ML070640539: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| Line 23: | Line 23: | ||
3277 DAEC Road | 3277 DAEC Road | ||
Palo, IA 52324-9785 | Palo, IA 52324-9785 | ||
SUBJECT: | SUBJECT: | ||
DUANE ARNOLD ENERGY CENTER | |||
NOTIFICATION OF AN NRC BIENNIAL HEAT SINK PERFORMANCE | |||
INSPECTION AND REQUEST FOR INFORMATION 05000331/2007003(DRS) | |||
Dear Mr. Van Middlesworth: | Dear Mr. Van Middlesworth: | ||
On April 23, 2007, the NRC will begin the on-site portion of the Biennial Heat Sink Performance | On April 23, 2007, the NRC will begin the on-site portion of the Biennial Heat Sink Performance | ||
Inspection at your Duane Arnold Energy Center. This inspection will be performed in | Inspection at your Duane Arnold Energy Center. This inspection will be performed in | ||
accordance with NRC baseline inspection procedure (IP) 71111.07. The heat exchangers | accordance with NRC baseline inspection procedure (IP) 71111.07. The heat exchangers | ||
selected for detailed review during this baseline inspection are the 1B emergency diesel | selected for detailed review during this baseline inspection are the 1B emergency diesel | ||
generator cooler and the 1B residual heat removal heat exchanger. | generator cooler and the 1B residual heat removal heat exchanger. | ||
We have enclosed a request for documents needed for the inspection. This information can be | We have enclosed a request for documents needed for the inspection. This information can be | ||
sent to the following e-mail address cea4@nrc.gov, no later than April 13, 2007, so that we may | sent to the following e-mail address cea4@nrc.gov, no later than April 13, 2007, so that we may | ||
start the review of these documents. A hard-copy with the required information is also an | start the review of these documents. A hard-copy with the required information is also an | ||
acceptable option. | acceptable option. | ||
The lead inspector for this inspection is Ms. Caroline Acosta Acevedo. If there are questions | The lead inspector for this inspection is Ms. Caroline Acosta Acevedo. If there are questions | ||
about the material requested, or the inspection, please call Ms. Acosta Acevedo at | about the material requested, or the inspection, please call Ms. Acosta Acevedo at | ||
(630) 829-9718. | (630) 829-9718. | ||
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and | In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and | ||
its enclosure will be available electronically for public inspection in the NRC Public Document | its enclosure will be available electronically for public inspection in the NRC Public Document | ||
Room or from the Publicly Available Records (PARS) component of NRC's document system | Room or from the Publicly Available Records (PARS) component of NRC's document system | ||
G. Van Middlesworth | G. Van Middlesworth | ||
-2- | |||
(ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the | (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the | ||
Public Electronic Reading Room). | Public Electronic Reading Room). | ||
Sincerely, | |||
/RA/ | |||
Ann Marie Stone, Chief | |||
Engineering Branch 2 | |||
Division of Reactor Safety | |||
Docket No. 50-331 | Docket No. 50-331 | ||
License No. DPR-49 | License No. DPR-49 | ||
Enclosure: Heat Sink Inspection Document Request | Enclosure: Heat Sink Inspection Document Request | ||
cc w/encl: | cc w/encl: | ||
J. Stall, Senior Vice President, Nuclear and Chief | |||
Nuclear Officer | |||
R. Helfrich, Senior Attorney | |||
M. Ross, Managing Attorney | |||
W. Webster, Vice President, Nuclear Operations | |||
M. Warner, Vice President, Nuclear Operations Support | |||
R. Kundalkar, Vice President, Nuclear Engineering | |||
J. Bjorseth, Site Director | |||
D. Curtland, Plant Manager | |||
S. Catron, Manager, Regulatory Affairs | |||
Chairman, Linn County Board of Supervisors | |||
D. McGhee, State Liaison Officer | |||
G. Van Middlesworth | G. Van Middlesworth | ||
-2- | |||
(ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the | (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the | ||
Public Electronic Reading Room). | Public Electronic Reading Room). | ||
Sincerely, | |||
/RA/ | |||
Ann Marie Stone, Chief | |||
Engineering Branch 2 | |||
Division of Reactor Safety | |||
Docket No. 50-331 | Docket No. 50-331 | ||
License No. DPR-49 | License No. DPR-49 | ||
Enclosure: Heat Sink Inspection Document Request | Enclosure: Heat Sink Inspection Document Request | ||
cc w/encl: | cc w/encl: | ||
J. Stall, Senior Vice President, Nuclear and Chief | |||
Nuclear Officer | |||
R. Helfrich, Senior Attorney | |||
M. Ross, Managing Attorney | |||
W. Webster, Vice President, Nuclear Operations | |||
M. Warner, Vice President, Nuclear Operations Support | |||
R. Kundalkar, Vice President, Nuclear Engineering | |||
J. Bjorseth, Site Director | |||
D. Curtland, Plant Manager | |||
S. Catron, Manager, Regulatory Affairs | |||
Chairman, Linn County Board of Supervisors | |||
DOCUMENT NAME: C:\FileNet\ML070640539.wpd | D. McGhee, State Liaison Officer | ||
G Publicly Available | DOCUMENT NAME: C:\\FileNet\\ML070640539.wpd | ||
To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy | G Publicly Available | ||
G Non-Publicly Available | |||
G Sensitive | |||
G Non-Sensitive | |||
To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy | |||
OFFICE | |||
RIII | |||
RIII | |||
N | |||
NAME | |||
CAcostaAcevedo:co | |||
AMStone | |||
DATE | |||
03/05/07 | |||
03/05/07 | |||
OFFICIAL RECORD COPY | |||
G. Van Middlesworth -3- | G. Van Middlesworth | ||
-3- | |||
DISTRIBUTION: | DISTRIBUTION: | ||
TEB | TEB | ||
| Line 113: | Line 129: | ||
TXN | TXN | ||
BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST | |||
Initial Document Request | |||
Inspection Report: | Enclosure | ||
Inspection Dates: | 1 | ||
Inspection Procedures: | Inspection Report: | ||
Lead Inspector: | 05000331/2007003(DRS) | ||
Inspection Dates: | |||
Information Requested Prior to the On-site Information Gathering/Inspection Week | April 23 - 27, 2007 | ||
Inspection Procedures: | |||
71111.07, Biennial Heat Sink Performance Inspection | |||
Lead Inspector: | |||
C. E. Acosta Acevedo | |||
(630) 829-9718, cea4@nrc.gov | |||
Information Requested Prior to the On-site Information Gathering/Inspection Week | |||
The following information is requested to be provided as soon as possible, but no later than | The following information is requested to be provided as soon as possible, but no later than | ||
April 13, 2007, to support the biennial Heat Sink Performance Inspection, IP 71111.07. | April 13, 2007, to support the biennial Heat Sink Performance Inspection, IP 71111.07. | ||
If some of the activities are not performed by your program, please note that fact. This request | If some of the activities are not performed by your program, please note that fact. This request | ||
is only for the time period from the onsite inspection back to the last Heat Sink Performance | is only for the time period from the onsite inspection back to the last Heat Sink Performance | ||
Inspection in year 2005. If nothing addressing the request was done in that time period then | Inspection in year 2005. If nothing addressing the request was done in that time period then | ||
the request applies to the last applicable document in the previous time period. Unless | the request applies to the last applicable document in the previous time period. Unless | ||
otherwise specified, all the below requests are for the selected heat exchangers (Hxs) which | otherwise specified, all the below requests are for the selected heat exchangers (Hxs) which | ||
are the 1B emergency diesel generator cooler and the 1B residual heat removal heat | are the 1B emergency diesel generator cooler and the 1B residual heat removal heat | ||
exchanger. | exchanger. | ||
1. | 1. | ||
Copies of the two most recent completed tests confirming thermal performance for | |||
2. | those heat exchangers which are performance tested. | ||
2. | |||
For the two most recently completed tests confirming thermal performance of the | |||
sample heat exchangers, please provide documentation and procedures that identify the | |||
types, accuracy, and location of any special instrumentation used for these tests, (e.g., | |||
3. | high accuracy ultrasonic flow instruments or temperature instruments). Include | ||
calibration records for the instruments used during these tests. | |||
3. | |||
A list of corrective action program documents (with a short description) associated with | |||
Hxs, heat sinks, silting, corrosion, fouling, or Hx testing, that are documented in your | |||
4. | corrective action system (for the previous 2 years or since the last biennial heat sink | ||
inspection), this request is for all the Generic Letter 89-13 Hxs and the ultimate heat | |||
sink. | |||
4. | |||
Copy of system description and design basis document for the Hxs under review (as | |||
applicable). | |||
BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST | |||
Initial Document Request | |||
5. | Enclosure | ||
2 | |||
6. | 5. | ||
Copy of any operability determinations or other documentation of degradation | |||
7. | associated with the Hxs or the systems that support the operation of the Hxs. | ||
6. | |||
8. | Copy of any self-assessment done within last 2 years on any of the licensees Hx | ||
programs (e.g., Generic Letter 89-13 program Hxs) or on the sample Hxs. | |||
9. | 7. | ||
A schedule of all inspections, cleanings, maintenance, or testing of any plant Hx to be | |||
10. Provide copy of the calculation which establishes the limiting (maximum) design basis | done during the on-site portion of the inspection. | ||
8. | |||
11. Copy of the calculation which correlates surveillance testing results from these Hxs with | List of operability evaluations currently relied upon and those that were previously (past | ||
2 years) relied upon for operability. | |||
9. | |||
12. The clean and inspection maintenance schedule for each Hx for the next 5 years. | Copy of the evaluations of data for the two most recent completed tests confirming the | ||
13. Copy of the document describing the inspection results for the last two clean and | thermal performance of each Hx. | ||
10. | |||
14. Copy of the document which identifies the current number of tubes in service for each | Provide copy of the calculation which establishes the limiting (maximum) design basis | ||
heat load which is required to be removed by each of these Hxs. | |||
11. | |||
15. Copy of the document establishing the repair criteria (plugging limit) for degraded tubes | Copy of the calculation which correlates surveillance testing results from these Hxs with | ||
design basis heat removal capability (e.g., basis for surveillance test acceptance | |||
16. Copy of the design specification and Hx data sheets for each Hx. | criteria). | ||
17. Copy of the vendor manuals including component drawings for each Hx. | 12. | ||
18. Copy of the calculations or documents which evaluate the potential for water hammer or | The clean and inspection maintenance schedule for each Hx for the next 5 years. | ||
13. | |||
19. Copy of Hx performance trending data tracked for each Hx. | Copy of the document describing the inspection results for the last two clean and | ||
20. Copies of those documents that describe the methods taken to control water chemistry | inspection activities completed on each Hx. | ||
14. | |||
Copy of the document which identifies the current number of tubes in service for each | |||
Hx and the supporting calculation which establishes the maximum number of tubes | |||
which can be plugged in each Hx. | |||
15. | |||
Copy of the document establishing the repair criteria (plugging limit) for degraded tubes | |||
which are identified in each Hx. | |||
16. | |||
Copy of the design specification and Hx data sheets for each Hx. | |||
17. | |||
Copy of the vendor manuals including component drawings for each Hx. | |||
18. | |||
Copy of the calculations or documents which evaluate the potential for water hammer or | |||
excessive tube vibration in the Hx or associated piping. | |||
19. | |||
Copy of Hx performance trending data tracked for each Hx. | |||
20. | |||
Copies of those documents that describe the methods taken to control water chemistry | |||
in the Hxs, including any provisions for controlling biotic fouling. | |||
BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST | |||
Initial Document Request | |||
21. Copies of the following documents: | Enclosure | ||
3 | |||
21. | |||
Copies of the following documents: | |||
a. | |||
Inspections of the weir or embankment and the crest of the dam; | |||
b. | |||
The rip rap protection placed on excavated side slopes; | |||
c. | |||
Licensees or third party dam inspections that monitor the integrity of the heat | |||
sink; | |||
d. | |||
Calculations demonstrating sufficient reservoir capacity; | |||
e. | |||
22. Copies of the documents that verify flow testing was done at maximum design flow | Maintenance records of inaccessible below-water portions of the UHS system | ||
with the methodology and results of underwater diving inspections; | |||
f. | |||
23. Copies of the documents that verify the structural integrity of the Hx, e.g., eddy current | Any design changes to the ultimate heat sink; | ||
g. | |||
24. Provide a list of calculations with a description which currently apply to each Hx. | Procedures or controls to address biotic fouling; | ||
25. Provide the Design Basis Documents for the above listed Hxs. | h. | ||
26. System health report(s) and maintenance rule system notebooks for these Hx(s). | Procedures for adverse weather conditions, e.g. icing or high temperatures; and | ||
27. Duane Arnold Energy Center Response to the Generic Letter 89-13. | i. | ||
28. Copies of procedures developed to implement the recommendations of GL 89-13, | Last two performance tests for all pumps and all valves in the safety-related | ||
service water system. If the components are not performance tested, please | |||
provide documentation verifying performance by the methods actually used. | |||
29. List of engineering-related Operator Workarounds/Temporary Modifications for these | 22. | ||
Copies of the documents that verify flow testing was done at maximum design flow | |||
during the last 2 years or since the last time it was done. Copies of the documents that | |||
verify maximum design flow testing will continue to be periodically done in the future. | |||
23. | |||
Copies of the documents that verify the structural integrity of the Hx, e.g., eddy current | |||
summary sheets, ultrasonic testing results, and visual inspection results. | |||
24. | |||
Provide a list of calculations with a description which currently apply to each Hx. | |||
25. | |||
Provide the Design Basis Documents for the above listed Hxs. | |||
26. | |||
System health report(s) and maintenance rule system notebooks for these Hx(s). | |||
27. | |||
Duane Arnold Energy Center Response to the Generic Letter 89-13. | |||
28. | |||
Copies of procedures developed to implement the recommendations of GL 89-13, | |||
Service Water System Problems Affecting Safety-Related Equipment, e.g., the | |||
GL 89-13 Heat Exchanger Program description. | |||
29. | |||
List of engineering-related Operator Workarounds/Temporary Modifications for these | |||
Hx(s) since the last Heat Sink Performance. | |||
BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST | |||
Initial Document Request | |||
30. | Enclosure | ||
4 | |||
31. | 30. | ||
Copy of self-assessments and audits for the selected Hxs and for the GL 89-13 Heat | |||
32. | Exchanger Program. | ||
31. | |||
Updated Final Safety Analysis Report pages for these Hx(s) and for the GL 89-13 Heat | |||
Exchanger Program. | |||
32. | |||
Information regarding any alarms which monitor on-line performance of these Hxs. | |||
If the information requested above will not be available, please contact Ms. Acosta Acevedo as | If the information requested above will not be available, please contact Ms. Acosta Acevedo as | ||
soon as possible at (630) 829-9718 or email cea4@nrc.gov. | soon as possible at (630) 829-9718 or email cea4@nrc.gov. | ||
}} | }} | ||
Latest revision as of 02:57, 15 January 2025
| ML070640539 | |
| Person / Time | |
|---|---|
| Site: | Duane Arnold |
| Issue date: | 03/05/2007 |
| From: | Ann Marie Stone NRC/RGN-III/DRS/EB2 |
| To: | Vanmiddlesworth G Nuclear Management Co |
| References | |
| IR-07-003 | |
| Download: ML070640539 (9) | |
See also: IR 05000331/2007003
Text
March 5, 2007
Mr. Gary Van Middlesworth
Vice-President
Duane Arnold Energy Center
3277 DAEC Road
Palo, IA 52324-9785
SUBJECT:
DUANE ARNOLD ENERGY CENTER
NOTIFICATION OF AN NRC BIENNIAL HEAT SINK PERFORMANCE
INSPECTION AND REQUEST FOR INFORMATION 05000331/2007003(DRS)
Dear Mr. Van Middlesworth:
On April 23, 2007, the NRC will begin the on-site portion of the Biennial Heat Sink Performance
Inspection at your Duane Arnold Energy Center. This inspection will be performed in
accordance with NRC baseline inspection procedure (IP) 71111.07. The heat exchangers
selected for detailed review during this baseline inspection are the 1B emergency diesel
generator cooler and the 1B residual heat removal heat exchanger.
We have enclosed a request for documents needed for the inspection. This information can be
sent to the following e-mail address cea4@nrc.gov, no later than April 13, 2007, so that we may
start the review of these documents. A hard-copy with the required information is also an
acceptable option.
The lead inspector for this inspection is Ms. Caroline Acosta Acevedo. If there are questions
about the material requested, or the inspection, please call Ms. Acosta Acevedo at
(630) 829-9718.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and
its enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRC's document system
G. Van Middlesworth
-2-
(ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the
Public Electronic Reading Room).
Sincerely,
/RA/
Ann Marie Stone, Chief
Engineering Branch 2
Division of Reactor Safety
Docket No. 50-331
License No. DPR-49
Enclosure: Heat Sink Inspection Document Request
cc w/encl:
J. Stall, Senior Vice President, Nuclear and Chief
Nuclear Officer
R. Helfrich, Senior Attorney
M. Ross, Managing Attorney
W. Webster, Vice President, Nuclear Operations
M. Warner, Vice President, Nuclear Operations Support
R. Kundalkar, Vice President, Nuclear Engineering
J. Bjorseth, Site Director
D. Curtland, Plant Manager
S. Catron, Manager, Regulatory Affairs
Chairman, Linn County Board of Supervisors
D. McGhee, State Liaison Officer
G. Van Middlesworth
-2-
(ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the
Public Electronic Reading Room).
Sincerely,
/RA/
Ann Marie Stone, Chief
Engineering Branch 2
Division of Reactor Safety
Docket No. 50-331
License No. DPR-49
Enclosure: Heat Sink Inspection Document Request
cc w/encl:
J. Stall, Senior Vice President, Nuclear and Chief
Nuclear Officer
R. Helfrich, Senior Attorney
M. Ross, Managing Attorney
W. Webster, Vice President, Nuclear Operations
M. Warner, Vice President, Nuclear Operations Support
R. Kundalkar, Vice President, Nuclear Engineering
J. Bjorseth, Site Director
D. Curtland, Plant Manager
S. Catron, Manager, Regulatory Affairs
Chairman, Linn County Board of Supervisors
D. McGhee, State Liaison Officer
DOCUMENT NAME: C:\\FileNet\\ML070640539.wpd
G Publicly Available
G Non-Publicly Available
G Sensitive
G Non-Sensitive
To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy
OFFICE
RIII
RIII
N
NAME
CAcostaAcevedo:co
AMStone
DATE
03/05/07
03/05/07
OFFICIAL RECORD COPY
G. Van Middlesworth
-3-
DISTRIBUTION:
TEB
DWS
RidsNrrDirsIrib
GEG
KGO
GLS
RJO
CAA1
DRPIII
DRSIII
PLB1
TXN
BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST
Initial Document Request
Enclosure
1
Inspection Report: 05000331/2007003(DRS)
Inspection Dates:
April 23 - 27, 2007
Inspection Procedures:
71111.07, Biennial Heat Sink Performance Inspection
Lead Inspector:
C. E. Acosta Acevedo
(630) 829-9718, cea4@nrc.gov
Information Requested Prior to the On-site Information Gathering/Inspection Week
The following information is requested to be provided as soon as possible, but no later than
April 13, 2007, to support the biennial Heat Sink Performance Inspection, IP 71111.07.
If some of the activities are not performed by your program, please note that fact. This request
is only for the time period from the onsite inspection back to the last Heat Sink Performance
Inspection in year 2005. If nothing addressing the request was done in that time period then
the request applies to the last applicable document in the previous time period. Unless
otherwise specified, all the below requests are for the selected heat exchangers (Hxs) which
are the 1B emergency diesel generator cooler and the 1B residual heat removal heat
exchanger.
1.
Copies of the two most recent completed tests confirming thermal performance for
those heat exchangers which are performance tested.
2.
For the two most recently completed tests confirming thermal performance of the
sample heat exchangers, please provide documentation and procedures that identify the
types, accuracy, and location of any special instrumentation used for these tests, (e.g.,
high accuracy ultrasonic flow instruments or temperature instruments). Include
calibration records for the instruments used during these tests.
3.
A list of corrective action program documents (with a short description) associated with
Hxs, heat sinks, silting, corrosion, fouling, or Hx testing, that are documented in your
corrective action system (for the previous 2 years or since the last biennial heat sink
inspection), this request is for all the Generic Letter 89-13 Hxs and the ultimate heat
sink.
4.
Copy of system description and design basis document for the Hxs under review (as
applicable).
BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST
Initial Document Request
Enclosure
2
5.
Copy of any operability determinations or other documentation of degradation
associated with the Hxs or the systems that support the operation of the Hxs.
6.
Copy of any self-assessment done within last 2 years on any of the licensees Hx
programs (e.g., Generic Letter 89-13 program Hxs) or on the sample Hxs.
7.
A schedule of all inspections, cleanings, maintenance, or testing of any plant Hx to be
done during the on-site portion of the inspection.
8.
List of operability evaluations currently relied upon and those that were previously (past
2 years) relied upon for operability.
9.
Copy of the evaluations of data for the two most recent completed tests confirming the
thermal performance of each Hx.
10.
Provide copy of the calculation which establishes the limiting (maximum) design basis
heat load which is required to be removed by each of these Hxs.
11.
Copy of the calculation which correlates surveillance testing results from these Hxs with
design basis heat removal capability (e.g., basis for surveillance test acceptance
criteria).
12.
The clean and inspection maintenance schedule for each Hx for the next 5 years.
13.
Copy of the document describing the inspection results for the last two clean and
inspection activities completed on each Hx.
14.
Copy of the document which identifies the current number of tubes in service for each
Hx and the supporting calculation which establishes the maximum number of tubes
which can be plugged in each Hx.
15.
Copy of the document establishing the repair criteria (plugging limit) for degraded tubes
which are identified in each Hx.
16.
Copy of the design specification and Hx data sheets for each Hx.
17.
Copy of the vendor manuals including component drawings for each Hx.
18.
Copy of the calculations or documents which evaluate the potential for water hammer or
excessive tube vibration in the Hx or associated piping.
19.
Copy of Hx performance trending data tracked for each Hx.
20.
Copies of those documents that describe the methods taken to control water chemistry
in the Hxs, including any provisions for controlling biotic fouling.
BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST
Initial Document Request
Enclosure
3
21.
Copies of the following documents:
a.
Inspections of the weir or embankment and the crest of the dam;
b.
The rip rap protection placed on excavated side slopes;
c.
Licensees or third party dam inspections that monitor the integrity of the heat
sink;
d.
Calculations demonstrating sufficient reservoir capacity;
e.
Maintenance records of inaccessible below-water portions of the UHS system
with the methodology and results of underwater diving inspections;
f.
Any design changes to the ultimate heat sink;
g.
Procedures or controls to address biotic fouling;
h.
Procedures for adverse weather conditions, e.g. icing or high temperatures; and
i.
Last two performance tests for all pumps and all valves in the safety-related
service water system. If the components are not performance tested, please
provide documentation verifying performance by the methods actually used.
22.
Copies of the documents that verify flow testing was done at maximum design flow
during the last 2 years or since the last time it was done. Copies of the documents that
verify maximum design flow testing will continue to be periodically done in the future.
23.
Copies of the documents that verify the structural integrity of the Hx, e.g., eddy current
summary sheets, ultrasonic testing results, and visual inspection results.
24.
Provide a list of calculations with a description which currently apply to each Hx.
25.
Provide the Design Basis Documents for the above listed Hxs.
26.
System health report(s) and maintenance rule system notebooks for these Hx(s).
27.
Duane Arnold Energy Center Response to the Generic Letter 89-13.
28.
Copies of procedures developed to implement the recommendations of GL 89-13,
Service Water System Problems Affecting Safety-Related Equipment, e.g., the
GL 89-13 Heat Exchanger Program description.
29.
List of engineering-related Operator Workarounds/Temporary Modifications for these
Hx(s) since the last Heat Sink Performance.
BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST
Initial Document Request
Enclosure
4
30.
Copy of self-assessments and audits for the selected Hxs and for the GL 89-13 Heat
Exchanger Program.
31.
Updated Final Safety Analysis Report pages for these Hx(s) and for the GL 89-13 Heat
Exchanger Program.
32.
Information regarding any alarms which monitor on-line performance of these Hxs.
If the information requested above will not be available, please contact Ms. Acosta Acevedo as
soon as possible at (630) 829-9718 or email cea4@nrc.gov.