{{#Wiki_filter:UNITED STATES
{{#Wiki_filter:UNITED STATES  
                            NUCLEAR REGULATORY COMMISSION
NUCLEAR REGULATORY COMMISSION  
                                                REGION IV
REGION IV  
                                          1600 E. LAMAR BLVD.
1600 E. LAMAR BLVD.  
                                        ARLINGTON, TX 76011-4511
ARLINGTON, TX 76011-4511  
                                            June 19, 2017
Mr. Fadi Diya, Senior Vice President
June 19, 2017  
   and Chief Nuclear Officer
Ameren Missouri
Callaway Plant
Mr. Fadi Diya, Senior Vice President
P.O. Box 620
   and Chief Nuclear Officer  
Fulton, MO 65251
Ameren Missouri  
SUBJECT:       CALLAWAY PLANT - NOTIFICATION OF NRC INSPECTION OF THE
Callaway Plant  
                IMPLEMENTATION OF MITIGATION STRATEGIES AND SPENT FUEL POOL
P.O. Box 620  
                INSTRUMENTATION ORDERS AND EMERGENCY PREPAREDNESS
Fulton, MO 65251  
                COMMUNICATION/ STAFFING/MULTI-UNIT DOSE ASSESSMENT PLANS
                (05000483/2017008) AND REQUEST FOR INFORMATION
SUBJECT:  
Dear Mr. Diya:
CALLAWAY PLANT - NOTIFICATION OF NRC INSPECTION OF THE  
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)
IMPLEMENTATION OF MITIGATION STRATEGIES AND SPENT FUEL POOL  
staff will conduct a mitigation strategies for beyond-design-basis external events, spent fuel pool
INSTRUMENTATION ORDERS AND EMERGENCY PREPAREDNESS  
instrumentation, and emergency preparedness enhancements inspection at the Callaway Plant
COMMUNICATION/ STAFFING/MULTI-UNIT DOSE ASSESSMENT PLANS  
from August 28 - September 1, 2017. The inspection will consist of three reactor inspectors
(05000483/2017008) AND REQUEST FOR INFORMATION  
from the NRCs Region IV office, plus one of the assigned Resident Inspectors at the Callaway
Plant for one week. The inspection will be conducted in accordance with the NRCs Temporary
Dear Mr. Diya:  
Instruction 2515/191, Inspection of the Implementation of Mitigating Strategies and Spent Fuel
Pool Instrumentation Orders, and Emergency Preparedness Communication/Staffing/Multi-Unit
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)  
Dose Assessment Plans.
staff will conduct a mitigation strategies for beyond-design-basis external events, spent fuel pool  
Experience has shown that this inspection is resource intensive both for the NRC inspectors
instrumentation, and emergency preparedness enhancements inspection at the Callaway Plant  
and licensee staff. In order to minimize the impact to your onsite resources and to ensure a
from August 28 - September 1, 2017. The inspection will consist of three reactor inspectors  
productive inspection, we have enclosed a request for documents needed for this inspection
from the NRCs Region IV office, plus one of the assigned Resident Inspectors at the Callaway  
activity. Please note that the documents are requested to be provided by August 11, 2017.
Plant for one week. The inspection will be conducted in accordance with the NRCs Temporary  
During the onsite inspection, inspectors will verify that plans for complying with NRC Orders
Instruction 2515/191, Inspection of the Implementation of Mitigating Strategies and Spent Fuel  
EA-12-049 and EA-12-051 are in place and are being implemented. Inspectors will also verify
Pool Instrumentation Orders, and Emergency Preparedness Communication/Staffing/Multi-Unit  
the establishment of staffing and communications plans provided in response to the March 12,
Dose Assessment Plans.  
2012, request for information letter, and multi-unit dose assessment information provided per
COMSECY-13-0010, Schedule and Plans for Tier 2 Order on Emergency Preparedness for
Experience has shown that this inspection is resource intensive both for the NRC inspectors  
Japan Lessons Learned, dated March 27, 2013. These plans and information were provided in
and licensee staff. In order to minimize the impact to your onsite resources and to ensure a  
the site specific submittals, which were subsequently reviewed by the NRC staff for
productive inspection, we have enclosed a request for documents needed for this inspection  
understanding and documented in the NRCs plant safety evaluations (SEs) and safety
activity. Please note that the documents are requested to be provided by August 11, 2017.
assessments. Therefore, appropriate personnel knowledgeable of the stations FLEX
During the onsite inspection, inspectors will verify that plans for complying with NRC Orders  
strategies, spent fuel pool instrumentation, and emergency preparedness enhancements should
EA-12-049 and EA-12-051 are in place and are being implemented. Inspectors will also verify  
be available to support the inspectors at the site during the inspection.
the establishment of staffing and communications plans provided in response to the March 12,  
2012, request for information letter, and multi-unit dose assessment information provided per  
COMSECY-13-0010, Schedule and Plans for Tier 2 Order on Emergency Preparedness for  
Japan Lessons Learned, dated March 27, 2013. These plans and information were provided in  
the site specific submittals, which were subsequently reviewed by the NRC staff for  
understanding and documented in the NRCs plant safety evaluations (SEs) and safety  
assessments. Therefore, appropriate personnel knowledgeable of the stations FLEX  
strategies, spent fuel pool instrumentation, and emergency preparedness enhancements should  
be available to support the inspectors at the site during the inspection.  


F. Diya                                           2
F. Diya  
We have discussed the schedule for this inspection activity with your staff and understand that
2  
our regulatory contact for this inspection will be Elizabeth Ptasznik of your licensing
organization. If there are any questions about this inspection or the material requested, please
contact the lead inspector, Ryan D. Alexander, by telephone at 817-200-1195 or by e-mail at
ryan.alexander@nrc.gov.
This letter does not contain new or amended information collection requirements subject to the
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection
We have discussed the schedule for this inspection activity with your staff and understand that  
requirements were approved by the Office of Management and Budget, control
our regulatory contact for this inspection will be Elizabeth Ptasznik of your licensing  
number 3150 0011. The NRC may not conduct or sponsor, and a person is not required to
organization. If there are any questions about this inspection or the material requested, please  
respond to, a request for information or an information collection requirement unless the
contact the lead inspector, Ryan D. Alexander, by telephone at 817-200-1195 or by e-mail at  
requesting document displays a currently valid Office of Management and Budget control
ryan.alexander@nrc.gov.
number.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its
This letter does not contain new or amended information collection requirements subject to the  
enclosure will be available electronically for public inspection in the NRC Public Document
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection  
Room or from the Publicly Available Records (PARS) component of NRCs document system
requirements were approved by the Office of Management and Budget, control  
(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
number 3150 0011. The NRC may not conduct or sponsor, and a person is not required to  
rm/adams.html (the Public Electronic Reading Room).
respond to, a request for information or an information collection requirement unless the  
                                                Sincerely,
requesting document displays a currently valid Office of Management and Budget control  
                                                /RA/
number.  
                                                John L. Dixon, Acting Chief
                                                Project Branch B
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its  
                                                Division of Reactor Projects
enclosure will be available electronically for public inspection in the NRC Public Document  
Docket No. 50-483
Room or from the Publicly Available Records (PARS) component of NRCs document system  
License No. NPF-30
(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
Enclosure:
rm/adams.html (the Public Electronic Reading Room).  
FLEX Strategies, Spent Fuel Pool
Instrumentation, & EP Enhancements
Sincerely,  
Inspection Request for Information
/RA/  
John L. Dixon, Acting Chief  
Project Branch B  
Division of Reactor Projects  
Docket No. 50-483  
License No. NPF-30  
Enclosure:  
FLEX Strategies, Spent Fuel Pool
Instrumentation, & EP Enhancements
Inspection Request for Information  


                                    Request for Information
    FLEX Strategies, Spent Fuel Pool Instrumentation, & EP Enhancements Inspection
                                          Callaway Plant
1
Inspection Report:             05000483/2017008
Enclosure
Inspection Dates:             August 28 - September 1, 2017
Request for Information  
Inspection Procedure:         Temporary Instruction 2515/191, Inspection of the
FLEX Strategies, Spent Fuel Pool Instrumentation, & EP Enhancements Inspection  
                              Implementation of Mitigating Strategies and Spent Fuel Pool
Callaway Plant  
                              Instrumentation Orders, and Emergency Preparedness
                              Communication/Staffing/Multi-Unit Dose Assessment Plans
Inspectors:                   Ryan D. Alexander, Team Lead, Sr. Project Engineer, Region IV
Inspection Report:  
                              Dan Bradley, Callaway Plant Senior Resident Inspector
05000483/2017008  
                              Steve Alferink, Reactor Inspector, Region IV
                              Michael Stafford, Project Engineer, Region IV
Inspection Dates:  
Information Requested for the In-Office Preparation Week
The following information should be sent to the Region IV office in hard copy or electronic
August 28 - September 1, 2017  
format (use of the Certrec IMS information portal is preferred), to the attention of Ryan
Alexander, by August 11, 2017. The inspectors will select specific items from the information
Inspection Procedure:  
requested below and then request from your staff additional documents needed during the
Temporary Instruction 2515/191, Inspection of the  
onsite inspection week. Also, we request that you categorize the documents in your response
Implementation of Mitigating Strategies and Spent Fuel Pool  
with the numbered list below. Please provide requested documentation electronically if
Instrumentation Orders, and Emergency Preparedness  
possible. If requested documents are large and only hard copy formats are available, please
Communication/Staffing/Multi-Unit Dose Assessment Plans  
inform the lead inspector, and provide subject documentation during the first day of the onsite
inspection. If you have any questions regarding this information request, please call the lead
Inspectors:  
inspector as soon as possible.
TI 2515/191 - Appendix A
A. Provide current revision of the FLEX Final Integrated Plan (i.e., current FLEX Program
Ryan D. Alexander, Team Lead, Sr. Project Engineer, Region IV  
    Document), including any revisions since July 2016 submission to the NRC.
B. Provide the FLEX Strategy Basis Document.
C. Provide each operating, off-normal, abnormal, and/or emergency procedures where entry
    into one or more FLEX Support Guideline(s) are initiated.
D. Provide a list and copies of every FLEX Support Guideline (FSG) or equivalent procedure
Dan Bradley, Callaway Plant Senior Resident Inspector  
    which you developed or revised to implement your mitigating strategies.
E. Provide a list of key pieces of equipment that directly perform a FLEX mitigation strategy for
    core cooling (RCS and Steam Generators), containment, and/or spent fuel pool cooling.
F. Provide a listing/summaries of plant modifications completed related to the FLEX program.
G. Provide a listing of calculations, evaluations, and 50.59 reviews related to the FLEX program
Steve Alferink, Reactor Inspector, Region IV  
    and modifications.
                                                1                                      Enclosure
Michael Stafford, Project Engineer, Region IV  
Information Requested for the In-Office Preparation Week  
The following information should be sent to the Region IV office in hard copy or electronic  
format (use of the Certrec IMS information portal is preferred), to the attention of Ryan  
Alexander, by August 11, 2017. The inspectors will select specific items from the information  
requested below and then request from your staff additional documents needed during the  
onsite inspection week. Also, we request that you categorize the documents in your response  
with the numbered list below. Please provide requested documentation electronically if  
possible. If requested documents are large and only hard copy formats are available, please  
inform the lead inspector, and provide subject documentation during the first day of the onsite  
inspection. If you have any questions regarding this information request, please call the lead  
inspector as soon as possible.  
TI 2515/191 - Appendix A  
A. Provide current revision of the FLEX Final Integrated Plan (i.e., current FLEX Program  
Document), including any revisions since July 2016 submission to the NRC.  
B. Provide the FLEX Strategy Basis Document.  
C. Provide each operating, off-normal, abnormal, and/or emergency procedures where entry  
into one or more FLEX Support Guideline(s) are initiated.  
D. Provide a list and copies of every FLEX Support Guideline (FSG) or equivalent procedure  
which you developed or revised to implement your mitigating strategies.
E. Provide a list of key pieces of equipment that directly perform a FLEX mitigation strategy for  
core cooling (RCS and Steam Generators), containment, and/or spent fuel pool cooling.
F. Provide a listing/summaries of plant modifications completed related to the FLEX program.  
G. Provide a listing of calculations, evaluations, and 50.59 reviews related to the FLEX program  
and modifications.  


H. Applicable site specific hazards for the Callaway Plant:
  1) Provide documents which show the locations and configuration of structure(s) which
      store FLEX equipment.
2
  2) Seismic
      (a) Provide the travel route(s) for FLEX equipment from storage location(s) to their
H. Applicable site specific hazards for the Callaway Plant:  
          location(s) of use, AND evaluation(s) which demonstrate that for the potential for soil
1) Provide documents which show the locations and configuration of structure(s) which  
          liquefaction is not of a concern for these travel route(s).
store FLEX equipment.  
      (b) Seismic concerns for water source(s)
2) Seismic  
          (1) If the FLEX water sources are seismically robust, then provide the assessment
(a) Provide the travel route(s) for FLEX equipment from storage location(s) to their  
              that shows that they are.
location(s) of use, AND evaluation(s) which demonstrate that for the potential for soil  
          (2) If the FLEX water sources are not seismically robust, then provide:
liquefaction is not of a concern for these travel route(s).  
              (a) an assessment of alternate water sources, and
(b) Seismic concerns for water source(s)  
              (b) the procedure(s) which describe when and how to access those sources.
(1) If the FLEX water sources are seismically robust, then provide the assessment  
  3) External Flooding
that shows that they are.  
      {Screened Out for Callaway Plant - no documents requested}
(2) If the FLEX water sources are not seismically robust, then provide:  
  4) Severe storms with high winds
(a) an assessment of alternate water sources, and
      (a) Provide evaluation/evidence as to how FLEX equipment is stored relative to
(b) the procedure(s) which describe when and how to access those sources.  
          protection from severe storms with high winds:
3) External Flooding  
          (1) In a structure that meets the plants design basis for high wind hazards (e.g.,
{Screened Out for Callaway Plant - no documents requested}  
              existing safety-related structure); OR
4) Severe storms with high winds  
          (2) In a structure that meets the design requirements as described in ASCE 7-10,
(a) Provide evaluation/evidence as to how FLEX equipment is stored relative to  
              Minimum Design Loads for Buildings and Other Structures, given the limiting
protection from severe storms with high winds:  
              tornado wind speeds from Regulatory Guide 1.76, and/or design-basis hurricane
(1) In a structure that meets the plants design basis for high wind hazards (e.g.,  
              wind speeds.
existing safety-related structure); OR  
      (b) Provide pathways via which you plan to move FLEX equipment from onsite storage
          areas to final deployment locations.
          (1) Show how you designated and evaluated those pathways for post-storm
              accessibility for staging and connecting FLEX equipment.
(2) In a structure that meets the design requirements as described in ASCE 7-10,  
  5) Snow, Ice, and Extreme Cold
Minimum Design Loads for Buildings and Other Structures, given the limiting  
      For each key piece of equipment described in Item 5 (above) that directly performs or
tornado wind speeds from Regulatory Guide 1.76, and/or design-basis hurricane  
      implements a FLEX mitigation strategy:
wind speeds.  
      (a) Provide procedures/documents demonstrating that the FLEX equipment is
(b) Provide pathways via which you plan to move FLEX equipment from onsite storage  
          maintained at a temperature within a range to ensure that it will function when called
areas to final deployment locations.  
          upon.
(1) Show how you designated and evaluated those pathways for post-storm  
      (b) Provide procedures/documents demonstrating how the FLEX equipment can be
accessibility for staging and connecting FLEX equipment.  
          moved from the storage location to its deployment location during extreme snowfall
5) Snow, Ice, and Extreme Cold  
          and ice storms.
For each key piece of equipment described in Item 5 (above) that directly performs or  
                                                2
implements a FLEX mitigation strategy:  
(a) Provide procedures/documents demonstrating that the FLEX equipment is  
maintained at a temperature within a range to ensure that it will function when called  
upon.  
(b) Provide procedures/documents demonstrating how the FLEX equipment can be  
moved from the storage location to its deployment location during extreme snowfall  
and ice storms.  


    6) Extreme high temperatures
        For each key piece of equipment described in Item 5 (above) that directly performs or
        implements a FLEX mitigation strategy:
3
        (a) Provide procedures/documents which describes the high-temperature limit of the
            range within which the equipment will function.
6) Extreme high temperatures  
        (b) Provide procedures/documents which describe how the equipment is maintained
For each key piece of equipment described in Item 5 (above) that directly performs or  
            below that limit in its storage location.
implements a FLEX mitigation strategy:  
I. Provide the station-specific FLEX strategies time validation study(ies).
(a) Provide procedures/documents which describes the high-temperature limit of the  
J. Provide the relevant station procedure(s)/guideline(s) which describe the testing and
range within which the equipment will function.  
    maintenance program for FLEX equipment. As applicable, provide a listing of the model
(b) Provide procedures/documents which describe how the equipment is maintained  
    work orders established to conduct period testing and maintenance activities for FLEX
below that limit in its storage location.  
    equipment. [A sample of records for completed maintenance/testing activities may be
I. Provide the station-specific FLEX strategies time validation study(ies).  
    requested for review during the onsite inspection week.]
J. Provide the relevant station procedure(s)/guideline(s) which describe the testing and  
K. Provide documents/procedures which describe the programmatic controls in place to ensure
maintenance program for FLEX equipment. As applicable, provide a listing of the model  
    that if equipment and applicable connections are unavailable (e.g., due to maintenance,
work orders established to conduct period testing and maintenance activities for FLEX  
    non-functionality), then compensatory measures are implemented in accordance with
equipment. [A sample of records for completed maintenance/testing activities may be  
    guidance outlined NEI 12-06.
requested for review during the onsite inspection week.]  
L. Provide the station-specific National SAFER Center Playbook
K. Provide documents/procedures which describe the programmatic controls in place to ensure  
M. Relative to personnel training on FLEX strategies, provide:
that if equipment and applicable connections are unavailable (e.g., due to maintenance,  
    1) FLEX training bases document(s)
non-functionality), then compensatory measures are implemented in accordance with  
    2) Lesson plans/training documents for site emergency response leaders responsible for
guidance outlined NEI 12-06.  
        the implementation of FLEX strategies. [Records for staff completing this training may be
L. Provide the station-specific National SAFER Center Playbook  
        requested for review during the onsite inspection week.]
M. Relative to personnel training on FLEX strategies, provide:  
    3) Lesson plans/training documents for site personnel responsible for the execution of
1) FLEX training bases document(s)  
        mitigating strategies for BDBEEs (i.e., operators, craft personnel, security, radiation
2) Lesson plans/training documents for site emergency response leaders responsible for  
        protection, etc.). [Records for staff completing this training may be requested for review
the implementation of FLEX strategies. [Records for staff completing this training may be  
        during the onsite inspection week.]
requested for review during the onsite inspection week.]  
N. A current copy of administrative procedure(s) for the CAP, modification program, operations
3) Lesson plans/training documents for site personnel responsible for the execution of  
    procedure writing and implementation, and top-level documents for the work control and
mitigating strategies for BDBEEs (i.e., operators, craft personnel, security, radiation  
    work scheduling programs. (If FLEX related procedures such as FSGs or the FIP are
protection, etc.). [Records for staff completing this training may be requested for review  
    maintained under a different process, please include copies of those procedures.)
during the onsite inspection week.]  
O. A current copy of the U/FSAR, Technical Specifications, and Technical Specification Bases
N. A current copy of administrative procedure(s) for the CAP, modification program, operations  
    documents.
procedure writing and implementation, and top-level documents for the work control and  
P. Listing of corrective action program document summaries generated related to FLEX
work scheduling programs. (If FLEX related procedures such as FSGs or the FIP are  
    equipment, strategies, procedures, and/or training.
maintained under a different process, please include copies of those procedures.)  
Q. A copy of any audits/self-assessments related to your preparation for this inspection, as well
O. A current copy of the U/FSAR, Technical Specifications, and Technical Specification Bases  
    as any related to the implementation or maintenance of the FLEX program.
documents.  
TI 2515/191 - Appendix B
P. Listing of corrective action program document summaries generated related to FLEX  
R. Provide the procedures implemented for maintenance, testing, calibration, and use of the
equipment, strategies, procedures, and/or training.  
    primary and backup Spent Fuel Pool (SFP) instrumentation channels.
Q. A copy of any audits/self-assessments related to your preparation for this inspection, as well  
S. Provide lesson plans/training documents which describe the training program that address
as any related to the implementation or maintenance of the FLEX program.  
    the use, maintenance, calibration, surveillance, and the use of alternate power to the
    primary and backup SFP instrument channels.
TI 2515/191 - Appendix B  
                                                    3
R. Provide the procedures implemented for maintenance, testing, calibration, and use of the  
primary and backup Spent Fuel Pool (SFP) instrumentation channels.  
S. Provide lesson plans/training documents which describe the training program that address  
the use, maintenance, calibration, surveillance, and the use of alternate power to the  
primary and backup SFP instrument channels.  


TI 2515/191 - Appendix C
T. Communications:
    1) Provide documents which show that the communications system(s), technologies,
4
        equipment and power supplies would be available from the beginning of the event and
        operate during an ELAP.
TI 2515/191 - Appendix C  
    2) Provide the procedures and/or guidance used to implement the communication
T. Communications:  
        capabilities.
1) Provide documents which show that the communications system(s), technologies,  
    3) Provide documents which show that you have added any new communications
equipment and power supplies would be available from the beginning of the event and  
        equipment, portable power supplies and/or systems have been added to ongoing testing
operate during an ELAP.  
        and preventative maintenance programs.
2) Provide the procedures and/or guidance used to implement the communication  
U. Staffing:
capabilities.  
    1) Provide documents which show that onsite and augmented staff will be available to
3) Provide documents which show that you have added any new communications  
        implement the strategies in response to a large scale natural event that results an ELAP
equipment, portable power supplies and/or systems have been added to ongoing testing  
        and impedes access to the site, and that functions/tasks have been appropriately
and preventative maintenance programs.  
        staffed.
U. Staffing:  
    2) Provide documents which show that the site access methods (e.g., roadways, navigable
1) Provide documents which show that onsite and augmented staff will be available to  
        bodies of water and dockage, airlift, etc.) expected to be available following the event
implement the strategies in response to a large scale natural event that results an ELAP  
        and available to the Emergency Response Organization (ERO) [as described in the
and impedes access to the site, and that functions/tasks have been appropriately  
        Phase 1 and 2 staffing assessments and NRC safety assessment].
staffed.  
    3) Provide documents which show the testing, training, and drills/exercises performed by
2) Provide documents which show that the site access methods (e.g., roadways, navigable  
        the station to demonstrate the EROs ability to utilize the communications systems
bodies of water and dockage, airlift, etc.) expected to be available following the event  
        and/or equipment.
and available to the Emergency Response Organization (ERO) [as described in the  
V. Provide documents and procedures which show that your dose assessment is capable of
Phase 1 and 2 staffing assessments and NRC safety assessment].  
    analyzing concurrent radiological releases from all on-site significant sources, including
3) Provide documents which show the testing, training, and drills/exercises performed by  
    releases from spent fuel pools (i.e., multi-unit/multi-source dose assessment capability).
the station to demonstrate the EROs ability to utilize the communications systems  
Lead Inspector Contact Information:
and/or equipment.  
  Ryan D. Alexander, Sr. Project Engineer             Mailing Address:
V. Provide documents and procedures which show that your dose assessment is capable of  
817-200-1195                                       U.S. NRC, Region IV
analyzing concurrent radiological releases from all on-site significant sources, including  
Ryan.Alexander@nrc.gov                             Attn: Ryan Alexander, DRP
releases from spent fuel pools (i.e., multi-unit/multi-source dose assessment capability).  
                                                    1600 East Lamar Blvd.
                                                    Arlington, TX 76011-4511
Lead Inspector Contact Information:  
                                                4
   
Ryan D. Alexander, Sr. Project Engineer  
Mailing Address:  
817-200-1195  
U.S. NRC, Region IV  
Ryan.Alexander@nrc.gov  
Attn: Ryan Alexander, DRP
1600 East Lamar Blvd.
Arlington, TX 76011-4511  




ML17170A091
  ML17170A091  
  SUNSI Review ADAMS:          Sensitive        Non-Publicly Available Keyword
SUNSI Review  
By: RDA/rdr     Yes  No      Non-Sensitive   Publicly Available     NRC-002
By: RDA/rdr  
OFFICE         DRP/RPBA         C:DRP/RPBB
ADAMS: 
  NAME           RAlexander       JDixon
Yes     No
  SIGNATURE       /RA/-E           /RA/
Sensitive 
  DATE           06/14/2017       06/19/2017
  Non-Sensitive  
Non-Publicly Available 
Publicly Available  
Keyword
NRC-002  
OFFICE  
DRP/RPBA  
C:DRP/RPBB  
   
NAME  
RAlexander  
JDixon  
   
SIGNATURE  
/RA/-E  
/RA/  
   
DATE  
06/14/2017  
06/19/2017
}}
}}

Latest revision as of 19:09, 8 January 2025

Notification of NRC Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/ Staffing/Multi-Unit Dose Assessment Plans (05000483/2017008) and Request for
ML17170A091
Person / Time
Site: Callaway Ameren icon.png
Issue date: 06/19/2017
From: Ryan Alexander, John Dixon
NRC/RGN-IV/DRP/RPB-B
To: Diya F
Ameren Corp
Dixon J
References
TI-2515/191 IR 2017008
Download: ML17170A091 (7)


See also: IR 05000483/2017008

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION IV

1600 E. LAMAR BLVD.

ARLINGTON, TX 76011-4511

June 19, 2017

Mr. Fadi Diya, Senior Vice President

and Chief Nuclear Officer

Ameren Missouri

Callaway Plant

P.O. Box 620

Fulton, MO 65251

SUBJECT:

CALLAWAY PLANT - NOTIFICATION OF NRC INSPECTION OF THE

IMPLEMENTATION OF MITIGATION STRATEGIES AND SPENT FUEL POOL

INSTRUMENTATION ORDERS AND EMERGENCY PREPAREDNESS

COMMUNICATION/ STAFFING/MULTI-UNIT DOSE ASSESSMENT PLANS

(05000483/2017008) AND REQUEST FOR INFORMATION

Dear Mr. Diya:

The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)

staff will conduct a mitigation strategies for beyond-design-basis external events, spent fuel pool

instrumentation, and emergency preparedness enhancements inspection at the Callaway Plant

from August 28 - September 1, 2017. The inspection will consist of three reactor inspectors

from the NRCs Region IV office, plus one of the assigned Resident Inspectors at the Callaway

Plant for one week. The inspection will be conducted in accordance with the NRCs Temporary

Instruction 2515/191, Inspection of the Implementation of Mitigating Strategies and Spent Fuel

Pool Instrumentation Orders, and Emergency Preparedness Communication/Staffing/Multi-Unit

Dose Assessment Plans.

Experience has shown that this inspection is resource intensive both for the NRC inspectors

and licensee staff. In order to minimize the impact to your onsite resources and to ensure a

productive inspection, we have enclosed a request for documents needed for this inspection

activity. Please note that the documents are requested to be provided by August 11, 2017.

During the onsite inspection, inspectors will verify that plans for complying with NRC Orders

EA-12-049 and EA-12-051 are in place and are being implemented. Inspectors will also verify

the establishment of staffing and communications plans provided in response to the March 12,

2012, request for information letter, and multi-unit dose assessment information provided per

COMSECY-13-0010, Schedule and Plans for Tier 2 Order on Emergency Preparedness for

Japan Lessons Learned, dated March 27, 2013. These plans and information were provided in

the site specific submittals, which were subsequently reviewed by the NRC staff for

understanding and documented in the NRCs plant safety evaluations (SEs) and safety

assessments. Therefore, appropriate personnel knowledgeable of the stations FLEX

strategies, spent fuel pool instrumentation, and emergency preparedness enhancements should

be available to support the inspectors at the site during the inspection.

F. Diya

2

We have discussed the schedule for this inspection activity with your staff and understand that

our regulatory contact for this inspection will be Elizabeth Ptasznik of your licensing

organization. If there are any questions about this inspection or the material requested, please

contact the lead inspector, Ryan D. Alexander, by telephone at 817-200-1195 or by e-mail at

ryan.alexander@nrc.gov.

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, control

number 3150 0011. The NRC may not conduct or sponsor, and a person is not required to

respond to, a request for information or an information collection requirement unless the

requesting document displays a currently valid Office of Management and Budget control

number.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRCs document system

(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

John L. Dixon, Acting Chief

Project Branch B

Division of Reactor Projects

Docket No. 50-483

License No. NPF-30

Enclosure:

FLEX Strategies, Spent Fuel Pool

Instrumentation, & EP Enhancements

Inspection Request for Information

1

Enclosure

Request for Information

FLEX Strategies, Spent Fuel Pool Instrumentation, & EP Enhancements Inspection

Callaway Plant

Inspection Report: 05000483/2017008

Inspection Dates:

August 28 - September 1, 2017

Inspection Procedure:

Temporary Instruction 2515/191, Inspection of the

Implementation of Mitigating Strategies and Spent Fuel Pool

Instrumentation Orders, and Emergency Preparedness

Communication/Staffing/Multi-Unit Dose Assessment Plans

Inspectors:

Ryan D. Alexander, Team Lead, Sr. Project Engineer, Region IV

Dan Bradley, Callaway Plant Senior Resident Inspector

Steve Alferink, Reactor Inspector, Region IV

Michael Stafford, Project Engineer, Region IV

Information Requested for the In-Office Preparation Week

The following information should be sent to the Region IV office in hard copy or electronic

format (use of the Certrec IMS information portal is preferred), to the attention of Ryan

Alexander, by August 11, 2017. The inspectors will select specific items from the information

requested below and then request from your staff additional documents needed during the

onsite inspection week. Also, we request that you categorize the documents in your response

with the numbered list below. Please provide requested documentation electronically if

possible. If requested documents are large and only hard copy formats are available, please

inform the lead inspector, and provide subject documentation during the first day of the onsite

inspection. If you have any questions regarding this information request, please call the lead

inspector as soon as possible.

TI 2515/191 - Appendix A

A. Provide current revision of the FLEX Final Integrated Plan (i.e., current FLEX Program

Document), including any revisions since July 2016 submission to the NRC.

B. Provide the FLEX Strategy Basis Document.

C. Provide each operating, off-normal, abnormal, and/or emergency procedures where entry

into one or more FLEX Support Guideline(s) are initiated.

D. Provide a list and copies of every FLEX Support Guideline (FSG) or equivalent procedure

which you developed or revised to implement your mitigating strategies.

E. Provide a list of key pieces of equipment that directly perform a FLEX mitigation strategy for

core cooling (RCS and Steam Generators), containment, and/or spent fuel pool cooling.

F. Provide a listing/summaries of plant modifications completed related to the FLEX program.

G. Provide a listing of calculations, evaluations, and 50.59 reviews related to the FLEX program

and modifications.

2

H. Applicable site specific hazards for the Callaway Plant:

1) Provide documents which show the locations and configuration of structure(s) which

store FLEX equipment.

2) Seismic

(a) Provide the travel route(s) for FLEX equipment from storage location(s) to their

location(s) of use, AND evaluation(s) which demonstrate that for the potential for soil

liquefaction is not of a concern for these travel route(s).

(b) Seismic concerns for water source(s)

(1) If the FLEX water sources are seismically robust, then provide the assessment

that shows that they are.

(2) If the FLEX water sources are not seismically robust, then provide:

(a) an assessment of alternate water sources, and

(b) the procedure(s) which describe when and how to access those sources.

3) External Flooding

{Screened Out for Callaway Plant - no documents requested}

4) Severe storms with high winds

(a) Provide evaluation/evidence as to how FLEX equipment is stored relative to

protection from severe storms with high winds:

(1) In a structure that meets the plants design basis for high wind hazards (e.g.,

existing safety-related structure); OR

(2) In a structure that meets the design requirements as described in ASCE 7-10,

Minimum Design Loads for Buildings and Other Structures, given the limiting

tornado wind speeds from Regulatory Guide 1.76, and/or design-basis hurricane

wind speeds.

(b) Provide pathways via which you plan to move FLEX equipment from onsite storage

areas to final deployment locations.

(1) Show how you designated and evaluated those pathways for post-storm

accessibility for staging and connecting FLEX equipment.

5) Snow, Ice, and Extreme Cold

For each key piece of equipment described in Item 5 (above) that directly performs or

implements a FLEX mitigation strategy:

(a) Provide procedures/documents demonstrating that the FLEX equipment is

maintained at a temperature within a range to ensure that it will function when called

upon.

(b) Provide procedures/documents demonstrating how the FLEX equipment can be

moved from the storage location to its deployment location during extreme snowfall

and ice storms.

3

6) Extreme high temperatures

For each key piece of equipment described in Item 5 (above) that directly performs or

implements a FLEX mitigation strategy:

(a) Provide procedures/documents which describes the high-temperature limit of the

range within which the equipment will function.

(b) Provide procedures/documents which describe how the equipment is maintained

below that limit in its storage location.

I. Provide the station-specific FLEX strategies time validation study(ies).

J. Provide the relevant station procedure(s)/guideline(s) which describe the testing and

maintenance program for FLEX equipment. As applicable, provide a listing of the model

work orders established to conduct period testing and maintenance activities for FLEX

equipment. [A sample of records for completed maintenance/testing activities may be

requested for review during the onsite inspection week.]

K. Provide documents/procedures which describe the programmatic controls in place to ensure

that if equipment and applicable connections are unavailable (e.g., due to maintenance,

non-functionality), then compensatory measures are implemented in accordance with

guidance outlined NEI 12-06.

L. Provide the station-specific National SAFER Center Playbook

M. Relative to personnel training on FLEX strategies, provide:

1) FLEX training bases document(s)

2) Lesson plans/training documents for site emergency response leaders responsible for

the implementation of FLEX strategies. [Records for staff completing this training may be

requested for review during the onsite inspection week.]

3) Lesson plans/training documents for site personnel responsible for the execution of

mitigating strategies for BDBEEs (i.e., operators, craft personnel, security, radiation

protection, etc.). [Records for staff completing this training may be requested for review

during the onsite inspection week.]

N. A current copy of administrative procedure(s) for the CAP, modification program, operations

procedure writing and implementation, and top-level documents for the work control and

work scheduling programs. (If FLEX related procedures such as FSGs or the FIP are

maintained under a different process, please include copies of those procedures.)

O. A current copy of the U/FSAR, Technical Specifications, and Technical Specification Bases

documents.

P. Listing of corrective action program document summaries generated related to FLEX

equipment, strategies, procedures, and/or training.

Q. A copy of any audits/self-assessments related to your preparation for this inspection, as well

as any related to the implementation or maintenance of the FLEX program.

TI 2515/191 - Appendix B

R. Provide the procedures implemented for maintenance, testing, calibration, and use of the

primary and backup Spent Fuel Pool (SFP) instrumentation channels.

S. Provide lesson plans/training documents which describe the training program that address

the use, maintenance, calibration, surveillance, and the use of alternate power to the

primary and backup SFP instrument channels.

4

TI 2515/191 - Appendix C

T. Communications:

1) Provide documents which show that the communications system(s), technologies,

equipment and power supplies would be available from the beginning of the event and

operate during an ELAP.

2) Provide the procedures and/or guidance used to implement the communication

capabilities.

3) Provide documents which show that you have added any new communications

equipment, portable power supplies and/or systems have been added to ongoing testing

and preventative maintenance programs.

U. Staffing:

1) Provide documents which show that onsite and augmented staff will be available to

implement the strategies in response to a large scale natural event that results an ELAP

and impedes access to the site, and that functions/tasks have been appropriately

staffed.

2) Provide documents which show that the site access methods (e.g., roadways, navigable

bodies of water and dockage, airlift, etc.) expected to be available following the event

and available to the Emergency Response Organization (ERO) [as described in the

Phase 1 and 2 staffing assessments and NRC safety assessment].

3) Provide documents which show the testing, training, and drills/exercises performed by

the station to demonstrate the EROs ability to utilize the communications systems

and/or equipment.

V. Provide documents and procedures which show that your dose assessment is capable of

analyzing concurrent radiological releases from all on-site significant sources, including

releases from spent fuel pools (i.e., multi-unit/multi-source dose assessment capability).

Lead Inspector Contact Information:

Ryan D. Alexander, Sr. Project Engineer

Mailing Address:

817-200-1195

U.S. NRC, Region IV

Ryan.Alexander@nrc.gov

Attn: Ryan Alexander, DRP

1600 East Lamar Blvd.

Arlington, TX 76011-4511

ML17170A091

SUNSI Review

By: RDA/rdr

ADAMS:

Yes No

Sensitive

Non-Sensitive

Non-Publicly Available

Publicly Available

Keyword

NRC-002

OFFICE

DRP/RPBA

C:DRP/RPBB

NAME

RAlexander

JDixon

SIGNATURE

/RA/-E

/RA/

DATE

06/14/2017

06/19/2017