, Cannister S/N-SSE-61BTH-1-2-050

Condition Reports

CR 2014-35887, 2014-36107, 2014-37018, 2014-37033, 2014-37036

Transnuclear Nonconformance Report No: 2014-313, Rev. 0

Procedures

NDE-LT-001, Rev. 2, Helium Mass Spectrometer Leak Test Procedure for Dry Fuel Storage

Casks

NDE-PT-001, Rev. 4, Color Contrast Liquid Penetrant Examination

NDE-PT-003, Rev. 2, Color Contrast Liquid Penetrant Examination High Temperature

NDE-UT-014, Rev. 7, Ultrasonic Examination

PTIP-30696-5.2, Rev. 0, Rev. 0, Susquehanna Weld Remediation

PTIP-30696-5.2, Rev. 0, Rev. 1, Susquehanna Weld Remediation Procedure

Miscellaneous

2014 Dry Fuel Storage, Status Report - Campaign No. 8

2.48 Screening, Susquehanna Weld Remediation of DFS Canister

AREVA E-41005, Executive Summary of PPL and TN Review of Fabrication Issues

AREVA E-42068, DSC Procurement Specification, May 22, 2015

AREVA TN Form 15.1-1, Rev. 10, Reportability Determination, CAR No. 2014-339

AREVA Presentation SSE-61BTH-1-2-052 Repair Plan

Certificate of Compliance No. 1004, Amendment 10

Form 3.5-1, Rev.8 10 CFR Part 72.48 Applicability and 10 CFR Part 71 Review, LR No.

21004-1388 Rev. 1

PPL Susquehanna Pool to Pad 30969 TN Logbook 2014

Radiation Work Permit 2014-0204, Repair Dry Fuel Storage Canister #83

TC/DSC Monitoring Log

WPS TN-P8-P8-GT1, Rev. 1

WPS TN-P8-P8-GT2, Rev. 1

LIST OF ACRONYMS USED

CoC

Certificate of Compliance

DNMS

Division of Nuclear Material Safety

DSC

Dry Shielded Canister

IP

Inspection Procedure

ISFSI

Independent Spent Fuel Storage Installation

NDE

Nondestructive Examination

NRC

Nuclear Regulatory Commission

OTC

Outer Top Cover

PT

Dye Penetrant Test

SSES

Susquehanna Steam Electric Station

TN

Transnuclear, Inc.

TS

Technical Specifications

UT

Ultrasonic Testing