{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION  


==REGION III==
==REGION III==
2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 June 23, 2011 NOTICE OF SIGNIFICANT LICENSEE MEETING THIS MEETING IS OPEN TO PUBLIC ATTENDANCE Name of Licensee: Northern States Power Company, Minnesota Name of Facility: Prairie Island Nuclear Generating Plant, Units 1 and 2 Docket Nos.: 50-282; 50-306 Time and Date: Thursday, July 28, 2011 1:30 p.m. to 3:30 p.m. (CDT),
2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352  
Location:  U. S. Nuclear Regulation Commission Region III Main Conference Room Suite 210 2443 Warrenville Road Lisle, IL 60532 Purpose:  This meeting is a Regulatory Conference at which the licensee will provide their perspectives on the significance of a preliminary White inspection finding discussed in Inspection Reports 05000282/2011010 and 05000306/2011010 (ML111610249)
pertaining to the safety-related battery chargers, the bases for their position, and the apparent violation associated with that finding.


Meeting Category: This is a Category 1 meeting. The public is invited to observe this meeting and will have one or more opportunities to communicate with the Nuclear Regulatory Commission after the business portion, but before the meeting is adjourne The Nuclear Regulatory Commission provides reasonable accommodation to individuals with disabilities where appropriat If you need a reasonable accommodation to participate in this meeting, or need this meeting notice or the transcript of other information from the meeting in another format (e.g. Braille or large print), please notify the Nuclear Regulatory Commissions meeting contact listed below. Determinations on requests for reasonable accommodation will be made on a case-by-case basi Notice of Significant  -2-Meeting Notice A telecommunications bridge will be available for the public. Members of the public should dial toll free 1-888-324-3412, pass code 38823, to access the bridge for the Prairie Island Regulatory Conference meetin NRC Attendees:
June 23, 2011
M. Satorius, Regional Administrator, RIII S. West, Director, Division of Reactor Projects, RIII G. Shear, Deputy Director, Division of Projects, RIII J. Giessner, Chief, Branch 4, Division of Reactor Projects, RIII K. Stoedter, Senior Resident Inspector, Prairie Island L. Kozak, Senior Risk Analyst, Division of Reactor Projects, RIII R. Lerch, Project Engineer, Division of Reactor Projects, RIII S. Shah, Reactor Engineer, Division of Reactor Projects, RIII Others as designated Licensee Attendees:
Dennis Koehl, Chief Nuclear Officer Mark Schimmel, Site Vice President Kevin Davison, Plant Manager Paula Anderson, Director Licensing / Regulatory Affairs Jon Anderson, Regulatory Affairs Manager Mark Brossart, Engineering Supervisor Darrell Lapcinski, Operations Shift Manager John Bickel, Engineer Others as designated Approved by: _____/RA/_________________
John B. Giessner, Chief Branch 4 Division of Reactor Projects Meeting Contact: Swetha Shah 630-829-9608 Swetha.Shah@nrc.gov DISTRIBUTION:
See next page


Notice of Significant -2-Licensee Meeting Distribution:
NOTICE OF SIGNIFICANT LICENSEE MEETING
 
THIS MEETING IS OPEN TO PUBLIC ATTENDANCE
 
Name of Licensee:
 
Northern States Power Company, Minnesota
 
Name of Facility:
 
Prairie Island Nuclear Generating Plant, Units 1 and 2
 
Docket Nos.:
 
50-282; 50-306
 
Time and Date:
 
Thursday, July 28, 2011
 
1:30 p.m. to 3:30 p.m. (CDT),
 
Location:
 
U. S. Nuclear Regulation Commission Region III Main Conference Room Suite 210 2443 Warrenville Road Lisle, IL 60532
 
Purpose:
This meeting is a Regulatory Conference at which the licensee will provide their perspectives on the significance of a preliminary White inspection finding discussed in Inspection Reports 05000282/2011010 and 05000306/2011010 (ML111610249)
pertaining to the safety-related battery chargers, the bases for their position, and the apparent violation associated with that findin Meeting Category:
This is a Category 1 meetin The public is invited to observe this meeting and will have one or more opportunities to communicate with the Nuclear Regulatory Commission after the business portion, but before the meeting is adjourne The Nuclear Regulatory Commission provides reasonable accommodation to individuals with disabilities where appropriat If you need a reasonable accommodation to participate in this meeting, or need this meeting notice or the transcript of other information from the meeting in another format (e.g. Braille or large print), please notify the Nuclear Regulatory Commissions meeting contact listed belo Determinations on requests for reasonable accommodation will be made on a case-by-case basi Notice of Significant
 
-2-Meeting Notice
 
A telecommunications bridge will be available for the publi Members of the public should dial toll free 1-888-324-3412, pass code 38823, to access the bridge for the Prairie Island Regulatory Conference meetin NRC Attendees:
 
M. Satorius, Regional Administrator, RIII S. West, Director, Division of Reactor Projects, RIII G. Shear, Deputy Director, Division of Projects, RIII J. Giessner, Chief, Branch 4, Division of Reactor Projects, RIII K. Stoedter, Senior Resident Inspector, Prairie Island L. Kozak, Senior Risk Analyst, Division of Reactor Projects, RIII R. Lerch, Project Engineer, Division of Reactor Projects, RIII S. Shah, Reactor Engineer, Division of Reactor Projects, RIII Others as designated
 
Licensee Attendees:
 
Dennis Koehl, Chief Nuclear Officer Mark Schimmel, Site Vice President Kevin Davison, Plant Manager Paula Anderson, Director Licensing / Regulatory Affairs Jon Anderson, Regulatory Affairs Manager Mark Brossart, Engineering Supervisor Darrell Lapcinski, Operations Shift Manager John Bickel, Engineer Others as designated
 
Approved by: _____/RA/_________________
 
John B. Giessner, Chief
 
Branch 4
 
Division of Reactor Projects
 
Meeting Contact:
Swetha Shah
 
630-829-9608
 
Swetha.Shah@nrc.gov
 
DISTRIBUTION:
See next page
 
Notice of Significant-2-Licensee Meeting  
 
Distribution:
Daniel Merzke, Region III Coordinator, OEDO Robert Nelson, Deputy Director, Division of Operating Reactor Licensing (DORL), NRR RidsNrrPMPrairieIsland Resource RidsNrrDorlLpl3-1 Resource Steven West, Director, Division of Reactor Projects, RIII Steven Reynolds, Director, Division of Reactor Safety, RIII Kenneth OBrien, Deputy Director, Division of Reactor Safety, RIII DRP Branch Chief SRI, Prairie Island DRS Branch Chiefs:
Daniel Merzke, Region III Coordinator, OEDO Robert Nelson, Deputy Director, Division of Operating Reactor Licensing (DORL), NRR RidsNrrPMPrairieIsland Resource RidsNrrDorlLpl3-1 Resource Steven West, Director, Division of Reactor Projects, RIII Steven Reynolds, Director, Division of Reactor Safety, RIII Kenneth OBrien, Deputy Director, Division of Reactor Safety, RIII DRP Branch Chief SRI, Prairie Island DRS Branch Chiefs:
Robert Daley David Hills Richard Skokowski AnnMarie Stone Billy Dickson Hironori Peterson Allan Barker, Regional State Liaison Officer, RIII PMNS Viktoria Mitlyng, RIII Public Affairs Prema Chandrathil Tammy Tomczak, ORA Patricia Buckley, ORA Marjorie Zerth, DRP
Robert Daley David Hills Richard Skokowski AnnMarie Stone Billy Dickson Hironori Peterson Allan Barker, Regional State Liaison Officer, RIII PMNS Viktoria Mitlyng, RIII Public Affairs Prema Chandrathil Tammy Tomczak, ORA Patricia Buckley, ORA Marjorie Zerth, DRP  
 
Notice of Significant
 
-2-Meeting Notice
 
A telecommunications bridge will be available for the publi Members of the public should dial toll free 1-888-324-3412, pass code 38823, to access the bridge for the Prairie Island Regulatory Conference meetin NRC Attendees:
 
M. Satorius, Regional Administrator, RIII S. West, Director, Division of Reactor Projects, RIII G. Shear, Deputy Director, Division of Projects, RIII J. Giessner, Chief, Branch 4, Division of Reactor Projects, RIII K. Stoedter, Senior Resident Inspector, Prairie Island L. Kozak, Senior Risk Analyst, Division of Reactor Projects, RIII R. Lerch, Project Engineer, Division of Reactor Projects, RIII S. Shah, Reactor Engineer, Division of Reactor Projects, RIII Others as designated
 
Licensee Attendees:
 
Dennis Koehl, Chief Nuclear Officer Mark Schimmel, Site Vice President Kevin Davison, Plant Manager Paula Anderson, Director Licensing / Regulatory Affairs Jon Anderson, Regulatory Affairs Manager Mark Brossart, Engineering Supervisor Darrell Lapcinski, Operations Shift Manager John Bickel, Engineer Others as designated
 
Approved by: ______/RA/________________
 
John B. Giessner, Chief
 
Branch 4
 
Division of Reactor Projects Meeting Contact:
Swetha Shah
 
630-829-9608
 
Swetha.Shah@nrc.gov
 
DISTRIBUTION:
See next page
 
DOCUMENT NAME: G:\\DRPIII\\PRAI\\Prairie Island Reg Conference Public Notice.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII
 
RIII
 
NAME SShah:dtp JGiessner
 
DATE 06/23/11 06/23/11


Notice of Significant    -2-Meeting Notice A telecommunications bridge will be available for the public. Members of the public should dial toll free 1-888-324-3412, pass code 38823, to access the bridge for the Prairie Island Regulatory Conference meetin NRC Attendees:
OFFICIAL RECORD COPY
M. Satorius, Regional Administrator, RIII S. West, Director, Division of Reactor Projects, RIII G. Shear, Deputy Director, Division of Projects, RIII J. Giessner, Chief, Branch 4, Division of Reactor Projects, RIII K. Stoedter, Senior Resident Inspector, Prairie Island L. Kozak, Senior Risk Analyst, Division of Reactor Projects, RIII R. Lerch, Project Engineer, Division of Reactor Projects, RIII S. Shah, Reactor Engineer, Division of Reactor Projects, RIII Others as designated Licensee Attendees:
Dennis Koehl, Chief Nuclear Officer Mark Schimmel, Site Vice President Kevin Davison, Plant Manager Paula Anderson, Director Licensing / Regulatory Affairs Jon Anderson, Regulatory Affairs Manager Mark Brossart, Engineering Supervisor Darrell Lapcinski, Operations Shift Manager John Bickel, Engineer Others as designated Approved by: ______/RA/________________
John B. Giessner, Chief Branch 4 Division of Reactor Projects Meeting Contact:  Swetha Shah 630-829-9608 Swetha.Shah@nrc.gov DISTRIBUTION:
See next page DOCUMENT NAME: G:\DRPIII\PRAI\Prairie Island Reg Conference Public Notice.docx Publicly Available  Non-Publicly Available  Sensitive  Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII  RIII NAME  SShah:dtp  JGiessner DATE  06/23/11  06/23/11 OFFICIAL RECORD COPY
}}
}}

Latest revision as of 05:43, 13 January 2025

Notice of Meeting with Prairie Island Units 1 & 2 to Discuss Inspection Reports 05000282/2011010 & 05000306/2011010
ML111741207
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 06/23/2011
From: Jack Giessner
Reactor Projects Region 3 Branch 4
To:
References
EA-11-110, IR-10-010, ir-11-010
Download: ML111741207 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352

June 23, 2011

NOTICE OF SIGNIFICANT LICENSEE MEETING

THIS MEETING IS OPEN TO PUBLIC ATTENDANCE

Name of Licensee:

Northern States Power Company, Minnesota

Name of Facility:

Prairie Island Nuclear Generating Plant, Units 1 and 2

Docket Nos.:

50-282; 50-306

Time and Date:

Thursday, July 28, 2011

1:30 p.m. to 3:30 p.m. (CDT),

Location:

U. S. Nuclear Regulation Commission Region III Main Conference Room Suite 210 2443 Warrenville Road Lisle, IL 60532

Purpose:

This meeting is a Regulatory Conference at which the licensee will provide their perspectives on the significance of a preliminary White inspection finding discussed in Inspection Reports 05000282/2011010 and 05000306/2011010 (ML111610249)

pertaining to the safety-related battery chargers, the bases for their position, and the apparent violation associated with that findin Meeting Category:

This is a Category 1 meetin The public is invited to observe this meeting and will have one or more opportunities to communicate with the Nuclear Regulatory Commission after the business portion, but before the meeting is adjourne The Nuclear Regulatory Commission provides reasonable accommodation to individuals with disabilities where appropriat If you need a reasonable accommodation to participate in this meeting, or need this meeting notice or the transcript of other information from the meeting in another format (e.g. Braille or large print), please notify the Nuclear Regulatory Commissions meeting contact listed belo Determinations on requests for reasonable accommodation will be made on a case-by-case basi Notice of Significant

-2-Meeting Notice

A telecommunications bridge will be available for the publi Members of the public should dial toll free 1-888-324-3412, pass code 38823, to access the bridge for the Prairie Island Regulatory Conference meetin NRC Attendees:

M. Satorius, Regional Administrator, RIII S. West, Director, Division of Reactor Projects, RIII G. Shear, Deputy Director, Division of Projects, RIII J. Giessner, Chief, Branch 4, Division of Reactor Projects, RIII K. Stoedter, Senior Resident Inspector, Prairie Island L. Kozak, Senior Risk Analyst, Division of Reactor Projects, RIII R. Lerch, Project Engineer, Division of Reactor Projects, RIII S. Shah, Reactor Engineer, Division of Reactor Projects, RIII Others as designated

Licensee Attendees:

Dennis Koehl, Chief Nuclear Officer Mark Schimmel, Site Vice President Kevin Davison, Plant Manager Paula Anderson, Director Licensing / Regulatory Affairs Jon Anderson, Regulatory Affairs Manager Mark Brossart, Engineering Supervisor Darrell Lapcinski, Operations Shift Manager John Bickel, Engineer Others as designated

Approved by: _____/RA/_________________

John B. Giessner, Chief

Branch 4

Division of Reactor Projects

Meeting Contact:

Swetha Shah

630-829-9608

Swetha.Shah@nrc.gov

DISTRIBUTION:

See next page

Notice of Significant-2-Licensee Meeting

Distribution:

Daniel Merzke, Region III Coordinator, OEDO Robert Nelson, Deputy Director, Division of Operating Reactor Licensing (DORL), NRR RidsNrrPMPrairieIsland Resource RidsNrrDorlLpl3-1 Resource Steven West, Director, Division of Reactor Projects, RIII Steven Reynolds, Director, Division of Reactor Safety, RIII Kenneth OBrien, Deputy Director, Division of Reactor Safety, RIII DRP Branch Chief SRI, Prairie Island DRS Branch Chiefs:

Robert Daley David Hills Richard Skokowski AnnMarie Stone Billy Dickson Hironori Peterson Allan Barker, Regional State Liaison Officer, RIII PMNS Viktoria Mitlyng, RIII Public Affairs Prema Chandrathil Tammy Tomczak, ORA Patricia Buckley, ORA Marjorie Zerth, DRP

Notice of Significant

-2-Meeting Notice

A telecommunications bridge will be available for the publi Members of the public should dial toll free 1-888-324-3412, pass code 38823, to access the bridge for the Prairie Island Regulatory Conference meetin NRC Attendees:

M. Satorius, Regional Administrator, RIII S. West, Director, Division of Reactor Projects, RIII G. Shear, Deputy Director, Division of Projects, RIII J. Giessner, Chief, Branch 4, Division of Reactor Projects, RIII K. Stoedter, Senior Resident Inspector, Prairie Island L. Kozak, Senior Risk Analyst, Division of Reactor Projects, RIII R. Lerch, Project Engineer, Division of Reactor Projects, RIII S. Shah, Reactor Engineer, Division of Reactor Projects, RIII Others as designated

Licensee Attendees:

Dennis Koehl, Chief Nuclear Officer Mark Schimmel, Site Vice President Kevin Davison, Plant Manager Paula Anderson, Director Licensing / Regulatory Affairs Jon Anderson, Regulatory Affairs Manager Mark Brossart, Engineering Supervisor Darrell Lapcinski, Operations Shift Manager John Bickel, Engineer Others as designated

Approved by: ______/RA/________________

John B. Giessner, Chief

Branch 4

Division of Reactor Projects Meeting Contact:

Swetha Shah

630-829-9608

Swetha.Shah@nrc.gov

DISTRIBUTION:

See next page

DOCUMENT NAME: G:\\DRPIII\\PRAI\\Prairie Island Reg Conference Public Notice.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII

RIII

NAME SShah:dtp JGiessner

DATE 06/23/11 06/23/11

OFFICIAL RECORD COPY