{{#Wiki_filter:UNITED STATES
{{#Wiki_filter:UNITED STATES
NUCLEAR REGULATORY COMMISSION
                            NUCLEAR REGULATORY COMMISSION
REGION IV 1600 E. LAMAR BLVD. ARLINGTON, TX
                                                REGION IV
  76011-4511 June 19, 201 7  Mr. Fadi Diya, Senior Vice President  
                                          1600 E. LAMAR BLVD.
  and Chief Nuclear Officer
                                        ARLINGTON, TX 76011-4511
Ameren Missouri
                                            June 19, 2017
Callaway Plant
Mr. Fadi Diya, Senior Vice President
P.O. Box 620 Fulton, MO 65251
  and Chief Nuclear Officer
  SUBJECT: CALLAWAY PLANT - NOTIFICATION OF NRC INSPECTION OF THE IMPLEMENTATION OF MITIGATION STRATEGIES AND SPENT FUEL POOL  
Ameren Missouri
INSTRUMENTATION ORDERS AND EMERGENCY PREPAREDNESS  
Callaway Plant
COMMUNICATION/
P.O. Box 620
STAFFING/MULTI
Fulton, MO 65251
-UNIT DOSE ASSESSMENT PLANS
SUBJECT:       CALLAWAY PLANT - NOTIFICATION OF NRC INSPECTION OF THE
(05000483/2017008) AND REQUEST FOR INFORMATION
                IMPLEMENTATION OF MITIGATION STRATEGIES AND SPENT FUEL POOL
  Dear Mr. Diya: The purpose of this letter is to notify you that
                INSTRUMENTATION ORDERS AND EMERGENCY PREPAREDNESS
the U.S. Nuclear Regulatory Commission (NRC) staff will conduct a mitigation strategies for beyond
                COMMUNICATION/ STAFFING/MULTI-UNIT DOSE ASSESSMENT PLANS
-design-basis external events, spent fuel pool instrumentation, and emergency preparedness enhancements inspection at the
                (05000483/2017008) AND REQUEST FOR INFORMATION
Callaway Plant
Dear Mr. Diya:
from August 28 - September 1, 2017. The inspection will consist of three reactor inspectors from the NRC
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)
's Region IV office, plus one of the assigned Resident Inspectors at the Callaway Plant for one week. The inspection will be conducted in accordance with
staff will conduct a mitigation strategies for beyond-design-basis external events, spent fuel pool
the NRC's Temporary Instruction 2515/191 , "Inspection of the Implementation of Mitigating Strategies and Spent Fuel Pool Instrumentation Orders, and Emergency Preparedness Communication/Staffing/Multi
instrumentation, and emergency preparedness enhancements inspection at the Callaway Plant
-Unit Dose Assessment Plans.
from August 28 - September 1, 2017. The inspection will consist of three reactor inspectors
Experience has shown that this inspection is resource intensive both for the NRC inspectors  
from the NRCs Region IV office, plus one of the assigned Resident Inspectors at the Callaway
and licensee staff. In order to minimize the impact to your onsite resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection
Plant for one week. The inspection will be conducted in accordance with the NRCs Temporary
activity. Please note that the documents
Instruction 2515/191, Inspection of the Implementation of Mitigating Strategies and Spent Fuel
are requested to be provided by
Pool Instrumentation Orders, and Emergency Preparedness Communication/Staffing/Multi-Unit
August 11, 2017
Dose Assessment Plans.
During the onsite inspection, inspectors will verify that plans for complying with NRC Orders  
Experience has shown that this inspection is resource intensive both for the NRC inspectors
EA-12-049 and EA
and licensee staff. In order to minimize the impact to your onsite resources and to ensure a
-12-051 are in place and are being implemented. Inspectors will also verify the establishment of staffing and communications plans provided in response to the March 12, 2012, request for information letter, and multi-unit dose assessment information provided per COMSECY-13-0010, Schedule and Plans for Tier 2 Order on Emergency Preparedness for Japan Lessons Learned, dated March 27, 2013. These plans and information were provided in the site specific submittals, which were subsequently reviewed by the NRC staff for  
productive inspection, we have enclosed a request for documents needed for this inspection
understanding and documented in the NRC's plant safety evaluations (SEs) and safety  
activity. Please note that the documents are requested to be provided by August 11, 2017.
assessments. Therefore, appropriate personnel knowledgeable of
During the onsite inspection, inspectors will verify that plans for complying with NRC Orders
the station's FLEX  
EA-12-049 and EA-12-051 are in place and are being implemented. Inspectors will also verify
strategies, spent fuel pool instrumentation, and emergency preparedness enhancements
the establishment of staffing and communications plans provided in response to the March 12,
should be available to support the inspector s at the site during the inspection.
2012, request for information letter, and multi-unit dose assessment information provided per
 
COMSECY-13-0010, Schedule and Plans for Tier 2 Order on Emergency Preparedness for
 
Japan Lessons Learned, dated March 27, 2013. These plans and information were provided in
F. Diya 2     We have discussed the schedule for th
the site specific submittals, which were subsequently reviewed by the NRC staff for
is inspection activit
understanding and documented in the NRCs plant safety evaluations (SEs) and safety
y with your staff and understand that our regulatory contact for this inspection will be
assessments. Therefore, appropriate personnel knowledgeable of the stations FLEX
Elizabeth Ptasznik
strategies, spent fuel pool instrumentation, and emergency preparedness enhancements should
of your licensing organization. If there are any questions about this inspection or the material requested, please contact the l ead inspector , Ryan D. Alexander
be available to support the inspectors at the site during the inspection.
, by telephone  
 
at 817-200-1195 or by e-mail at ryan.alexander@nrc.gov.  
F. Diya                                           2
This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection  
We have discussed the schedule for this inspection activity with your staff and understand that
requirements were approved by the Office of Management and Budget, control number 3150 0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control  
our regulatory contact for this inspection will be Elizabeth Ptasznik of your licensing
number.
organization. If there are any questions about this inspection or the material requested, please
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC
contact the lead inspector, Ryan D. Alexander, by telephone at 817-200-1195 or by e-mail at
's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading
ryan.alexander@nrc.gov.
-rm/adams.html
This letter does not contain new or amended information collection requirements subject to the
(the Public Electronic Reading Room).
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection
  Sincerely,       /RA/   John L. Dixon , Acting Chief Project Branch B
requirements were approved by the Office of Management and Budget, control
Division of Reactor Projects
number 3150 0011. The NRC may not conduct or sponsor, and a person is not required to
Docket No. 50
respond to, a request for information or an information collection requirement unless the
-483 License No. NPF
requesting document displays a currently valid Office of Management and Budget control
-30
number.
Enclosure:   FLEX Strategies, Spent Fuel Pool  
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its
Instrumentation
enclosure will be available electronically for public inspection in the NRC Public Document
, & EP Enhancements  
Room or from the Publicly Available Records (PARS) component of NRCs document system
Inspection
(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
Request for Information
rm/adams.html (the Public Electronic Reading Room).
     
                                                Sincerely,
  1 Enclosure Request for Information
                                                /RA/
FLEX Strategies, Spent Fuel Pool Instrumentation, & EP Enhancements
                                                John L. Dixon, Acting Chief
Inspection
                                                Project Branch B
Callaway Plant
                                                Division of Reactor Projects
  Inspection Report:
Docket No. 50-483
050004 83/2017 008  Inspection Dates:
License No. NPF-30
  August 28  
Enclosure:
- September 1
FLEX Strategies, Spent Fuel Pool
, 2017
Instrumentation, & EP Enhancements
Inspection Procedure:
Inspection Request for Information
Temporary Instruction 2515/191 , "Inspection of the Implementation of Mitigating Strategies and Spent Fuel Pool Instrumentation Orders, and Emergency Preparedness Communication/Staffing/Multi
 
-Unit Dose Assessment Plans"
                                    Request for Information
  Inspect o r s:   Ryan D. Alexander
    FLEX Strategies, Spent Fuel Pool Instrumentation, & EP Enhancements Inspection
, Team Lead, Sr.
                                          Callaway Plant
Project Engineer, Region IV
Inspection Report:             05000483/2017008
    Dan Bradley , Callaway Plant
Inspection Dates:             August 28 - September 1, 2017
Senior Resident Inspector
Inspection Procedure:         Temporary Instruction 2515/191, Inspection of the
    Steve Alferink, Reactor Inspector, Region IV
                              Implementation of Mitigating Strategies and Spent Fuel Pool
    Michael Stafford, Project Engineer, Region IV
                              Instrumentation Orders, and Emergency Preparedness
 
                              Communication/Staffing/Multi-Unit Dose Assessment Plans
Information Requested for the In-Office Preparation Week
Inspectors:                   Ryan D. Alexander, Team Lead, Sr. Project Engineer, Region IV
  The following information should be sent to the Region IV office in hard copy or electronic format (use of the Certrec IMS
                              Dan Bradley, Callaway Plant Senior Resident Inspector
information portal is preferred), to the attention  
                              Steve Alferink, Reactor Inspector, Region IV
of Ryan Alexander , by August 11, 2017. The inspector s will select specific items from the information requested below and then request from your staff additional documents needed during the onsite inspection week. Also, we request that you categorize the documents in your response with the numbered list below.  
                              Michael Stafford, Project Engineer, Region IV
Please provide requested documentation electronically if possible. If requested documents are large and only hard copy formats are available, please inform the
Information Requested for the In-Office Preparation Week
lead inspector, and provide
The following information should be sent to the Region IV office in hard copy or electronic
subject documentation during the first day of the onsite inspection. If you have any questions regarding this information request, please call the lead  
format (use of the Certrec IMS information portal is preferred), to the attention of Ryan
Alexander, by August 11, 2017. The inspectors will select specific items from the information
requested below and then request from your staff additional documents needed during the
onsite inspection week. Also, we request that you categorize the documents in your response
with the numbered list below. Please provide requested documentation electronically if
possible. If requested documents are large and only hard copy formats are available, please
inform the lead inspector, and provide subject documentation during the first day of the onsite
inspection. If you have any questions regarding this information request, please call the lead
inspector as soon as possible.
inspector as soon as possible.
  TI 2515/191  
TI 2515/191 - Appendix A
- Appendix A
A. Provide current revision of the FLEX Final Integrated Plan (i.e., current FLEX Program
A. Provide current revision of the FLEX Final Integrated Plan
    Document), including any revisions since July 2016 submission to the NRC.
(i.e., current FLEX Program Document), including any revisions since July 2016 submission to the NRC
B. Provide the FLEX Strategy Basis Document.
. B. Provide the FLEX Strategy Basis Document.
C. Provide each operating, off-normal, abnormal, and/or emergency procedures where entry
C. Provide each operating, off
    into one or more FLEX Support Guideline(s) are initiated.
-normal, abnormal, and/or emergency procedures where entry into one or more
D. Provide a list and copies of every FLEX Support Guideline (FSG) or equivalent procedure
FLEX Support Guideline(s) are initiated
    which you developed or revised to implement your mitigating strategies.
. D. Provide a list  
E. Provide a list of key pieces of equipment that directly perform a FLEX mitigation strategy for
and copies of every FLEX Support Guideline (FSG) or equivalent procedure which you developed or revised to implement your mitigating strategies.  
    core cooling (RCS and Steam Generators), containment, and/or spent fuel pool cooling.
E. Provide a list of key piece
F. Provide a listing/summaries of plant modifications completed related to the FLEX program.
s of equipment that directly perform a FLEX mitigation strategy for core cooling (RCS and Steam Generators), containment, and/or spent fuel pool
G. Provide a listing of calculations, evaluations, and 50.59 reviews related to the FLEX program
cooling. F. Provide a listing/summaries
    and modifications.
of plant modifications completed related to the FLEX program.
                                                1                                      Enclosure
G. Provide a listing of calculations, evaluations, and 50.59 reviews related to the FLEX program
 
and modifications
H. Applicable site specific hazards for the Callaway Plant:
.   
  1) Provide documents which show the locations and configuration of structure(s) which
  2  H. Applicable site specific hazards for the Callaway Plant
      store FLEX equipment.
: 1) Provide documents which show the locations and configuration of structure(s) which store FLEX equipment
  2) Seismic
. 2) Seismic (a) Provide the travel route(s) for FLEX equipment from storage location(s) to their location(s) of use, AND evaluation(s) which demonstrate that for the potential for soil liquefaction is not of a concern for these travel route(s).
      (a) Provide the travel route(s) for FLEX equipment from storage location(s) to their
(b) Seismic concerns for water source(s)
          location(s) of use, AND evaluation(s) which demonstrate that for the potential for soil
(1) If the FLEX water sources are seismically robust, then provide the assessment that shows that they are.
          liquefaction is not of a concern for these travel route(s).
(2) If the FLEX water sources are not seismically robust, then provide:
      (b) Seismic concerns for water source(s)
(a) an assessment of alternate water sources, and  
          (1) If the FLEX water sources are seismically robust, then provide the assessment
(b) the procedure(s) which describe when and how to access those sources.
              that shows that they are.
3) External Flooding {"Screened Out
          (2) If the FLEX water sources are not seismically robust, then provide:
" for Callaway Plant  
              (a) an assessment of alternate water sources, and
- no documents requested}
              (b) the procedure(s) which describe when and how to access those sources.
4) Severe storms with high winds
  3) External Flooding
(a) Provide evaluation/evidence as to how FLEX equipment is stored relative to protection from severe storms with high winds:
      {Screened Out for Callaway Plant - no documents requested}
(1) In a structure that meets the plant's design basis for high wind hazards (e.g., existing safety
  4) Severe storms with high winds
-related structure); OR
      (a) Provide evaluation/evidence as to how FLEX equipment is stored relative to
    (2) In a structure that meets the design requirements as described in ASCE 7-10, "Minimum Design Loads for Buildings and Other Structures," given the limiting tornado wind speeds
          protection from severe storms with high winds:
from Regulatory Guide 1.76, and/or design
          (1) In a structure that meets the plants design basis for high wind hazards (e.g.,
-basis hurricane wind speeds.
              existing safety-related structure); OR
(b) Provide pathways via which you plan to move FLEX equipment from onsite storage areas to final deployment locations.
          (2) In a structure that meets the design requirements as described in ASCE 7-10,
(1) Show how you designated and evaluated those pathways for post
              Minimum Design Loads for Buildings and Other Structures, given the limiting
-storm accessibility for staging and connecting FLEX equipment.
              tornado wind speeds from Regulatory Guide 1.76, and/or design-basis hurricane
5) Snow, Ice, and Extreme Cold
              wind speeds.
For each key piece of equipment described in Item 5
      (b) Provide pathways via which you plan to move FLEX equipment from onsite storage
(above) that directly performs or implements a FLEX mitigation strategy:
          areas to final deployment locations.
(a) Provide procedures/documents
          (1) Show how you designated and evaluated those pathways for post-storm
demonstrating that the FLEX equipment is maintained at a temperature within a range to ensure that it will function when called  
              accessibility for staging and connecting FLEX equipment.
  5) Snow, Ice, and Extreme Cold
      For each key piece of equipment described in Item 5 (above) that directly performs or
      implements a FLEX mitigation strategy:
      (a) Provide procedures/documents demonstrating that the FLEX equipment is
          maintained at a temperature within a range to ensure that it will function when called
          upon.
      (b) Provide procedures/documents demonstrating how the FLEX equipment can be
          moved from the storage location to its deployment location during extreme snowfall
          and ice storms.
                                                2
 
    6) Extreme high temperatures
        For each key piece of equipment described in Item 5 (above) that directly performs or
        implements a FLEX mitigation strategy:
        (a) Provide procedures/documents which describes the high-temperature limit of the
            range within which the equipment will function.
        (b) Provide procedures/documents which describe how the equipment is maintained
            below that limit in its storage location.
I.  Provide the station-specific FLEX strategies time validation study(ies).
J. Provide the relevant station procedure(s)/guideline(s) which describe the testing and
    maintenance program for FLEX equipment. As applicable, provide a listing of the model
    work orders established to conduct period testing and maintenance activities for FLEX
    equipment. [A sample of records for completed maintenance/testing activities may be
    requested for review during the onsite inspection week.]
K. Provide documents/procedures which describe the programmatic controls in place to ensure
    that if equipment and applicable connections are unavailable (e.g., due to maintenance,
    non-functionality), then compensatory measures are implemented in accordance with
    guidance outlined NEI 12-06.
L. Provide the station-specific National SAFER Center Playbook
M. Relative to personnel training on FLEX strategies, provide:
    1) FLEX training bases document(s)
    2) Lesson plans/training documents for site emergency response leaders responsible for
        the implementation of FLEX strategies. [Records for staff completing this training may be
        requested for review during the onsite inspection week.]
    3) Lesson plans/training documents for site personnel responsible for the execution of
        mitigating strategies for BDBEEs (i.e., operators, craft personnel, security, radiation
        protection, etc.). [Records for staff completing this training may be requested for review
        during the onsite inspection week.]
N. A current copy of administrative procedure(s) for the CAP, modification program, operations
    procedure writing and implementation, and top-level documents for the work control and
    work scheduling programs. (If FLEX related procedures such as FSGs or the FIP are
    maintained under a different process, please include copies of those procedures.)
O. A current copy of the U/FSAR, Technical Specifications, and Technical Specification Bases
    documents.
P. Listing of corrective action program document summaries generated related to FLEX
    equipment, strategies, procedures, and/or training.
Q. A copy of any audits/self-assessments related to your preparation for this inspection, as well
    as any related to the implementation or maintenance of the FLEX program.
TI 2515/191 - Appendix B
R. Provide the procedures implemented for maintenance, testing, calibration, and use of the
    primary and backup Spent Fuel Pool (SFP) instrumentation channels.
S. Provide lesson plans/training documents which describe the training program that address
    the use, maintenance, calibration, surveillance, and the use of alternate power to the
    primary and backup SFP instrument channels.
                                                    3
 
TI 2515/191 - Appendix C
T. Communications:
    1) Provide documents which show that the communications system(s), technologies,
        equipment and power supplies would be available from the beginning of the event and
        operate during an ELAP.
    2) Provide the procedures and/or guidance used to implement the communication
        capabilities.
    3) Provide documents which show that you have added any new communications
        equipment, portable power supplies and/or systems have been added to ongoing testing
        and preventative maintenance programs.
U. Staffing:
    1) Provide documents which show that onsite and augmented staff will be available to
        implement the strategies in response to a large scale natural event that results an ELAP
        and impedes access to the site, and that functions/tasks have been appropriately
        staffed.
    2) Provide documents which show that the site access methods (e.g., roadways, navigable
        bodies of water and dockage, airlift, etc.) expected to be available following the event
        and available to the Emergency Response Organization (ERO) [as described in the
        Phase 1 and 2 staffing assessments and NRC safety assessment].
    3) Provide documents which show the testing, training, and drills/exercises performed by
        the station to demonstrate the EROs ability to utilize the communications systems
        and/or equipment.
V. Provide documents and procedures which show that your dose assessment is capable of
    analyzing concurrent radiological releases from all on-site significant sources, including
    releases from spent fuel pools (i.e., multi-unit/multi-source dose assessment capability).
Lead Inspector Contact Information:
Ryan D. Alexander, Sr. Project Engineer            Mailing Address:
817-200-1195                                        U.S. NRC, Region IV
Ryan.Alexander@nrc.gov                              Attn: Ryan Alexander, DRP
                                                    1600 East Lamar Blvd.
                                                    Arlington, TX 76011-4511
                                                4


upon. (b) Provide procedures/documents
demonstrating how the FLEX equipment can be moved from the storage location to its deployment location during extreme snowfall and ice storms.
   
  3  6) Extreme high temperatures
For each key piece of equipment described in Item
5 (above) that directly performs or implements a FLEX mitigation strategy
: (a) Provide procedures/documents
which describes the high
-temperature limit of the range within which the equipment will function.
(b) Provide procedures/documents
which describe how the equipment is maintained below that limit in its storage location.
I. Provide the station
-specific FLEX strategies time validation study(ies)
. J. Provide the relevant station procedure(s)/guideline(s) which describe
the testing and maintenance program for FLEX equipment.
  As applicable, provide a listing of the model work orders established to conduct period testing and maintenance activities for FLEX equipment.  [A sample of records for completed maintenance/testing activities
may be requested for review
during the onsite inspection week.]
K. Provide documents/procedures
which describe the programmatic controls in place
to ensure that if equipment and applicable connections are unavailable (e.g., due to maintenance , non-functionality), then compensatory measures are implemented in accordance with guidance outlined NEI 12
-06. L. Provide the station
-specific National SAFER Center "Playbook"
M. Relative to personnel training on FLEX strategies, provide:
1) FLEX training bases document(s)
2) Lesson plans/training documents
for site emergency response leaders responsible for the implementation of FLEX strategies. [Records for staff completing this training may be requested for review
during the onsite inspection week.]
3) Lesson plans/training documents
for site personnel responsible for the execution of mitigating strategies for BDBEEs (i.e., operators, craft personnel, security, radiation protection, etc.). [Records for staff completing this training may be requested for review
during the onsite inspection week.]
N. A current copy of administrative procedure(s) for the CAP, modification program, operations
procedure writing and implementation, and top-level documents for the work control and work scheduling programs.
(If FLEX related procedures such as FSGs or the FIP are maintained under a different process
, please include copies of those
procedures.
) O. A current copy of the U/FSAR, Technical Specifications, and Technical Specification Bases documents.
P. Listing of corrective action program document summaries generated related to FLEX equipment, strategies, procedures, and/or training.
Q. A copy of any audits/self
-assessments related to your preparation for this inspection, as well as any related to the implementation or maintenance of the FLEX program.
  TI 2515/191
- Appendix B
R. Provide the procedures implemented for maintenance, testing, calibration, and use of the primary and backup Spent Fuel Pool (SFP) instrumentation channels.
S. Provide lesson plans/training documents which describe the training program that address the use, maintenance, calibration, surveillance, and the use of alternate power to the primary and backup SFP instrument channels. 
 
  4  TI 2515/191
- Appendix C
T. Communications:
1) Provide documents which show that
the communications system(s), technologies, equipment and power supplies would be available from the beginning of the event and operate during an ELAP.
2) Provide the procedures and/or guidance used to implement the communication capabilities
. 3) Provide documents which show that you have added any new communications equipment, portable power supplies and/or systems have been added to ongoing testing and preventative maintenance programs.
U. Staffing: 1) Provide documents which show that onsite and augmented staff will be available to
implement the strategies
in response to a large scale natural event that results an ELAP and impedes access to the site, and that functions/tasks have been appropriately
staffed. 2) Provide documents which show that the site access methods (e.g., roadways, navigable bodies of water and dockage, airlift, etc.) expected to be available
following the event and available to the Emergency Response Organization (ERO) [as described in the Phase 1 and 2 staffing assessments and NRC safety assessment]. 3) Provide documents which show the testing, training, and drills/exercises performed by
the station
to demonstrate the ERO's ability to utilize the communications systems and/or equipment.
V. Provide documents and procedures which show that your dose
assessment is capable of analyzing concurrent radiological releases from all on-site significant sources, including releases from spent fuel pools (i.e., multi
-unit/multi
-source dose assessment capability)
.  Lead Inspector Contact Information:
  Ryan D. Alexander , Sr. Project Engineer
Mailing Address
: 817-200-11 95 U.S. NRC, Region IV
Ryan.Alexander@nrc.gov
Attn:  Ryan Alexander, DRP
  1600 East Lamar Blvd.
  Arlington, TX  76011
-4511 


  ML17170A091
ML17170A091
   SUNSI Review By: RDA/rdr ADAMS:    Yes      No  Sensitive 
   SUNSI Review ADAMS:          Sensitive        Non-Publicly Available Keyword
  Non-Sensitive Non-Publicly Available 
By: RDA/rdr     Yes No     Non-Sensitive   Publicly Available     NRC-002
  Publicly Available
OFFICE         DRP/RPBA         C:DRP/RPBB
Keyword NRC-002 OFFICE DRP/RPBA C:DRP/RPBB
NAME           RAlexander       JDixon
  NAME RAlexander
  SIGNATURE       /RA/-E           /RA/
  JDixon  SIGNATURE /RA/-E /RA/   DATE 06/14/2017
DATE           06/14/2017       06/19/2017
06/19/2017
}}
}}

Revision as of 02:00, 30 October 2019

Notification of NRC Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/ Staffing/Multi-Unit Dose Assessment Plans (05000483/2017008) and Request for
ML17170A091
Person / Time
Site: Callaway Ameren icon.png
Issue date: 06/19/2017
From: Ryan Alexander, John Dixon
NRC/RGN-IV/DRP/RPB-B
To: Diya F
Ameren Corp
Dixon J
References
TI-2515/191 IR 2017008
Download: ML17170A091 (7)


See also: IR 05000483/2017008

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION IV

1600 E. LAMAR BLVD.

ARLINGTON, TX 76011-4511

June 19, 2017

Mr. Fadi Diya, Senior Vice President

and Chief Nuclear Officer

Ameren Missouri

Callaway Plant

P.O. Box 620

Fulton, MO 65251

SUBJECT: CALLAWAY PLANT - NOTIFICATION OF NRC INSPECTION OF THE

IMPLEMENTATION OF MITIGATION STRATEGIES AND SPENT FUEL POOL

INSTRUMENTATION ORDERS AND EMERGENCY PREPAREDNESS

COMMUNICATION/ STAFFING/MULTI-UNIT DOSE ASSESSMENT PLANS

(05000483/2017008) AND REQUEST FOR INFORMATION

Dear Mr. Diya:

The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)

staff will conduct a mitigation strategies for beyond-design-basis external events, spent fuel pool

instrumentation, and emergency preparedness enhancements inspection at the Callaway Plant

from August 28 - September 1, 2017. The inspection will consist of three reactor inspectors

from the NRCs Region IV office, plus one of the assigned Resident Inspectors at the Callaway

Plant for one week. The inspection will be conducted in accordance with the NRCs Temporary

Instruction 2515/191, Inspection of the Implementation of Mitigating Strategies and Spent Fuel

Pool Instrumentation Orders, and Emergency Preparedness Communication/Staffing/Multi-Unit

Dose Assessment Plans.

Experience has shown that this inspection is resource intensive both for the NRC inspectors

and licensee staff. In order to minimize the impact to your onsite resources and to ensure a

productive inspection, we have enclosed a request for documents needed for this inspection

activity. Please note that the documents are requested to be provided by August 11, 2017.

During the onsite inspection, inspectors will verify that plans for complying with NRC Orders

EA-12-049 and EA-12-051 are in place and are being implemented. Inspectors will also verify

the establishment of staffing and communications plans provided in response to the March 12,

2012, request for information letter, and multi-unit dose assessment information provided per

COMSECY-13-0010, Schedule and Plans for Tier 2 Order on Emergency Preparedness for

Japan Lessons Learned, dated March 27, 2013. These plans and information were provided in

the site specific submittals, which were subsequently reviewed by the NRC staff for

understanding and documented in the NRCs plant safety evaluations (SEs) and safety

assessments. Therefore, appropriate personnel knowledgeable of the stations FLEX

strategies, spent fuel pool instrumentation, and emergency preparedness enhancements should

be available to support the inspectors at the site during the inspection.

F. Diya 2

We have discussed the schedule for this inspection activity with your staff and understand that

our regulatory contact for this inspection will be Elizabeth Ptasznik of your licensing

organization. If there are any questions about this inspection or the material requested, please

contact the lead inspector, Ryan D. Alexander, by telephone at 817-200-1195 or by e-mail at

ryan.alexander@nrc.gov.

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, control

number 3150 0011. The NRC may not conduct or sponsor, and a person is not required to

respond to, a request for information or an information collection requirement unless the

requesting document displays a currently valid Office of Management and Budget control

number.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRCs document system

(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

John L. Dixon, Acting Chief

Project Branch B

Division of Reactor Projects

Docket No. 50-483

License No. NPF-30

Enclosure:

FLEX Strategies, Spent Fuel Pool

Instrumentation, & EP Enhancements

Inspection Request for Information

Request for Information

FLEX Strategies, Spent Fuel Pool Instrumentation, & EP Enhancements Inspection

Callaway Plant

Inspection Report: 05000483/2017008

Inspection Dates: August 28 - September 1, 2017

Inspection Procedure: Temporary Instruction 2515/191, Inspection of the

Implementation of Mitigating Strategies and Spent Fuel Pool

Instrumentation Orders, and Emergency Preparedness

Communication/Staffing/Multi-Unit Dose Assessment Plans

Inspectors: Ryan D. Alexander, Team Lead, Sr. Project Engineer, Region IV

Dan Bradley, Callaway Plant Senior Resident Inspector

Steve Alferink, Reactor Inspector, Region IV

Michael Stafford, Project Engineer, Region IV

Information Requested for the In-Office Preparation Week

The following information should be sent to the Region IV office in hard copy or electronic

format (use of the Certrec IMS information portal is preferred), to the attention of Ryan

Alexander, by August 11, 2017. The inspectors will select specific items from the information

requested below and then request from your staff additional documents needed during the

onsite inspection week. Also, we request that you categorize the documents in your response

with the numbered list below. Please provide requested documentation electronically if

possible. If requested documents are large and only hard copy formats are available, please

inform the lead inspector, and provide subject documentation during the first day of the onsite

inspection. If you have any questions regarding this information request, please call the lead

inspector as soon as possible.

TI 2515/191 - Appendix A

A. Provide current revision of the FLEX Final Integrated Plan (i.e., current FLEX Program

Document), including any revisions since July 2016 submission to the NRC.

B. Provide the FLEX Strategy Basis Document.

C. Provide each operating, off-normal, abnormal, and/or emergency procedures where entry

into one or more FLEX Support Guideline(s) are initiated.

D. Provide a list and copies of every FLEX Support Guideline (FSG) or equivalent procedure

which you developed or revised to implement your mitigating strategies.

E. Provide a list of key pieces of equipment that directly perform a FLEX mitigation strategy for

core cooling (RCS and Steam Generators), containment, and/or spent fuel pool cooling.

F. Provide a listing/summaries of plant modifications completed related to the FLEX program.

G. Provide a listing of calculations, evaluations, and 50.59 reviews related to the FLEX program

and modifications.

1 Enclosure

H. Applicable site specific hazards for the Callaway Plant:

1) Provide documents which show the locations and configuration of structure(s) which

store FLEX equipment.

2) Seismic

(a) Provide the travel route(s) for FLEX equipment from storage location(s) to their

location(s) of use, AND evaluation(s) which demonstrate that for the potential for soil

liquefaction is not of a concern for these travel route(s).

(b) Seismic concerns for water source(s)

(1) If the FLEX water sources are seismically robust, then provide the assessment

that shows that they are.

(2) If the FLEX water sources are not seismically robust, then provide:

(a) an assessment of alternate water sources, and

(b) the procedure(s) which describe when and how to access those sources.

3) External Flooding

{Screened Out for Callaway Plant - no documents requested}

4) Severe storms with high winds

(a) Provide evaluation/evidence as to how FLEX equipment is stored relative to

protection from severe storms with high winds:

(1) In a structure that meets the plants design basis for high wind hazards (e.g.,

existing safety-related structure); OR

(2) In a structure that meets the design requirements as described in ASCE 7-10,

Minimum Design Loads for Buildings and Other Structures, given the limiting

tornado wind speeds from Regulatory Guide 1.76, and/or design-basis hurricane

wind speeds.

(b) Provide pathways via which you plan to move FLEX equipment from onsite storage

areas to final deployment locations.

(1) Show how you designated and evaluated those pathways for post-storm

accessibility for staging and connecting FLEX equipment.

5) Snow, Ice, and Extreme Cold

For each key piece of equipment described in Item 5 (above) that directly performs or

implements a FLEX mitigation strategy:

(a) Provide procedures/documents demonstrating that the FLEX equipment is

maintained at a temperature within a range to ensure that it will function when called

upon.

(b) Provide procedures/documents demonstrating how the FLEX equipment can be

moved from the storage location to its deployment location during extreme snowfall

and ice storms.

2

6) Extreme high temperatures

For each key piece of equipment described in Item 5 (above) that directly performs or

implements a FLEX mitigation strategy:

(a) Provide procedures/documents which describes the high-temperature limit of the

range within which the equipment will function.

(b) Provide procedures/documents which describe how the equipment is maintained

below that limit in its storage location.

I. Provide the station-specific FLEX strategies time validation study(ies).

J. Provide the relevant station procedure(s)/guideline(s) which describe the testing and

maintenance program for FLEX equipment. As applicable, provide a listing of the model

work orders established to conduct period testing and maintenance activities for FLEX

equipment. [A sample of records for completed maintenance/testing activities may be

requested for review during the onsite inspection week.]

K. Provide documents/procedures which describe the programmatic controls in place to ensure

that if equipment and applicable connections are unavailable (e.g., due to maintenance,

non-functionality), then compensatory measures are implemented in accordance with

guidance outlined NEI 12-06.

L. Provide the station-specific National SAFER Center Playbook

M. Relative to personnel training on FLEX strategies, provide:

1) FLEX training bases document(s)

2) Lesson plans/training documents for site emergency response leaders responsible for

the implementation of FLEX strategies. [Records for staff completing this training may be

requested for review during the onsite inspection week.]

3) Lesson plans/training documents for site personnel responsible for the execution of

mitigating strategies for BDBEEs (i.e., operators, craft personnel, security, radiation

protection, etc.). [Records for staff completing this training may be requested for review

during the onsite inspection week.]

N. A current copy of administrative procedure(s) for the CAP, modification program, operations

procedure writing and implementation, and top-level documents for the work control and

work scheduling programs. (If FLEX related procedures such as FSGs or the FIP are

maintained under a different process, please include copies of those procedures.)

O. A current copy of the U/FSAR, Technical Specifications, and Technical Specification Bases

documents.

P. Listing of corrective action program document summaries generated related to FLEX

equipment, strategies, procedures, and/or training.

Q. A copy of any audits/self-assessments related to your preparation for this inspection, as well

as any related to the implementation or maintenance of the FLEX program.

TI 2515/191 - Appendix B

R. Provide the procedures implemented for maintenance, testing, calibration, and use of the

primary and backup Spent Fuel Pool (SFP) instrumentation channels.

S. Provide lesson plans/training documents which describe the training program that address

the use, maintenance, calibration, surveillance, and the use of alternate power to the

primary and backup SFP instrument channels.

3

TI 2515/191 - Appendix C

T. Communications:

1) Provide documents which show that the communications system(s), technologies,

equipment and power supplies would be available from the beginning of the event and

operate during an ELAP.

2) Provide the procedures and/or guidance used to implement the communication

capabilities.

3) Provide documents which show that you have added any new communications

equipment, portable power supplies and/or systems have been added to ongoing testing

and preventative maintenance programs.

U. Staffing:

1) Provide documents which show that onsite and augmented staff will be available to

implement the strategies in response to a large scale natural event that results an ELAP

and impedes access to the site, and that functions/tasks have been appropriately

staffed.

2) Provide documents which show that the site access methods (e.g., roadways, navigable

bodies of water and dockage, airlift, etc.) expected to be available following the event

and available to the Emergency Response Organization (ERO) [as described in the

Phase 1 and 2 staffing assessments and NRC safety assessment].

3) Provide documents which show the testing, training, and drills/exercises performed by

the station to demonstrate the EROs ability to utilize the communications systems

and/or equipment.

V. Provide documents and procedures which show that your dose assessment is capable of

analyzing concurrent radiological releases from all on-site significant sources, including

releases from spent fuel pools (i.e., multi-unit/multi-source dose assessment capability).

Lead Inspector Contact Information:

Ryan D. Alexander, Sr. Project Engineer Mailing Address:

817-200-1195 U.S. NRC, Region IV

Ryan.Alexander@nrc.gov Attn: Ryan Alexander, DRP

1600 East Lamar Blvd.

Arlington, TX 76011-4511

4

ML17170A091

SUNSI Review ADAMS: Sensitive Non-Publicly Available Keyword

By: RDA/rdr Yes No Non-Sensitive Publicly Available NRC-002

OFFICE DRP/RPBA C:DRP/RPBB

NAME RAlexander JDixon

SIGNATURE /RA/-E /RA/

DATE 06/14/2017 06/19/2017