ML081370218: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
| Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter:OPL 171.036 | |||
Revision 11 | |||
Page 24 of 58 | |||
(7) CASx (CASA or CASB) accident signal -122" RxVL OR | |||
(after 5 second delay via BBRX relay) 2.45 DWP AND | |||
< 450# RPV | |||
I. 4kV Shutdown Boards (Normal Power Seeking) Refer to prints | |||
15E-500 series Key | |||
Diagram of STDBY | |||
Aux. Power System | |||
1. Power sources Obj. V.B.6.c | |||
Obj. V.C.1.c | |||
a. 4kV supplies to each U1/2 Shutdown Board: | |||
Obj. V.D.6.c | |||
are as follows: | |||
Board NORMAL Supply | |||
A Shutdown Bus 1 | |||
B Shutdown Bus 1 | |||
C Shutdown Bus 2 | |||
D Shutdown Bus 2 | |||
The first alternate is from the other Shutdown SBO | |||
Bus. The second alternate is from the diesel | |||
3 % via bustie | |||
generator. The third alternate is from the U3 | |||
board | |||
diesel generators via a U3 Shutdown Board. | |||
% % via other | |||
SO Bus | |||
b. There are two possible 4kV supplies to each | |||
U3 Shutdown Board: | |||
Board NORMAL Supply | |||
3EA Unit Board 3A | |||
3EB Unit Board 3A | |||
3EC Unit Board 3B | |||
3ED Unit Board 3B | |||
(1) The first alternate is from the diesel | |||
generators. The U1/2 diesel | |||
generators cannot supply power to the | |||
U3 Shutdown Boards alone. They | |||
may, however, be paralleled with the | |||
U3 diesel generators for backfeed | |||
operation. The tie breaker off the unit 3 | |||
Shutdown Board is interlocked as | |||
follows: | |||
OPL171.036 | |||
Revision 11 | |||
Page 31 of 58 | |||
7. Shutdown Board Transfer Scheme | |||
a. The only automatic transfer of power on a Obj. V.B.8.c | |||
shutdown board is a delayed (slow) transfer. Obj. V.C.2.c | |||
In order for the transfer to take place, the bus Obj. V.D.8.c | |||
transfer control switch (43Sx) must be in Procedural | |||
AUTOMATIC. Adherence when | |||
transferring | |||
boards | |||
(1) Undervoltage is sensed on the line | |||
side of the normal feeder breaker. | |||
(2) Voltage is available on the line side of | |||
the alternate feeder breaker. | |||
(3) The normal feeder breaker then | |||
receives a trip signal. | |||
(4) A 52b contact on the normal supply | |||
breaker shuts in the close circuit of | |||
the alternate feeder breaker, | |||
indicating that the normal breaker is | |||
open. | |||
(5) A residual voltage relay shuts in the | |||
close circuit of the alternate supply | |||
breaker, indicating that ooara voltage | |||
bas decayed to less than 30 percent | |||
of normal. | |||
(6) The alternate supply breaker then | |||
closes. | |||
The shutdown board transfer scheme is | |||
NORMAL seeking. If power is restored | |||
to the line side of the normal feeder | |||
breaker, and if the 43Sx switch is still in | |||
AUTOMATIC, then a "slow" transfer | |||
back to the normal supply will occur. | |||
This will cause momentary power loss | |||
to loads on the bus and ESF actuations | |||
are possible. | |||
**b Manual High Speed (Fast Transfer) Obj. V.B.8.c | |||
Obj. V.C.2.c | |||
To fast transfer a shutdown board perform the Review INPO | |||
following: SOER 83-06 | |||
( | |||
OPL 171.036 | |||
Revision 11 | |||
Page 32 of 58 | |||
( (1) Ensure voltage is available from the Procedural | |||
alternate source. Adherence | |||
(2) Place 43Sx switch to MANUAL. | |||
(3) Place alternate breaker SYNC switch Self Check | |||
to ON. | |||
(4) Place alternate supply breaker switch | |||
in CLOSE. | |||
(5) Place normal supply breaker switch in | |||
TRIP. | |||
(6) Alternate breaker closes when 52b Alternate supply is | |||
contact from normal breaker closes, not a qualified Off- | |||
indicating that breaker has opened. If site supply | |||
the Alternate Supply from SO Bus is | |||
closed to a Unit 1/2 SID Board, an | |||
Accident Signal will trip it open. | |||
(7) Turn off SYNC switch. | |||
(8) DO NOT place 43Sx switch back to | |||
AUTOMATIC (Transfer back to | |||
normal supply would occur). | |||
Note: If the SYNC SW was not ON for Self Check | |||
the alternate breaker, a delayed | |||
transfer would occur when the | |||
normal breaker opens and the | |||
board residual voltage relay | |||
detects less than 30% voltage, | |||
assuming the alternate breaker's | |||
control switch is held in the | |||
CLOSE position. | |||
c. Conditions which automatically trip the board | |||
transfer control switch (43Sx) to MANUAL: | |||
(1 ) Normal Feeder Lockout Relay (86-xxx) | |||
(2) Alternate Feeder Lockout Relay (86- | |||
,xxx) | |||
(3) Normal Feeder Control Transfer Switch | |||
in EMERGENCY | |||
(4) Alternate Feeder Control Transfer -122" RxVL | |||
Switch in EMERGENCY OR | |||
2.45 DWP AND | |||
(5) CASx accident signal | |||
( < 450# RPV | |||
----- | |||
20. RO 262002Al.02 OO l/C/Am/GI/UNIT PREFFERRED/C/A 2.5/2.9/262002AA l.02/BF0530I/RO/SRO/lO/27/2007 | |||
Given the following plant conditions: | |||
* Unit 3 is in a normal lineup . | |||
( . | |||
* The following alarm is received : | |||
- UNIT PFD SUPPLY ABNORMAL | |||
* It is determined that the alarm is due to the Unit-3 Unit Preferred AC Generator Overvoltage | |||
condition | |||
Wh ich ONE of the following describes the correct result of this condition? Assume NO Operator actions. | |||
A. Unit 3 bkr 1001 trips open; Unit 2 bkr 1003 interlocked open; the MMG set automatically shuts down. | |||
B. Unit 3 bkr 1001 interlocked open ; Unit 2 bkr 1003 trips open; the MMG set automatically shuts down. | |||
C~ Unit 3 bkr 1001 trips open ; Unit 2 bkr 1003 interlocked open; the MMG set continues to run without | |||
excitation. | |||
D. Unit 3 bkr 1001 interlocked open ; Unit 2 bkr 1003 trips open; the MMG set cont inues to run without | |||
excitation . | |||
KIA Statement: | |||
262002 UPS (AC/DC) | |||
KIA: A1.02 Ability to predict and/or monitor changes in parameters associated with operating the | |||
UNINTERRUPTABLE POWER SUPPLY (A.C./D.C.) controls including: Motor generator outputs . | |||
KIA Justification: This question satisfies the KIA statement by requiring the candidate to correctly apply | |||
a specific operating condition of the UPS MMG Set to the correct response of the system to that condition. | |||
References: OPL171 .102, Rev.6, pg 20 & 21, 3-ARP-9-8B, Rev.9, tile 35 | |||
Level of Knowledge Justification: This question is rated as CIA due to the requirement to assemble , | |||
sort, and integrate the parts of the question to solve a problem . This requires mentally using this | |||
knowledge and its meaning to resolve the problem . | |||
0610 NRC Exam | |||
REFERENCE PROVIDED: None | |||
Plausibility Analysis: | |||
( In order to answer this question correctly the candidate must determine the following: | |||
1. The 1001 and 1003 breakers from an MMG set will trip on overvoltage or underfrequency at the output | |||
of the MMG. | |||
2. Unit 2 MMG Breakers are interlocked to prevent alternate power to unit 1 and 3 at the same time. | |||
3. When an overvoltage condition exists at the Generator Output, the 1001 breaker from the MMG Set | |||
trips. | |||
4. Excitation is lost and the MMG Set continues to run. | |||
5. The Hold to build up voltage switch must be depressed to restore voltage.Also | |||
A is incorrect. The MMG set does not automatically shut down. This is plausible because the breaker | |||
lineup is correct. | |||
B is incorrect. The MMG set does not automatically shut down. This is plausible although the breaker | |||
lineup is backwards. | |||
C is correct. | |||
D is incorrect. The breaker lineup is backwards. This is plausible because the MMG Set will continue to | |||
run without excitation. | |||
( | |||
BFN Panel 1-9-8 1-ARP-9-8B | |||
Unit 1 1-XA-55-8B Rev. 0009 | |||
( Page 42 of 42 | |||
Senso rlTrip Point: | |||
UNIT PFD | |||
SUPPLY Relay SE - loss of normal DC power source . | |||
ABNORMAL Relay TS - DC Xfer switch transfers to Emergency DC Power Source. | |||
Regulating Transformer Common Alarm. | |||
1-INV-252-001 , INVT-1 System Common Alarm . | |||
(Page 1 of 1) | |||
Sensor EL 593' 250V DC Battery Board 2 | |||
Location: | |||
Probable A. Loss of normal DC power source | |||
Cause: B. DC power transfer. | |||
C. Relay failure | |||
D. INVT-1 System Common Alarms | |||
1. Fan Failure Rectifier | |||
2. Over temperature Rectifier | |||
3. AC Power Failure to Rectifier | |||
4. Low DC Voltage | |||
5. High DC Voltage | |||
6. Low DC Disconnect | |||
7. Fan Failure Inverter | |||
8. Alternate Source Failure | |||
9. :Low AC Output Voltage | |||
10. High Output Voltage | |||
11. Inverter Fuse Blown | |||
12. Static Switch Fuse Blown | |||
13. Over Temperature Inverter | |||
E. PFD Regulating XFMR Common Alarms | |||
1. Transformer Over temperature | |||
2. Fan Failure | |||
3. CB1 Breaker Trip | |||
4. CB2 Breaker Trip | |||
Automatic A. Auto transfer to DC Power Source on Rectifier failure . | |||
Action: B. Auto transfer to Alternate AC supply (Regulated Transformer) on Inverter failure. | |||
Operator A. IF 120V AC Unit Preferred is lost, THEN | |||
Action: REFER TO 1-AOI-57-4 , Loss of Unit Preferred . o | |||
B. REFER TO appropriate portion of 0-OI-57C, 208V/120V AC | |||
Electrical System. o | |||
References: 0-45E641-2 1-45E620-11 1-3300D15A4585-1 | |||
10-100467 0-20-100756 20-110437 | |||
OPL171.102 | |||
Revision 6 | |||
Page 20 of 69 | |||
( | |||
(d) Another Unit's MMG set | |||
The second alternate is from | |||
another unit's MMG set | |||
output. Unit 2 MMG is the | |||
second alternate for either | |||
Unit 1 or Unit 3; Unit 3 is the | |||
second alternate for Unit 2. | |||
Transfers to this source are | |||
done manually at Battery | |||
Board 2 panel 11. | |||
b. MMG Sets (Unit 2&3) Obj. V.B.2.b | |||
TP-11 | |||
(1) The MMG is normally driven By the Obj'v.D.2.c | |||
AC motor, powered from 480V Obj.V.D.2.d/j | |||
Shutdown Board A. Should this Obj V.E.2.c | |||
supply fail, the AC motor is Obj'v.E.2.d/i | |||
automatically disconnected and the Obj V.B.2.h | |||
DC motor starts, powered from Obj'v.C.3.e | |||
250V Battery Board. The DC Obj'v.D.2.j | |||
motor has an alternate power Obj'v.E.2.i | |||
supply from another 250V Battery | |||
Board. Transfer to the alternate | |||
DC source is manual. | |||
Underfrequency on the generator | |||
output will trip the DC motor. | |||
Transfer of the MMG set back to | |||
the AC motor is manual. | |||
(2) The 1001 and 1003 breakers from | |||
an MMG set will trip on overvoltage | |||
or underfrequency at the output of | |||
the MMG. Also Unit 2 MMG | |||
Breakers are interlocked to prevent | |||
alternate power to unit 1 and 3 at | |||
the same time. | |||
OPL171.102 | |||
Revision 6 | |||
Page 21 of 69 | |||
(3) When an under frequency or Obj. V.B.2.h | |||
overvoltage condition exists at the Obj. V.C.3.e | |||
Generator Output the following Obj. V.D.2.j | |||
occurs Obj. V.E.2.i | |||
(a) BB panel 10 breakers from | |||
the MMG Set trip. | |||
U2 1001 (U2) 1003 (U1&3) | |||
}} | }} | ||
Revision as of 16:36, 14 November 2019
| ML081370218 | |
| Person / Time | |
|---|---|
| Site: | Browns Ferry |
| Issue date: | 04/08/2008 |
| From: | NRC/RGN-II/DRS/OLB |
| To: | Tennessee Valley Authority |
| References | |
| 50-259/08-301 50-259/08-301 | |
| Download: ML081370218 (86) | |
See also: IR 05000259/2008301
Text
OPL 171.036
Revision 11
Page 24 of 58
(7) CASx (CASA or CASB) accident signal -122" RxVL OR
(after 5 second delay via BBRX relay) 2.45 DWP AND
< 450# RPV
I. 4kV Shutdown Boards (Normal Power Seeking) Refer to prints
15E-500 series Key
Diagram of STDBY
Aux. Power System
1. Power sources Obj. V.B.6.c
Obj. V.C.1.c
a. 4kV supplies to each U1/2 Shutdown Board:
Obj. V.D.6.c
are as follows:
Board NORMAL Supply
A Shutdown Bus 1
B Shutdown Bus 1
C Shutdown Bus 2
D Shutdown Bus 2
The first alternate is from the other Shutdown SBO
Bus. The second alternate is from the diesel
3 % via bustie
generator. The third alternate is from the U3
board
diesel generators via a U3 Shutdown Board.
% % via other
SO Bus
b. There are two possible 4kV supplies to each
U3 Shutdown Board:
Board NORMAL Supply
3EA Unit Board 3A
3EB Unit Board 3A
3EC Unit Board 3B
3ED Unit Board 3B
(1) The first alternate is from the diesel
generators. The U1/2 diesel
generators cannot supply power to the
U3 Shutdown Boards alone. They
may, however, be paralleled with the
U3 diesel generators for backfeed
operation. The tie breaker off the unit 3
Shutdown Board is interlocked as
follows:
OPL171.036
Revision 11
Page 31 of 58
7. Shutdown Board Transfer Scheme
a. The only automatic transfer of power on a Obj. V.B.8.c
shutdown board is a delayed (slow) transfer. Obj. V.C.2.c
In order for the transfer to take place, the bus Obj. V.D.8.c
transfer control switch (43Sx) must be in Procedural
AUTOMATIC. Adherence when
transferring
boards
(1) Undervoltage is sensed on the line
side of the normal feeder breaker.
(2) Voltage is available on the line side of
the alternate feeder breaker.
(3) The normal feeder breaker then
receives a trip signal.
(4) A 52b contact on the normal supply
breaker shuts in the close circuit of
the alternate feeder breaker,
indicating that the normal breaker is
open.
(5) A residual voltage relay shuts in the
close circuit of the alternate supply
breaker, indicating that ooara voltage
bas decayed to less than 30 percent
of normal.
(6) The alternate supply breaker then
closes.
The shutdown board transfer scheme is
NORMAL seeking. If power is restored
to the line side of the normal feeder
breaker, and if the 43Sx switch is still in
AUTOMATIC, then a "slow" transfer
back to the normal supply will occur.
This will cause momentary power loss
to loads on the bus and ESF actuations
are possible.
- b Manual High Speed (Fast Transfer) Obj. V.B.8.c
Obj. V.C.2.c
To fast transfer a shutdown board perform the Review INPO
following: SOER 83-06
(
OPL 171.036
Revision 11
Page 32 of 58
( (1) Ensure voltage is available from the Procedural
alternate source. Adherence
(2) Place 43Sx switch to MANUAL.
(3) Place alternate breaker SYNC switch Self Check
to ON.
(4) Place alternate supply breaker switch
in CLOSE.
(5) Place normal supply breaker switch in
TRIP.
(6) Alternate breaker closes when 52b Alternate supply is
contact from normal breaker closes, not a qualified Off-
indicating that breaker has opened. If site supply
the Alternate Supply from SO Bus is
closed to a Unit 1/2 SID Board, an
Accident Signal will trip it open.
(7) Turn off SYNC switch.
(8) DO NOT place 43Sx switch back to
AUTOMATIC (Transfer back to
normal supply would occur).
Note: If the SYNC SW was not ON for Self Check
the alternate breaker, a delayed
transfer would occur when the
normal breaker opens and the
board residual voltage relay
detects less than 30% voltage,
assuming the alternate breaker's
control switch is held in the
CLOSE position.
c. Conditions which automatically trip the board
transfer control switch (43Sx) to MANUAL:
(1 ) Normal Feeder Lockout Relay (86-xxx)
(2) Alternate Feeder Lockout Relay (86-
,xxx)
(3) Normal Feeder Control Transfer Switch
in EMERGENCY
(4) Alternate Feeder Control Transfer -122" RxVL
Switch in EMERGENCY OR
2.45 DWP AND
(5) CASx accident signal
( < 450# RPV
20. RO 262002Al.02 OO l/C/Am/GI/UNIT PREFFERRED/C/A 2.5/2.9/262002AA l.02/BF0530I/RO/SRO/lO/27/2007
Given the following plant conditions:
- Unit 3 is in a normal lineup .
( .
- The following alarm is received :
- UNIT PFD SUPPLY ABNORMAL
- It is determined that the alarm is due to the Unit-3 Unit Preferred AC Generator Overvoltage
condition
Wh ich ONE of the following describes the correct result of this condition? Assume NO Operator actions.
A. Unit 3 bkr 1001 trips open; Unit 2 bkr 1003 interlocked open; the MMG set automatically shuts down.
B. Unit 3 bkr 1001 interlocked open ; Unit 2 bkr 1003 trips open; the MMG set automatically shuts down.
C~ Unit 3 bkr 1001 trips open ; Unit 2 bkr 1003 interlocked open; the MMG set continues to run without
excitation.
D. Unit 3 bkr 1001 interlocked open ; Unit 2 bkr 1003 trips open; the MMG set cont inues to run without
excitation .
KIA Statement:
262002 UPS (AC/DC)
KIA: A1.02 Ability to predict and/or monitor changes in parameters associated with operating the
UNINTERRUPTABLE POWER SUPPLY (A.C./D.C.) controls including: Motor generator outputs .
KIA Justification: This question satisfies the KIA statement by requiring the candidate to correctly apply
a specific operating condition of the UPS MMG Set to the correct response of the system to that condition.
References: OPL171 .102, Rev.6, pg 20 & 21, 3-ARP-9-8B, Rev.9, tile 35
Level of Knowledge Justification: This question is rated as CIA due to the requirement to assemble ,
sort, and integrate the parts of the question to solve a problem . This requires mentally using this
knowledge and its meaning to resolve the problem .
0610 NRC Exam
REFERENCE PROVIDED: None
Plausibility Analysis:
( In order to answer this question correctly the candidate must determine the following:
1. The 1001 and 1003 breakers from an MMG set will trip on overvoltage or underfrequency at the output
of the MMG.
2. Unit 2 MMG Breakers are interlocked to prevent alternate power to unit 1 and 3 at the same time.
3. When an overvoltage condition exists at the Generator Output, the 1001 breaker from the MMG Set
trips.
4. Excitation is lost and the MMG Set continues to run.
5. The Hold to build up voltage switch must be depressed to restore voltage.Also
A is incorrect. The MMG set does not automatically shut down. This is plausible because the breaker
lineup is correct.
B is incorrect. The MMG set does not automatically shut down. This is plausible although the breaker
lineup is backwards.
C is correct.
D is incorrect. The breaker lineup is backwards. This is plausible because the MMG Set will continue to
run without excitation.
(
BFN Panel 1-9-8 1-ARP-9-8B
Unit 1 1-XA-55-8B Rev. 0009
( Page 42 of 42
Senso rlTrip Point:
UNIT PFD
SUPPLY Relay SE - loss of normal DC power source .
ABNORMAL Relay TS - DC Xfer switch transfers to Emergency DC Power Source.
Regulating Transformer Common Alarm.
1-INV-252-001 , INVT-1 System Common Alarm .
(Page 1 of 1)
Sensor EL 593' 250V DC Battery Board 2
Location:
Probable A. Loss of normal DC power source
Cause: B. DC power transfer.
C. Relay failure
D. INVT-1 System Common Alarms
1. Fan Failure Rectifier
2. Over temperature Rectifier
3. AC Power Failure to Rectifier
4. Low DC Voltage
5. High DC Voltage
6. Low DC Disconnect
7. Fan Failure Inverter
8. Alternate Source Failure
9. :Low AC Output Voltage
10. High Output Voltage
11. Inverter Fuse Blown
12. Static Switch Fuse Blown
13. Over Temperature Inverter
E. PFD Regulating XFMR Common Alarms
1. Transformer Over temperature
2. Fan Failure
3. CB1 Breaker Trip
4. CB2 Breaker Trip
Automatic A. Auto transfer to DC Power Source on Rectifier failure .
Action: B. Auto transfer to Alternate AC supply (Regulated Transformer) on Inverter failure.
Operator A. IF 120V AC Unit Preferred is lost, THEN
Action: REFER TO 1-AOI-57-4 , Loss of Unit Preferred . o
B. REFER TO appropriate portion of 0-OI-57C, 208V/120V AC
Electrical System. o
References: 0-45E641-2 1-45E620-11 1-3300D15A4585-1
10-100467 0-20-100756 20-110437
OPL171.102
Revision 6
Page 20 of 69
(
(d) Another Unit's MMG set
The second alternate is from
another unit's MMG set
output. Unit 2 MMG is the
second alternate for either
Unit 1 or Unit 3; Unit 3 is the
second alternate for Unit 2.
Transfers to this source are
done manually at Battery
Board 2 panel 11.
b. MMG Sets (Unit 2&3) Obj. V.B.2.b
(1) The MMG is normally driven By the Obj'v.D.2.c
AC motor, powered from 480V Obj.V.D.2.d/j
Shutdown Board A. Should this Obj V.E.2.c
supply fail, the AC motor is Obj'v.E.2.d/i
automatically disconnected and the Obj V.B.2.h
DC motor starts, powered from Obj'v.C.3.e
250V Battery Board. The DC Obj'v.D.2.j
motor has an alternate power Obj'v.E.2.i
supply from another 250V Battery
Board. Transfer to the alternate
DC source is manual.
Underfrequency on the generator
output will trip the DC motor.
Transfer of the MMG set back to
the AC motor is manual.
(2) The 1001 and 1003 breakers from
an MMG set will trip on overvoltage
or underfrequency at the output of
the MMG. Also Unit 2 MMG
Breakers are interlocked to prevent
alternate power to unit 1 and 3 at
the same time.
OPL171.102
Revision 6
Page 21 of 69
(3) When an under frequency or Obj. V.B.2.h
overvoltage condition exists at the Obj. V.C.3.e
Generator Output the following Obj. V.D.2.j
occurs Obj. V.E.2.i
(a) BB panel 10 breakers from
the MMG Set trip.
U2 1001 (U2) 1003 (U1&3)
U3 1001 (U3) 1003 (U2)
(b) Excitation is lost and the
MMG Set continues to run.
(The Hold to build up
voltage switch must be
depressed to restore
voltage.)
21 . RO 263000KI .02 00 I/MEMlT2G I1250VDC/3/263000KI .02//RO/SROI
Wh ich ONE of the following statements describes the operat ion of 250 VDC Battery Charger 2B?
( A. The normal power supply to Battery Charger 2B is 480V Common Board 1.
8. Battery Charger 2B can supply . directly from unit 2 Battery Board room, any of the six Unit & Plant
250VDC battery boards.
C. Battery Charger 2B is capable of supplying two Battery Boards simultaneously.
0 . 01 Load shedding of the battery charger can be bypassed by placing the Emergency ON select
switch in the Emergency ON Position.
KIA Statement:
263000 DC Electrical Distribution
K1.02 - Knowledge of the physical connections and/or cause - effect relationships between D.C.
ELECTRICAL DISTRIBUTION and the following : Battery charger and battery
KIA Justification: This question satisfies the KIA statement by requiring the candidate to use specific
knowledge of battery charger operation.
References : OPL 171.037
Level of Knowledge Justification: This question is rated as MEM due to the requ irement to recall
or recognize discrete bits of information.
0610 NRC Exam
REFERENCE PROVIDED: None
Plausibility Analysis:
In order to answer this question correctly the cand idate must determine the following:
1. Normal and Alternate power to Battery Charger 2B.
2. Loads capable of being supplied by Battery Charger 2B.
3. Load Shedd ing logic and bypass capability.
A is incorrect. This is plausible because 480V Common Board 1 is the Alternate supply to Battery
Charger 2B.
B is incorrect. This is plausible because Battery Charger 2B is capable of supplying any of the six 250V
Battery Boards, but NOT directly from Unit 2 Battery Board Room.
C is incorrect. Th is is plaus ible because Battery Charger 2B is sufficiently large enough to support the
loads , but mechanical interlocks prevent closing more than one output feeder breaker.
D is correct.
(
OPL 171.037
Revision 10
Page 11 of 70
(2) The Plant/Station Batteries (4, 5, and 6) are Obj V.B.1
( Class Non-1 E and are utilized primarily for U-2, Obj. V.C.1
U-1, and U-3 respectively --for normal loads Obj. V.D.1
(3) Battery (4) Room is located on Unit 3 in the
Turbine Building on Elev. 586
(4) Battery (5 & 6) Rooms are located on the
Turbine Floor, Elev. 617
(5) The boards and chargers for the Unit Batteries
are located in Battery Board Rooms adjacent
to the batteries they serve, with the spare
charger being in the Unit 2 Battery Board
room. (Battery Boards 5 & 6 and their
associated chargers are located adjacent to
the batteries, but are in the open space of the
turbine floor.)
c. 250V Plant DC components
(1) Battery charger
(a) The battery chargers are of the solid state
rectifier type. They normally supply loads
on the 250V Plant DC Distribution
System. Upon loss of power to the
charger, the battery supplies the loads.
(b) The main bank chargers only provide
float and equalize charge when tied to
their loads. The chargers are not placed
on fast charge (high voltage equalize)
with any loads attached.
(c) They can recharge a fully discharged
battery in 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> while supplying
normal loads.
(d) Battery charger power supplies are Follow Procedure
manual transfer only.
250V Battery Alternate Source
Normal Source Obj. V.B.2
Charaer (Charger Service bus)
Obj. V.C.2
480V SD Bd 1A 480V Common Bd 1
1 Obj V.D.2
Comp 6D Comp 3A
480V SD Bd 2A 480V Common Bd 1
2A
Comp6D Comp 3A
480V SD Bd 2B 480V Common Bd 1
2B
( Comp6D
480V SD Bd 3A
Comp 3A
480V Common Bd 1
3
Comp 6D Comp3A
OPL171.037
Revision 10
Page 12 of 70
480V SO Bd 3B 480V Common Bd 1
( 4
Com 60 Com 3A
480V Com Bd 1
5 (no alternate)
Com 5C
6 480~o~or;gd 3 (no alternate)
2B spare charger DC output can be directed to any of four
feeders. Three DC outputs can be connected to battery board 1,
2, or 3. The fourth output is connected to a new output transfer TP-2 & TP-7
switch (located in battery board room 4) which charges batteries
4, 5, or 6 plant batteries. A meclianical interlocK permits closing
only: one output feeaer at a time. (A slide bar is utilized in battery Attention to Detail
board room 2 and a Kirk key interlock is used in battery board
room 4
OPL171.037
Revision 10
Page 31 of 70
( XI. Summary
We have discussed in detail the DC Power Systems at BFN.
The electrical design and operation which makes these
systems so reliable has been explained. The various systems
have been described with reference to function, components,
locations, and electrical loads. Power sources have been
identified, and instrumentation has been noted. Significant
control and alarm aspects have also been pointed out.
250V Battery Charger Normal Source Alternate Source
(Charger Service bus)
1 480V SO Bd 1A, Comp 60 480V Common Bd 1, Comp 3A
2A 480V SO Bd 2A Comp 60 480V Common Bd 1, Comp 3A
2B 480V SO Bd 2B, Comp 60 480V Common Bd 1, Comp 3A
3 480V SO Bd 3A, Comp 60 480V Common Bd 1, Comp 3A
4 480V SO Bd 3B, Comp 60 480V Common Bd 1, Comp 3A
5 480V Com Bd 1 Comp 5C (no alternate)
6 480V Com Bd 3 Comp 3D (no alternate)
The 2B spare charger DC output can be directed to any of four feeders. Three DC outputs
can be connected to battery board 1, 2, or 3. The fourth DC output is connected to output
transfer switch (BBR 4) to batteries 4, 5, or 6. Mechanical interlock permits closing only one
output feeder at a time. (A slide bar is utilized in battery board room 2 and a Kirk key interlock
is used in battery board room 4.)
250V DC battery chargers 1, 2A and 2B will load shed upon receipt of a Unit 1 or Unit 2
accident signal and any Unit 1/2 shutdown board being supplied by its respective diesel
generator or cross tied to a Unit 3 shutdown board and a unit three Diesel Generator. 250
VDC Battery Charger 3 will load shed on a unit 3 load shed signal. e oad shedding feature
can be b~ssed by. placing the "Emergency" switCii on the charger. to tfie "EMERG" P.Qsition.
Station Battery charger 4 does not have load shed logic; however, battery charger 4 will
deenergize when 3B 480 SID Board deenergizes and will return when the 480V SID Board
voltage returns.
They also supply alternate control power for Units 1 and 2 4kV Shutdown Boards; however, on
Unit 3, the A, C, and 0 4kV Shutdown Boards receive both normal and alternate control power
from the 250V DC Unit Systems. (3EB receives alternate control power only.) The 250V DC
RMOV Boards are supplied from the Unit Battery Board as follows:
BB-1 supplies 250V RMOV Boards 1A, 2C, 3B.
BB-2 supplies 250V RMOV Bds 2A, 1C, 3C.
OPL171.037
Revision 10
Page 47 of70
( -
480vSO BO 1A
..=. -= -:= -:=
NOR
............
BATTERY
CHARGER
No .1
............
480v SO B02A
............
BATTERY
CHARGER
No.2A
.............
480v SO BO 2B
NOR
............
BATTERY
CHARGER ~
en
No.2B 0:
w
u..
ALT en
z
1 ************ -
~
I-
~
480v SO B03A 0..
I-
- )
NOR ,.-------.---i 0
I
- aJ
N
BATTERY
CHARGER *:*
0
I-
No.3
............ ;
480v SO BO 3B
NOR
BATTERY
CHARGER t--------+-----+--+----i--+---;--i----+---+-____
NO.4
1-----' ALT
BATT BATT BATT BATT
BO 1 B02 B03 B04
480v .... ... ........_.. ..................
COMMON
BO 1
TP-2 250V DC Power Distribution
22. RO 264000K5.06 00 l/C/A/T2Gl/82 - DG/9/264000K5.06//RO/SRO/
Given the following plant conditions:
- Unit 2 is operating at Full Power.
( * No Equipment is Out of Service.
- A large leak occurs in the drywell and the following conditions exist:
- Drywell Pressure peaked at 28 psig and is currently at 20 psig.
- Reactor Pressure is at 110 psig.
- Reactor Water Level is at -120 inches
- Offsite power is available .
Which ONE of the following describes the proper loading sequence and associated equipment?
A. II 28 RHR and 28 Core Spray pumps start at 7 seconds after the accident signal is received .
B. RHRSW pumps lined up for EECW start at 14 seconds after the accident signal is received.
c. Core Spray pumps (2A, 28, 2C, 2D) start immediately when voltage is available on the respective
shutdown board.
D. 2C RHR and 2C Core Spray pumps start at 7 seconds after the accident signal is received .
KIA Statement:
( 264000 EDGs
K5.06 - Knowledge of the operational implications of the following concepts as they apply to
EMERGENCY GENERATORS (DIESEUJET): Load sequencing
KIA Justification: This question satisfies the KIA statement by requiring the candidate to use specific
plant conditions and times to correctly determine the effect of.load sequencing on plant equipment
supplied by the Emergency Generators.
References:
Level of Knowledge Justification: This question is rated as CIA due to the requirement to assemble,
sort, and integrate the parts of the question to predict an outcome. This requires mentally using this
knowledge and its meaning to predict the correct outcome .
0610 NRC Exam
REFERENCE PROVIDED: None
Plausibility Analysis:
( In order to answer this question correctly the candidate must determine the following :
1. Load Sequencing is NVA (Normal Voltage Available) and NOT DGVA (DIG Voltage Available).
2. Based on Item 1 above, theproper load sequencing with a Common Accident Signal (CAS) on Unit-2
alone and NOT in addition to a CAS on Unit 1.
A is correct.
B is incorrect. This is plusible because RHRSW pumps all start at 14 seconds if load sequencing is
DGVA.
C is incorrect. This is plausible based on Load Sequencing logic prior to a modification for Unit 1 restart
activities.
D is incorrect. This is plausible because 2-01-74 P&L 3.2.B defines the start time as 7 second
"intervals".
(
OPL171.038
Revision 16
Page 38 of63
( INSTRUCTOR NOTES
(2) Opens diesel output breakers if shut. ou.v.s.s
b. If normal voltage is available, load will ou.v.c.e
sequence on as follows: (NVA) Obj.v.D.15
oejv.s. 15
Time After Accident SID Board SID Board SID Board SID Board
A C B D
, 0- RHR/GS-A_ l
7 RHR/CS B
14 RHR/CS C
21 RHR/CS D
- RHRSW pumps assigned for. EECW automatic start
c. If ormal voltage is NeT- available: (DGVA) ouv.e.s
ouv.c.e
(1) After 5-second time delay, all4kV
Shutdown Board loads except
4160/480V transformer breakers are
automatically tripped.
(2) Diesel generator output breaker closes
when diesel is at speed.
(3) Loads sequence as indicated below
Time After Accident SID Board SID Board SID Board SID Board
A B C D
14 RHRSW* RHRSW* RHRSW* RHRSW*
- RHRSW pumps assigned for EECW automatic start
d. Certain 480V loads are shed whenever an
accident signal is received in conjunction with
the diesel generator tied to the board. (see
OPL171.072)
c.
BFN Residual Heat Removal System 2-01-74
Unit 2 Rev. 0133
( Page 17 of 367
3.2 LPCI (continued)
B. Upon an automatic LPCI initiation with normal power available, RFiR P-ump 2~
starts imme aiately. and 2B, 2C, 2D sequentially start at 7 second intervals.
Otherwise, all RHR pumps start immediately once diesel power is available
(and normal power unavailable).
C. Manually stopping an RHR pump after LPCI initiation disables automatic restart
of that pump until the initiation signal is reset. The affected RHR pump can still
be started manually.
3.3 Shutdown Cooling
A. Prior to initiating Shutdown Cooling, RHR should be flushed to Radwaste until
conductivity is less than 2.0 micromho/cm with less than 0.1 ppm chlorides
(unless directed otherwise by 2-AOI-74-1, Loss of Shutdown Cooling). If CS&S
has been aligned as the keep fill source for two days or more a chemistry
sample should be requested and results analyzed to determine if flushing is
required.
B. When in Shutdown Cooling, reactor temperature should be maintained greater
than 72°F and only be controlled by throttling RHRSW flow. This is to assure
adequate mixing of reactor water.
1. [NER/C] Reactor vessel water temperatures below 68°F exceed the
temperature reactivity assumed in the criticality analysis. [INPO SER 90-017]
2. [NER/C] Maintaining water temperature below 100°F minimizes the release of
soluble activity. [GE SIL 541]
C. Shutdown Cooling operation at saturated conditions (212°F) with 2 RHR pumps
operating at or near combined maximum flow (20,000 gpm) could cause Jet
Pump Cavitation. Indications of Jet Pump Cavitation are as follows:
1. Rise in RHR System flow without a corresponding rise in Jet Pump flow.
2. Fluctuation of Jet Pump flow.
3. Louder "Rumbling" noise heard when vessel head is off.
Corrective action for any of these symptoms would be to reduce RHR flow until
the symptom is corrected.
(
23. RO 300000K2.02 001/MEM/T2Gl/CAI1300000K2.02/2.8/2.8/RO/SR0/1l/16/07 RMS
Which ONE of the follow ing desc ribes the power supplies to the Control and Service Air Compressor
motors?
(
A. "A" and "8" are fed from the 480V Common 8d. #1
"C" and "0" from 480V SID 8d . 18 & 28 , respectively
"G" from 4KV SID 8d . 8 and 480 SO 8d . 2A
"E" from the 480V Common 8d . #1
B. "A" and "0" from 480V Common 8d . 1
"8" and "C" from 480V SID 8d . 18 & 28, respectively
"G" from 4KV SID 8d . 8 and 480V RMOV 8d. 2A
"F" from 480V Common 8d. #3
C. "A" from 480V SID 8d . 18
"8" and "F" from 480V Common 8d . #3
"C" from 480V SID 8d . 1A
"0" from 480V SID 8d . 2A
"G" from 4KV Common 8d .#2
0. 01 "A" from 480V SID 8d . 18
"8" and "C" from 480V Common 8d . #1
"0" from 480V SID 8d . 2A
"G" from 4KV SID 8d. 8 and 480V RMOV 8d . 2A
"E" from 480V Common 8d. #3
KJA Statement:
300000 Instrument Air .
K2.02 - Knowledge of electrical power supplies to the following : Emergency air compressor
KJA Justification: This question satisfies the KIA statement by requiring the candidate to use specific
knowledge of the power supplies of ALL air compressors.
References:
Level of Knowledge Justification: This question is rated as MEM due to the requirement to recall
or recognize discrete bits of information.
0610 NRC Exam
REFERENCE PROVIDED: None
Plausibility Analysis:
( In order to answer this question correctly the candidate must determine the following:
1. Power supplies to six air compressors.
NOTE: Regarding plausibility, all the power supplies listed in the distractors are capable of supplying
power to each air compressor.
A is incorrect. B, G & E are correct. A, C & D are incorrect.
B is incorrect. F & G are correct. A, B, C, & D are incorrect.
C is incorrect. A, D & F are correct. B, C & G are incorrect
D is correct.
OPL 171.054
Revision 12
Page 9 of 72
( X. Lesson Body
A. Control Air System
1. **The purpose of the Control Air System is to process ** SOER 88-1
and distribute oil-free control air, dried to a low dew point Obj . V.E.1
and free of foreign materials. This high-quality air is
required throughout the plant and yard to ensure the
proper functioning of pneumatically operated
instruments, valves, and final operators.
2. Basic Description of Flow Path TP-1
a. The station control air system has 5 air compressors, Obj. V.E.3
each designed for continuous operation. Obj. V.D.1
b. Common header (fed by air compressors A-D and G)
(1) The control air system is normally aligned with the The G air compressor
G air compressor running and loaded. The will be discussed later in
existing A-D air compressors are aligned with one this section of the lesson
in second lead , one in third lead, and at least one plan.
compressor in standby.
(2) 3 control air receivers
(3) 4 dual dryers One for each unit's control air
header (units 1, 2 & 3 through their 4-inch
headers) and One standby dryer supplies the
standby, 3- inch common control air header for all normally aligned to all
three units three units
(4) Outlet from large service air receiver is connected
to the control air receivers through a pressure
control valve 0-FCV-33-1, which will automatically
open to supply service air to the control air
header if control air pressure falls to 85 psig .
c. 4-inch control air header (1 per unit) is supplied from TP-1
each unit dryer and backed up by a common, 3-inch
standby header.
3. Control Air System Component Description
a. Four Reciprocating Air Compressors A-D (2-stage,
double acting, V-type) are located EI 565, U-1
Turbine Building.
(1) Supply air to the control air receivers at 610 scfm
each at a normal operating pressure of 90 - 101
psig.
(2) 480V, 60 Hz, 3-phase, drive motors
( (3) Power supplies
A from 480V Shutdown Board 1B
OPL171 .054
Revision 12
Page 10 of 72
( o from 480V Shutdown Board 2A
B from 480V Common Board 1
C from 480V Common Board 1
(a) Control air compressors which are powered Obj . V .B.1.
from the 480 VAC shutdown boards are Obj . V .C.1.
tripped automatically due to:
i. under voltage on the shutdown board.
ii. load shed logic during an accident signal
concurrent with a loss of offsite power.
NOTE: The compressors must be
restarted manually after power is restored
to the board.
(b) Units powered from common boards also trip
due to under voltage.
(4) Lubrication provided from attached oil system via
gear-type oil pump
(a) Compressor trips on Obj . V .B.2.
lube oil pressure < 10 psig Obj. V .C.2.
or Obj. V .E.12
lube oil temperature >180 of Obj . V .D.10
(b) Compressor cylinder is a non lubricated type
(5) Cooling water is from the Raw Cooling Water
system with backup from EECW
(a) Compressor oil cooler, compressor inter-
cooler, after cooler and cylinder water jackets
(b) Compressor inter-cooler and after cooler
moisture traps drain moisture to the Unit 1
station sump .
NOTE: Cooling water flows to the compressors are regulated Obj. V .B.2.
such that the RCW outlet temperature is maintained Obj . V .C.2.
between 70° F and 100° F. Outlet temperatures Obj. V .E.12
should be adjusted low in the band (high flow rates)
during warm seasons (river temps. ~ 70°F). Outlet
temperatures should be adjusted high in the band
during the cooler seasons (river temps ~ 70°F) to
reduce condensation in the cylinders.
(c) Compressor auto trips if discharge
temperature of air> 310° F.
b. Unloaders Obj. V.D .10
OPL 171.054
Revision 12
Page 14 of 72
( (b) Should both the primary and the backup Cutout switch setpoints
controllers fail, all four compressors will come are set at 112 psig to
on line at full load until these pressure prevent spurious
switches cause the compressors to unload at operation when G air
112 psig. compressor running
(c) When air pressure drops below the high
pressure cutoff setpoint (110.8 psig), the
compressors will again come on line at full
load until the high pressure cutoff switches
cause the compressors to unload.
d. Relief valves on the compressors discharge set at
120 psig protects the compressor and piping.
e. G Air Compressor - centrifugal type, two stage
(1) Located 565' EL Turbine Bldg. , Unit 1 end.
Control Air Compressor G is the primary control
air compressor and provides most of the control
air needed for normal plant operation.
(2) Rated at 1440 SCFM @ 105 psig.
(3) Power Supply
(a) 4 kV Shutdown Board B supplies power to
the compressor motor.
(b) 480 V RMOV Bd. 2A Supplies the following :
- Pre lube pump
- Oil reservoir heater
- Cooling water pumps
- Panel(s) control power
- Auto Restart circuit
(c) Except for short power interruptions on the
480v RMOV Bd, Loss of either of these two
power supplies will result in a shutdown of the
G air compressor.
(4) A complete description of the G Air compressor Cover 01 illustrations
controls and indications can be found in 0-01-32 .
(The G and the F air compressor indications and
Microcontrollers are similar).
(a) UNLOAD MODULATE AUTO DUAL TP-8
handswitch is used to select the mode of
operation for the compressor
OPL171.054
Revision 12
Page 30 of 72
3. Component Description Obj. V.E.6
a. Compressors E and F (EL 565, U-3 Turbine Building) Obj. V.DA
are designated for service air.
b. The F air compressor is rated for approximately 630
SCFM @ 105 psig, centrifugal type, 2 stages
c. The power supply for both compressors is 480VAC
Common Board 3.
d. FIG air compressor comparison
(1) Controls are similar to that of the G air TP-16
compressor. There is no 4KV breaker control on ouv.s.r
the F air compressor control panel. Obj. V.D.5
(2) Control system modulates discharge air pressure Set to control at approx.
in the same manner as is done on the G air 95 psig - Relief Valve is
compressor. set to lift at. ~ 115 psig.
(3) Air system is similar to the G air compressor. A
difference is that the 2 stages of compression are TP-17
driven by one shaft for the F air compressor. On
the G air compressor, there is a separate drives;
one for each of 3 compression stages.
(4) Oil system similar to that on the G air compressor TP-18
with exception of location of components and
capacity. E compressor has an electric oil pump
that runs whenever control power is on.
(5) Cooling system is similar to that on the G air TP-19
compressor with exception of flow rate, location,
and capacity of components.
(6) Loss of power will result in F air compressor trip ,
loss of the pre lube pump, and the cooling water
pumps .
(7) Restart of the compressor can be accomplished
once the compressor has come to a full stop and
any trip conditions cleared and reset.
e. AlarmslTrips
(1) The Alert and Shutdown setpoints for the Fair See for latest setpoints
compressor are listed in 0-01-33.
24. RO 300000K3.0 1 00 lIelA /T2G lISGT/B 1OB/300000 K3 .0 113 .2/3 A/RO/SRO/l l /l 6/07 RMS
A LOCA has occurred on Unit 1 and the drywell is being vented to SBGT, when a loss of the Control Air
system occurs .
( Which ONE of the following describes the operatio n of vent valves 1-FCV-64-29, DRYWELL VENT INBD
ISOL VALVE and 1-FCV-84-19, PATH B VENT FLOW CONT?
A. Both vent valves 1-FCV-64-29 & 1-FCV-84-19 will fail close and can not be operated .
8. Both vent valves 1-FCV-64-29 & 1-FCV-84-19 will auto swap to control from the CAD supply line
with no operator action required.
C.oI Both vent valves 1-FCV-64-29 & 1-FCV-84-19 will auto swap to control from the CAD supply line,
however CAD supply must be manually aligned from the control room .
D. The CAD system must be manually initiated and then vent valves 1-FCV-64-29 & 1-FCV-84-19 may
be realigned to the CAD supply .
KIA Statement:
300000 Instrument Air
K3.01 - Knowledge of the effect that a loss or malfunction of the (INSTRUMENT AIR SYSTEM) will have
on the following: Conta inment air system
KIA Justification: This question satisfies the KIA statement by requiring the candidate to use specific
plant conditions to determine the effect on the conta inment air system due to a loss of Control Air.
References: 1-EOI Appendicies 8G and 12, 1-AOI-32-2
Level of Knowledge Justification: This question is rated as CIA due to the requirement to assemble ,
sort, and integrate the parts of the question to predict an outcome . This requires mentally using this
knowledge and its meaning to predict the correct outcome.
0610 NRC Exam
REFERENCE PROVIDED: None
Plausibility Analysis:
In order to answer this question correctly the candidate must determine the following :
1. Whether the vent valves automatically swap to be supplied by CAD or must be manuall y aligned.
2. Whether CAD supply to DW Control Air automatically swaps or must be manually aligned .
A is incorrect. This is plausible because the vent valves DO fail closed, however, they can be operated
with manual alignment of the CAD Tanks.
B is incorrect. This is plausible because the vent valves will auto swap to control from the CAD supply
line, howeve r the CAD tanks must be manually aligned.
C is correct.
D is incorrect. This is plausible becase the CAD system must be manually initiated, however once this is
accomplished, no further alignment is necessary.
1*EOI APPENDIX*12
PRIMARY CONTAINMENT VENTING Rev. 0
UNIT 1
( Page 4 ofa
f. VERIFY 1-FIC-84-20, PATH A VENT FLOW CONT, is indicating
approximately 100 scfm.
g. CONTINUE in this procedure at step 12.
10. VENT the Drywell using 1-FIC-84-19, PATH B VENT FLOW CONT, as
follows:
a. VERIFY CLOSED 1-FCV-64-141 , DRYWELL DP COMP
BYPASS VALVE (Panel 1-9-3).
b. PLACE keylock switch 1-HS-84-36, SUPPR CHBR/DW VENT
ISOL BYP SELECT, to DRYWELL position (Panel 1-9-54).
c. VERIFY OPEN 1-FCV-64-29, DRYWELL VENT INBD ISOL
VALVE (Panel 1-9-54).
d. PLACE 1-FIC-84-19, PATH B VENT FLOW CONT, in AUTO
with setpoint at 100 scfm (Panel 1-9-55).
e. PLACE keylock switch 1-HS-84-19, 1-FCV-84-19 CONTROL, in
OPEN (Panel 1-9-55).
f. VERIFY 1-FIC-84-19, PATH B VENT FLOW CONT, is indicating
approximately 100 scfm.
g. CONTINUE in this procedure at step 12.
11. VENT the Drywell using 1-FIC-84-20, PATH A VENT FLOW CONT, as
follows:
a. VERIFY CLOSED 1-FCV-64-141, DRYWELL DP COMP
BYPASS VALVE (Panel 1-9-3).
b. PLACE keylock switch 1-HS-84-35, SUPPR CHBR I DWVENT
ISOL BYP SELECT, to DRYWELL position (Panel 1-9-54).
c. VERIFY OPEN 1-FCV-64-31 , DRYWELL INBD ISOL VALVE
(Panel 1-9-54).
d. VERIFY 1-FIC-84-20, PATH A VENT FLOW CONT, in AUTO
with setpoint at 100 scfm (Panel 1-9-55).
e. PLACE keylock switch 1-HS-84-20, 1-FCV-84-20 ISOLATION
BYPASS, in BYPASS (Panel 1-9-55).
f. VERIFY 1-FIC-84-20, PATH A VENT FLOW CONT, is indicating
approximately 100 scfm.
1-EOI APPENDIX-12
BFN Rev. 0
( UNIT 1
PRIMARY CONTAINMENT VENTING
Page 7 of 8
A ITACHMENT 1
...J
...J
~
o
3:
w
sIt: en
I- 2"
0
W oen &,
>0 0
..... 64-34
I- c>> ~
- E A- N
....eo ~ N
W 0 '?
..... -e
en eo
>-
en -
..... I
z
w
> I
'---
~
0
'?
-e
0 0 '"
'"
....eo
eo
9£-\79
~
en
we::
ClW
e::~
i
~-
Q.u.
o0 ...Jo
...JZ
...J w< o
al en ~en gz
e::< z >-z alO
Ou. e::<
Ou.
1-1- e::i=1-
tl en o~en
I-_~
i5~
e::~ <;
I tll-<
i5 wx
Z J:
ox
I-W
e::>w
1-EOI APPENDIX-8G
Rev. 0
UNIT 1 DRYWELL CONTROL AIR
( Page 1 of 2
LOCATION: Unit 1 Control Room
ATTACHMENTS: None (~
1. OPEN the following valves:
- 0-FCV-84-5, CAD A TANK N2 OUTLET VALVE
(Unit 1, Panel 1-9-54)
- 0-FCV-84-16, CAD B TANK N2 OUTLET VALVE
(Unit 1, Panel 1-9-55).
2. VERIFY 0-PI-84-6, VAPOR A OUTLET PRESS, and 0-PI-84-17 ,
VAPOR B OUTLET PRESS, indicate approximately 100 psig
Panel 1-9-54 and Panel 1-9-55).
3. PLACE keylock switch 1-HS-84-48, CAD A CROSS TIE TO DW
CONTROL AIR, in OPEN (Panel 1-9-54).
4. CHECK OPEN 1-FSV-84-48, CAD A CROSS TIE TO DW CONTROL
AIR, (Panel 1-9-54).
5. PLACE keylock switch 1-HS-84-49, CAD B CROSS TIE TO DW
CONTROL AIR, in OPEN (Panel 1-9-55).
6. CHECK OPEN 1-FSV-84-49, CAD B CROSS TIE TO DW CONTROL
AIR (Panel 1-9-55).
7. CHECK MAIN STEAM RELIEF VLV AIR ACCUM PRESS LOW,
1-PA-32-31, alarm cleared (1-XA-55-3D, Window 18).
8. IF MAIN STEAM RELIEF VLV AIR ACCUM PRESS LOW,
1-PA-32-31, annunciator is or remains in alarm
(1-XA-55-3D, Window 18),
THEN DETERMINE which Drywell Control Air header is
depressurized as follows:
a. DISPATCH personnel to Unit 1, RB, EI 565 ft, to MONITOR the
following indications for low pressure:
- 1-PI-084-0051, DW CONT AIR N2 SUPPLY PRESS
indicator, for CAD A (RB, EI. 565, by Drywell Access
Door),
- 1-PI-084-0050, DW CONT AIR N2 SUPPLY PRESS
indicator, for CAD B (RB, EI. 565, left side of 480V RB
Vent Board 1B).
BFN Loss Of Control Air 1-AOI-32-2
Unit 1 Rev. 0001
( Page 5 of 27
2.0 SYMPTOMS (continued)
- REACTOR CHANNEL A(B) AUTO SCRAM annunciator, (1-XA-55-5B,
Window 1(2)) in alarm .
- MAIN STEAM RELIEF VLV AIR ACCUM PRESS LOW annunciator,
(1-XA-55-3D, Window 18) in alarm .
3.0 AUTOMATIC ACTIONS
A. U-1 TO U-2 CONT AIR CROSSTIE, 1-PCV-032-3901, will CLOSE to separate
Units 1 & 2 when control Air Header Control Air Header pressure reaches
65 psig lowering at the valve.
B. UNIT 2 TO UNIT 3 CONTROL AIR CROSSTIE, 2-PCV-032-3901, will CLOSE
to separate Units 2 and 3 when Control Air Header pressure reaches 65 psig
lowering at the valve.
C. CAD SUPPLY PRESS REGULATOR, 1-PCV-084-0706, will select nitrogen
from CAD Tank A at s 75 psig Control Air pressure to supply the following:
1. SUPPR CHBR VAC RELIEF VALVE , 1-FSV-064-0020
2. SUPPR CHBR VAC RELIEF VALVE, 1-FSV-064-0021
D. INST GAS SELECTOR VALVE, 1-PCV-084-0033, will select nitrogen from CAD
Tank A to supply the following:
1. DRYWELL OR SUPPRESS CHMBR EXHAUST TO SGTS,
1-FSV-084-0019
2. DRYWELL VENT INBD ISOL VALVE, 1-FSV-064-0029
3. SUPPR CHMBR VENT INBD ISOL VALVE, 1-FSV-064-0032
E. INST GAS SELECTOR VALVE, 1-PCV-084-0034, will select nitrogen from CAD
Tank B to supply the following:
1. DRYWELL OR SUPPRESS CHMBR EXHAUST TO SGTS,
1-FSV-084-0020
2. DRYWELL INBD ISOLATION VLV, 1-FSV-064-0031
3. SUPPR CHBR INBD ISOLATION VLV, 1-FSV-064-0034.
BFN Loss Of Control Air 1-AOI-32-2
Unit 1 Rev. 0001
( Page 7 of 27
4.2 Subsequent Actions (continued)
NOTE
CNDS BSTR PMPS DISCH BYPASS TO COND 1C, 1-FCV-002-0029A and CNDS BSTR
PMPS DISCH BYPASS TO COND 1B, 1-FCV-002-0029B both fail CLOSED on a loss of
control air.
[3] IF there is NOT a flow path for Condensate system, THEN
STOP the Condensate Pumps and Condensate Booster
Pumps. REFER TO 1-01-2. o
[4] IF any Outboard MSIV closes, THEN
PLACE the associated handswitch on Panel 1-9-3 in the
CLOSE position. o
NOTE
RSW STRG TNK ISOLATION, 0-FCV-25-32, fails CLOSED on loss of control air.
[5] START a High Pressure Fire Pump. REFER TO 0-01-26. 0
[6] OPEN CAD SYSTEM A N2 SHUTOFF VALVE, 0-FCV-84-5, at
Panel 1-9-54. 0
[7] OPEN CAD SYSTEM B N2 SHUTOFF VALVE, 0-FCV-84-16,
at Panel 1-9-55. 0
[8] CHECK RCW pump motor amps and PERFORM Steps
4.2[8.1] through 4.2[8.5]to reduce RCW flow:
25. RO 400000A2.02 OO l/C/A/T2G I/RBCCW//400000A2 .02/3.8/4.I/RO/SRO/ll /l6/07 RMS
With Unit 2 operat ing at power, the following changes are observed:
- RBCCW Temperature lower than normal.
( - Annunc iator 2-XA -55-4C-6 RBCCW Surge Tank High Level is in alarm.
Wh ich ONE of the following describes a cause for these indications and the corrective action required?
A. Reactor Recirculation Pump seal cooler leak into RBCCW. Trip and isolate the Recirculation Pump.
B.oI RCW leak in the RBCCW heat exchanger(s). Remove RBCCW from service follow ing unit
shutdown .
C. RWCU leak into RBCCW via non-regenerative heat exchanger. Isolate RWCU.
D. Drywell equipment drain sump heat exchanger leak into RBCCW. Isolate DW Equipment Drain
Sump heat exchanger.
KIA Statement:
400000 Component Cooling Water
A2.02 - Ability to (a) predict the impacts of the follow ing on the CCWS and (b) based on those
predictions , use procedures to correct, control, or mitigate the consequences of those abnormal
operation: High/low surge tank level
KIA Justification: This question satisfies the KIA statement by requiring the candidate to use specific
plant conditions to determine the effect of a leak into the RBCCW system and determine which procedure
addresses this condition .
References:
Level of Knowledge Justification: This question is rated as CIA due to the requirement to assemb le,
sort, and integrate the parts of the question to predict an outcome. This requires mentally using this
knowledge and its meaning to predict the correct outcome.
0610 NRC Exam
REFERENCE PROVIDED: None
Plausibility Analysis:
In order to answer this question correctly the candidate must determine the follow ing:
1. Which leak path would provide the indications given in the question stem .
2. What actions would be required to mitigate the problem .
NOTE: All distracto rs are plaus ible leak paths into RBCCW but would indicate higher temperatures.
A is incorrect. A Reactor Rec irculation Pump seal cooler leak would cause RBCCW temperature to rise.
B is Correct.
C is incorrect. A RWCU leak would cause RBCCW temperature to rise.
D is incorrect. A DW Equipment Drain Sump HX leak would cause RBCCW temperature to rise.
Unit 1 1-XA-55-4C Rev. 0015
( Page 12 of 43
SensorlTrip Point:
SURGE TANK
LEVEL HIGH 1-LS-070-0002A 4 Inches Above Center Line of Tank
1-LA-70-2A
(Page 1 of 2)
Sensor RBCCW surge tank on the fourth floor in the M-G set room .
Location:
Probable A. Makeup valve 1-FCV-70-1 open.
Cause: B. Bypass valve 1-2-1369 leaking.
<'S . Leak into the system.
Automatic None
Action:
Operator A. VERIFY make-up valve 1-FCV-70-1 closed, using RBCCW SYS
Action: SURGE TANK FILL VALVE, 1-HS-70-1 , on Panel 1-9-4. o
B. CHECK RBCCW PUMP SUCTION HDR TEMP, 1-TIS -70-3,
indicates water temperature is 100°F or less , on Panel 1-9-4. o
C. DISPATCH personnel to verify high level , ensure bypass valve,
1-2-1369, is closed and observe sight glass level. o
D. OPEN surge tank drain valve , 1-70-609, then CLOSE valve when
desired level is obtained. o
E. REQUEST Chemistry to pull and analyze a sample for total gamma
activity and attempt to qualify source of leak. o
F. CHECK activity reading on RM-90-131D. o
Continued on Next Page
c.
Unit 1 1-XA-55-4C Rev. 0015
( Page 13 of 43
RBCCW SURGE TANK LEVEL HIGH 1-LA-70-2A, Window 6
(Page 2 of 2)
Operator
Action: (Continued)
NOTE
[NERlC] Reactor Recirculation Pump seal cooler leakage may be indicated by a rise in 1-RM-90-131
(Panel 1-9-10) activity (1-RR-90-131/132 Panel 1-9-2) or 1-TE-68-54 or 67 temperature
(Panel 1-9-21) or lowering of any Recirc pump seal pressure.
G. IF it is suspected that the Reactor Recirculation Pump seal cooler is
leaking, THEN
PERFORM the following:
- DETERMINE which Reactor Recirculation loop is leaking and at
the discretion of the Unit Supervisor, ISOLATE. REFER TO
1-01-68 Section 7.1 or 8.2 as applicable. COOLDOWN is
required to prevent hanger or shock suppressors from exceeding
their maximum travel range. 0
- WHEN primary system pressure is below 125 psig and at the
discretion of the Unit Supervisor, THEN
ISOLATE the RBCCW System to preclude damage to the
RBCCW PIPING.[IEN 89-054 , GE SIL-459) 0
H. START selective valving to determine in-leakage source, if present. 0
References: 1-45E620-4 1-47E610-70-1
FSAR Section 10.6.4 and 13.6.2
(
26. RO 400000G2.4.31 00 lICfA/T2G 1IRBCCWff4000002.4.3Of/ROfSRO/NO
Unit 3 is at 100% rated power with the following indications :
- RECIRC PUMP MTR B TEMP HIGH (3-ARP-9-4B W13) in alarm.
- RBCCW EFFLUENT RADIATION HIGH (3-ARP-9-3A W17) in alarm .
- RBCCW SURGE TANK LEVEL HIGH (3-ARP-9-4C W6) in alarm .
- RX BLDG AREA RADIATION HIGH (3-ARP-9-3A W22) in alarm.
rising.
- AREA RADIATION MONITOR RE-90-13 and RE-90-14 are in alarm reading 55 mrlhr and rising.
Which ONE of the following describes the action(s) that should be taken?
REFERENCE PROVIDED
A. 01 Enter 3-EOI-3, Secondary Containment Control. Trip and isolate 3B Recirc Pump . Commence a
normal shutdown and cooldown in accordance with 3-GOI -100-12A, Unit Shutdown .
B. Enter 3-EOI-3, Secondary Containment Control. Trip and isolate 3B Recirc Pump. Enter 3-EOI-1 ,
RPV Control at Step RC-1 .
C. Trip RWCU pumps and isolate RWCU system. Close RBCCW Sectionalizing Valve 3-FCV-70-48
to isolate non-essential loads and maximize cooling to 3B Recirc . Pump . EOI entry is not required.
D. Enter 3-EOI-3 , Secondary Containment Control. Trip RWCU pumps and isolate RWCU system.
Commence a normal shutdown in accordance with 3-GOI-100-12A, Unit Shutdown .
KIA Statement:
400000 Component Cooling Water
2.4.31 - Emergency Procedures I Plan Knowledge of annunciators alarms and indications, and use of the
response instructions.
KIA Justification: This question satisfies the KIA statement by requiring the candidate to use specific
plant conditions to determine the corrective actions required due to an emergency involving RBCCW
based on annunciators and indications.
References: 3-EOI-3 flowchart, 3-ARP 9-3 and 3-ARP-9-4
Level of Knowledge Justification: This question is rated as CIA due to the requirement to assemble ,
sort, and integrate the parts of the question to predict an outcome. This requires mentally using this
knowledge and its meaning to predict the correct outcome.
( 0610 NRC Exam
REFERENCE PROVIDED: 3-EOI-3 flowchart
Plausibility Analysis:
( In order to answer this question correctly the candidate must determine the following:
1. EOI Entry is required solely based on ARM alarms.
2. Location of the leak is from the 3B Recic Pump.
3. RWCU temperature indications are due to insufficient cooling by RBCCW, not a RWCU leak.
4. Appropriate actions per 3-EOI-3 are to isolate the leak and monitor radiation levels.
5. Justification for Unit Shudwon and Cooldown are due to the Recirc Loop being isolated at rated
temperature and pressure (pipe hanger and support issue), and NOT Directed by 3-EOI-3.
A is correct.
B is incorrect. Entering 3-EOI-1 to initiate a scram is NOT required until radiation levels approach 1000
mr/hr in any area. This is plausible becuase the location of the leak and required isolation are correct.
C is incorrect. This is plausible if the candidate incorrectly determines that RWCU is causing the
temperature issues with 3B Recirc Pump and not vice versa . If RWCU was the leak location, the
RBCCW temperature would not be high enough to provide the given indications. The leak would have to
have occurred in the NRHX which is below the indicated RBCCW temperature.
D is incorrect. This is plausible if the candidate incorrectly determines that RWCU is causing the
temperature issues with 3B Recirc Pump and not vice versa . In addition to the justification above,
commencing a shutdown in accordance with 3-EOI-3 is not appropriate until ARMs indicate greater than
1000 mr/hr.
(
OPL 171.047
Revision 12
Appendix C
Page 35 of 41
(
DEMIN
WATER ----.,r-I~>l<lh
MAKEUP
DRW
RCW
- ,II1II""* *"" TCV'S
RCW
I&lfiI~~**~~f:J---+-"OUTLET
RETURN ",--====-__ J 601 RCW
U2-11.....-1 .""",,~n TCV'S
623
626
.................. ................
0-70-607
CHEMICAL
FEED RCW
t-_........
633
U2 TCV'S
' - -........
638 U3
SUPPLY
67 69
U2 U3
68 70
TP-1: RBCCW SYSTEM FLOW DIAGRAM
8FN Panel 9-4 3-ARP-9-48
Unit 3 3-XA-55-48 Rev. 0036
( Page 17 of 45
SensorlTrip Point: Alarm is from 3-TR-68-84, Panel 3-9-2
RECIRC 3-TE-68-73A RECIRC PMP MTR 3B-THR BRG UPPER FACE (190°F)
PUMP MTR B 3-TE-68-73C RECIRC PMP MTR 3B-THR BRG LOWER FACE (190°F)
TEMP HIGH 3-TE-68-73E RECIRC PMP MTR 3B-UPPER GUIDE BRG (190°F)
3-TA-68-84 3-TE-68-73N RECIRC PMP MTR 3B-LOWER GUIDE BRG (190°F)
3-TE-68-73G RECIRC PMP MTR 3B-MOTOR WINDING A (216°F)
3-TE-68-73J RECIRC PMP MTR 3B-MOTOR WINDING B (216°F)
(Page 1 of 1) 3-TE-68-73L RECIRC PMP MTR 3B-MOTOR WINDING C (216°F)
3-TE-68-73T RECIRC PMP MTR 3B-SEAL NO.2 CAVITY(180°F)
3-TE-68-73U RECIRC PMP MTR 3B-SEAL NO.1 CAVITY(180°F)
3-TE-68-67 RECIRC PMP MTR 3B-CLG WTR FROM SEAL CLG (140°F)
3-TE-68-70 RECIRC PMPMTR 3B-CLG WTR FROM BRG (140°F)
Sensor Temperature elements are located on recirculation pump motor, Elevation 563.12,
Location: Unit 3 drywell.
Probable A. Possible bearing failure.
Cause: B. Possible motor overload.
C. Insufficient cooling water.
D. Possible seal failure.
E. High drywell temperature.
Automatic None
Action:
Operator A. . CHECK following on Panel 3-9-4: o
Action: * RBCCW PUMP SUCTION HDR TEMP temperature indicating
switch, 3-TIS-70-3 normal (summer 70-95°F, winter 60-80°F). o
(3-FCV-70-47) OPEN. o
B. CHECK the temperature of the cooling water leaving the seal and
bearing coolers < 140°F on RECIRC PMP MTR 3B WINDING AND
BRG TEMP temperature recorder, 3-TR-68-84 on Panel 3-9-21 . 0
C. LOWER recire pump speed until Bearing and/or Winding
temperatures are below the alarm setpoint. 0
D. CONTACT Site Engineering to PERFORM a complete assessment
and monitoring of all seal conditions particularly seal leakage,
temperature, and pressure of all stages for Recirc Pump seal
temperatures in excess of 180°F. 0
References: 3-45E620-5 3-47E610-68-1 Tech Spec 3.4.1
GE 731E320RE 3-SIMI-68B FSAR Section 13.6.2
Unit3 3-XA-55-3A Rev. 0036
( Page 25 of 51
SensorlTrip Point:
RBCCW EFFLUENT
RADIATION
HIGH
ill HI-HI
RE-90-131D (NOTE 2) (NOTE 2)
3-RA-90-131 A
Hi alarm from recorder
Hi-Hi alarm from drawer
(Page 1 of 2)
(2) Chemlab should be contacted for current setpoints per 0-TI-45.
Sensor RE-90-131A RBCCW HX Rx Bldg, EI593, R-20 S-L1NE
Location:
Probable HX tube leak into RBCCW system.
Cause:
Automatic None
Action:
Operator A. DETERMINE cause of alarm by observing following:
Action: 1. RBCCWand RCW EFFLUENT RADIATION recorder,
3-RR-90-131/132 Red pen on Panel 3-9-2. o
2. RBCCW EFFLUENT OFFLINE RAD MON, 3-RM-90-131D on
Panel 3-9-10. o
B. NOTIFY Chemistry to sample RBCCW for total gamma activity to
verify condition. 0
C. START an immediate investigation to determine if source of leak is
RWCU Non-regenerative, Fuel Pool Cooling, Reactor Water Sample
or RWCU Recirc Pump 3A or 3B Seal Water heat exchanger(s). 0
D. (NERlC] CHECK Following for indication of Reactor Recirculation
Pump Seal Heat Exchanger leak:
1. LOWERING in reactor Recirculation pump 3A(3B) NO.1 or 2
SEAL, 3-PI-68-64A or 3-PI-68-63A (3-PI-68-76A or 3-PI-68-75A)
on Panel 3-9-4. 0
2. Temperature rise on CLG WTR FROM SEAL CLG TE-68-54, on
RECIRC PMP MTR 3A WINDING AND BRG TEMP temperature
recorder, 3-TR-68-58 , on Panel 3-9-21. 0
3. Temperature rise on CLG WTR FROM SEAL CLG TE-68-67, on
RECIRC PMP MTR 3B WINDING AND BRG TEMP temperature
recorder, 3-TR-68-84, on Panel 3-9-21. 0
Continued on Next Page
Unit 3 3-XA-55-3A Rev. 0036
( Page 26 of 51
RBCCW EFFLUENT RADIATION HIGH 3-RA-90-131A, Window 17
(Page 2 of 2)
Operator
Action: (Continued)
E. IF it is determ ined the source of leakage is from Reactor Recirc
Pump A(B) , THEN
1. ISOLATE Reactor Recirculation Loop A(B) per 3-01-68, as
applicable. 0
NOTE
Cooldown is required to prevent hangers or shock suppressors from exceeding their maximum travel
range.
2. WHEN primary system pressure is less than 125 psig, THEN
ISOLATE RBCCW System to preclude damage to RBCCW
piping. [lEN 89-054 , GE SIL-459 ) 0
References: 3-45E620-3 3-47E610-90-3 GE 3-729E814-3
Unit3 3-XA-55-3A Rev. 0036
Page 32 of 51
SensorlTrip Point:
RX BLDG AREA
RADIATION RI-90-4A RI-90-23A For setpoints REFER TO
HIGH 3-SIMI-90B.
RI-90-8A RI-90-24A
3-RA-90-1D
RI-90-9A RI-90-25A
RI-90-13A RI-90-26A
RI-90-14A RI-90-27A
(Page 1 of 2)
RI-90-20A RI-90-28A
RI-90-21A RI-90-29A
RI-90-22A
Sensor RE-90-4 MG set area Rx Bldg EI. 639 R-17 Q-L1NE
Location: RE-90-8 Main Control Room Rx Bldg EI. 617 R-16 R-L1NE
RE-90-9 Clean-up System Rx Bldg EI. 621 R-16 T-L1NE
RE-90-13 North Clean-up Sys. Rx Bldg EI. 593 R-16 P-L1NE
RE-90-14 South Clean-up Sys. Rx Bldg EI. 593 R-16 S-L1NE
RE-90-20 CRD-HCU West Rx Bldg EI. 565 R-16 R-L1NE
RE-90-21 CRD-HCU East Rx Bldg EI. 565 R-20 R-L1NE
RE-90-22 Tip Room Rx Bldg EI. 565 R-19 P-L1NE
RE-90-23 Tip Drive Rx Bldg EI. 565 R-19 P-L1NE
RE-90-24 HPCI Room* Rx Bldg EI. 519 R-21 U-L1NE
RE-90-25 RHR West Rx Bldg EI. 519 R-16 U-L1NE
RE-90-26 Core Spray-RCIC Rx Bldg EI. 519 R-16 N-L1NE
RE-90-27 Core Spray Rx Bldg EI. 519 R-20 N-L1NE
RE-90-28 RHR East Rx Bldg EI. 519 R-20 U-L1NE
RE-90-29 Suppression Pool . Rx Bldg EI. 519 R-19 U-L1NE
- Due to the location of the Rad Monitor in relation to the Test line in the HPCI
Quad, the HPCI Room Rad Alarm may be received when the HPCI Flow test
is in progress.
Probable Radiation levels have risen above alarm set point. HPCI Flow Rate Surveillance in
Cause: Progress.
Automatic None
Action:
Continued on Next Page
Unit3 3-XA-55-3A Rev. 0036 *
( Page 33 of 51
RX BLDG AREA RADIATION HIGH 3-RA-90-1D, Window 22
(Page 2 of 2)
Operator A. DETERMINE area with high radiation level on Panel 3-9-11. (Alarm
Action: on Panel 3-9-11 will automatically reset if radiation level lowers
below setpoint.) o
B. IF the alarm is from the HPCI Room while Flow testing is being
performed, THEN
REQUEST personnel at the HPCI Quad to validate conditions. o
C. NOTIFY RADCON. o
D. IF the TSC is NOT manned and a "VALID" radiological condition
exists ., THEN
USE public address system to evacuate area where high airborne
conditions exist o
E. IF the TSC is manned and a "VALID" radiological condition exists,
THEN
REQUEST the TSC to evacuate non-essential personnel from
affected areas. o
F. MONITOR other parameters providing input to this annunciator
frequently as these parameters will be masked from alarming while
this alarm is sealed in. o
G. IF a CREV initiation is received, THEN
1. VERIFY CREV A(B) Flow is ~ 2700 CFM, and ~ 3300 CFM as
indicated on 0-FI-031-7214(7213) within 5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> of the CREV
initiation. [BFPER 03-017922] o
2. IF CREV A(B) Flow is NOT ~ 2700 CFM, and s 3300 CFM as
indicated on 0-FI-031-7214(7213) THEN
PERFORM the following : (Otherwise N/A)
[BFPER 03-017922]
a. STOP the operating CREV per 0-01-31. o
b. START the standby CREV per 0-01-31. o
H. IF alarm is due to malfunction, THEN
REFER TO 0-01-55. o
I. ENTER 3-EOI-3 Flowchart. o
J. REFER TO 3-AOI-79-1 or 3-A01-79-2 if applicable. o
References: 3-45E620-3 3-45E61 0-90-1 GE 730E356-1
Unit 3 3-XA-55-4C Rev. 0028
( Page 12 of 44
SensorlTrip Point:
SURGE TANK
LEVEL HIGH 3-LS-070-0002A 4 inches above center line of tank
3-LA-70-2A
(Page 1 of 2)
Sensor RBCCW surge tank in the MG set room EI 639'.
Location:
Probable A. Makeup valve, 3-FCV-70-1, open.
Cause: B. Bypass valve 3-BYV-002-1369 leaking.
C. Leak into the system.
Automatic None
Action:
Operator A. CHECK make-up valve 3-FCV-70-1, 3-HS-70-1, CLOSED on
Action: Panel 3-9-4. o
B. CHECK RBCCW system water leaving the RBCCW system heat
exchangers is 100°F or less on 3-TI-70-3, Panel 3-9-4. n
C. DISPATCH personnel to verify high level and to ensure
3-BYV-002-1369, FCV-70-1 BYPASS VALVE is CLOSED.
OBSERVE sight glass level. o
D. OPEN surge tank drain valve, 3-DRV-070-0609. CLOSE valve
when desired level is obtained. o
E. REQUEST Chemistry to pull and analyze a sample for total gamma
activity and attempt to qualify source of leak. o
F. CHECK activity reading on 3-RM-90-131 Band 3-RM-90-131 D. o
Continued on Next Page
Unit 3 3-XA-55-4C Rev. 0028
( Page 13 of 44
RBCCW SURGE TANK LEVEL HIGH 3-LA-70-2A, Window 6
(Page 2"of 2)
Operator
Action: (Continued)
NOTE
[NER/C) Reactor Recirculation Pump seal cooler leakage may be indicated by a rise in 3-RM-90-131
(Panel 3-9-10) activity (3-RR-90-131 /132, Panel 3-9-2 or 3-TE-68-54 or 67 temperature,
Panel 3-9-21) or a lowering in any Recirc pump seal pressure .
G. IF it is suspected that the Reactor Recirculation Pump seal cooler is
leaking, THEN
PERFORM the following:
- DETERMINE which Reactor Recirculation loop is leaking and
ISOLATE. REFER TO 3-01-68 Section 7.1 or 8.2 as applicable.
Cooldown is required to prevent hangers or shock suppressors
from exceeding their maximum travel range. 0
- WHEN primary system pressure is below 125 psig, THEN
ISOLATE the RBCCW System to preclude damage to the
RBCCW piping. [IEN89 -054 , GE SIL-459) 0
H. START select ive valving to determine in-leakage source , if present.
References: 3-45N620-4 3-47E610-70-1 3-47E822-1
FSAR Sections 10.6.4 and 13.6.2
OPL 171.034
Revision 11
Append ix C
Page 30 of 30
(
EOI - 3
TABLE 4
SECONDARY CONTAINMENT AREA RADIATION
APPLICABLE MAX NORMAL MAX SAFE POTENTIAL
AREA RADIATION VALUE VALUE ISOLATION
INDICATORS MRIHR MR/HR SOURCES
RHR SYS I PUMPS90-25A A LARMED 1000 FCV -74-47, 48
RHR SYS II PUMPS ALARMED 1000 FCV-74 -47,48
90-2BA
FCV-73- 44
CS SYS I PUMPS 1000
90-26A ALARMED FCV -71 -2, 3, 39
RCIC ROOM
CS SYS II PUMPS90-27A A LAR MED 1000 NO'l E
FCV-73 -2 , 3 , 81
90-29A FCV-74 -47 , 48
GENERAL AREA
FCV-71 -2, 3
RB EL 565 W 90-20A ALARMED 1000 FCV -69-1, 2, 12
SD V V ENTS & DRAI NS
RB EL 565 E 90-2 1A ALARMED 1000 SDV VENTS & DRAI NS
RB EL 565 NE AL A RM ED 1000 NO'l E
TIP ROOM 90-22A ALAR MED 100 ,000 TI P BAL L VALVE
RB EL 593 A LA RM ED 1000 FCV -74 -47 ,48
90-13A, 14A
RB EL 621 ALARMED 1000 FCV-43-13 , 14
90-9A
REC IRC MG SETS 90-4A ALARMED 1000 NO'lE
REFUEL FLOOR 90-1A , 2A, 3A ALARMED 1000 NO'l E
TP -7 EOI-3 TABLE 4
E MINATION
REFERENCE
.PROVIDED TO
CANDIDATE
(
-ow
C")
~
il,H-t1UIIrrrn
I
SlH"tt rr-r<l I I I I
-
~
oau
~ 1!l1 !! !! I
-! I
iii I
III!
- i ,I: II.
iii! II 1
I I iI iii I 1111 I or
II
I r It ..
I IIi
I I' I'"III!
I!! I II II I
C")
I -*
ow
27. RO 201003K3.03 OOl/MEM/TIG2/85-3/Bl1/201003K3.03/3.6/3.7/RO/SR0/1 1/l6/07 RMS
Given the following plant conditions :
- AOI 85-3, CRD System Failure, directs a manual scram based on low reactor pressure.
(
Which ONE of the following PROCEDURAL reactor pressure limits should be adhered to in this case and
WHY?
A. 980 psig reactor pressure, because this would be the lowest pressure a scram can be ensured due
to the loss of accumulators.
B.oI 900 psig reactor pressure, because this would be the lowest pressure a scram can be ensured due
to the loss of accumulators.
C. 445 psig reactor pressure, because this would be the lowest pressure required to lift a control rod
blade.
D. 800 psig reactor pressure, because this is the Technical Specification pressure for scramming
control rods for scram time testing .
KIA Statement:
201003 Control Rod and Drive Mechanism
K3.03 - Knowledge of the effect that a loss or malfunction of the CONTROL ROD AND DRIVE
MECHANISM will have on following : Shutdown margin
KIA Justification: Th is question satisfies the KIA statement by requiring the candidate to use specific
knowledge of CRD mechanism limitations and the basis for that limitation related to the ability to effect
and maintain shutdown margin.
References: 1/2/3-AOI-85-3, OPL 171.005, OPL171.006
Level of Knowledge Justification: This question is rated as MEM due to the requ irement to recall
or recognize discrete bits of information.
06 10 NRC Exam
REFERENCE PROVIDED: None
Plausibility Analysis:
( In order to answer this question correctly the candidate must determine the following:
1. The minimum pressure allowed by 1/2/3-AOI 85-3, CRD System Failure.
2. The basis for that minimum pressure.
A is incorrect. This is plausible because 980 psig is the setpoint for the Low Accumulator Pressure
alarm.
B is correct.
C is incorrect. This is plausible because the entire statement is accurate, but is not the pressure
specified by 1/2/3-AOI 85-3, CRD System Failure.
D is incorrect. This is plausible because the entire statement is accurate, but is not the pressure
specified by 1/2/3-AOI 85-3, CRD System Failure.
OPL 171.006
Revision 9
Page 17 of 60
C (a) A specific pattern of control rod
withdrawal or insertion
(b) Written step-by-step path used by
the operator in establishing the
expected rod pattern and flux
shape at rated power
(c) Deviation from the established
path could result in potentially
high control rod worths
(9) Shutdown margin OBJ. V.B.15.c
(a) Technical specifications of the
plant require knowing whether the
plant can be shutdown to a safe
level
(b) Without the insertion capability of Obj. V.B.20.g
all control rods, shutdown margin
will not be as great, thus closer to
an inadvertent criticality
(10) Control Rod Worth variables
(a) Moderator temperature OBJ. V.8.20.e
i. As temperature rises, SER 3-05
slowing down length and
thermal diffusion length
increase
ii. Rod worth increases with
as moderator temperature
increases
(b) Void effects on rod worth
i. As voids increase, average
neutron flux energy
increases
ii. U238 and Pu240 will
capture more epithermal
( neutrons through
resonance
BFN CRD System Failure 1-AOI-85-3
Unit 1 Rev. 0003
( Page 7 of 11
4.1 Immediate Actions (continued)
[2] IF operating CRD PUMP has tripped AND backup CRD PUMP
is NOT available, THEN (Otherwise N/A)
PERFORM the following at Panel 1-9-5:
[2.1 ] PLACE CRD SYSTEM FLOW CONTROL, 1-FIC-85-11 ,
in MAN at minimum setting. D
[2.2] ATTEMPT TO RESTART tripped CRD Pump using one
of the follow ing:
- CRD PUMP 1B, using 1-HS-85-2A
- CRD Pump 1A, using 1-HS-85-1A D
[2.3] ADJUST CRD SYSTEM FLOW CONTROL,
1-FIC-85-11, to establish the following cond itions:
approx imately 20 psid. D
- CRD SYSTEM FLOW CONTROL, 1-FIC-85-11,
between 40 and 65 gpm. D
[2.4] BALANCE CRD SYSTEM FLOW CONTROL,
1-FIC-85-11 , and PLACE in AUTO or BALANCE. D
[3] IF Reactor Pressure is less than 900 psig AND either of the
following conditions exists :
be started , OR
- Charging Water Pressure can NOT be restored and
maintained above 940 psig, THEN
PERFORM the follow ing: (Otherwise N/A)
[3.1] MANUALLY SCRAM Reactor and IMMEDIATELY
PLACE the Reactor Mode Switch in the SHUTDOWN
position. D
[3.2] REFER TO 1-AOI-100-1. [Item 020] D
OPL 171.006
Revision 9
Page 30 of 60
( (6) The withdraw motion is terminated prior
to reaching the desired position and the
rod is settled as discussed earlier.
d. Cooling water is continuously supplied via the
P-under port and insert header.
(1) Flow from plug type orifice in flange
follows passage between outer tube and
thermal sleeve to outer screen.
(2) Cooling water is required to protect the OBJ. V.B.18
graphitar seals from high reactor
temperatures.
(3) Long exposures at high temperatures will
result in brittle, fast- wearing seals.
(4) Drive temperature should be maintained
at <350°F and the cause should be
investigated if it exceeds this value.
(5) Concern is that the high temperature
may be caused by a leaking scram
discharge valve.
(6) This problem should be corrected as
soon as possible to prevent damage to
the valve.
e. Scram function
(1) There are two sources of water that can OBJ . V.B/E.11,
be used to scram a drive: reactor water V.D.10
and accumulator water.
(2) Reactor water scram feature
(a) Reactor water, if at high enough
pressure, is capable of scramming More on required
the drive without any accumulator amount of
assistance. pressure to lift
drive and control
(b) The over-piston area is opened to rod later in LP.
OPL171 .006
Revision 9
Page 35 of 60
( (2) The primary effect is reduced 10 of the
inner tube just below the bottom of the
collet piston.
(a) In serious overpressure situations,
this squeezes the inner tube
against the circumference of the
index tube.
(b) The index tube is then held in the
insert overtravel position and often
cannot be withdrawn.
(3) Bulging of the index tube as described
above also occurs.
b. Extensive procedural controls are specified to
prevent improper valving of the hydraulic
module.
c. Particular caution should be observed during
the startup test program.
3. Scram Capability
a. Piston areas
(1) Under-piston area equals 4.0 in2.
(2) Over-piston area equals 2.8 in2 .
b. Normal scram forces
(1) During a normal scram condition, the
over-piston area is opened to the scram
discharge volume which is initially at
atmospheric pressure.
(2) Accumulator and/or reactor pressure is
simultaneously applied to the under-
piston area. The net initial force applied
to the drive (taking no credit for the
accumulator) can be calculated as
follows.
Fnet =(Forces Up) - (Forces Down)
OPL171.006
Revision 9
Page 36 of 60
( Fnet = (Rx Pressure x Under-Piston Area) -
(Rx Pressure x Area of Index Tube
Note: 4 in2
+ Weight of Blade + Friction)
upward force -
2
1.2 in
Fnet =(1000 psig x 4.0 in2) - [1000 psig downward force
= 2.8 in2
x (4.0 in2 - 1.2 in2)] - 255 Ibs -
- 500 Ibs
Fnet = 4000 - 2800 - 255 - 500
Fnet = 445 Ibs (Upward)
c. Single failure proof - There is no single-mode
failure to the hydraulic system which would
prevent the drive from scramming .
d. Accumulator versus reactor vessel pressure
(1 ) TP-9 represents a plot of 90 percent TP-9
scram times versus reactor pressure .
(a) Reactor pressure only
(b) Accumulator pressure only
(c) Combined reactor and
accumulator pressure
(2) Scram times are measured for only the
first 90% of the rod insertion since the
buffer holes at the top end of the stroke
slow the drive.
(3) Reactor-pressure-only scram
(a) As can be seen from TP-9, the
drive cannot be scrammed with
reactor pressure ~ 400 psig.
(b) The net initial upward force
available to scram the drive can
be calculated as follows.
OPL 171.006
Revision 9
Page 38 of 60
(
e. Average scram times (normal drive) TP-9
(1) Technical Specifications state that scram
times are to be obtained without reliance
on the CRD pumps.
(2) Consequently, the charging water must
be valved out on the drive to be tested .
(3) Maximum scram time for a typical drive
occurs at 800 psig reactor pressure.
(4) This is why Technical Specifications
specify that scram times are to be taken
at 800 psig or greater reactor pressure.
f. Abnormal scram conditions
(1) Scram outlet valve failure to open
(2) Drive will slowly scram on seal leakage
as long as accumulator charging water
pressure stays greater than reactor
pressure.
(3) If the accumulator is not available, the
drive will not scram (this is a double
failure) .
g. Control Rods failure to Insert After Scram Obj. V.D .11
(1) This condition could be due to hydraulic
lock.
(2) Procedure has operator close the See 2-01-85 & 2-
Withdraw Riser Isolation valve. Connect EOI App-1 E for
drain hose to Withdraw Riser Vent Test detailed
Connection on the affected HCU. Slowly operations
open Withdraw Riser Vent. When inward
motion has stopped, close Withdraw Self Check
Riser Vent. Peer Check
28. RO 201006K4 .09 OOl/MEM/T2G2/RWM//201006K4.09/3.2/3.2/RO/SR0/11/l6/07 RMS
The Rod Worth Minimizer must be INITIALIZED to properly determine rod position and sequence .
Which ONE of the following describes how RWM System INITIALIZATION is accomplished?
(
A. INITIALIZATION occurs automatically when the RWM is unbypassed.
B. INITIALIZATION occurs automatically every 5 seconds while in the transition zone .
C.oI INITIALIZATION must be performed manually using the INITIALIZATION push-button when the
RWM is unbypassed.
D. INITIALIZATION must be performed manually using the INITIALIZATION push-button when power
drops below the LPSP.
KIA Statement:
201006 RWM
K4.09 - Knowledge of ROD WORTH MINIMIZER SYSTEM (RWM) (PLANT SPECIF IC) design feature(s)
and/or interlocks which provide for the following : System initialization : P-Spec(Not-BWR6)
KIA Justification: This question satisfies the KIA statement by requiring the candidate to use specific of
which plant condition would INITIALIZE the RWM.
References: 1/2/3-01-85, OPL 171.024
Level of Knowledge Justification: This question is rated as MEM due to the requirement to recall
or recognize discrete bits of information.
0610 NRC Exam
REFERENCE PROVIDED: None
Plausibility Analysis:
In order to answer this question correctly the candidate must determine the following :
1. When RWM INITIALIZATION is required .
2. How RWM INITIALIZATION is accomplished.
A is incorrect. This is plausible because initialization is required when the RWM is unbypassed, but this
must be done manually.
B is incorrect. This is plausible because the RWM automatically initiates a "scanllatch" to determine the
correct latched rod group, but this is not the same as INITIALIZATION.
C is correct.
D is incorrect. This is plausible because the RWM must be manually INITIALIZED, but the RWM does
not require initialization because the LPSP is reached . THe RWM will automatically perform a
"scanllatch" at that point.
(
OPL171.024
Revision 13
Page 19 of 53
( INSTRUCTOR NOTES
(2) The MANUAL indicator light will then be Obj. V.B.6
lit and all error and alarm indications
that were on prior to bypass will be
blanked out on the RWM system
displays.
(3) A manual bypass will also light the
RWM and PROGR indicator on the
RWM-COMP-PROGR-BUFF
pushbutton.
f. SYSTEM INITIALIZE pushbutton
switch/indicator
(1) The SYSTEM INITIALIZE switch is
depressed to initialize the RWM
system.
(2) Initialization must be performed
whenever the RWM has been taken off
line, as occurs whenever the RWM
program is aborted or manually
bypassed.
(3) Therefore, following any program abort
or bypass, the SYSTEM INITIALIZE
switch must be depressed before the
program can be run again.
(4) The SYSTEM INITIALIZE window
lights white while the switch is held
down.
g. SYSTEM DIAGNOSTIC switch/indicator
(1) This switch can be pressed at any time
after the system has been initialized to
request that the system diagnostic
routine be performed.
(2) The RWM program will thereupon be
initiated and will perform the routine,
which consists of applying and then
removing in sequence the insert and
withdraw blocks (nominal 10 second
frequency).
(3) The operator can verify the operability NOTE: Rod insert
of the rod block circuits by observing and withdrawal
( that the INSERT BLOCK and
WITHDRAW BLOCK alarm lights come
permit lights will go
off when block is
on and then go off as the blocks are applied.
BFN Control Rod Drive System 1-01-85
Unit 1 Rev. 0005
( Paue 136 of 179
8.18 Reinitialization of the Rod Worth Minimizer
[1 ] VERIFY the following initial conditions are satisfied:
- The Rod Worth Minimizer is available to be placed in
operation D
- Integrated Computer System (ICS) is available D
- The Shift Manager/Reactor Engineer has directed
reinitialization of the Rod Worth Minimizer D
[2] REVIEW all Precautions and Limitations in Section 3.3. D
[3] VERIFY RWM SWITCH PANEL, 1-XS-85-9025 in NORMAL. D
[4] CHECK the Manual/Auto Bypass lights are extinguished. D
[5] DEPRESS AND HOLD INOP/RESET pushbutton. D
[6] CHECK all four lights (RWM/COMP/PROG/BUFF) are
illuminated. D
[7] RELEASE INOP/RESET pushbutton and CHECK all four
lights extinguished. D
[8] SIMUL TANEOUSLY DEPRESS OUT OF
SEQUENCE/SYSTEM INITIALIZE pushbutton and
INOP/RESET pushbutton to place the Rod Worth Minimizer in
service. D
[9] IF Rod Worth Minim izer will NOT initialize, THEN
DETERMINE alarms on RWM Display Screen and CORRECT
problems. D
[10] IF unable to correct problems and initialize RWM, THEN
NOTIFY Reactor Engineer. D
(
BFN Control Rod Drive System 1-01-85
Unit 1 Rev. 0005
( Page 19 of 179
3.3 Rod Worth Minimizer (RWM) (continued)
N. For group limits only, RWM recognizes the Nominal Limits only. The Nominal
Limit is the insert or withdraw limit for the group assigned by RWM. The
Alternate Limit is no longer recognized by the RWM as an Acceptable
Group Limit.
O. During RWM latching, the latched group will be the highest numbered
group with 2 or less insert errors and having at least 1 rod withdrawn past its
insert limits.
1. With Sequence Control ON, latching occurs as follows: (Normally, startups
will be performed with Sequence Control ON)
a. RWM will latch down when all rods in the presently latched
group have been inserted to the group insert limit and a rod in the next
lower group is selected.
b. RWM will latch up when a rod within the next higher group is selected,
provided that no more than two insert errors result.
2. With Sequence Control OFF, latching occurs as follows:
a. For non-repeating groups, latching occurs as described above, OR
b. For repeating groups, latching occurs to the next setup or set down
based on rod movement as opposed to rod selection.
P. Latching occurs at the following times:
1. System initialization.
2. Following a "System Diagnostic" request.
3. When operator demands entry or termination of "Rod Test."
4. When power drops below LPAP.
5. When power drops below LPSP.
6. Every five seconds in the transition zone.
7. Following any full control rod scan when power is below LPAP.
8. Upon demand by the Operator (Scan/Latch Request function).
9. Following correction of insert or withdraw errors.
29. RO 20200 1K6.09 OOl/C/A/T2G2/68 - RECIRC/24/202001 K6.09//RO/SROI
Given the following plant conditions:
( idling.
- Both Recirculation Pump speeds are 53%.
- The "A" RFP trips, resulting in the following conditions:
Reactor Water level Abnormal alarm sealed in
Reactor Vessel Wtr Level Low Half Scram alarm sealed in
- Indicated Reactor Water Level drops to _10" before RFP "B" is brought on line to reverse the level
trend and level is stabilized at 33".
Which ONE of the following describes the steady state condition of both Recirculation Pumps?
A. Running at 53% speed
B. Running at 45% speed
c. Y' Running at 28% speed
D. Tripped on ATWS/RPT signal.
KIA Statement:
202001 Recirculation
K6.09 - Knowledge of the effect that a loss or malfunction of the follow ing will have on the
RECIRCULATION SYSTEM: Reactor water level
KIA Justification: This question satisfies the KIA statement by requiring the candidate to use specific
plant conditions and times to determine the effect of a change in reactor water level on the Recirculation
System .
References: 3-01-68 , OPL 171.007, OPL 171.012
Level of Knowledge Justification: This question is rated as CIA due to the requirement to assemble ,
sort, and integrate the parts of the question to predict an outcome. This requires menta lly using this
knowledge and its meaning to predict the correct outcome .
0610 NRC Exam
REFERENCE PROVIDED: None
Plausibility Analysis:
( In order to answer this question correctly the candidate must determine the following:
1. Did plant conditions exceed the Recirc Runback setpoint.
2. Which Runback is appropriate for the given conditions.
A is incorrect. Total Feedflow would drop below 19% with only one RFP running at 55% rated power,
thus initiating a Recirc Runback to 28%. This is plausible based on the initial power level being close
enough to create doubt on total feedflow resulting from the trip of one RFP.
B is incorrect. This is plausible because a Recirc Runback DID occur, but the 45% speed given in the
distractor is the typical speed the Recirc Pumps run at during startup , not following a RFP trip.
C is correct.
D is incorrect. This is plausible because ATWS/RPT signals are associated with low RPV level, however
the setpoint is -45 inches and level only lowered to -10 inches.
l
BFN Reactor Recirculation System 3-01-68
Unit 3 Rev. 0066
( Page 13 of 179
3.0 PRECAUTIONS AND LIMITATIONS (continued)
10. The out of service pump may NOT be started unless the temperature of the
coolant between the operating and idle Recirc loops are within 50°F of
each other. This 50°F delta T limit is based on stress analysis for reactor
nozzles, stress analysis for reactor recirculation components and piping,
and fuel thermal limits. [GE Sll517 Supplement 1]
11. The out of service pump may NOT be started unless the reactor is verified
outside of regions 1, 2 and 3 of the Unit 3 Power to Flow Map (ICS or
Station Reactor Engineering, 0-TI-248).
12. The temperature of the coolant between the dome and the idle Recirc loop
should be maintained within 75°F of each other. If this limit cannot be
maintained a plant cooldown should be initiated . Failure to maintain this
limit and NOT cooldown could result in hangers and/or shock suppressers
exceeding their maximum travel range. [GE SIl251, 430 and 517]
M. Recirc Pump controller limits are as follows:
1. When any individual RFP flow is less than 19% and reactor water level is
below 27 inches, speed limit is set to 75%(-1130 RPM speed) and if speed
is greater than 75%(-1130 RPM speed), Recirc speed will run back to
75%(-1130 RPM speed).
2. When total feed water flow is less than 19% (15 sec TD) or Recirc Pump
discharge valve is less than 90% open, speed limit is set to 28%
(-480 RPM speed) and if speed is greater than 28%(-480 RPM speed),
Recirc speed will run back to 28%(-480 RPM speed).
BFN Reactor Recirculation System 3-01-68
Unit 3 Rev. 0066
( Page 15 of 179
3.0 PRECAUTIONS AND LIMITATIONS (continued)
R. The power supplies to the MMR and DFR relays are listed below.
VFD3A
I&C BUS A (BKR 215) 3-RLY-068-MMR3/A & DFR3/A
ICS PNL 532 (BKR 30) 3-RLY-068-MMR2/A & DFR2/A
UNIT PFD (BKR 615) 3-RLY-068-MMR1/A & DFR1/A
VFD3B
I&C BUS B (BKR 315) 3-RLY-068-MMR3/B & DFR3/B
ICS PNL 532 (BKR 26) 3-RLY-068-MMR2/B & DFR2/B
UNIT PFD (BKR 616) 3-RLY-068-MMR1/B & DFR1/B
S. A complete list of Recirc System trip functions is provided in Illustration 4. The
RPT breakers between the recirc drives and pump motors will open on any of
the following:
1. Reactor dome Pressure ~ 1148 psig (ATWS/RPT). (Both pressure
switches in Logic A or both pressure switches in Logic B will cause RPT
breakers to trip both pumps.) (2 out of 2 taken once logic)
2. Reactor Water Level s -45" (ATWS/RPT) . (Both level switches in Logic A
or both level switches in Level B will cause RPT breakers to trip both
pumps.) (2 out of 2 taken once logic)
3. Turbine trip or load reject condition, when ~ 30% power by turbine first
stage pressure (EOC/RPT) .
1. The ATWS/RPT A(B) logic to trip the RPT breakers is defeated if the
ATWS/RPT/ARI A(B) manual logic is armed using the arming collar on
Panel 3-9-5. B(A) logic would still be functional and trip the RPT breakers if the
setpoints are reached. If both manual push-buttons on 3-9-5 are armed,
ATWS/RPT automatic logic is totally defeated (no RPT breaker trip will occur if
the ATWS/RPT trip setpoints are reached) . EOC/RPT logic and ATWS/ARI
logic will function without regard to the position of the arming collars.
ATWS/R PT/AR I logic can be reset 30 seconds after setpoints are reset.
(
30. RO 215001Al.Ol OOlIMEMlTIG2/TIPI121500IAl.Ol//RO/SROI
Which ONE of the following describes the procedural requirements in accordance with 2-01-94 ,
Traversing In-Core Probe System while running TIP traces?
(
A. The TIP detector shall be withdrawn to the In-Shield position and the ball valve closed following
each TIP trace .
8. Running a TIP trace while personnel are working inside the Drywell is prohibited .
C." The Radiation Protection Shift Supervisor is required to be notified prior to TIP System operation.
D. The TIP Machine will automatically withdraw to the in-shield position, then the ball valve will
automatically close following a PCIS Group 6 isolation .
KIA Statement:
215001 Traversing In-core Probe
A1.01 - Ability to predict and/or monitor changes in parameters associated with operating the
TRAVERSING IN-CORE PROBE controls including: Radiation levels: (Not-BWR1)
KIA Justification: This question satisfies the KIA statement by requiring the candidate to determine the
operating limitations of the TIP system with respect to high radiation .
References: 2-01-94 Precautions & Limitations
Level of Knowledge Justification: This question is rated as MEM due to the requirement to recall
or recognize discrete bits of information.
0610 NRC Exam
REFERENCE PROVIDED: None
Plausibility Analysis:
In order to answer this question correctly the candidate must determine the following :
1. Limitations for running TIP traces with personnel in the Drywell.
2. Notification requirements prior to running TIPs .
3. Which PCIS Group will cause a TIP retraction and isolation .
4. Requirements for running multiple simultaneous TIP traces.
A is incorrect. This is plausible because that limitation is placed on TIP operation, but only when TIP
operation is no longer required. The TIP detector can be stored in the Indexer in-between traces using
the same TIP Machine for ALARA concerns.
8 is incorrect. This is plausible because specific permission and controls are required to allow this
condition, but it is allowable.
C is correct.
D is incorrect. This is plausible because the TIP response to a PCIS isolation is correct, but it is not a
Group 6 isolation.
(
BFN Traversing Incore Probe System 2-01-94
Unit2 Rev. 0029
( Page 7 of 26
3.0 PRECAUTIONS AND LIMITATIONS
A. [NER/C] Verification of a digit in CORE LIMIT and DETECTOR POSITION
windows prior to or during TIP insertion ensures TIPs retain the ability to
determine its proper position. This will prevent malfunctions which could
damage the TI P detector. [GE SIL-166]
B. To prevent accidental exposure to personnel , immediately evacuate the area if
the TIP drive area radiation monitor alarms .
C. [NER/C] Always observe READY light illuminated prior to inserting detector. [GE
SIL-166]
D. (NERlC] DO NOT move CHANNEL SELECT switch with detector inserted past
Indexer position (0001). The common channel interlock can be defeated in this
manner resulting in detector and equipment damage. [GE SIL-092]
E. (NERlC] Should detector fail to shift to slow speed when it enters the core, the
LOW switch should be turned on, switched to manual mode, and the detector
withdrawn. [GE SIL-166]
F. [NER/C] Length of time detector is left in core should be minimized to limit
activation of detector and cable . [GE SIL-166]
G. (NERlC] When TIP System operation is not desired, detectors should be retracted
and stored in chamber shield with ball valves closed . [GE SIL-166] Storage of
detector in Indexer (0001) is allowed only for ALARA concerns and to prevent
unnecessary masking of multiple inputs to annunciator RX BLDG AREA
RADIATION HIGH 2-RA-90-1 D (2-XA-55-3A, Window 22).
. H. [NER/C] Upon receipt of a PCIS signal (low reactor water level or high drywell
pressure), any detector inserted beyond its shield chamber should be verified to
automatically shift to reverse mode and begin withdrawal. Once in shield, ball
and purge valves close. [GE SIL-166] Ball valve cannot be reopened until PCIS is
reset on Panel 2-9-4 and manual reset of TIP ISOLATION RESET pushbutton
2-HS-94-7D/S2 located on Panel 2-9-13.
I. A detector should not be abruptly stopped from fast speed to off without first
switching to slow speed.
J. [NER/C] Drive Control Units (DCU) should be monitored during withdrawal to
prevent any chamber shield withdrawal limit from being overrun. Detectors
should be stopped manually at shield limit if auto stop limit switch should fail
and verify ball valve closes. [GE SIL-166]
K. Only one TIP at a time should be operated when maintenance is being
performed in TI P drive area.
BFN Traversing Incore Probe System 2-01-94
Unit2 Rev. 0029
( Page 8 of 26
3.0 PRECAUTIONS AND LIMITATIONS (continued)
L. [NRC/CJ DO NOT operate TIPswith personnel inside TIP Room or in vicinity of
TIP tubing and Indexers in Drywell. Requirement may be waived with approval
of Shift Manager and site RADCON manager or designee. In this instance,
RADCON is required to establish such controls as are necessary to prevent
access to TIP tubing and Indexer areas to preclude unnecessary exposure to
personnel working in Drywell. RADCON Field Operations Shift Supervisor is
required to be notified prior to operation of TIP System. [NRC InformationNotice 88-063,
Supplement 2J
M. No channel should be indexed to common channel 10 unless all other channels
are not indexed to channel 10 and all their READY lights are illuminated .
N. [NERlC] DO NOT turn MODE switch to OFF on Drive Control Unit if detector is
outside shield chamber unless personnel safety requires it. [GE SIL-166J This
removes power preventing automatic withdrawal on PCIS signal and causing
ball valves to close on cable or detector. Tip Ball Valves CANNOT fully close
and shear valves may have to be actuated.
O. CHANNEL SELECT switches on Drive Control Units should always be rotated
in clockwise direction when selecting channels.
P. Connector on shear valve indicator circuit should not be removed while testing
shear valve explosive charges or performing shear valve maintenance with
detector inserted. This will cause an automatic detector withdrawal.
Q. Continuous voice communication should be maintained between TIP operator
or maintenance personnel in control room and drive mechanism area while
maintenance is being performed and TIP detector driving is necessary.
R. Each applicable ball valve should be opened prior to operating that TIP
machine.
S. TIP Drive Mechanisms and Indexers should have continuous purge supply
unless required to be removed from service for maintenance.
T. During outages when containment is deinerted for personnel access, TIP
Indexer purge supply should be transferred from nitrogen to Control Air for
personnel safety.
U. Detector damage is possible if TIP ball valve is left open , or is opened during
DRYWELL PRESSURE TEST. (GE SIL-166)
l
31. RO 216000K l.l O00l/MEM/T2G2/PR.INSTRJ9/216000Kl.lO//RO/SRO/
Wh ich ONE of the following indicates how raising recirculation flow affects the Emergency System Range
indicators (3-58A -58B) and Narrow Range Indicators (e.g., L1-3-53) on Panel 9-5?
(
A. No effect on Emergency System Range; Narrow Range will indicate higher.
B. Emergency System Range will indicate higher; Narrow Range will not be affected.
C. Both Emergency System Range and Narrow Range will indicate lower.
D.oI Emergency System Range will indicate lower and Narrow Range will not be affected.
KIA Statement:
216000 Nuclear Boiler Inst
K1.10 - Knowledge of the physical connections and/or cause- effect relationships between NUCLEAR
BOILER INSTRUMENTATION and the following : Recirculation flow control system
KIA Justification: This question satisfies the KIA statement by requiring the candidate to use specific
knowledge of the effect of changes in Recirculation flow on reactor water level instrumentation.
References: OPL 171.003
Level of Knowledge Justification: This question is rated as MEM due to the requirement to recall
or recognize discrete bits of information.
0610 NRC Exam
REFERENCE PROVIDED: None
Plausibility Analysis:
In order to answer this question correctly the candidate must determine the effect of raising Recirc flow on
Normal Range and Emergency Systems Range level instrumentation.
A is incorrect. This is plausible because Narrow Range instruments may read slightly higher at colder
conditions, but this does NOT apply to Recirc flow changes.
B is incorrect. This is plausible because Narrow Range instruments are not effected by Recirc Flow
changes , but Emergency System Range isntruments will read lower.
C is incorrect. This is plaus ible because Emergency System Range instruments will read lower, but the
Narrow Range instruments will not.
D is correct.
(
OPL 171.003
Revision 17
Page 20 of 54
( INSTRUCTOR NOTES
d. Four ranges of level indication
(1) Normal Control Range (Narrow Range) Obj. V.B.5
(a) oto +60 inch range covering the Obj. V.B.6
normal operating range (analog) with TP-3 shows only
+60" up to +70" digital and 0" down to analog scale
- 10" digital readings.
(b) Referenced to instrument zero
(c) Four of these instruments are
used by Feedwater Level Control
System (FWLCS). The level
signal utilized by the FWLCS is
not directed through the Analog
Trip System.
i. Temperature Obj. V.B.11.
compensated by a Obj. V.B.13.
pressure signal
ii. Most accurate level
indication available to the
operator
iii. Calibrated for normal
operating pressure and
temperature
(d) These indicators and a recorder
point (average of the four) are
located on Panel 9-5 .
NOTE: An air bubble or leak in LER 85-006-02
the reference leg can cause (See LP Folder)
inaccurate readings in a non- (Section X.C.1.j.
conservative direction resulting in provides more
a mismatch between level detail)
indicators.
This problem is particularly
prevalent after extended outages
when starting up from cold
shutdown conditions and at low
reactor pressures.
(
OPL171 .003
Revision 17
Page 21 of 54
( INSTRUCTOR NOTES
(e) Four other narrow range Associated with
instruments are located in the RFPT/Main Turbine
control room, two above the and HPCIIRCIC trip
FWLCS level indicators on panel instruments
9-5 (3-208A & D), one above
HPCI (3-208B)and one above
(2) Emergency Systems Range (Wide Range) 2 Analog meters
and 2 Digital meters .
(a) -155 to +60 inches range
covering normal operating range
and down to the lower instrument
nozzle return
(b) Referenced to instrument zero
(c) Four MCR indicators on Panel 9-
5 monitor this range of level
indication.
(d) Calibrated for normal operating
pressure and temperature
(e) The level signal utilized by the
Wide Range instruments have
safety related functions and are
directed through the Analog Trip
System.
(f) Level indication for this range is Obj. V.B.12.
also provided on the Backup
Control Panel (25-32).
(3) Shutdown Vessel Flood Range (Flood-up
Range)
(a) oto +400 inches range covering
upper portion of reactor vessel
(b) Referenced to instrument zero
Calibrated for cold conditions
<<212°F, 0 psig)
(c) Provides level indication during
vessel flooding or cool down.
OPL171.003
Revision 17
Page 32 of 54
( INSTRUCTOR NOTES
Transient flashing effects can cause
indicated level to oscillate or be
erratic . As the reference leg refills,
the indicated level approaches a
more accurate water level indication .
The RVLlS mod decreases the time
necessary for this refill to occur
j. Normal Control Range (Narrow Range) and
Emergency Systems Range (Wide Range) Level
Discrepancies
(1) Narrow Range level instrumentation is
calibrated to be most accurate at rated
temperature and pressure (particularly
the instruments for FWLCS , since they
are temperature compensated). At cold
conditions the non-FWLCS instruments
read high (not temperature
compensated).
(2) Wide Range instruments are also
calibrated for rated temperature and
pressure
(a) The indicated level on the Wide Obj. V.B.15
Range (9-5) is also affected by
changes in the subcooling of
recirculation water and the
amount of flow at the lower
(variable leg) tap.
(b) At rated conditions with
minimum recirculation flow the
Wide Range instruments are
accurate. As recirculation flow is
increased past the lower tap it
has a significant velocity head
and some friction loss which
reduces the pressure on the
variable leg to the differential
pressure instrument, resulting in
an indicated level lower than
actual. This could be as much
as 10-15 inches error when at
rated flow and power.
(c) Due to calibration for rated
conditions and no density
compensation at cold conditions
these instruments read high.
32. RO 219000K2 .02 00l/C/A/T2G2/0I-74//219000K2.02//RO/SRO/NEW 10/16/07
Given the following plant conditions:
- Unit-2 is at 100% rated power with RHR Loop II in Suppression Pool Cooling mode to support
( a HPCI Full Flow test surveillance.
Which ONE of the following describes the current status of Unit-2 RHR system and what actions must be
taken to restore Suppression Pool Cooling on Unit-2?
A. 2A and 2C RHR Pumps are tripped . 28 and 2D pumps are unaffected . No additional action is
required.
B. 28 and 2D RHR Pumps are tripped. 2A and 2C pumps are unaffected. Place RHR Loop I in
Suppression Pool Cooling immediately.
c. All four RHR pumps receive a trip signal. Place RHR Loop II in Suppression Pool Cooling
immediately.
D~ All four RHR pumps receive a trip signal. Place RHR Loop II in Suppression Pool Cooling after a 60
second time delay .
KIA Statement:
219000 RHR/LPCI: Torus/Pool Cooling Mode
K2.02 - Knowledge of electrical power supplies to the following : Pumps
KIA Justification: This question satisfies the KIA statement by requiring the candidate to use specific
plant conditions and times to determine which RHR pumps can be used for Suppression Pool Cooling.
References: 2-01-74 , OPL 171.044
Level of Knowledge Justification: This question is rated as CIA due to the requirement to assemble ,
sort, and integrate the parts of the question to predict an outcome . This requires mentally using this
knowledge and its meaning to predict the correct outcome.
0610 NRC Exam
REFERENCE PROVIDED: None
Plausibility Analysis:
( In order to answer this question correctly the candidate must determine the following:
1. Response of Unit-2 RHR pumps due to a Unit 1 CAS initition.
2. Recognize the difference between a Single Unit CAS and Simultaneous Unit CAS.
3. Recognize that Preferred and Non-preferred ECCS pumps do NOT apply with the given conditions.
A is incorrect. This is plausible based on RHR Loop II being the Preferred pumps for Unit-2.
B is incorrect. This is plausible if taken from the perspective of Unit 1 operation, not Unit 2 operation.
C is incorrect. This is plausible because all four RHR pumps on Unit 2 will trip, but they are locked out
from manual start for 60 seconds based on D/G and/or Shutdown Board loading concerns.
D is correct.
(
BFN Residual Heat Removal System 2-01-74
Unit2 Rev. 0133
( Page 331 of 367
Appendix A
(Page 2 of 7)
Unit 1 & 2 Core Spray/RHR Logic Discussion
2.2 ECCS Preferred Pump Logic
Concurrent Accident Signals On Unit 1 and Unit 2
With normal power available, the starting and running of RHR pumps on a 4KV
Shutdown Board already loaded by the opposite unit's Core Spray, RHR pumps, and
RHRSW pumps could overload the affected 4KV Shutdown Boards and trip the
normal feeder breaker. This would result in a temporary loss of power to the
affected 4KV Shutdown Boards while the boards are being transferred to their
diesels . To prevent this undesirable transient, Unit 2 RHR Pumps 2A and 2C are
load shed on a Unit 1 accident signal and Unit 1 Pumps 1Band 10 will be load shed
on a Unit 2 accident signal. Unit 2 Core Spray Pumps 2A and 2C are load shed on a
Unit 1 accident signal and Unit 1 Core Spray Pumps 1Band 10 will be load shed on
a Unit 2 accident signal. This makes the Preferred ECCS pumps Unit 1 Division I
Core Spray and RHR Pumps and Unit 2 Division 2 Core Spray and RHR Pumps.
Conversely, the Non-preferred ECCS pumps are Unit 1 Division 2 Core Spray and
RHR Pumps and Unit 2 Division 1 Core Spray and RHR Pumps.
The preferred and non-preferred ECCS pumps are as follows:
UNIT 1 & 2
PREFERRED ECCS Pumps
CS1A,CS1C,RHR1A,RHR1C
NON-PREFERRED ECCS Pumps
CS2~CS2C,RHR2A,RHR2C
UNIT3
Unit 3 does not have ECCS Preferred/Non-Preferred Pump Logic.
Accident Signal On One Unit
With an accident on one unit, ECCS Preferred pump logic trips all running RHR and
Core Spray pumps on the non-accident unit.
OPL171.044
Revision 15
Page 50 of 159
( INSTRUCTOR NOTES
Note:
Presently Unit 1 Accident signal will not affect Unit 2 due to DCN H2735A that lifted wires
from relays. Unit 2 will still affect Unit 1. However, the following represents modifications
to the inter-tie logic as it will be upon Unit 1 recovery.
Obj. V.B.13.
Obj. V.C.3
(1) Unit 1 Preferred RHR pumps are 1A and 1C
Obj. V.C.7
Obj. V.D.6
(2) Unit 2 Preferred RHR pumps are 28 and 2D Obj. V.E.II
(3) Unit 2 initiation logic is as follows:Div 1 RHR
logic initiates Div 1 pumps ( A and C), and Div
2 logic initiates Div 2 pumps (B and D)
f. Accident Signal
(1) LOCA signals are divided into two separate Obj. V.B.13.
signals, one referred to as a Pre Accident Obj. V.C.3
Signal (PAS) and the other referred to as a Obj. V.C.7
Common Accident Signal (CAS) . Obj. V.D.6
Obj. V.E.II
- PAS
-122" Rx water level (Level 1) Note:
It should be clear
that the only
2.45 psig DW pressure difference
- CAS between the two
signals is the
-122" Rx water level (Level 1) inclusion of Rx
OR pressure in the
CAS signal. The
2.45 psig DW pressure AND <450 PAS signal is an
psig Rx pressure anticipatory signal
that allows the
DG's to start on
(2) If a unit receives an accident signal, then all rising OW
its respective RHR and Core Spray pumps pressure and be
will sequence on based upon power source to ready should a
the SD Boards. CAS be received.
(3) All RHR and Core Spray pumps on the non-
affected unit will trip (if running) and will be
blocked from manual starting for 60 seconds.
(
OPL171 .044
Revision 15
Page 51 of 159
( INSTRUCTOR NOTES
(4) After 60 seconds all RHR pumps on the non- Operator diligence
affected unit may be manually started . required to
prevent
(5) The non-preferred pumps on the non-
overloading SO
affected unit are also prevented from
boards/DG's
automatically starting until the affected unit's
accident signal is clear.
(6) The preferred pumps on the non-affected
unit are locked out from automatically starting
until the affected unit accident signal is clear
OR the non-affected unit receives an
accident signal.
g. 4KV Shutdown Board Load Shed Obj. V.C .B.
(1) A stripping of motor loads on the 4KV boards
occurs when the board experiences an
undervoltage condition. This is referred to as a
4KV Load Shed . This shed prepares the board
for the DG ensuring the DG will tie on to the
bus unloaded and without faults.
(2) The Load Shed occurs when an undervoltage
is experienced on the board i.e. or if the Diesel
were tied to the board (only source) and one of
the units experienced an accident signal which
trips the Diesel output breaker.
(3) Then, when the Diesel output breaker
interlocks are satisfied, the DG output breaker
would close and, if an initiation signal is
present (CAS) the RHR, CS, and RHRSW
pumps would sequence on
(4) Following an initiation of a Common Accident
Signal (which trips the diesel breaker), if a
subsequent accident signal is received from
another unit, a second diesel breaker trip on a
"unit priority" basis is provided to ensure that
the Shutdown boards are stripped prior to
starting the RHR pumps and other ECCS
loads
(5) When an accident signal trip of the diesel Occurs due to
breakers is initiated from one unit (CASA or actuation of the
CASB) , subsequent CAS trips of all eight diesel breaker
( diesel breakers are blocked . TSCRN relay
33. RO 226001A4.I2 OOlIMEM/T2G2/PC/P//226001A4.12/3.8/3.9/RO/SRO/
Given the following plant conditions:
- A pipe break inside containment results in the below parameters:
( - Drywell pressure is 20 psig
- Drywell temperature is 210°F
- Suppression chamber pressure is 18 psig.
- Suppression chamber temperature is 155°F.
- Suppression pool level is +2 inches
- Reactor water level is +30 inches
Which ONE list of parameters below must ALWAYS be addressed to determine when it is appropriate to
spray the drywell?
A. -Suppression Chamber temperature
-Drywell pressure
-Drywell temperature
B. -Suppression Chamber pressure
-Drywell temperature
-Suppression Pool level
C." -Drywell pressure
-Drywell temperature
-Reactor water level
D. -Reactor water level
-Suppression Chamber temperature
-Drywell pressure
KIA Statement:
226001 RHR/LPCI: CTMT Spray Mode
A4.12 - Ability to manually operate and/or monitor in the control room: ContainmenUdrywell pressure
KIA Justification: This question satisfies the KIA statement by requiring the candidate to use specific
knowledge of which containment parameters are used to determine when Contain merit Sprays can be
used.
References: 1/2/3-EOI-2 Flowchart
Level of Knowledge Justification: This question is rated as MEM due to the requirement to recall
or recognize discrete bits of information.
0610 NRC Exam
REFERENCE PROVIDED: None
Plausibility Analysis:
( In order to answer this question correctly the candidate must determine the following:
1. Orywell temperature and pressure are always required to ensure Curve 5 limits are not exceeded.
2. RPV level is always required to verify adequate core cooling is assured prior to diverting RHR flow
for Orywell sprays.
3. Suppression Pool level is always required to verify Suppression Chamber to Orywell vacuum breakers
are uncovered.
4. Suppression Chamber pressure is ONLY required when initiating Orywell Sprays from flowpath PC/Po
5. Suppression Chamber temperature is NOT required to initiate Orywell Sprays.
A is incorrect. This is plaus ible because OW temp and press are required , but SC temp is not.
B is incorrect. This is plausible because OW temp and SP level are required , but SC press is ONLY
required when initiating OW Sprays using PC/P o
C is correct.
D is incorrect. This is plausible because RPV level and OW press are required, but SC temp is not.
WHEN SUPPR CHMBR PRESS EXCEEDS 12 PSIG,
THEN CONnNUE INTHISPROCEDURE
L
-_... _....----_..... __. __.._---------_ ...., ..
" ~'.
PClP-7
L
SHUT DOWN RECIRC PUfA'PS ANDOWBLOWERS
L
- 2 PUMP NPSH AND VORTEX m"TS
L
INITlAm r:JN SPRAYS USING W:lL:! PUMPSWIREQUJRED
ro ASSUREAIEQUATE OORE COOLING BY CON11NUOUS
INJ (APPX 178)
L
L !
0"
,p'
~
!
"
.. ,J~"~
L
S HUT DOWN RS CIRC i'IIllWS RJO r:1" BLO'/ IB'tS
L
L
L
34. RO 234000G2.4.50 OO l/C/NTIG2///234000G2.4.50/IRO/SRO/
Given the following plant conditions:
- Fuel movement is in progress for channel changeou t activities in the Fuel Prep Machine.
( * Gas bubbles are visible coming from the de-channeled bundle .
- An Area Radiation Monitor adjacent to the SFSP begins alarm ing.
Wh ich ONE of the following describes the action (s) to take?
Immediately STOP fuel handling, then _
A. notify RADCON to monitor & evaluate radiation levels.
B." evacuate non-essential personnel from the RFF.
C. evacuate ALL personnel from the RFF .
D. obtain Reactor Engineering Supervisor's recommendation for movement and sipping of the
damaged fuel assembly.
KIA Statement:
234000 Fuel Handling Equipment
2.4.50 - Emergency Procedures / Plan Ability to verify system alarm setpoints and operate controls
identified in the alarm response manual
KIA Justification: This question satisfies the KIA statement by requiring the candidate to use specific
plant conditions to determine the corrective actions involving Fuel Handling equipment under emergency
conditions.
References: 1/2/3-AOI-79-1 & 79-2 , 1/2/3-ARP-9-3A (W1)
Level of Knowledge Justification: This question is rated as CIA due to the requirement to assemble ,
sort, and integrate the parts of the question to predict an outcome. This requires mentally using this
knowledge and its mean ing to predict the correct outcome.
0610 NRC Exam
REFERENCE PROVIDED: None
Plausibility Analvsis:
( In order to answer this question correctly the candidate must determine the following :
1. Whether indications are consistent with fuel damage or inadvertant criticality.
2. Based on the answer to Item 1 above, enter the appropriate AOI.
3. Immediate Operator Actions for the selected procedure, AOI-70-1.
A is incorrect. This is plausible because RADCON notification is a subsequent action in AOI-70-1,
however non-essential personnel evacuation is an IMMEDIATE action .
B is correct.
C is incorrect. This is plausible because evacuation of ALL personnel is an IMMEDIATE action in
AOI-70-2 , however non-essential personnel evacuation is an IMMEDIATE action in the appropriate AOI.
D is incorrect. This is plausible because RE recommendations are a subsequent action in AOI-70-1 ,
however non-essential personnel evacuation is an IMMEDIATE action.
Unit2 2-XA-55-3A Rev. 0036
( Page 4 of 50
SensorlTrip Point:
FUEL POOL
FLOOR AREA
RADIATION HIGH RI-90-1 B
RI-90-2B For setpo ints
2-RA-90-1A RI-90-3B REFER TO 2-SIMI-90B.
11
(Page 1 of 1)
Sensor RE-90-1 B EI664' R-11 P-L1NE
Location: RE-90-2B E1664' R-10 U-L1NE
RE-90-3B E1639' R-10 Q-L1NE
Probable A. Change in general radiation levels.
Cause: B. Refueling accident.
C. Sensor malfunction.
Automatic None
Action:
Operator A. CHECK 2-RI-90-1A, 2-RI-90-2A and 2-RI-90-3A on Panel 2-9-11. o
Action: B. NOTIFY refuel floor personnel. o
C. IF Dry Cask loading/unloading activities are in progress, THEN
NOTIFY Cask Supervisor. o
D. IF airborne levels rise by 100 DAC AND RADCON confirms, THEN
REFER TO EPIP-1. o
E. REFER TO 2-AOI-79-1 or 2-AOI-79-2 as applicable. o
F. IF this alarm is not valid, THEN REFER TO 0-01-55. o
G. IF this alarm is valid , THEN
MONITOR the other parameters that input to it frequently. These
other parameters will be masked from alarming while this alarm is
sealed in. o
H. ENTER 2-EOI-3 Flowchart. o
References: 0-47E600-13 2-47E61 0-90-1 2-45E620-3
GE 730E356 Series, TVA Calc NDQ00902005001/EDC63693
BFN Fuel Damage During Refueling 2-AOI-79-1
Unit 2 Rev. 0017
( Page 3 of7
1.0 PURPOSE
This instruction provides the symptoms, automatic actions and operator actions for a
fuel damage accident.
2.0 SYMPTOMS
A. Possible annunciators in alarm:
1. FUEL POOL FLOOR AREA RADIATION HIGH (2-XA-55-3A, window 1).
2. AIR PARTICULATE MONITOR RADIATION HIGH (2-XA-55-3A,
window 2).
3. RX BLDG, TURB BLDG, RF ZONE EXH RADIATION HIGH (2-XA-55-3A,
window 4).
4. REACTOR ZONE EXHAUST RADIATION HIGH (2-XA-55-3A, window 21).
5. RX BLDG AREA RADIATION HIGH (2-XA-55-3A, window 22).
6. REFUELING ZONE EXHAUST RADIATION HIGH (2-XA-55-3A,
window 34).
B. Gas bubbles visible, in the Spent Fuel Storage Pool and/or Reactor Cavity,
attributed to physical fuel damage.
C. Known dropped or physically damaged fuel bundle.
D. Portable CAM in alarm.
E. Radiation level on the Refuel Floor is greater than 25 mr/hr and cause is
unknown.
BFN Fuel Damage During Refueling 2-AOI-79-1
Unit2 Rev. 0017
Page 5 of 7
4.0 OPERATOR ACTIONS
4.1 Immediate Actions
[1] STOP all fuel handling. o
[2] EVACUATE all non-essential personnel from Refuel Floor. o
4.2 Subsequent Actions
CAUTION
The release of iodine is of major concern. If gas bubbles are identified at any time, Iodine
release should be assumed until RADCON determines otherwise.
[1] VERIFY secondary containment is intact.
(REFER TO Tech Spec 3.6.4.1) n
[2] IF any EOI entry condition is met, THEN
ENTER the appropriate EOI(s). o
[3] VERIFY automatic actions. o
[4] NOTIFY RADCON to perform the following:
- EVALUATE the radiation levels. 0
- MAKE recommendation for personnel access. 0
- MONITOR around the Reactor Building Equipment Hatch,
at levels below the Refuel Floor, for possible spread of the
release. 0
[5] REFER TO EPIP-1 for proper notification. o
BFN Fuel Damage During Refueling 2-AOI-79-1
Unit 2 Rev. 0017
( Page 6 of 7
4.2 Subsequent Actions (continued)
[6] MONITOR radiation levels, for the affected areas, using the
following radiation recorders and indicators:
A. 2-RR-90-1 (points 1 and 2), 2-MON-90-50 (Address 11),
2-RR-90-142 and 2-RR-90-140 (Panel 2-9-2) . 0
B. 2-RM-90-142, 2-RM-90-140, 2-RM-90-143
and 2-RM-90-141 Detectors A and B (Panel 2-9-10). 0
C. 2-RI-90-1A and 2-RI-90-2A (Panel 2-9-11). 0
D. 0-CONS-90-362A (Address 09, 10, 08) for Unit 1, 2,
3-RM-90-250, respectively (Panel 1-9-44). 0
[7] IF possible, MONITOR portable CAMs & ARMs.
[8] REQUEST Chemistry to perform 0-SI-4.8.8.2-1 to determine if
iodine concentration has risen . 0
[9] NOTIFY Reactor Engineering Supervisor, or his designee, and
OBTAIN recommendation for movement and sipping of the
damaged fuel assembly. 0
[10] OBTAIN Plant Managers approval prior to resuming any fuel
transfer operations. 0
[11] WHEN condition has cleared AND if required, THEN
RETURN ventilation systems, including SGTS, to normal.
REFER TO 2-01-30A, 2-01-30B, 0-01-30F, 0-01-31,
and 0-01-65. 0
(
BFN Inadvertent Criticality During Incore 2-AOI-79-2
Unit 2 Fuel Movements Rev. 0013
Page 5 of 8
4.0 OPERATOR ACTIONS
4.1 Immediate Actions
[1 ] IF unexpected criticality is observed following control rod
withdrawal, THEN
REINSERT the control rod. 0
[2] IF all control rods CANNOT be fully inserted, THEN
MANUALLY SCRAM the reactor. 0
[3] IF unexpected criticality is observed following the insertion of a
fuel assembly, THEN
PERFORM the following: 0
[3.1] VERIFY fuel grapple latched onto the fuel assembly
handle AND immediately REMOVE the fuel assembly
from the reactor core. 0
[3.2] IF the reactor can be determined to be subcritical AND
no radiological hazard is apparent, THEN
PLACE the fuel assembly in a spent fuel storage pool
location with the least possible number of surrounding
fuel assemblies, leaving the fuel grapple latched to the
fuel assembly handle. 0
[3.3] IF the reactor CANNOT be determined to be subcritical
OR adverse radiological conditions exist, THEN
TRAVERSE the refueling bridge and fuel assembly
away from the reactor core, preferably to the area of the
cattle chute, AND CONTINUE at Step 4.1[4]. 0
[4] IF the reactor CANNOT be determined to be subcritical OR
adverse radiological conditions exist, THEN
EVACUATE the refuel floor . 0
(
35. RO 245000K6.04 OOI /C/A/TIG2/0I-35//245000K6.04/fRO/SRO/Il/28/07 RMS
Given the following plant conditions:
- Unit 2 is operating at 100% power.
( * Main Generator is at 1150 MWe.
- The Chattanooga Load Coordinator requires a 0.95 lagging power factor.
- Generator hydrogen pressure is 65 psig.
Wh ich ONE of the following describes the required action and reason if Generator hydrogen pressure
drops to 45 psig?
REFERENCE PROVIDED
A. Reduce excitation to obtain a power factor of unity to maintain current generator load. Pole slippage
will not occur at this power factor.
B~ Reduce generator load below 800 MWe. Sufficient cooling capability still exists at this hydrogen
pressure.
C. Reduce generator load below 800 MWe . Pole slippage will not occur at this generator load.
D. Reduce excitation to obta in a power factor of unity to maintain current generator load. Suffic ient
cooling capab ility still exists at this hydrogen pressure.
KJA Statement:
245000 Main Turb ine Gen . / Aux .
K6.04 - Knowledge of the effect that a loss or malfunction of the following will have on the MAIN TURBINE
GENERATOR AND AUXILIARY SYSTEMS : Hydrogen cooling
KJA Justification: This question satisfies the KIA statement by requiring the candidate to use spec ific
plant conditions to determine the effect of a loss of hydrogen cooling on Main Generator operation.
Reference Provided: Generator Capability Curve without axis labeled
Level of Knowledge Justification: This question is rated as CIA due to the requ irement to assemble,
sort, and integrate the parts of the question to predict an outcome. This requi res mentally using this
knowledge and its meaning to predict the correct outcome.
0610 NRC Exam
REFERENCE PROVIDED: Generator Capability Curve without the axis labeled.
Plausibility Analysis:
In order to answer this question correctly the candidate must determine the following:
1. Current operating point on the Generator Capability Curve based on given condiions.
2. Recognize that pole slippage is only a concern when operating with a significant leading power factor.
3. Recognize that pole slippage is a result of under excitation, not excessive generator load.
4. Recognize that generator hydrogen pressure is directly related to cooling capability.
A is incorrect. This is plausible because reducing excitation DOES reduce heat generation within the
generator, but not sufficient enough to prevent generator damage. However, pole slippage is not a
concern at a unity power factor.
B is correct.
C is incorrect. This is plausible because generator load is properly reduced, but the basis for the
reduction is not related to slipping poles .
D is incorrect. This is plausible because reducing excitation DOES reduce heat generation within the
generator, but not sufficient enough to prevent generator damage. In addition, insufficient hydrogen
pressure exists at the current generator load even wih a power factor of unity .