ML070640539: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter:March 5, 2007Mr. Gary Van MiddlesworthVice-President
{{#Wiki_filter:March 5, 2007
Mr. Gary Van Middlesworth
Vice-President
Duane Arnold Energy Center
Duane Arnold Energy Center
3277 DAEC Road
3277 DAEC Road
Palo, IA 52324-9785SUBJECT:DUANE ARNOLD ENERGY CENTERNOTIFICATION OF AN NRC BIENNIAL HEAT SINK PERFORMANCE
Palo, IA 52324-9785
INSPECTION AND REQUEST FOR INFORMATION 05000331/2007003(DRS)Dear Mr. Van Middlesworth:
SUBJECT:       DUANE ARNOLD ENERGY CENTER
On April 23, 2007, the NRC will begin the on-site portion of the Biennial Heat Sink PerformanceInspection at your Duane Arnold Energy Center. This inspection will be performed in
                NOTIFICATION OF AN NRC BIENNIAL HEAT SINK PERFORMANCE
accordance with NRC baseline inspection procedure (IP) 71111.07. The heat exchangers
                INSPECTION AND REQUEST FOR INFORMATION 05000331/2007003(DRS)
Dear Mr. Van Middlesworth:
On April 23, 2007, the NRC will begin the on-site portion of the Biennial Heat Sink Performance
Inspection at your Duane Arnold Energy Center. This inspection will be performed in
accordance with NRC baseline inspection procedure (IP) 71111.07. The heat exchangers
selected for detailed review during this baseline inspection are the 1B emergency diesel
selected for detailed review during this baseline inspection are the 1B emergency diesel
generator cooler and the 1B residual heat removal heat exchanger.We have enclosed a request for documents needed for the inspection. This information can besent to the following e-mail address cea4@nrc.gov, no later than April 13, 2007, so that we maystart the review of these documents. A hard-copy with the required information is also an
generator cooler and the 1B residual heat removal heat exchanger.
acceptable option.The lead inspector for this inspection is Ms. Caroline Acosta Acevedo. If there are questionsabout the material requested, or the inspection, please call Ms. Acosta Acevedo at
We have enclosed a request for documents needed for the inspection. This information can be
(630) 829-9718.In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter andits enclosure will be available electronically for public inspection in the NRC Public DocumentRoom or from the Publicly Available Records (PARS) component of NRC's document system
sent to the following e-mail address cea4@nrc.gov, no later than April 13, 2007, so that we may
G. Van Middlesworth-2-(ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (thePublic Electronic Reading Room).Sincerely,/RA/Ann Marie Stone, ChiefEngineering Branch 2
start the review of these documents. A hard-copy with the required information is also an
Division of Reactor Safety Docket No. 50-331License No. DPR-49Enclosure: Heat Sink Inspection Document Request
acceptable option.
cc w/encl:J. Stall, Senior Vice President, Nuclear and Chief Nuclear Officer
The lead inspector for this inspection is Ms. Caroline Acosta Acevedo. If there are questions
R. Helfrich, Senior Attorney
about the material requested, or the inspection, please call Ms. Acosta Acevedo at
M. Ross, Managing Attorney
(630) 829-9718.
W. Webster, Vice President, Nuclear Operations
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and
M. Warner, Vice President, Nuclear Operations Support
its enclosure will be available electronically for public inspection in the NRC Public Document
R. Kundalkar, Vice President, Nuclear Engineering
Room or from the Publicly Available Records (PARS) component of NRC's document system
J. Bjorseth, Site Director
 
D. Curtland, Plant Manager
G. Van Middlesworth                             -2-
S. Catron, Manager, Regulatory Affairs
(ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the
Chairman, Linn County Board of Supervisors
Public Electronic Reading Room).
D. McGhee, State Liaison Officer  
                                              Sincerely,
G. Van Middlesworth-2-(ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (thePublic Electronic Reading Room).Sincerely,/RA/Ann Marie Stone, ChiefEngineering Branch 2
                                              /RA/
Division of Reactor Safety Docket No. 50-331License No. DPR-49Enclosure: Heat Sink Inspection Document Request
                                              Ann Marie Stone, Chief
cc w/encl:J. Stall, Senior Vice President, Nuclear and Chief Nuclear Officer
                                              Engineering Branch 2
R. Helfrich, Senior Attorney
                                              Division of Reactor Safety
M. Ross, Managing Attorney
Docket No. 50-331
W. Webster, Vice President, Nuclear Operations
License No. DPR-49
M. Warner, Vice President, Nuclear Operations Support
Enclosure: Heat Sink Inspection Document Request
R. Kundalkar, Vice President, Nuclear Engineering
cc w/encl:     J. Stall, Senior Vice President, Nuclear and Chief
J. Bjorseth, Site Director
                Nuclear Officer
D. Curtland, Plant Manager
              R. Helfrich, Senior Attorney
S. Catron, Manager, Regulatory Affairs
              M. Ross, Managing Attorney
Chairman, Linn County Board of Supervisors
              W. Webster, Vice President, Nuclear Operations
D. McGhee, State Liaison OfficerDOCUMENT NAME: C:\FileNet\ML070640539.wpd  
              M. Warner, Vice President, Nuclear Operations Support
G Publicly Available
              R. Kundalkar, Vice President, Nuclear Engineering
G Non-Publicly Available
              J. Bjorseth, Site Director
G Sensitive
              D. Curtland, Plant Manager
G Non-SensitiveTo receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copyOFFICERIIIRIIINNAMECAcostaAcevedo:coAMStoneDATE03/05/0703/05/07OFFICIAL RECORD COPY  
              S. Catron, Manager, Regulatory Affairs
G. Van Middlesworth-3-DISTRIBUTION
              Chairman, Linn County Board of Supervisors
:TEB
              D. McGhee, State Liaison Officer
 
G. Van Middlesworth                                                         -2-
(ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the
Public Electronic Reading Room).
                                                                          Sincerely,
                                                                          /RA/
                                                                          Ann Marie Stone, Chief
                                                                          Engineering Branch 2
                                                                          Division of Reactor Safety
Docket No. 50-331
License No. DPR-49
Enclosure: Heat Sink Inspection Document Request
cc w/encl:               J. Stall, Senior Vice President, Nuclear and Chief
                            Nuclear Officer
                          R. Helfrich, Senior Attorney
                          M. Ross, Managing Attorney
                          W. Webster, Vice President, Nuclear Operations
                          M. Warner, Vice President, Nuclear Operations Support
                          R. Kundalkar, Vice President, Nuclear Engineering
                          J. Bjorseth, Site Director
                          D. Curtland, Plant Manager
                          S. Catron, Manager, Regulatory Affairs
                          Chairman, Linn County Board of Supervisors
                          D. McGhee, State Liaison Officer
DOCUMENT NAME: C:\FileNet\ML070640539.wpd
G Publicly Available                       G Non-Publicly Available                 G Sensitive             G Non-Sensitive
To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy
OFFICE            RIII                                    RIII                                                          N
NAME              CAcostaAcevedo:co                        AMStone
DATE              03/05/07                                03/05/07
                                                          OFFICIAL RECORD COPY
 
G. Van Middlesworth -3-
DISTRIBUTION:
TEB
DWS
DWS
RidsNrrDirsIrib
RidsNrrDirsIrib
Line 65: Line 106:
KGO
KGO
GLS
GLS
RJO
RJO
CAA1
CAA1
DRPIII
DRPIII
DRSIII
DRSIII
PLB1
PLB1
TXN  
TXN
BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUESTInitial Document RequestEnclosure 1Inspection Report
 
:05000331/2007003(DRS)Inspection Dates
        BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST
:April 23 - 27, 2007Inspection Procedures
                                        Initial Document Request
:71111.07, Biennial "Heat Sink Performance Inspection"Lead Inspector
Inspection Report:               05000331/2007003(DRS)
:C. E. Acosta Acevedo(630) 829-9718, cea4@nrc.govInformation Requested Prior to the On-site Information Gathering/Inspection Week
Inspection Dates:                 April 23 - 27, 2007
The following information is requested to be provided as soon as possible, but no later thanApril 13, 2007, to support the biennial "Heat Sink Performance Inspection," IP 71111.07.  
Inspection Procedures:           71111.07, Biennial Heat Sink Performance Inspection
If some of the activities are not performed by your program, please note that fact. This request
Lead Inspector:                   C. E. Acosta Acevedo
                                  (630) 829-9718, cea4@nrc.gov
Information Requested Prior to the On-site Information Gathering/Inspection Week
The following information is requested to be provided as soon as possible, but no later than
April 13, 2007, to support the biennial Heat Sink Performance Inspection, IP 71111.07.
If some of the activities are not performed by your program, please note that fact. This request
is only for the time period from the onsite inspection back to the last Heat Sink Performance
is only for the time period from the onsite inspection back to the last Heat Sink Performance
Inspection in year 2005. If nothing addressing the request was done in that time period then
Inspection in year 2005. If nothing addressing the request was done in that time period then
the request applies to the last applicable document in the previous time period. Unless
the request applies to the last applicable document in the previous time period. Unless
otherwise specified, all the below requests are for the selected heat exchangers (Hxs) which
otherwise specified, all the below requests are for the selected heat exchangers (Hxs) which
are the 1B emergency diesel generator cooler and the 1B residual heat removal heat
are the 1B emergency diesel generator cooler and the 1B residual heat removal heat
exchanger.1.Copies of the two most recent completed tests confirming thermal performance forthose heat exchangers which are performance tested.2.For the two most recently completed tests confirming thermal performance of thesample heat exchangers, please provide documentation and procedures that identify the
exchanger.
types, accuracy, and location of any special instrumentation used for these tests, (e.g.,
1.       Copies of the two most recent completed tests confirming thermal performance for
high accuracy ultrasonic flow instruments or temperature instruments). Include
        those heat exchangers which are performance tested.
calibration records for the instruments used during these tests.3.A list of corrective action program documents (with a short description) associated withHxs, heat sinks, silting, corrosion, fouling, or Hx testing, that are documented in your
2.       For the two most recently completed tests confirming thermal performance of the
corrective action system (for the previous 2 years or since the last biennial heat sink
        sample heat exchangers, please provide documentation and procedures that identify the
inspection), this request is for all the Generic Letter 89-13 Hxs and the ultimate heat
        types, accuracy, and location of any special instrumentation used for these tests, (e.g.,
sink.4.Copy of system description and design basis document for the Hxs under review (asapplicable).  
        high accuracy ultrasonic flow instruments or temperature instruments). Include
BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUESTInitial Document RequestEnclosure 25.Copy of any operability determinations or other documentation of degradationassociated with the Hxs or the systems that support the operation of the Hxs.6.Copy of any self-assessment done within last 2 years on any of the licensee's Hxprograms (e.g., Generic Letter 89-13 program Hxs) or on the sample Hxs.7.A schedule of all inspections, cleanings, maintenance, or testing of any plant Hx to bedone during the on-site portion of the inspection.8.List of operability evaluations currently relied upon and those that were previously (past2 years) relied upon for operability.9.Copy of the evaluations of data for the two most recent completed tests confirming thethermal performance of each Hx.10.Provide copy of the calculation which establishes the limiting (maximum) design basisheat load which is required to be removed by each of these Hxs.11.Copy of the calculation which correlates surveillance testing results from these Hxs withdesign basis heat removal capability (e.g., basis for surveillance test acceptancecriteria).12.The clean and inspection maintenance schedule for each Hx for the next 5 years.
        calibration records for the instruments used during these tests.
13.Copy of the document describing the inspection results for the last two clean andinspection activities completed on each Hx.14.Copy of the document which identifies the current number of tubes in service for eachHx and the supporting calculation which establishes the maximum number of tubes
3.       A list of corrective action program documents (with a short description) associated with
which can be plugged in each Hx.15.Copy of the document establishing the repair criteria (plugging limit) for degraded tubeswhich are identified in each Hx.16.Copy of the design specification and Hx data sheets for each Hx
        Hxs, heat sinks, silting, corrosion, fouling, or Hx testing, that are documented in your
.17.Copy of the vendor manuals including component drawings for each Hx.18.Copy of the calculations or documents which evaluate the potential for water hammer orexcessive tube vibration in the Hx or associated piping.19.Copy of Hx performance trending data tracked for each Hx.
        corrective action system (for the previous 2 years or since the last biennial heat sink
20.Copies of those documents that describe the methods taken to control water chemistryin the Hxs, including any provisions for controlling biotic fouling.  
        inspection), this request is for all the Generic Letter 89-13 Hxs and the ultimate heat
BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUESTInitial Document RequestEnclosure 321.Copies of the following documents:a.Inspections of the weir or embankment and the crest of the dam;
        sink.
b.The rip rap protection placed on excavated side slopes;
4.       Copy of system description and design basis document for the Hxs under review (as
c.Licensee's or third party dam inspections that monitor the integrity of the heatsink;d.Calculations demonstrating sufficient reservoir capacity;
        applicable).
e.Maintenance records of inaccessible below-water portions of the UHS systemwith the methodology and results of underwater diving inspections;f. Any design changes to the ultimate heat sink;
                                                    1                                      Enclosure
g. Procedures or controls to address biotic fouling;
 
h.Procedures for adverse weather conditions, e.g. icing or high temperatures; and
    BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST
i.Last two performance tests for all pumps and all valves in the safety-relatedservice water system. If the components are not performance tested, please
                                Initial Document Request
provide documentation verifying performance by the methods actually used.22.Copies of the documents that verify flow testing was done at maximum design flowduring the last 2 years or since the last time it was done. Copies of the documents that
5. Copy of any operability determinations or other documentation of degradation
verify maximum design flow testing will continue to be periodically done in the future.23.Copies of the documents that verify the structural integrity of the Hx, e.g., eddy currentsummary sheets, ultrasonic testing results, and visual inspection results.24.Provide a list of calculations with a description which currently apply to each Hx.
    associated with the Hxs or the systems that support the operation of the Hxs.
25.Provide the Design Basis Documents for the above listed Hxs.
6. Copy of any self-assessment done within last 2 years on any of the licensees Hx
26.System health report(s) and maintenance rule system notebooks for these Hx(s).
    programs (e.g., Generic Letter 89-13 program Hxs) or on the sample Hxs.
27.Duane Arnold Energy Center Response to the Generic Letter 89-13.
7. A schedule of all inspections, cleanings, maintenance, or testing of any plant Hx to be
28.Copies of procedures developed to implement the recommendations of GL 89-13,"Service Water System Problems Affecting Safety-Related Equipment," e.g., the
    done during the on-site portion of the inspection.
GL 89-13 Heat Exchanger Program description.29.List of engineering-related Operator Workarounds/Temporary Modifications for theseHx(s) since the last Heat Sink Performance.  
8. List of operability evaluations currently relied upon and those that were previously (past
BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUESTInitial Document RequestEnclosure 430.Copy of self-assessments and audits for the selected Hxs and for the GL 89-13 HeatExchanger Program.31.Updated Final Safety Analysis Report pages for these Hx(s) and for the GL 89-13 HeatExchanger Program.32.Information regarding any alarms which monitor on-line performance of these Hxs.
    2 years) relied upon for operability.
If the information requested above will not be available, please contact Ms. Acosta Acevedo assoon as possible at (630) 829-9718 or email cea4@nrc.gov
9. Copy of the evaluations of data for the two most recent completed tests confirming the
.
    thermal performance of each Hx.
10. Provide copy of the calculation which establishes the limiting (maximum) design basis
    heat load which is required to be removed by each of these Hxs.
11. Copy of the calculation which correlates surveillance testing results from these Hxs with
    design basis heat removal capability (e.g., basis for surveillance test acceptance
    criteria).
12. The clean and inspection maintenance schedule for each Hx for the next 5 years.
13. Copy of the document describing the inspection results for the last two clean and
    inspection activities completed on each Hx.
14. Copy of the document which identifies the current number of tubes in service for each
    Hx and the supporting calculation which establishes the maximum number of tubes
    which can be plugged in each Hx.
15. Copy of the document establishing the repair criteria (plugging limit) for degraded tubes
    which are identified in each Hx.
16. Copy of the design specification and Hx data sheets for each Hx.
17. Copy of the vendor manuals including component drawings for each Hx.
18. Copy of the calculations or documents which evaluate the potential for water hammer or
    excessive tube vibration in the Hx or associated piping.
19. Copy of Hx performance trending data tracked for each Hx.
20. Copies of those documents that describe the methods taken to control water chemistry
    in the Hxs, including any provisions for controlling biotic fouling.
                                              2                                    Enclosure
 
    BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST
                                  Initial Document Request
21. Copies of the following documents:
    a.       Inspections of the weir or embankment and the crest of the dam;
    b.       The rip rap protection placed on excavated side slopes;
    c.       Licensees or third party dam inspections that monitor the integrity of the heat
            sink;
    d.       Calculations demonstrating sufficient reservoir capacity;
    e.       Maintenance records of inaccessible below-water portions of the UHS system
            with the methodology and results of underwater diving inspections;
    f.       Any design changes to the ultimate heat sink;
    g.       Procedures or controls to address biotic fouling;
    h.       Procedures for adverse weather conditions, e.g. icing or high temperatures; and
    i.       Last two performance tests for all pumps and all valves in the safety-related
            service water system. If the components are not performance tested, please
            provide documentation verifying performance by the methods actually used.
22. Copies of the documents that verify flow testing was done at maximum design flow
    during the last 2 years or since the last time it was done. Copies of the documents that
    verify maximum design flow testing will continue to be periodically done in the future.
23. Copies of the documents that verify the structural integrity of the Hx, e.g., eddy current
    summary sheets, ultrasonic testing results, and visual inspection results.
24. Provide a list of calculations with a description which currently apply to each Hx.
25. Provide the Design Basis Documents for the above listed Hxs.
26. System health report(s) and maintenance rule system notebooks for these Hx(s).
27. Duane Arnold Energy Center Response to the Generic Letter 89-13.
28. Copies of procedures developed to implement the recommendations of GL 89-13,
    Service Water System Problems Affecting Safety-Related Equipment, e.g., the
    GL 89-13 Heat Exchanger Program description.
29. List of engineering-related Operator Workarounds/Temporary Modifications for these
    Hx(s) since the last Heat Sink Performance.
                                              3                                      Enclosure
 
        BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST
                                  Initial Document Request
30.     Copy of self-assessments and audits for the selected Hxs and for the GL 89-13 Heat
        Exchanger Program.
31.     Updated Final Safety Analysis Report pages for these Hx(s) and for the GL 89-13 Heat
        Exchanger Program.
32.     Information regarding any alarms which monitor on-line performance of these Hxs.
If the information requested above will not be available, please contact Ms. Acosta Acevedo as
soon as possible at (630) 829-9718 or email cea4@nrc.gov.
                                                4                                    Enclosure
}}
}}

Revision as of 08:51, 23 November 2019

Ltr. 03/05/07 Duane Arnold Request for Information IR 5000331-07-003
ML070640539
Person / Time
Site: Duane Arnold NextEra Energy icon.png
Issue date: 03/05/2007
From: Ann Marie Stone
NRC/RGN-III/DRS/EB2
To: Vanmiddlesworth G
Nuclear Management Co
References
IR-07-003
Download: ML070640539 (9)


See also: IR 05000331/2007003

Text

March 5, 2007

Mr. Gary Van Middlesworth

Vice-President

Duane Arnold Energy Center

3277 DAEC Road

Palo, IA 52324-9785

SUBJECT: DUANE ARNOLD ENERGY CENTER

NOTIFICATION OF AN NRC BIENNIAL HEAT SINK PERFORMANCE

INSPECTION AND REQUEST FOR INFORMATION 05000331/2007003(DRS)

Dear Mr. Van Middlesworth:

On April 23, 2007, the NRC will begin the on-site portion of the Biennial Heat Sink Performance

Inspection at your Duane Arnold Energy Center. This inspection will be performed in

accordance with NRC baseline inspection procedure (IP) 71111.07. The heat exchangers

selected for detailed review during this baseline inspection are the 1B emergency diesel

generator cooler and the 1B residual heat removal heat exchanger.

We have enclosed a request for documents needed for the inspection. This information can be

sent to the following e-mail address cea4@nrc.gov, no later than April 13, 2007, so that we may

start the review of these documents. A hard-copy with the required information is also an

acceptable option.

The lead inspector for this inspection is Ms. Caroline Acosta Acevedo. If there are questions

about the material requested, or the inspection, please call Ms. Acosta Acevedo at

(630) 829-9718.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and

its enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRC's document system

G. Van Middlesworth -2-

(ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the

Public Electronic Reading Room).

Sincerely,

/RA/

Ann Marie Stone, Chief

Engineering Branch 2

Division of Reactor Safety

Docket No. 50-331

License No. DPR-49

Enclosure: Heat Sink Inspection Document Request

cc w/encl: J. Stall, Senior Vice President, Nuclear and Chief

Nuclear Officer

R. Helfrich, Senior Attorney

M. Ross, Managing Attorney

W. Webster, Vice President, Nuclear Operations

M. Warner, Vice President, Nuclear Operations Support

R. Kundalkar, Vice President, Nuclear Engineering

J. Bjorseth, Site Director

D. Curtland, Plant Manager

S. Catron, Manager, Regulatory Affairs

Chairman, Linn County Board of Supervisors

D. McGhee, State Liaison Officer

G. Van Middlesworth -2-

(ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the

Public Electronic Reading Room).

Sincerely,

/RA/

Ann Marie Stone, Chief

Engineering Branch 2

Division of Reactor Safety

Docket No. 50-331

License No. DPR-49

Enclosure: Heat Sink Inspection Document Request

cc w/encl: J. Stall, Senior Vice President, Nuclear and Chief

Nuclear Officer

R. Helfrich, Senior Attorney

M. Ross, Managing Attorney

W. Webster, Vice President, Nuclear Operations

M. Warner, Vice President, Nuclear Operations Support

R. Kundalkar, Vice President, Nuclear Engineering

J. Bjorseth, Site Director

D. Curtland, Plant Manager

S. Catron, Manager, Regulatory Affairs

Chairman, Linn County Board of Supervisors

D. McGhee, State Liaison Officer

DOCUMENT NAME: C:\FileNet\ML070640539.wpd

G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive

To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE RIII RIII N

NAME CAcostaAcevedo:co AMStone

DATE 03/05/07 03/05/07

OFFICIAL RECORD COPY

G. Van Middlesworth -3-

DISTRIBUTION:

TEB

DWS

RidsNrrDirsIrib

GEG

KGO

GLS

RJO

CAA1

DRPIII

DRSIII

PLB1

TXN

BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST

Initial Document Request

Inspection Report: 05000331/2007003(DRS)

Inspection Dates: April 23 - 27, 2007

Inspection Procedures: 71111.07, Biennial Heat Sink Performance Inspection

Lead Inspector: C. E. Acosta Acevedo

(630) 829-9718, cea4@nrc.gov

Information Requested Prior to the On-site Information Gathering/Inspection Week

The following information is requested to be provided as soon as possible, but no later than

April 13, 2007, to support the biennial Heat Sink Performance Inspection, IP 71111.07.

If some of the activities are not performed by your program, please note that fact. This request

is only for the time period from the onsite inspection back to the last Heat Sink Performance

Inspection in year 2005. If nothing addressing the request was done in that time period then

the request applies to the last applicable document in the previous time period. Unless

otherwise specified, all the below requests are for the selected heat exchangers (Hxs) which

are the 1B emergency diesel generator cooler and the 1B residual heat removal heat

exchanger.

1. Copies of the two most recent completed tests confirming thermal performance for

those heat exchangers which are performance tested.

2. For the two most recently completed tests confirming thermal performance of the

sample heat exchangers, please provide documentation and procedures that identify the

types, accuracy, and location of any special instrumentation used for these tests, (e.g.,

high accuracy ultrasonic flow instruments or temperature instruments). Include

calibration records for the instruments used during these tests.

3. A list of corrective action program documents (with a short description) associated with

Hxs, heat sinks, silting, corrosion, fouling, or Hx testing, that are documented in your

corrective action system (for the previous 2 years or since the last biennial heat sink

inspection), this request is for all the Generic Letter 89-13 Hxs and the ultimate heat

sink.

4. Copy of system description and design basis document for the Hxs under review (as

applicable).

1 Enclosure

BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST

Initial Document Request

5. Copy of any operability determinations or other documentation of degradation

associated with the Hxs or the systems that support the operation of the Hxs.

6. Copy of any self-assessment done within last 2 years on any of the licensees Hx

programs (e.g., Generic Letter 89-13 program Hxs) or on the sample Hxs.

7. A schedule of all inspections, cleanings, maintenance, or testing of any plant Hx to be

done during the on-site portion of the inspection.

8. List of operability evaluations currently relied upon and those that were previously (past

2 years) relied upon for operability.

9. Copy of the evaluations of data for the two most recent completed tests confirming the

thermal performance of each Hx.

10. Provide copy of the calculation which establishes the limiting (maximum) design basis

heat load which is required to be removed by each of these Hxs.

11. Copy of the calculation which correlates surveillance testing results from these Hxs with

design basis heat removal capability (e.g., basis for surveillance test acceptance

criteria).

12. The clean and inspection maintenance schedule for each Hx for the next 5 years.

13. Copy of the document describing the inspection results for the last two clean and

inspection activities completed on each Hx.

14. Copy of the document which identifies the current number of tubes in service for each

Hx and the supporting calculation which establishes the maximum number of tubes

which can be plugged in each Hx.

15. Copy of the document establishing the repair criteria (plugging limit) for degraded tubes

which are identified in each Hx.

16. Copy of the design specification and Hx data sheets for each Hx.

17. Copy of the vendor manuals including component drawings for each Hx.

18. Copy of the calculations or documents which evaluate the potential for water hammer or

excessive tube vibration in the Hx or associated piping.

19. Copy of Hx performance trending data tracked for each Hx.

20. Copies of those documents that describe the methods taken to control water chemistry

in the Hxs, including any provisions for controlling biotic fouling.

2 Enclosure

BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST

Initial Document Request

21. Copies of the following documents:

a. Inspections of the weir or embankment and the crest of the dam;

b. The rip rap protection placed on excavated side slopes;

c. Licensees or third party dam inspections that monitor the integrity of the heat

sink;

d. Calculations demonstrating sufficient reservoir capacity;

e. Maintenance records of inaccessible below-water portions of the UHS system

with the methodology and results of underwater diving inspections;

f. Any design changes to the ultimate heat sink;

g. Procedures or controls to address biotic fouling;

h. Procedures for adverse weather conditions, e.g. icing or high temperatures; and

i. Last two performance tests for all pumps and all valves in the safety-related

service water system. If the components are not performance tested, please

provide documentation verifying performance by the methods actually used.

22. Copies of the documents that verify flow testing was done at maximum design flow

during the last 2 years or since the last time it was done. Copies of the documents that

verify maximum design flow testing will continue to be periodically done in the future.

23. Copies of the documents that verify the structural integrity of the Hx, e.g., eddy current

summary sheets, ultrasonic testing results, and visual inspection results.

24. Provide a list of calculations with a description which currently apply to each Hx.

25. Provide the Design Basis Documents for the above listed Hxs.

26. System health report(s) and maintenance rule system notebooks for these Hx(s).

27. Duane Arnold Energy Center Response to the Generic Letter 89-13.

28. Copies of procedures developed to implement the recommendations of GL 89-13,

Service Water System Problems Affecting Safety-Related Equipment, e.g., the

GL 89-13 Heat Exchanger Program description.

29. List of engineering-related Operator Workarounds/Temporary Modifications for these

Hx(s) since the last Heat Sink Performance.

3 Enclosure

BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST

Initial Document Request

30. Copy of self-assessments and audits for the selected Hxs and for the GL 89-13 Heat

Exchanger Program.

31. Updated Final Safety Analysis Report pages for these Hx(s) and for the GL 89-13 Heat

Exchanger Program.

32. Information regarding any alarms which monitor on-line performance of these Hxs.

If the information requested above will not be available, please contact Ms. Acosta Acevedo as

soon as possible at (630) 829-9718 or email cea4@nrc.gov.

4 Enclosure