ML070640539: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
Line 23: Line 23:
3277 DAEC Road
3277 DAEC Road
Palo, IA 52324-9785
Palo, IA 52324-9785
SUBJECT:       DUANE ARNOLD ENERGY CENTER
SUBJECT:
                NOTIFICATION OF AN NRC BIENNIAL HEAT SINK PERFORMANCE
DUANE ARNOLD ENERGY CENTER
                INSPECTION AND REQUEST FOR INFORMATION 05000331/2007003(DRS)
NOTIFICATION OF AN NRC BIENNIAL HEAT SINK PERFORMANCE
INSPECTION AND REQUEST FOR INFORMATION 05000331/2007003(DRS)
Dear Mr. Van Middlesworth:
Dear Mr. Van Middlesworth:
On April 23, 2007, the NRC will begin the on-site portion of the Biennial Heat Sink Performance
On April 23, 2007, the NRC will begin the on-site portion of the Biennial Heat Sink Performance
Inspection at your Duane Arnold Energy Center. This inspection will be performed in
Inspection at your Duane Arnold Energy Center. This inspection will be performed in
accordance with NRC baseline inspection procedure (IP) 71111.07. The heat exchangers
accordance with NRC baseline inspection procedure (IP) 71111.07. The heat exchangers
selected for detailed review during this baseline inspection are the 1B emergency diesel
selected for detailed review during this baseline inspection are the 1B emergency diesel
generator cooler and the 1B residual heat removal heat exchanger.
generator cooler and the 1B residual heat removal heat exchanger.
We have enclosed a request for documents needed for the inspection. This information can be
We have enclosed a request for documents needed for the inspection. This information can be
sent to the following e-mail address cea4@nrc.gov, no later than April 13, 2007, so that we may
sent to the following e-mail address cea4@nrc.gov, no later than April 13, 2007, so that we may
start the review of these documents. A hard-copy with the required information is also an
start the review of these documents. A hard-copy with the required information is also an
acceptable option.
acceptable option.
The lead inspector for this inspection is Ms. Caroline Acosta Acevedo. If there are questions
The lead inspector for this inspection is Ms. Caroline Acosta Acevedo. If there are questions
about the material requested, or the inspection, please call Ms. Acosta Acevedo at
about the material requested, or the inspection, please call Ms. Acosta Acevedo at
(630) 829-9718.
(630) 829-9718.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and
its enclosure will be available electronically for public inspection in the NRC Public Document
its enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRC's document system
Room or from the Publicly Available Records (PARS) component of NRC's document system  


G. Van Middlesworth                             -2-
G. Van Middlesworth
-2-
(ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the
(ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the
Public Electronic Reading Room).
Public Electronic Reading Room).
                                              Sincerely,
Sincerely,
                                              /RA/
/RA/
                                              Ann Marie Stone, Chief
Ann Marie Stone, Chief
                                              Engineering Branch 2
Engineering Branch 2
                                              Division of Reactor Safety
Division of Reactor Safety  
Docket No. 50-331
Docket No. 50-331
License No. DPR-49
License No. DPR-49
Enclosure: Heat Sink Inspection Document Request
Enclosure: Heat Sink Inspection Document Request
cc w/encl:     J. Stall, Senior Vice President, Nuclear and Chief
cc w/encl:
                Nuclear Officer
J. Stall, Senior Vice President, Nuclear and Chief
              R. Helfrich, Senior Attorney
  Nuclear Officer
              M. Ross, Managing Attorney
R. Helfrich, Senior Attorney
              W. Webster, Vice President, Nuclear Operations
M. Ross, Managing Attorney
              M. Warner, Vice President, Nuclear Operations Support
W. Webster, Vice President, Nuclear Operations
              R. Kundalkar, Vice President, Nuclear Engineering
M. Warner, Vice President, Nuclear Operations Support
              J. Bjorseth, Site Director
R. Kundalkar, Vice President, Nuclear Engineering
              D. Curtland, Plant Manager
J. Bjorseth, Site Director
              S. Catron, Manager, Regulatory Affairs
D. Curtland, Plant Manager
              Chairman, Linn County Board of Supervisors
S. Catron, Manager, Regulatory Affairs
              D. McGhee, State Liaison Officer
Chairman, Linn County Board of Supervisors
D. McGhee, State Liaison Officer


G. Van Middlesworth                                                         -2-
G. Van Middlesworth
-2-
(ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the
(ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the
Public Electronic Reading Room).
Public Electronic Reading Room).
                                                                          Sincerely,
Sincerely,
                                                                          /RA/
/RA/
                                                                          Ann Marie Stone, Chief
Ann Marie Stone, Chief
                                                                          Engineering Branch 2
Engineering Branch 2
                                                                          Division of Reactor Safety
Division of Reactor Safety  
Docket No. 50-331
Docket No. 50-331
License No. DPR-49
License No. DPR-49
Enclosure: Heat Sink Inspection Document Request
Enclosure: Heat Sink Inspection Document Request
cc w/encl:               J. Stall, Senior Vice President, Nuclear and Chief
cc w/encl:
                            Nuclear Officer
J. Stall, Senior Vice President, Nuclear and Chief
                          R. Helfrich, Senior Attorney
  Nuclear Officer
                          M. Ross, Managing Attorney
R. Helfrich, Senior Attorney
                          W. Webster, Vice President, Nuclear Operations
M. Ross, Managing Attorney
                          M. Warner, Vice President, Nuclear Operations Support
W. Webster, Vice President, Nuclear Operations
                          R. Kundalkar, Vice President, Nuclear Engineering
M. Warner, Vice President, Nuclear Operations Support
                          J. Bjorseth, Site Director
R. Kundalkar, Vice President, Nuclear Engineering
                          D. Curtland, Plant Manager
J. Bjorseth, Site Director
                          S. Catron, Manager, Regulatory Affairs
D. Curtland, Plant Manager
                          Chairman, Linn County Board of Supervisors
S. Catron, Manager, Regulatory Affairs
                          D. McGhee, State Liaison Officer
Chairman, Linn County Board of Supervisors
DOCUMENT NAME: C:\FileNet\ML070640539.wpd
D. McGhee, State Liaison Officer
G Publicly Available                       G Non-Publicly Available                 G Sensitive             G Non-Sensitive
DOCUMENT NAME: C:\\FileNet\\ML070640539.wpd  
To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy
G Publicly Available
OFFICE             RIII                                     RIII                                                           N
G Non-Publicly Available
NAME               CAcostaAcevedo:co                       AMStone
G Sensitive
DATE               03/05/07                                 03/05/07
G Non-Sensitive
                                                          OFFICIAL RECORD COPY
To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy
OFFICE
RIII
RIII
N
NAME
CAcostaAcevedo:co
AMStone
DATE
03/05/07
03/05/07
OFFICIAL RECORD COPY


G. Van Middlesworth -3-
G. Van Middlesworth
-3-
DISTRIBUTION:
DISTRIBUTION:
TEB
TEB
Line 113: Line 129:
TXN
TXN


        BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST
BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST
                                        Initial Document Request
Initial Document Request
Inspection Report:               05000331/2007003(DRS)
Enclosure
Inspection Dates:                 April 23 - 27, 2007
1
Inspection Procedures:           71111.07, Biennial Heat Sink Performance Inspection
Inspection Report:
Lead Inspector:                   C. E. Acosta Acevedo
05000331/2007003(DRS)
                                  (630) 829-9718, cea4@nrc.gov
Inspection Dates:
Information Requested Prior to the On-site Information Gathering/Inspection Week
April 23 - 27, 2007
Inspection Procedures:
71111.07, Biennial Heat Sink Performance Inspection
Lead Inspector:
C. E. Acosta Acevedo
(630) 829-9718, cea4@nrc.gov
Information Requested Prior to the On-site Information Gathering/Inspection Week  
The following information is requested to be provided as soon as possible, but no later than
The following information is requested to be provided as soon as possible, but no later than
April 13, 2007, to support the biennial Heat Sink Performance Inspection, IP 71111.07.
April 13, 2007, to support the biennial Heat Sink Performance Inspection, IP 71111.07.  
If some of the activities are not performed by your program, please note that fact. This request
If some of the activities are not performed by your program, please note that fact. This request
is only for the time period from the onsite inspection back to the last Heat Sink Performance
is only for the time period from the onsite inspection back to the last Heat Sink Performance
Inspection in year 2005. If nothing addressing the request was done in that time period then
Inspection in year 2005. If nothing addressing the request was done in that time period then
the request applies to the last applicable document in the previous time period. Unless
the request applies to the last applicable document in the previous time period. Unless
otherwise specified, all the below requests are for the selected heat exchangers (Hxs) which
otherwise specified, all the below requests are for the selected heat exchangers (Hxs) which
are the 1B emergency diesel generator cooler and the 1B residual heat removal heat
are the 1B emergency diesel generator cooler and the 1B residual heat removal heat
exchanger.
exchanger.
1.       Copies of the two most recent completed tests confirming thermal performance for
1.
        those heat exchangers which are performance tested.
Copies of the two most recent completed tests confirming thermal performance for
2.       For the two most recently completed tests confirming thermal performance of the
those heat exchangers which are performance tested.
        sample heat exchangers, please provide documentation and procedures that identify the
2.
        types, accuracy, and location of any special instrumentation used for these tests, (e.g.,
For the two most recently completed tests confirming thermal performance of the
        high accuracy ultrasonic flow instruments or temperature instruments). Include
sample heat exchangers, please provide documentation and procedures that identify the
        calibration records for the instruments used during these tests.
types, accuracy, and location of any special instrumentation used for these tests, (e.g.,
3.       A list of corrective action program documents (with a short description) associated with
high accuracy ultrasonic flow instruments or temperature instruments). Include
        Hxs, heat sinks, silting, corrosion, fouling, or Hx testing, that are documented in your
calibration records for the instruments used during these tests.
        corrective action system (for the previous 2 years or since the last biennial heat sink
3.
        inspection), this request is for all the Generic Letter 89-13 Hxs and the ultimate heat
A list of corrective action program documents (with a short description) associated with
        sink.
Hxs, heat sinks, silting, corrosion, fouling, or Hx testing, that are documented in your
4.       Copy of system description and design basis document for the Hxs under review (as
corrective action system (for the previous 2 years or since the last biennial heat sink
        applicable).
inspection), this request is for all the Generic Letter 89-13 Hxs and the ultimate heat
                                                    1                                      Enclosure
sink.
4.
Copy of system description and design basis document for the Hxs under review (as
applicable).


    BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST
BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST
                                Initial Document Request
Initial Document Request
5. Copy of any operability determinations or other documentation of degradation
Enclosure
    associated with the Hxs or the systems that support the operation of the Hxs.
2
6. Copy of any self-assessment done within last 2 years on any of the licensees Hx
5.
    programs (e.g., Generic Letter 89-13 program Hxs) or on the sample Hxs.
Copy of any operability determinations or other documentation of degradation
7. A schedule of all inspections, cleanings, maintenance, or testing of any plant Hx to be
associated with the Hxs or the systems that support the operation of the Hxs.
    done during the on-site portion of the inspection.
6.
8. List of operability evaluations currently relied upon and those that were previously (past
Copy of any self-assessment done within last 2 years on any of the licensees Hx
    2 years) relied upon for operability.
programs (e.g., Generic Letter 89-13 program Hxs) or on the sample Hxs.
9. Copy of the evaluations of data for the two most recent completed tests confirming the
7.
    thermal performance of each Hx.
A schedule of all inspections, cleanings, maintenance, or testing of any plant Hx to be
10. Provide copy of the calculation which establishes the limiting (maximum) design basis
done during the on-site portion of the inspection.
    heat load which is required to be removed by each of these Hxs.
8.
11. Copy of the calculation which correlates surveillance testing results from these Hxs with
List of operability evaluations currently relied upon and those that were previously (past
    design basis heat removal capability (e.g., basis for surveillance test acceptance
2 years) relied upon for operability.
    criteria).
9.
12. The clean and inspection maintenance schedule for each Hx for the next 5 years.
Copy of the evaluations of data for the two most recent completed tests confirming the
13. Copy of the document describing the inspection results for the last two clean and
thermal performance of each Hx.
    inspection activities completed on each Hx.
10.
14. Copy of the document which identifies the current number of tubes in service for each
Provide copy of the calculation which establishes the limiting (maximum) design basis
    Hx and the supporting calculation which establishes the maximum number of tubes
heat load which is required to be removed by each of these Hxs.
    which can be plugged in each Hx.
11.
15. Copy of the document establishing the repair criteria (plugging limit) for degraded tubes
Copy of the calculation which correlates surveillance testing results from these Hxs with
    which are identified in each Hx.
design basis heat removal capability (e.g., basis for surveillance test acceptance
16. Copy of the design specification and Hx data sheets for each Hx.
criteria).
17. Copy of the vendor manuals including component drawings for each Hx.
12.
18. Copy of the calculations or documents which evaluate the potential for water hammer or
The clean and inspection maintenance schedule for each Hx for the next 5 years.
    excessive tube vibration in the Hx or associated piping.
13.
19. Copy of Hx performance trending data tracked for each Hx.
Copy of the document describing the inspection results for the last two clean and
20. Copies of those documents that describe the methods taken to control water chemistry
inspection activities completed on each Hx.
    in the Hxs, including any provisions for controlling biotic fouling.
14.
                                              2                                    Enclosure
Copy of the document which identifies the current number of tubes in service for each
Hx and the supporting calculation which establishes the maximum number of tubes
which can be plugged in each Hx.
15.
Copy of the document establishing the repair criteria (plugging limit) for degraded tubes
which are identified in each Hx.
16.
Copy of the design specification and Hx data sheets for each Hx.
17.
Copy of the vendor manuals including component drawings for each Hx.
18.
Copy of the calculations or documents which evaluate the potential for water hammer or
excessive tube vibration in the Hx or associated piping.
19.
Copy of Hx performance trending data tracked for each Hx.
20.
Copies of those documents that describe the methods taken to control water chemistry
in the Hxs, including any provisions for controlling biotic fouling.


    BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST
BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST
                                  Initial Document Request
Initial Document Request
21. Copies of the following documents:
Enclosure
    a.       Inspections of the weir or embankment and the crest of the dam;
3
    b.       The rip rap protection placed on excavated side slopes;
21.
    c.       Licensees or third party dam inspections that monitor the integrity of the heat
Copies of the following documents:
            sink;
a.
    d.       Calculations demonstrating sufficient reservoir capacity;
Inspections of the weir or embankment and the crest of the dam;
    e.       Maintenance records of inaccessible below-water portions of the UHS system
b.
            with the methodology and results of underwater diving inspections;
The rip rap protection placed on excavated side slopes;
    f.       Any design changes to the ultimate heat sink;
c.
    g.       Procedures or controls to address biotic fouling;
Licensees or third party dam inspections that monitor the integrity of the heat
    h.       Procedures for adverse weather conditions, e.g. icing or high temperatures; and
sink;
    i.       Last two performance tests for all pumps and all valves in the safety-related
d.
            service water system. If the components are not performance tested, please
Calculations demonstrating sufficient reservoir capacity;
            provide documentation verifying performance by the methods actually used.
e.
22. Copies of the documents that verify flow testing was done at maximum design flow
Maintenance records of inaccessible below-water portions of the UHS system
    during the last 2 years or since the last time it was done. Copies of the documents that
with the methodology and results of underwater diving inspections;
    verify maximum design flow testing will continue to be periodically done in the future.
f.  
23. Copies of the documents that verify the structural integrity of the Hx, e.g., eddy current
Any design changes to the ultimate heat sink;
    summary sheets, ultrasonic testing results, and visual inspection results.
g.  
24. Provide a list of calculations with a description which currently apply to each Hx.
Procedures or controls to address biotic fouling;
25. Provide the Design Basis Documents for the above listed Hxs.
h.
26. System health report(s) and maintenance rule system notebooks for these Hx(s).
Procedures for adverse weather conditions, e.g. icing or high temperatures; and
27. Duane Arnold Energy Center Response to the Generic Letter 89-13.
i.
28. Copies of procedures developed to implement the recommendations of GL 89-13,
Last two performance tests for all pumps and all valves in the safety-related
    Service Water System Problems Affecting Safety-Related Equipment, e.g., the
service water system. If the components are not performance tested, please
    GL 89-13 Heat Exchanger Program description.
provide documentation verifying performance by the methods actually used.
29. List of engineering-related Operator Workarounds/Temporary Modifications for these
22.
    Hx(s) since the last Heat Sink Performance.
Copies of the documents that verify flow testing was done at maximum design flow
                                              3                                      Enclosure
during the last 2 years or since the last time it was done. Copies of the documents that
verify maximum design flow testing will continue to be periodically done in the future.
23.
Copies of the documents that verify the structural integrity of the Hx, e.g., eddy current
summary sheets, ultrasonic testing results, and visual inspection results.
24.
Provide a list of calculations with a description which currently apply to each Hx.
25.
Provide the Design Basis Documents for the above listed Hxs.
26.
System health report(s) and maintenance rule system notebooks for these Hx(s).
27.
Duane Arnold Energy Center Response to the Generic Letter 89-13.
28.
Copies of procedures developed to implement the recommendations of GL 89-13,
Service Water System Problems Affecting Safety-Related Equipment, e.g., the
GL 89-13 Heat Exchanger Program description.
29.
List of engineering-related Operator Workarounds/Temporary Modifications for these
Hx(s) since the last Heat Sink Performance.


        BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST
BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST
                                  Initial Document Request
Initial Document Request
30.     Copy of self-assessments and audits for the selected Hxs and for the GL 89-13 Heat
Enclosure
        Exchanger Program.
4
31.     Updated Final Safety Analysis Report pages for these Hx(s) and for the GL 89-13 Heat
30.
        Exchanger Program.
Copy of self-assessments and audits for the selected Hxs and for the GL 89-13 Heat
32.     Information regarding any alarms which monitor on-line performance of these Hxs.
Exchanger Program.
31.
Updated Final Safety Analysis Report pages for these Hx(s) and for the GL 89-13 Heat
Exchanger Program.
32.
Information regarding any alarms which monitor on-line performance of these Hxs.
If the information requested above will not be available, please contact Ms. Acosta Acevedo as
If the information requested above will not be available, please contact Ms. Acosta Acevedo as
soon as possible at (630) 829-9718 or email cea4@nrc.gov.
soon as possible at (630) 829-9718 or email cea4@nrc.gov.
                                                4                                    Enclosure
}}
}}

Latest revision as of 02:57, 15 January 2025

Ltr. 03/05/07 Duane Arnold Request for Information IR 5000331-07-003
ML070640539
Person / Time
Site: Duane Arnold NextEra Energy icon.png
Issue date: 03/05/2007
From: Ann Marie Stone
NRC/RGN-III/DRS/EB2
To: Vanmiddlesworth G
Nuclear Management Co
References
IR-07-003
Download: ML070640539 (9)


See also: IR 05000331/2007003

Text

March 5, 2007

Mr. Gary Van Middlesworth

Vice-President

Duane Arnold Energy Center

3277 DAEC Road

Palo, IA 52324-9785

SUBJECT:

DUANE ARNOLD ENERGY CENTER

NOTIFICATION OF AN NRC BIENNIAL HEAT SINK PERFORMANCE

INSPECTION AND REQUEST FOR INFORMATION 05000331/2007003(DRS)

Dear Mr. Van Middlesworth:

On April 23, 2007, the NRC will begin the on-site portion of the Biennial Heat Sink Performance

Inspection at your Duane Arnold Energy Center. This inspection will be performed in

accordance with NRC baseline inspection procedure (IP) 71111.07. The heat exchangers

selected for detailed review during this baseline inspection are the 1B emergency diesel

generator cooler and the 1B residual heat removal heat exchanger.

We have enclosed a request for documents needed for the inspection. This information can be

sent to the following e-mail address cea4@nrc.gov, no later than April 13, 2007, so that we may

start the review of these documents. A hard-copy with the required information is also an

acceptable option.

The lead inspector for this inspection is Ms. Caroline Acosta Acevedo. If there are questions

about the material requested, or the inspection, please call Ms. Acosta Acevedo at

(630) 829-9718.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and

its enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRC's document system

G. Van Middlesworth

-2-

(ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the

Public Electronic Reading Room).

Sincerely,

/RA/

Ann Marie Stone, Chief

Engineering Branch 2

Division of Reactor Safety

Docket No. 50-331

License No. DPR-49

Enclosure: Heat Sink Inspection Document Request

cc w/encl:

J. Stall, Senior Vice President, Nuclear and Chief

Nuclear Officer

R. Helfrich, Senior Attorney

M. Ross, Managing Attorney

W. Webster, Vice President, Nuclear Operations

M. Warner, Vice President, Nuclear Operations Support

R. Kundalkar, Vice President, Nuclear Engineering

J. Bjorseth, Site Director

D. Curtland, Plant Manager

S. Catron, Manager, Regulatory Affairs

Chairman, Linn County Board of Supervisors

D. McGhee, State Liaison Officer

G. Van Middlesworth

-2-

(ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the

Public Electronic Reading Room).

Sincerely,

/RA/

Ann Marie Stone, Chief

Engineering Branch 2

Division of Reactor Safety

Docket No. 50-331

License No. DPR-49

Enclosure: Heat Sink Inspection Document Request

cc w/encl:

J. Stall, Senior Vice President, Nuclear and Chief

Nuclear Officer

R. Helfrich, Senior Attorney

M. Ross, Managing Attorney

W. Webster, Vice President, Nuclear Operations

M. Warner, Vice President, Nuclear Operations Support

R. Kundalkar, Vice President, Nuclear Engineering

J. Bjorseth, Site Director

D. Curtland, Plant Manager

S. Catron, Manager, Regulatory Affairs

Chairman, Linn County Board of Supervisors

D. McGhee, State Liaison Officer

DOCUMENT NAME: C:\\FileNet\\ML070640539.wpd

G Publicly Available

G Non-Publicly Available

G Sensitive

G Non-Sensitive

To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE

RIII

RIII

N

NAME

CAcostaAcevedo:co

AMStone

DATE

03/05/07

03/05/07

OFFICIAL RECORD COPY

G. Van Middlesworth

-3-

DISTRIBUTION:

TEB

DWS

RidsNrrDirsIrib

GEG

KGO

GLS

RJO

CAA1

DRPIII

DRSIII

PLB1

TXN

BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST

Initial Document Request

Enclosure

1

Inspection Report: 05000331/2007003(DRS)

Inspection Dates:

April 23 - 27, 2007

Inspection Procedures:

71111.07, Biennial Heat Sink Performance Inspection

Lead Inspector:

C. E. Acosta Acevedo

(630) 829-9718, cea4@nrc.gov

Information Requested Prior to the On-site Information Gathering/Inspection Week

The following information is requested to be provided as soon as possible, but no later than

April 13, 2007, to support the biennial Heat Sink Performance Inspection, IP 71111.07.

If some of the activities are not performed by your program, please note that fact. This request

is only for the time period from the onsite inspection back to the last Heat Sink Performance

Inspection in year 2005. If nothing addressing the request was done in that time period then

the request applies to the last applicable document in the previous time period. Unless

otherwise specified, all the below requests are for the selected heat exchangers (Hxs) which

are the 1B emergency diesel generator cooler and the 1B residual heat removal heat

exchanger.

1.

Copies of the two most recent completed tests confirming thermal performance for

those heat exchangers which are performance tested.

2.

For the two most recently completed tests confirming thermal performance of the

sample heat exchangers, please provide documentation and procedures that identify the

types, accuracy, and location of any special instrumentation used for these tests, (e.g.,

high accuracy ultrasonic flow instruments or temperature instruments). Include

calibration records for the instruments used during these tests.

3.

A list of corrective action program documents (with a short description) associated with

Hxs, heat sinks, silting, corrosion, fouling, or Hx testing, that are documented in your

corrective action system (for the previous 2 years or since the last biennial heat sink

inspection), this request is for all the Generic Letter 89-13 Hxs and the ultimate heat

sink.

4.

Copy of system description and design basis document for the Hxs under review (as

applicable).

BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST

Initial Document Request

Enclosure

2

5.

Copy of any operability determinations or other documentation of degradation

associated with the Hxs or the systems that support the operation of the Hxs.

6.

Copy of any self-assessment done within last 2 years on any of the licensees Hx

programs (e.g., Generic Letter 89-13 program Hxs) or on the sample Hxs.

7.

A schedule of all inspections, cleanings, maintenance, or testing of any plant Hx to be

done during the on-site portion of the inspection.

8.

List of operability evaluations currently relied upon and those that were previously (past

2 years) relied upon for operability.

9.

Copy of the evaluations of data for the two most recent completed tests confirming the

thermal performance of each Hx.

10.

Provide copy of the calculation which establishes the limiting (maximum) design basis

heat load which is required to be removed by each of these Hxs.

11.

Copy of the calculation which correlates surveillance testing results from these Hxs with

design basis heat removal capability (e.g., basis for surveillance test acceptance

criteria).

12.

The clean and inspection maintenance schedule for each Hx for the next 5 years.

13.

Copy of the document describing the inspection results for the last two clean and

inspection activities completed on each Hx.

14.

Copy of the document which identifies the current number of tubes in service for each

Hx and the supporting calculation which establishes the maximum number of tubes

which can be plugged in each Hx.

15.

Copy of the document establishing the repair criteria (plugging limit) for degraded tubes

which are identified in each Hx.

16.

Copy of the design specification and Hx data sheets for each Hx.

17.

Copy of the vendor manuals including component drawings for each Hx.

18.

Copy of the calculations or documents which evaluate the potential for water hammer or

excessive tube vibration in the Hx or associated piping.

19.

Copy of Hx performance trending data tracked for each Hx.

20.

Copies of those documents that describe the methods taken to control water chemistry

in the Hxs, including any provisions for controlling biotic fouling.

BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST

Initial Document Request

Enclosure

3

21.

Copies of the following documents:

a.

Inspections of the weir or embankment and the crest of the dam;

b.

The rip rap protection placed on excavated side slopes;

c.

Licensees or third party dam inspections that monitor the integrity of the heat

sink;

d.

Calculations demonstrating sufficient reservoir capacity;

e.

Maintenance records of inaccessible below-water portions of the UHS system

with the methodology and results of underwater diving inspections;

f.

Any design changes to the ultimate heat sink;

g.

Procedures or controls to address biotic fouling;

h.

Procedures for adverse weather conditions, e.g. icing or high temperatures; and

i.

Last two performance tests for all pumps and all valves in the safety-related

service water system. If the components are not performance tested, please

provide documentation verifying performance by the methods actually used.

22.

Copies of the documents that verify flow testing was done at maximum design flow

during the last 2 years or since the last time it was done. Copies of the documents that

verify maximum design flow testing will continue to be periodically done in the future.

23.

Copies of the documents that verify the structural integrity of the Hx, e.g., eddy current

summary sheets, ultrasonic testing results, and visual inspection results.

24.

Provide a list of calculations with a description which currently apply to each Hx.

25.

Provide the Design Basis Documents for the above listed Hxs.

26.

System health report(s) and maintenance rule system notebooks for these Hx(s).

27.

Duane Arnold Energy Center Response to the Generic Letter 89-13.

28.

Copies of procedures developed to implement the recommendations of GL 89-13,

Service Water System Problems Affecting Safety-Related Equipment, e.g., the

GL 89-13 Heat Exchanger Program description.

29.

List of engineering-related Operator Workarounds/Temporary Modifications for these

Hx(s) since the last Heat Sink Performance.

BIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST

Initial Document Request

Enclosure

4

30.

Copy of self-assessments and audits for the selected Hxs and for the GL 89-13 Heat

Exchanger Program.

31.

Updated Final Safety Analysis Report pages for these Hx(s) and for the GL 89-13 Heat

Exchanger Program.

32.

Information regarding any alarms which monitor on-line performance of these Hxs.

If the information requested above will not be available, please contact Ms. Acosta Acevedo as

soon as possible at (630) 829-9718 or email cea4@nrc.gov.